Pmp pRESENTATION 012345

57
Project Management Conference PMP Overview PMP Exam Ice Cracker! Dr. Kanabar Note: This workshop is not endorsed by PMI. They don’t endorse any Examination Content.

description

Pmp pRESENTATION 012345

Transcript of Pmp pRESENTATION 012345

Page 1: Pmp pRESENTATION 012345

Project Management ConferencePMP Overview

PMP Exam Ice Cracker!Dr. Kanabar

Note: This workshop is not endorsed by PMI. They don’t endorse any Examination Content.

Page 2: Pmp pRESENTATION 012345

Exam Overview

• Why become PMP certified?• Do you Qualify?• How to Apply?• Schedule the Exam!• Exam Content Outline

Page 3: Pmp pRESENTATION 012345

Use a Spreadsheet

INITIATING PROCESS Hours spentConduct project selection methods to evaluate the feasibility of new products or services 0

Identify key stakeholders and perform analysis to gain buy-in and requirements for the success of the project. 20

Define the scope of the project based on the organization’s need to meet the customer project expectations 40

Develop the project charter and review it with key stakeholders to confirm project scope, risks, issues, assumptions and constraints as well as obtain project charter approval from the project sponsor. 12

Identify and document high level risks, assumptions and constraints using historical data and expert judgment. 12TOTAL HOURS 84

Page 4: Pmp pRESENTATION 012345

The Changes… from PMI website

• “The education and experience eligibility requirements for the existing PMP examination remain appropriate and will not be changed.

• Approximately 30% of the PMP exam content will change.

Page 5: Pmp pRESENTATION 012345

Exam Content

Page 6: Pmp pRESENTATION 012345

PMP Exam Prep

• To earn your Project Management Professional (PMP)® credential, you need to meet the experience and education requirements, and pass the PMP® examination, a 200-question, multiple-choice test.

• You must be prepared – Take courses ahead of time. 35 hrs is not enough.

Page 7: Pmp pRESENTATION 012345

Professional and Social Responsibility content area (cont)

• “Specifically, the Professional and Social Responsibility content area (Domain 6) will now be tested in every domain, rather than as a separate domain.

• Therefore, PMI’s Code of Ethics and Professional Conduct should be viewed as integrated into the day-to-day role of a project manager and important in each phase of the project lifecycle.”

Page 8: Pmp pRESENTATION 012345

Questions from PMI.ORG

• PROCESS/Workflow based questions….• 1. An accepted deadline for a project approaches.

However, the project manager realizes only 75% percent of the work has been completed. The project manager then issues a change request.

• What should the change request authorize? A. Additional resources using the contingency fund B. Escalation approval to use contingency funding C. Team overtime to meet schedule D. Corrective action based on causes

Page 9: Pmp pRESENTATION 012345

Do you know the Terminology?

2. The project manager develops a process improvement plan to encourage continuous process improvement during the life of the project. Which of the following is a valid tool or technique to assist the project manager to assure the success of the process improvement plan? A. Change control system B. Process analysis C. Benchmarking D. Configuration management system

Page 10: Pmp pRESENTATION 012345

PMBOK based questions

3. The project manager meets with the project team to review lessons learned from previous projects. In what activity is the team involved? A. Performance management B. Scope identification C. Risk identification D. Project team status meeting

Page 11: Pmp pRESENTATION 012345

Preparation

• PMBOK must read very well.• Books.. We have Head First PMP available in

the library and PMP by Solomon.• If you are on the road use: PMP Study Guide

by Philips (has a ebook on CD)• PMP by Rita Mulcahy • PMP by Heldman (also on CD)

Page 12: Pmp pRESENTATION 012345

Preparation

• PMP from Crosswind• PMP from Sanghera

Page 13: Pmp pRESENTATION 012345

PMP Recap

First the Processes

Page 14: Pmp pRESENTATION 012345

Initiating Processes

Develop Charter

Integration

Knowledge Area

Identify Stakeholders

Knowledge Area Communication

Page 15: Pmp pRESENTATION 012345

Planning Processes (1 of 2)Develop Project Plan

Collect Requirements Define Scope Create WBS

Define Activities Sequence Activities

Estimate Activity Resources

Estimate Activity Durations

Develop Schedule

Estimate Costs Determine Budgets

Integration

Scope

Time

Cost

Page 16: Pmp pRESENTATION 012345

Planning Processes (2 of 2)Plan Quality

Develop Human Resource Plan

Plan Risk Management Identify Risks

Perform Quantitative Risk Analysis

Perform Qualitative Risk Analysis

Plan Risk Responses

Plan Procurements

Quality

HR

Procurement

Risk

Communications Plan Communications

Page 17: Pmp pRESENTATION 012345

Executing ProcessesDirect & Manage Project

Execution

Perform Quality Assurance

Acquire Team Develop Team

Distribute Information

Manage Project Team

Manage Stakeholders Expectations

Conduct Procurements

Integration

Quality

HR

Procurements

Communications

Page 18: Pmp pRESENTATION 012345

Monitoring & Controlling ProcessesMonitor & Control

Project Work

Verify Scope

Integration

Scope

Cost

Control ScheduleTime

Perform Integrated Change Control

Control Scope

Control Cost

Quality Perform Quality Control

1 of 2

Page 19: Pmp pRESENTATION 012345

Monitoring & Controlling Processes (contd.)

Report Performance

Monitor & Control Risks

Communications

Risk

Administer ProcurementsProcurement

2 of 2

Page 20: Pmp pRESENTATION 012345

Closing Processes

Close Project/PhaseIntegration

Close ProcurementsProcurement

Page 21: Pmp pRESENTATION 012345

Processes

• Better way to digest this…. Is to understand the grid.

Page 22: Pmp pRESENTATION 012345

Knowledge Area Initiating Process

Planning Process Executing Monitor and Control Closing

IntegrationManagement

Develop Project Charter

Develop Project Management Plan

Direct & Manage Project Execution

Monitor & Control WorkPerform Change Control

Close Project or Phase

Scope Management Collect Requirements

Define Scope

Create WBS

Verify Scope

Control Scope

Time Management Define Activities

Sequence Activities

Estimate Activity ResourcesEstimate Activity Durations

Develop Schedule

Control Schedule

Cost Management Estimate Costs

Determine Budget

Control Costs

Quality Management Plan Quality Perform Quality Assurance

Perform Quality Control

Human Resource Management

Develop HR Plan Acquire TeamDevelop TeamManage Team

Project Management Process Groups with Knowledge Mapping (p. 1 of 2)

Page 1

Page 23: Pmp pRESENTATION 012345

Knowledge Area Initiating Process

Planning Process Executing Monitor and Control Closing

Communica-tions Management

Identify Stake-holders

Plan Communications Distribute Information

Manage Stakeholder Expectations

Report Performance

Risk Management Plan Risk Management

Identify Risks

Perform Qualitative Risk Analysis

Perform Quantitative Risk Analysis

Plan Risk Response

Monitor and Control Risks

Procurement Management

Plan Procurements Conduct Procurements Administer Procure-ments

Close Procure-ments

© PMBOK, PMI, 4th Edition, 2008

Page 2

Process Groups with Knowledge Mapping -- Page 2 of 2

Page 24: Pmp pRESENTATION 012345

Using a Spreadsheet to build the Knowledgebase

1 Develop Project Charter Formally authorizes a project or project phase

contract, SOW, enterprise environmental factors, organizational process assets

Project selction methods (benefit/comparative approches), mathematical models), Project management methodology, Project management information systems, expert judgment

Project Charter

Down load from: http://www.projectmanagementinpractice.com and select PMP page

Page 25: Pmp pRESENTATION 012345

Process•“Management steps” to help you to complete your project successfully.•E.g., “define project scope” or “estimate cost”, or “control budget”.

Project Management

Step

Can be Grouped

Page 26: Pmp pRESENTATION 012345

A Process has Inputs and OutputsProcess is executed by a

project manager who uses “Tools and Techniques”

InputsOutputsTools & Techniques

Page 27: Pmp pRESENTATION 012345

Initiating

Executing

Closing

Planning

Page 28: Pmp pRESENTATION 012345

BUG Inc

Page 29: Pmp pRESENTATION 012345

Case Study• Will BUG Inc. leverage external contractors

along with internal resources? In our casestudy “yes”.

• Does BUG Inc have experience with previous migrations? “yes”

• Issues: What considerations should be made for transitioning to a 64-bit platform? Applications might crash! How do we migrate directly from XP to Windows 7 while retaining user-specific files and settings?

Do it as one project or two projects?Project one: Implement a pilot in each department.

Project two: Migrate remaining XP machines.

Page 30: Pmp pRESENTATION 012345

GroupProcesesInitiating

Page 31: Pmp pRESENTATION 012345

Develop Project Charter

Identify Stakeholders

Page 32: Pmp pRESENTATION 012345

Develop Project Charter

Identify Stakeholders

Authority to Start a Project

People who have power to help or

hinder

Page 33: Pmp pRESENTATION 012345

Inputs

Case Study: So what are the Inputs? Let us look at

inputs first….

Page 34: Pmp pRESENTATION 012345

INPUTS

Enterprise Environmental Factors

Contract

Business Case

SOW

Process Assets

Develop Charter

Is the project worth the investment?

Page 35: Pmp pRESENTATION 012345

Description of Products or Services created by sponsor

Statement of Work

External Project: This is turned in

as a “Bid”

Scope + Strategy

Page 36: Pmp pRESENTATION 012345

How do we do business?Various departments & how they operate?Governmental/Industry Standards

Marketplace ConditionsAssigning ResourcesCulture & Infrastructure

How does BUG Inc conduct

business?

Page 37: Pmp pRESENTATION 012345

Procedures/Standards

Tools and Templates

Historical Information

Information Systems

Organizational Process Assets

Knowledgebase

How does BUG Inc execute

projects?

Of Course, they use PMBOK ®

Page 38: Pmp pRESENTATION 012345

Expert Judgment

Tools & Techniques

Provided by any group or

individual with specialized knowledge

Experts: Internal units, consultants, stakeholders, industry groups, SME, PMO

Page 39: Pmp pRESENTATION 012345

Output

Project Charter

Output

Page 40: Pmp pRESENTATION 012345

CHARTER: Project OS Migration (POSM)

Start Date/End Date … Project Manager: ……

Project Purpose / Justification

Measurable Project Objectives

Success Criteria

Assumptions, Known Issues and Risks

Summary: Milestone Schedule, Budget

Signatures of all stakeholders

Released by BUG Inc CEO

Page 41: Pmp pRESENTATION 012345

C o n c e p tP r o c e s s F l o w

P r o c e s s N a m e

DEVELOP CHARTER

INPUTS

ENTERPRISE DATA

PROCESS ASSETS

BUSINESS CASE

TOOLS & TECHNIQUES EXPERT JUDGMENT

OUTPUTS PROJECT CHARTER

Recap

Page 42: Pmp pRESENTATION 012345

Inputs

Let us look at inputs first….

Page 43: Pmp pRESENTATION 012345

Inputs

Enterprise Environmental Factors

Procurement Documents

Charter

Process Assets

BUG Inc has subcontracted XP migration

Identify Stakeholders

Page 44: Pmp pRESENTATION 012345

Stakeholder AnalysisExpert Judgment

Tools & Techniques

Page 45: Pmp pRESENTATION 012345

Stakeholder Analysis

Keep Satisfied

Manage Closely

MonitorKeep

InformedPo

wer

Interest in Project Execution & Result

Ref: p.249 PMBOK ® - 4th Edition

HIGHMedium

MediumLOW

Page 46: Pmp pRESENTATION 012345

Output

Stakeholder Register

Output 1

Page 47: Pmp pRESENTATION 012345

Stakeholder Register

Name: Nichole – Internal Stakeholder

Goal: Make sure that there is no disruption during migration. Expectations: Has access back to her PC within half a day.Constraints: Busy might not have much time for general training. But is comfortable with Technology.

Page 48: Pmp pRESENTATION 012345

Stakeholder Register

Name: Supplier – External StakeholderResponsibility: Provide WIN 7 license.Goal: Make sure that there is no disruption during migration. Expectations: Licenses available before execution phase.Constraints: None

Page 49: Pmp pRESENTATION 012345

Output

Stakeholder Management Strategy

Output 2

Page 50: Pmp pRESENTATION 012345

Stakeholder Management Strategy 2 of 2

Stakeholder Rating:High/Med/Low

Assessment Potential Strategy

Page 51: Pmp pRESENTATION 012345

C o n c e p tP r o c es s

F l o w

P ro c es s

N a m e

IDENTIFY STAKEHOLDERS

INPUTS

CHARTER

PROCUREMENT DOCS

ENTERPRISE FACTORS

ORG. PROCESS ASSETS

TOOLS & TECHNIQUES

EXPERT JUDGMENT

STAKEHOLDER ANALYSIS

OUTPUTS- STAKEHOLDER REGISTER- STAKEHOLDER MGMT STRATEGY

Recap

Page 52: Pmp pRESENTATION 012345

What about Knowledge

Areas?

Develop Project

Charter Identify

Stakeholders

Communications Management

Integration Management

Page 53: Pmp pRESENTATION 012345

We have focused on process & process groups.

We introduced two processes in the Initiating phase

Develop Project Charter Key Output = Project Charter

Identify StakeholdersKey Outputs = Stakeholder Register and Stakeholder Management Strategy

Summary

Page 54: Pmp pRESENTATION 012345

The Key Study Points

Page 55: Pmp pRESENTATION 012345

Organizational Structure

• Functional• Weak Matrix• Balanced Matrix• Strong Matrix• Projectized

Page 56: Pmp pRESENTATION 012345

Selecting a Project

• Benefit Measurement Methods– Scoring Models, Cost Benefit

• Constrained Optimization– Linear, Integer, dynamic programming

Page 57: Pmp pRESENTATION 012345

Exercise

• Create a Spreadsheet for the Initiation Phase