Presentation On Small Hydropower Development in Nepal Sanjeev Pokhrel Energy Development Officer Rural Energy Development Program(REDP) Nepal Int. Training on Real Time Digital Simulators 8 th -19 th July,2010 IIT Roorkee,Uttharakhanda, India.

description

Presentation presented at IIT, Roorkee

Transcript of Small Hydro presentation Nepal

Page 1: Small Hydro presentation Nepal

Presentation On

Small Hydropower Development in Nepal

Sanjeev PokhrelEnergy Development Officer

Rural Energy Development Program(REDP)Nepal

Int. Training on Real Time Digital Simulators8th -19th July,2010

IIT Roorkee,Uttharakhanda, India.

Page 2: Small Hydro presentation Nepal

Land Lock Country

Land Area:147,181 sq.km

Literacy Rate: 48.6%

Political System: Federal Democratic Republic

Page 3: Small Hydro presentation Nepal

Major River Schemes :◦Sapta Koshi : Eastern Nepal◦Narayani (Gandaki ) : Central Nepal◦Karnali : Far-Western ◦Mahakali : Far – Western

More than 6,000 rivers and rivulets

An annual 224 billion cubic meter of surface run-off with over 20,000 liters of water available to a person per day

Page 4: Small Hydro presentation Nepal

ENERGY CONSUMPTION BY TYPE IN 2006

Page 5: Small Hydro presentation Nepal

Around 1 million GW h of electricity Total Hydropower Potential : 83,000 MW Proposed Major Power Plants:

◦Karnali Chisapani : 10800MW◦Pancheshwor : 6400 MW◦Sapta Koshi : 3000 MW◦Sunkoshi Storage -2 : 1100 MW

Page 6: Small Hydro presentation Nepal

On the Basis of Capacity:• Pico Hydro : less than 5 KW• Micro Hydropower plants : up to 100 kW• Mini Hydropower plants : 101 KW to 1 MW• Small Hydropower plants : 1 MW to 25 MW

( previously only up to 10MW)• Large Hydropower plants : >25 MW

Page 7: Small Hydro presentation Nepal

Pharping (500 KW) @ 1911 AD

Only 40% of people have access to electricity

Among them, Only 7% of rural people have access to electricity

Page 8: Small Hydro presentation Nepal

Overall Scenario of Power Projects in Nepal Total Major Hydro Grid Connected 472.994MW Total Small Hydro Isolated 4.536MW Total Hydro NEA 477.530MW Total hydro IPP 158.315MW Total Hydro -Nepal 635.845MW Total thermal (NEA) 53.410MW Total Solar (NEA) 100kW Total Installed Capacity (including Private and Others) 689.355 MW

Page 9: Small Hydro presentation Nepal

Peak Demand : 812 MW

Energy Demand: 3859 Gwh

Energy Supply : 3130 Gwh

Annual demand growth:10%

Page 10: Small Hydro presentation Nepal

MoEnMoE

AEPC

IPPs

Page 11: Small Hydro presentation Nepal

PPP (Public Private Partnership ) Modality◦ Approach to encourage Local People in the

development of SHP MINI Grid Approach

◦ To develop local grid to make pool of small power generation which ultimately helps to stabilize the local electricity supply system

◦ AEPC have launched MGSP (Mini Grid Support Program ) to enhance this approach

Page 12: Small Hydro presentation Nepal

Agencies:◦NEA Small Hydropower and Rural Electrification

Department (SHPRED) Community Rural Electrification

Department ( CRED )◦AEPC Energy Sector Assistance Program (ESAP ) Rural Energy Development Program

(REDP )

Page 13: Small Hydro presentation Nepal

Context:◦At present only about 7% of the people

living in rural areas getting electricity services

Major challenges ◦Poor Infrastructure,

◦lack of capital and coordination◦Unprofitable

Low consumption per household High connection cost, and

Low initial consumer connection ratio.

Page 14: Small Hydro presentation Nepal

Basically divided into two sub-sectors◦ the grid-based (on-grid) and ◦ the isolated (off-grid)

Grid-based electrification :◦Carried out through the extension of the national grid ◦By Nepal Electricity Authority (NEA)

The isolated (local) grids based Electrification◦Supplied by mini, micro and small hydro plants ◦By Alternative Energy Promotion Centre (AEPC)

Several Independent Power Producers (IPPs) and NGOs are engaged in rural electrification with assistance from donors.

Page 15: Small Hydro presentation Nepal

Responsible for:◦ Construction, Operation and Maintenance of isolated Small

Hydropower Plants,◦ Execution of Rural Electrification, and Extension of the National

Grid to remote hilly regions and◦ Establishment of distribution system

Under the Department◦ 26 small hydropower plants 7 leased out to private firms &

4 have been leased out to the consumer communities, 2 Solar Plants

◦ 7 Distribution branch offices Covering 27 districts in 12 zones of the country

Page 16: Small Hydro presentation Nepal

Established in February 2003 to carry out community based electrification works in an

organized way

In order to promote community participation, declared a policy

80 % of the capital cost of electrification by the government,

20% of the cost by the community

To promote and regulate the activity, NEA has enacted "Community Distribution Regulation-2060"

Page 17: Small Hydro presentation Nepal

•Alternative Energy Promotion Center(AEPC)•Ministry of Environment

•Rural Energy Development Program(REDP)

•Energy Sector Assistance Program (ESAP)

UNDP, World Bank Denmark, Norway.

Page 18: Small Hydro presentation Nepal

Acute shortage of electricity , though Nepal is the richest country in the world after Brazil in water resources

Require optimal resources mobilization to get safe and reliable electricity for urban as well as rural people

Pioneer in Micro hydro Technology.

Page 19: Small Hydro presentation Nepal
Page 20: Small Hydro presentation Nepal
Page 21: Small Hydro presentation Nepal

Pharping Micro Hydro Scheme, Nepal First Hydro Scheme,1911

Page 22: Small Hydro presentation Nepal
Page 23: Small Hydro presentation Nepal
Page 24: Small Hydro presentation Nepal
Page 25: Small Hydro presentation Nepal

Thank You !