Jpm Tqm Course Mat-5 T-3 Imba 2013

download Jpm Tqm Course Mat-5 T-3 Imba 2013

of 14

Transcript of Jpm Tqm Course Mat-5 T-3 Imba 2013

  • 7/30/2019 Jpm Tqm Course Mat-5 T-3 Imba 2013

    1/14

    RUN Test_

    A RUN is a consecutive increase or decrease in the observations plotted on the

    X -Control Chart. It indicates statisticallynon-randombehaviourof the process.

    Long Run-UP or Long Run-DOWN (ie increasing ordecreasing

    cont inuous lyformo re than5 consecutive observations) shows that theprocess is OUT OF CONTROL, though the observations are within the

    control limits.

    Long Run-up (8)

    CL

    UCL

    LCL

    _

    X

    N (Sample No.)

    _

    X

    N (Sample No.)

    LCL

    CL

    UCL

    Long Run-down (7)

    Runs Test is to test whether

    the process is out of control, using the

    data from control chart. Here, the first case is out of control due to Long

    Run-up and the second case is out of control due to Long Run-down.

    # When the process is out o f con tro l , ident i fy the Assign able Causes behindit and immediately remove (rect i fy) them.

  • 7/30/2019 Jpm Tqm Course Mat-5 T-3 Imba 2013

    2/14

    Chart SENSITIVITY Test_

    It is the tool applied on X-Chart to judge how far the process is under Control.

    _Rule 1: Even if only one Point (X)

    falls beyon d Zone-3, the process isSaid to be out of control.

    Rule 2 : Iftwo consecutive Points

    fall in same side Zone-3, the process issaid to be out of control.

    Rule 3 : Iffour consecutive Pointsfall in same side Zone-2, the process issaid to be out of control.

    Rule 4 : Ifeight consecutive pointsfall in same

    side Zone-1,The process is said to be out of control.

    # When the process is out of control , ident i fy the Assig nable Causes

    behind it and immediately remove (rect i fy) them.

    _

    X

    N

    ( 3 Zone)

    ( 2) Zone

    ( 1) Zone

    (+ 1) Zone 8

    (+ 2) Zone

    4

    (+ 3) Zone 2

    =X

    UNTL=X +

    3 1

    = LNTLX - 3

  • 7/30/2019 Jpm Tqm Course Mat-5 T-3 Imba 2013

    3/14

    RUN - SUM Test _It is the tool applied on X-Chart to judge how far the process is under Control.

    Steps1) Divide the Control Chart into 6zones, each with width of one ieStandard Deviation of population,in both Upper & Lower direction of the

    _Centre Line of the X-chart

    _

    X

    N

    ( 3 Zone)

    ( 2) Zone

    ( 1) Zone

    (+ 1) Zone +1

    (+ 2) Zone

    +2

    (+ 3) Zone +3

    =X

    UNTL

    =X + 3

    = LNTLX - 3

    _

    2) Successive Observations (X) are

    plotted.

    3) Assign each Observation a SCOREaccording to the ZONE in which it falls.

    On Centre Line score= 0

    In +1 Zone score= + 1

    In - 1 Zone score= 1

    In +2 Zone score= + 2

    In - 3 Zone score= 3

    4) Sum-up the individual scores (ki)

    earned by all the observations. K = ki

    5) If the Sum-up Score, I K I > 4, the Process is not under Control.# When the proc ess is not und er contro l , ident i fy the Assignable Causes

    behind it and immediately remove (rect i fy) them.

  • 7/30/2019 Jpm Tqm Course Mat-5 T-3 Imba 2013

    4/14

    SPECIFIED TOLERANCE : (example : 250 +3 4 )

    Process Control Limits :

    USL = Upper specified Limit (here 253) LSL = Lower specified Limit (here 246)

    (USL LSL) = SPECIFIED SPREADor simply SPREAD (S) (here 253 246 = 7)CENTER LINE of Specified Spread = (USL + LSL) / 2 (here 249.5)

    NATURAL TOLERANCE: =Process Central Line = = X

    Upper Natural Tolerance Limit = UNTL = + 3

    Lower Natural Tolerance Limit = LNTL = 3

    NATURAL /PROCESS SPREADor simply BAND (B) = (UNTL LNTL) = 6

    PROCESS CAPABILITY RATIO (PCR) = Specified Spread.Process Spread

    PCR = Cp =Specified spread = (USL LSL) = Spread (S) = S

    Process Spread (UNTL LNTL) Band (B) 6

  • 7/30/2019 Jpm Tqm Course Mat-5 T-3 Imba 2013

    5/14

    Quality-Control based on SPREAD and Process BAND1) If 6 < SThe processcan be easily be

    kept under control by adjusting=

    the position of X very near to Centre

    Line (SC) of the

    Spread.Position2 is shifted and keptat position 1.

    2) If 6 = SStrict Centering care to be taken

    =to keep the Control (Centre) Line Xperfectly at the Centre Line of Spread.

    It is also better to relax the SpecifiedTolerance to make S> 6 . Position2is shifted and kept at position 1.

    3) If6 > S

    Even with Extreme care & control andPerfect Centering, the process is not underControl. The Process is said to beOut of Control. Quality non-conformance will be there and there by Quality RejectionWill take place.Care to be taken : (1) Fundamental change in process,(2) Revision of Specified Tolerance, (3) Perfect Centering,

    (4) 100% inspection

    21

    2

    SC

    USL

    LSL

    6

    6S

    USL

    LSL

    SC S2

    1

    6 2

    6

    1

    1

    UNTL

    LNTL

    UNTL

    UNTL

    LNTL

    (

    SC)S/2

    S/2

  • 7/30/2019 Jpm Tqm Course Mat-5 T-3 Imba 2013

    6/14

    PROCESS CAPABILITY

    PROCESS CAPABILITY RATIO = Specified Spread Process Spread PCR or Cp = (USL LSL) = S .

    (UNTL LNTL) 6 (i) PCR should be considerably greater than 1, ie

    Specified Spread (USL LSL) >> Natural Spread 6 . and

    (ii) USL should be greater than UNTL ie ( + 3 ), and

    LSL should be lesser than LNTL ie ( 3 ).

    Even though, (USL LSL) >> 6 , if upper Natural Tolerance Limit(UNTL), UNTL > USL or LNTL < LSL, there will be quality rejections.

    Thus, PCR ie Cp can not truly indicate the process capability, iewhether there will be no

    quality-rejections (defects).

    Cp is corrected to Cpk which truly indicates the Process Capability.

    Cplower

    = LSL = LSL , Cpupper

    = USL = USL LNTL 3 UNTL 3

    Cpk = Min [Cplower , Cpupper]

    Cpk = (1 K) Cp

    Where K is

    Correction

    Factor

    K = I (SC) IS / 2

    = Process CL.

    SC = Specified CL.When sc= Cpk = Cp.

    Cpk can never be > Cp).

  • 7/30/2019 Jpm Tqm Course Mat-5 T-3 Imba 2013

    7/14

    PROCESS CAPABILITY (Cp & Cpk) is less due to two reasons,i) If Process Capability Ratio (PCR orCp) is low, then Process

    Improvement is needed)

    ii) IfCpk is low (then Process Improvement as well as setting ofProcessCenter lineclose to Specified Center line are needed), [because, Process

    Center line ie Design Center line ( ) has moved away from the specifiedCenter line (SC), increasing the value of Correction Factor K].

    Recommendations on Cpk

    Minimum Recommended Cpk : 2

    Ideal Cpk : 5

    Cases with different Cpk & Cp Case 1 When Cpk = Cp < 1 : Process mean is centrally located, K

    =0,

    but the Process is not CAPABLE,

    Quality rejection is inevitable. Case 2 When Cpk = Cp = 1 : Process mean is centrally located, K

    = 0,

    and Specified spread exactlymatches with Process Spread, so theProcess is marginally capable,

    any slight variation will cause rejection.

  • 7/30/2019 Jpm Tqm Course Mat-5 T-3 Imba 2013

    8/14

    Cases with different Cpk & Cp

    Case 3 When Cpk = Cp >> 1 : Process mean is centrally located, K= 0,

    Process is capableand safe,

    less chance of rejections/defectives.

    Case 4 When Cpk < 1,but Cp > 1 : Process mean is not centrally located, though Process is

    Capable,

    the process is not under controlto

    prevent quality rejection.

    Case 5 When Cpk = 1, but Cp > 1 : Process mean is not centrally located, though Process is

    Capable,

    Process is marginally undercontrol& any slight variation will cause

    quality rejection.

    Case 6 When Cpk = 0 : Process Mean (Centerline) comes on USL or LSL

    Case 7 When Cpk < 0 : The Process Mean ie Process CL

    () comes either above USL or belowLSL.

    C ith diff t C k & C

  • 7/30/2019 Jpm Tqm Course Mat-5 T-3 Imba 2013

    9/14

    Cases with different Cpk & Cp

    = Explanation of Case-6 and Case-7

    Case 6 When Cpk = 0 : The Process Mean ie Process CL(X)

    comes either on USL or on LSL.

    [ Cpk = Min [Cplower, Cpupper], so either LSL = 0 or USL = 0

    3 3

    ie =USL or LSL ]

    [then ( sc) = S/2 , K = I ( sc) I =1 then Cpk= (1 K) Cp =0 ]

    S /2

    = Case 7 When Cpk < 0 : The Process Mean ie Process CL (X)

    comes either above USL or below LSL.

    [ Cpk = Min [Cplower, Cpupper], so either ( LSL) < 0 or (USL) < 0 ie Process Center-line is beyond USL or LSL ]

    [when ( sc) > S/2 , K = I ( sc) I >1 then Cpk= (1 K) Cp 0,

  • 7/30/2019 Jpm Tqm Course Mat-5 T-3 Imba 2013

    11/14

    Control Chart

    Problem-1 Page - 1

    For the quality measurement under Inspection process, if the sub-group Sample size is

    14, no. of sub-group is 20, sum of measurements of the sample is 357.50 and Sum of

    the sample-ranges is 9.90, (i) Indicate Center Line, UCL & LCL for X-chart & R- Chart,

    (ii) Comment on the Process Capability and Whether the process is under control, if

    specified dimension is 17.5 0.5. (iii) Suggest possible ways for improving theSituation, (iv) Test the Process Capability with Cpk .

    [Given A2 = 0.18, d2 = 3.735, D3 = 0.41, D4 = 1.59]

    Solution :Process Mean of measurements, = N = 357.50 / 20 = 17.875

    _Mean Range, R = R N = 9.90 / 20 = 0.495

    (i) For X-chart,Central Line = =17.875 , UCL = + A2R= 17.875 + 0.18 x0.495 = 17.9641

    LCL=17.875 0.18 x0.495 = 17.7859

    For R-chart _ _Central Line = R =0.495 , UCL = D4 x R = 1.59 x 0.495 = 0.78705

    _LCL = D3 x R = 0.41 x 0.495 = 0.20295

    _(ii) Standard Deviation of Universe, =R / d2 = 0.495 / 3.735 = 0.13253

    Natural Spread (Band) = 6 = 6 x 0.13253 = 0.79518

    and 3 = 0.39759

    X X

    X X

    S l ti 1( td )

  • 7/30/2019 Jpm Tqm Course Mat-5 T-3 Imba 2013

    12/14

    Solution -1(contd.) (Control Chart) Page-2Upper Natural Tolerance Limit, UNTL = + 3 = 17.875 + 0.39759 = 18.2726

    Lower Natural Tolerance Limit, LNTL = - 3 = 17.875 - 0.39759 = 17.4774

    PROCESS CENTER LINE (Center Line of natural Spread) , = = 17.875,Specified dimension =17.5 0.5Upper Specified Limit, USL = 17.5 + 0.5 = 18.00Lower Specified Limit, LSL = 17.5 - 0.5 = 17.00

    Specified Spread , S= USL LSL = 18 17 =1.0

    Center line of Specified Spread , SC = (USL + LSL )/2 = (18 + 17)/2 =17.5

    Shifting of Process Center Line (from Specified Center Line) = SC= 17.875 17.5 = 0.375

    Process Capability Ratio, Cp = S = 1.0 . =1.257577 >1 but

  • 7/30/2019 Jpm Tqm Course Mat-5 T-3 Imba 2013

    13/14

    Solution -1(contd.) (Control Chart) Page-3Now,

    UNTL > USL , UNTL is not within the specified limit,so considerable

    rejections are expected which indicates that the process is not

    under control.

    LNTL > LSL , LNTL is within the specified limit,so no rejections are

    expected which indicates that the process is under control.

    (iii) Suggestion :

    1) Process is marginally capable, soprocess improvement is

    recommended

    2) Designed Process Center-line must be set very close to

    Center Line of the specified spread

    3) Specified Spread is also to be relaxed to some extent, if

    possible, asCp value is very low (close to 1).

    S ( ) (C C )

  • 7/30/2019 Jpm Tqm Course Mat-5 T-3 Imba 2013

    14/14

    Solution -1(contd.) (Control Chart) Page-4

    (iv) Testing of Process Capability with CpK

    CpK

    Testing :

    CpK = (1 K) Cp = (1 K) . S

    6

    where K = SC = 0.375 = 0.75

    S / 2 1.0 / 2

    CpK = (1 0.75) x 1.257577 = 0.314394 < < 1.0 ,

    so the process is not under control.