UNIVERSIDAD NACIONAL MAYOR DE SAN MARCOS (UNIVERSIDAD DEL PERÚ, DECANA DE AMÉRICA) INGENIERÍA GEOLÓGICA CURSO: GEOLOGIA DE MINAS PROFESOR: ING. ORLANDO ORBEGOZO TEMA: REGISTROS DE DIAMOND DRILL ALUMNOS: HUAMANI SALGUERON JHONATHAN CÓDIGO: 11160095 HUAPAYA CABELLO LUIS ANDRES CODIGO: 06160071 JARAMILLO RODRIGUEZ ELMER CODIGO: 10160208

description

informe

Transcript of Diamond Drill Finallll

Page 1: Diamond Drill Finallll

UNIVERSIDAD NACIONAL MAYOR DE SAN MARCOS

(UNIVERSIDAD DEL PERÚ, DECANA DE AMÉRICA)

INGENIERÍA GEOLÓGICA

CURSO: GEOLOGIA DE MINAS

PROFESOR: ING. ORLANDO ORBEGOZO

TEMA: REGISTROS DE DIAMOND DRILL

ALUMNOS:

HUAMANI SALGUERON JHONATHAN CÓDIGO: 11160095

HUAPAYA CABELLO LUIS ANDRES CODIGO: 06160071

JARAMILLO RODRIGUEZ ELMER CODIGO: 10160208

MAMANI VARGAS JOHN CODIGO: 04160002

CIUDAD UNIVERSITARIA, 2015

Page 2: Diamond Drill Finallll

ESTABLECIMIENTO DE LEYES EN REGISTROS DIAMOND DRILL

1.-DATOS.

Las brocas utilizadas en la perforación son de tipo AX, BX y NX, las cuales presentan las siguientes dimensiones, que se resumen en el cuadro:

DIMENSIONES DE LAS BROCAS USADAS

DIMENSION AX BX NXdiámetro interior 1 7/32 in. 1 7/16 in. 2 3/16 in.

diámetro exterior 1 21/32 in. 1 5/16 in. 2 15/15 in.

diámetro de núcleo 1 1/8 in. 1 5/8 in. 2 1/8 in.

área de núcleo (pgl²) 0.99 in². 2.07 in². 3.55 in².

diámetro del hueco (plg) 1 7/8 in. 1 3/16 in. 3 in.

área del hueco (plg²) 2.66 in². 4.43 in². 7.07 in².

Page 3: Diamond Drill Finallll

2. CÁLCULOS PARA EL NÚCLEO DEL SONDAJE.

Peso Teórico del Núcleo.

Se tiene que:

Peso Teo núcleo = Área núcleo X Longitud X Peso Específico

1 DIA

Peso Teo núcleo = 3.55 pulg2 X 3088.577 pulg X 0.0975 lb/pulg3

Peso Teo núcleo = 1069.0337 Lbs

2 DIA

Peso Teo núcleo = 0.99 pulg2 X 3415.3475 pulg X 0.0939lb/pulg3

Peso Teo núcleo = 317.4941 Lbs

3 DIA

Peso Teo núcleo = 0.99 pulg2 X 3749.9925 pulg X 0.0939 lb/pulg3

Peso Teo núcleo = 348.6031 Lbs

4 DIA

Peso Teo núcleo = 2.07 pulg2 X 2765.7425 pulg X 0.0975 lb/pulg3

Peso Teo núcleo = 558.1959 Lbs

5 DIA

Peso Teo núcleo = 2.07 X 3416.5286 pulg X 0.0939 lb/pulg3

Peso Teo núcleo = 664.0809 Lbs

6 DIA

Peso Teo núcleo = 2.07 X 2568.8925 pulg X 0.1012 lb/pulg3

Peso Teo núcleo = 538.1419 Lbs

7 DIA

Page 4: Diamond Drill Finallll

Peso Teo núcleo = 2.07 X 1781.4925 pulg X 0.1012 lb/pulg3

Peso Teo núcleo = 373.1942 Lbs.

Page 5: Diamond Drill Finallll

Peso Real del Núcleo.

El peso recuperado está dado por la siguiente expresión, que muestra el peso recuperado del núcleo en el sondaje diamantino:

Se tiene que:

Peso Real. núcleo = Área núcleo X Longitud X Peso Específico X % Rec.

Teniendo las fechas y los datos de las brocas, tenemos:

1 DIA

Peso real núcleo = 3.55 pulg2 X 3088.577 pulg X 0.0975 lb/pulg3 X 0.95

Peso real núcleo = 1015.5820 Lbs

2 DIA

Peso real núcleo = 0.99 pulg2 X 3415.3475 pulg X 0.0939lb/pulg3 X 0.89

Peso real núcleo = 282.5697 Lbs

3 DIA

Peso real núcleo = 0.99 pulg2 X 3749.9925 pulg X 0.0939 lb/pulg3 X 0.94

Peso real núcleo = 327.6869 Lbs

4 DIA

Peso real núcleo = 2.07 pulg2 X 2765.7425 pulg X 0.0975 lb/pulg3 X 0.94

Peso real núcleo = 524.7041 Lbs

5 DIA

Peso real núcleo = 2.07 X 3416.5286 pulg X 0.0939 lb/pulg3 X 0.76

Peso real núcleo = 504.7015 Lbs

Page 6: Diamond Drill Finallll

6 DIA

Peso real núcleo = 2.07 X 2568.8925 pulg X 0.1012 lb/pulg3 X 0.93

Peso real núcleo = 500.4720 Lbs

7 DIA

Peso real núcleo = 2.07 X 1781.4925 pulg X 0.1012 lb/pulg3 X 0.94

Peso real núcleo = 350.8025 Lbs

3. CÁLCULOS PARA LA LAMA DEL SONDAJE.

Page 7: Diamond Drill Finallll

Peso Teórico de la lama.

Esta esta dad por la siguiente expresión:

Peso Teolama = Peso Teo hueco - Peso Teo núcleo

A.- PESO TEORICO HUECO:

Peso Teo hueco = Área hueco X Longitud X Peso Específico

1 DIA

Peso Teo hueco = 7.07 X 3088.577 pulg X 0.0975 lb/pulg3

Peso Teo hueco = 2129.033 Lbs

2 DIA

Peso Teo hueco = 2.66 X 3415.3475 pulg X 0.0939lb/pulg3

Peso Teo hueco = 853.065 Lbs

3 DIA

Peso Teo hueco = 2.66 X 3749.9925 pulg X 0.0939 lb/pulg3

Peso Teo hueco = 936.651 Lbs

4 DIA

Peso Teo hueco = 4.43 X 2765.7425 pulg X 0.0975 lb/pulg3

Peso Teo hueco = 1194.593 Lbs

5 DIA

Peso Teo hueco = 4.43 X 3416.5286 pulg X 0.0939 lb/pulg3

Peso Teo hueco = 1421.197 Lbs

6 DIA

Peso Teo hueco = 4.43 X 2568.8925 pulg X 0.1012 lb/pulg3

Page 8: Diamond Drill Finallll

Peso Teo hueco = 1151.6756 Lbs

7 DIA

Peso Teo hueco = 4.43 X 1781.4925 pulg X 0.1012 lb/pulg3

Peso Teo hueco = 798.6716 Lbs

Entonces se tiene que:

B.- PESO TEORICO LAMA:

Peso Teolama = (Volumen Teo hueco - Volumen Teo núcleo ) * pe

1 DIA

Peso Teo lama = (21836.2 Lbs - 10964.4 Lbs)*0.0975

Peso Teo lama = 1060.00 lbs

2 DIA

Peso Teo lama = (9084.8 Lbs – 3381.2 Lbs )* 0.0939

Peso Teo lama = 535.57 lbs.

3 DIA

Peso Teo lama = (9974.9 Lbs – 3712.5 Lbs )* 0.0939

Peso Teo lama = 588.04 lbs

4 DIA

Peso Teo lama = (12252.2 Lbs – 5725.1 Lbs )*0.0975

Peso Teo lama = 636.39 lbs

5 DIA

Page 9: Diamond Drill Finallll

Peso Teo lama = (15132.2 Lbs - 7072.2 Lbs )*0.0939

Peso Teo lama = 756.83 Lbs

6 DIA

Peso Teo lama = (11380.2 Lbs – 5317.6 Lbs )*0.1012

Peso Teo lama = 613.54 lbs

7 DIA

Peso Teo lama = (7892.0 Lbs - 3687.7 Lbs )*0.1012

Peso Teo lama = 425.48 Lbs

Peso Real de la lama:

Page 10: Diamond Drill Finallll

El peso recuperado de la lama lo obtenemos a partir de los siguientes cálculos.

Peso Reclama = Peso Teo hueco - Peso Real núcleo

1 DIA

Peso Rec lama = (2129.033 – 1015.5820)

Peso Rec lama = 1113.452 lbs

2 DIA

Peso Teo lama = (853.065 – 282.5697)

Peso Rec lama = 570.4953 lbs.

3 DIA

Peso Teo lama = (936.651 – 327.6869)

Peso Rec lama = 608.9641 lbs

4 DIA

Peso Teo lama = (1194.593 – 524.7041)

Peso Rec lama = 669.8889 lbs

5 DIA

Peso lama = (1421.197 – 504.7015)

Peso Rec lama = 916.4955 Lbs

6 DIA

Peso Teo lama = (1151.6756 – 500.4720)

Page 11: Diamond Drill Finallll

Peso Rec lama = 651.2036 lbs

7 DIA

Peso lama = (798.6716 – 350.8025)

Peso Rec lama = 447.8691 Lbs

Page 12: Diamond Drill Finallll

4. Cálculos para la ley promedio por tramos de sondaje.

LEY = (FACT NUCLEO*% NUCLEO + FACT LAMA*% LAMA)/SUM FACTS

Y obtenemos las siguientes leyes finales:

PARA EL CASO DE LA COMPOSICIÓN Y PROMEDIO DE ZINC

DIA 1 LEY = (1015.5820X 3,2 + 1113.452X 3,1)/2129.034

LEY = 3.14

DIA 2 LEY = (282.5697 X 2,4 + 570.4953 X 2,8)/853.065

LEY =2.68

DIA 3 LEY = (327.6869 X5,2 + 608.9641 X 4,7)/936.651

LEY = 4.84

DIA 4 LEY = (524.7041 X2,8 + 669.8889 X 2,5)/1194.593

LEY = 2.61

DIA 5

LEY = (504.7015 X 3,2 + 916.4955 X 3,03)/1421.197

LEY = 3.11

DIA 6

Page 13: Diamond Drill Finallll

LEY = (500.4720 X 3,1 + 651.2036 X 3,02)/1151.6756

LEY = 3.11

DIA 7LEY = (350.8025 X5,2 + 447.8691 X 4,7)/798.6716

LEY = 4.84

PARA EL CASO DE LA COMPOSICIÓN Y PROMEDIO DE PB

Page 14: Diamond Drill Finallll

DIA 1

LEY = (1015.5820X 2.2 + 1113.452X 2.8)/2129.034

LEY = 2.63

DIA 2

LEY = (282.5697 X 1.98 + 570.4953 X 2.01)/853.065

LEY =2.oo

DIA 3

LEY = (327.6869 X3.52 + 608.9641 X 4.29)/936.651

LEY = 4.09

DIA 4 LEY = (524.7041 X2.75 + 669.8889 X 2.01)/1194.593

LEY = 2.31

DIA 5

LEY = (504.7015 X 3,22 + 916.4955 X 2.99)/1421.197

LEY = 3.14

DIA 6

Page 15: Diamond Drill Finallll

LEY = (500.4720 X 3,2 + 651.2036 X 3,03)/1151.6756

LEY = 3.11

DIA 7LEY = (350.8025 X3,2 + 447.8691 X 4,7)/798.6716

LEY = 4.84

PARA EL CASO DE LA COMPOSICIÓN Y PROMEDIO DE LA AG

Page 16: Diamond Drill Finallll

DIA 1

LEY = (1015.5820X 4.06 + 1113.452X 6.12/2129.034

LEY = 5.45

DIA 2

LEY = (282.5697 X 5.87+ 570.4953 X 3.65)/853.065

LEY =4.26

DIA 3

LEY = (327.6869 X4.04 + 608.9641 X 4,71)/936.651

LEY = 4.54

DIA 4 LEY = (524.7041 X5.36 + 669.8889 X 6.79)/1194.593

LEY = 6.162

DIA 5

LEY = (504.7015 X 4.26 + 916.4955 X 2.47)/1421.197

LEY = 3.14

DIA 6

Page 17: Diamond Drill Finallll

LEY = (500.4720 X 4.26 + 651.2036 X 2.47)/1151.6756

LEY = 3.14

DIA 7LEY = (350.8025 X4.26 + 447.8691 X 3.47)/798.6716

LEY = 4.53

PARA EL CASO DE LA COMPOSICIÓN Y PROMEDIO DE LA AU

Page 18: Diamond Drill Finallll

DIA 1

LEY = (1015.5820X 6.06 + 1113.452X 5.12/2129.034

LEY = 5.75

DIA 2

LEY = (282.5697 X 7.87+ 570.4953 X 5.65)/853.065

LEY =6.67

DIA 3

LEY = (327.6869 X8.04 + 608.9641 X 5.,71)/936.651

LEY = 7,87

DIA 4 LEY = (524.7041 X9.36 + 669.8889 X 6.79)/1194.593

LEY = 7.03

DIA 5

LEY = (504.7015 X 5.26 + 916.4955 X 5.47)/1421.197

LEY = 5.34

DIA 6

Page 19: Diamond Drill Finallll

LEY = (500.4720 X 4.26 + 651.2036 X 2.47)/1151.6756

LEY = 4.06

DIA 7LEY = (350.8025 X5.26 + 447.8691 X 5.47)/798.6716

LEY = 5.52