    Wiley 2010 1

    Chapter 13 AggregatePlanning

    Operations Managementby

    R. Dan Reid & Nada R. Sanders4th Edition Wiley 2010

  • 8/10/2019 presentasi Manamen Operasional

    2/28

    Wiley 2010 2

    Learning Objectives Explain business planning

    Explain sales and operations planning

    Identify different aggregate planning strategies & optionsfor changing demand and/or capacity in aggregate plans

    Develop aggregate plans, calculate associated costs, and

    evaluate the plan in terms of operations, marketing,

    finance, and human resources

    Describe differences between aggregate plans for service

    and manufacturing companies

  • 8/10/2019 presentasi Manamen Operasional

    3/28

    Wiley 2010 3

    The Role of Aggregate

    Planning Integral to part of the business planning

    process

    Supports the strategic planAlso known as the production plan

    Identifies resources required for

    operations for the next 6-18 months Details the aggregate production rate and

    size of work force required

  • 8/10/2019 presentasi Manamen Operasional

    4/28

    Wiley 2010 4

    The Role of the Aggregate Plan

  • 8/10/2019 presentasi Manamen Operasional

    5/28

    Wiley 2010 5

    Types of Aggregate Plans Level Aggregate Plans

    Maintains a constant workforce

    Sets capacity to accommodate average demand Often used for make-to-stock products like appliances

    Disadvantage- builds inventory and/or uses back orders

    Chase Aggregate Plans

    Produces exactly what is needed each period

    Sets labor/equipment capacity to satisfy period demands

    Disadvantage- constantly changing short term capacity

  • 8/10/2019 presentasi Manamen Operasional

    6/28

    Wiley 2010 6

    Level Plan Example Level production rate= 28,000 units/7 periods= 4000 units

    Level workforce= (4000 units x .64 std.)/160 = 16 people

  • 8/10/2019 presentasi Manamen Operasional

    7/28

    Wiley 2010 7

    Chase Plan Example Chase hires and fires staff to exactly meet each periods

    demand Period 1 = (500 units x .64 std.)/160 = 2 people, need to fire

    16 people

  • 8/10/2019 presentasi Manamen Operasional

    8/28

    Wiley 2010 8

    Types of Aggregate Plans cont Hybrid Aggregate Plans

    Uses a combination of options

    Options should be limited to facilitate execution

    May use a level workforce with overtime & temps

    May allow inventory buildup and some backordering

    May use short term sourcing

  • 8/10/2019 presentasi Manamen Operasional

    9/28

    Wiley 2010 9

    Aggregate Planning Options Demand-based options

    Reactive:uses finished goods inventories and

    backorders for fluctuations Proactive:shifts the demand patterns to minimize

    fluctuations e.g. early bird dinner prices at a restaurant

    Capacity-based options

    Changes output capacity to meet demand

    Uses overtime, under time, subcontracting, hiring, firing,and part-timerscost and operational implications

  • 8/10/2019 presentasi Manamen Operasional

    10/28

    Wiley 2010 10

    Evaluating the Current SituationImportant to evaluate current situation in

    terms of: Point of Departure

    Current % of normal capacity Options are different depending on present situation

    Magnitude of change Larger changes need more dramatic measures

    Duration of change Is the length of time a brief seasonal change? Is a permanent change in capacity needed?

  • 8/10/2019 presentasi Manamen Operasional

    11/28

    Wiley 2010 11

    Developing the Aggregate PlanStep 1-Choose strategy: level, chase, or Hybrid

    Step 2-Determine the aggregate production rate

    Step 3-Calculate the size of the workforceStep 4-Test the plan as follows:

    Calculate Inventory, expected hiring/firing, overtime needs

    Calculate total cost of plan

    Step 5-Evaluate performance: cost, service,human resources, and operations

  • 8/10/2019 presentasi Manamen Operasional

    12/28

    Wiley 2010 12

    Aggregate Plans for Companies

    with Tangible ProductsPlan A:Level aggregate plan using

    inventories and back orders

    Plan B: Chase aggregate plan using hiringand firing

  • 8/10/2019 presentasi Manamen Operasional

    13/28

  • 8/10/2019 presentasi Manamen Operasional

    14/28

    Wiley 2010 14

    Plan A- Level Using Inventory &

    BackordersFirst

    calculatethe level

    productionrate

    (14400/8=

    1800)

  • 8/10/2019 presentasi Manamen Operasional

    15/28

    Wiley 2010 15

    Plan AEvaluation Fill rate is 83.9%

    Fill rate is likely to low

    Inventory levels seem to be okay

    Human resources fires two employees

  • 8/10/2019 presentasi Manamen Operasional

    16/28

    Wiley 2010 16

    Plan BChase AggregatePlan Using Hiring and Firing

    Using the sameproblem dataas previous

    example,develop achaseaggregate planusing hires and

    fires but noovertimeproduction.

  • 8/10/2019 presentasi Manamen Operasional

    17/28

    Wiley 2010 17

    Plan BEvaluation

    Plan B costs slightly less than the level plan.

    Hiring demands ranges from two in November

    to thirty-four in February Utilization is highest, 70.6%, in December and

    even lower in the other months

    Space and equipment are underutilized in everyother month of the plan

  • 8/10/2019 presentasi Manamen Operasional

    18/28

  • 8/10/2019 presentasi Manamen Operasional

    19/28

    Wiley 2010 19

    Problem Data for Plans C, D, and E

    45

    67

    8

    910

    111213

    1415

    1617

    1819

    202122

    23

    2425

    26

    2728

    A B

    Cost Data

    Regular time labor cost per hour $8.00

    Overtime labor cost per hour $12.00Subcontracting cost per unit (labor only) $60.00

    Hiring cost per employee $250.00

    Firing cost per employee $150.00

    Capacity Data

    Beginning workforce (employees) 60Service standard per call (hours) 4

    Regular time available per period (hours) 160Overtime available per period (hours) 24

    Demand Data (calls)

    Period 1 2400Period 2 1560

    Period 3 1200Period 4 2040Period 5 2760

    Period 6 1680

    Period 7 1320Period 8 2400

    Total Number of Periods 8

  • 8/10/2019 presentasi Manamen Operasional

    20/28

    Wiley 2010 20

    Plan CLevel Aggregate Plan withNo Back Orders or Tangible Product

    Staff of 69 people creates excessive UT (averages 30% UT)

    Cost per service call is $46.15($708,000 Divided by 15360 calls)

  • 8/10/2019 presentasi Manamen Operasional

    21/28

    Wiley 2010 21

    Plan DHybrid Aggregate Plan UsingInitial Workforce and OT as Needed

    Costs reduced by $77K and under time to an average of 20%

    Cost per service call reduced to $41.13 (-$5.02)

    Pl E Ch A t Pl f

  • 8/10/2019 presentasi Manamen Operasional

    22/28

    Wiley 2010 22

    Plan EChase Aggregate Plan forNontangible Products Using Hiringand Firing

    Total cost reduced by $114K over Plan F, utilization improved to100%, and cost per service call now $33.72 (-$7.41)

    Workforce fluctuates from 30-69 people- morale problems

    Solution?? Compare smaller permanent workforce, more OT??

  • 8/10/2019 presentasi Manamen Operasional

    23/28

  • 8/10/2019 presentasi Manamen Operasional

    24/28

    Wiley 2010 24

    Aggregate Planning within OM: How it allfits together

    Aggregate planning determines the resources available to operationsto support the overall business plan. It is critical that accurate demandforecasts be available (Ch 8) so that a reasonable production plan canbe developed. A company needs to determine the aggregate

    production rate output required to determine the appropriate size ofthe workforce. After these determinations have been made, the company can

    calculate its inventory levels, back-order levels, capacity requirements,and customer service levels. If the plan requires seven-day-a-weekoperations, appropriate staff schedules need to be developed (Ch 15).

    The aggregate plan specifies the number of employees needed. Thisallows company to determine how much equipment and workspace isneeded, as well as to provide the input needed for developing aworkplace layout (Ch 9) within the operations area. Aggregateplanning provides the resources needed by operations to achieve thecompanys strategic objective.

  • 8/10/2019 presentasi Manamen Operasional

    25/28

    Wiley 2010 25

    Aggregate Planning Across theOrganization

    Aggregate planning, MPS, and rough-cutcapacity affection functional areas throughoutthe organization Accounting is affected because aggregate plan

    details the resources needed by operations

    Marketing as the aggregate plan supports themarketing plan

    Information systems maintains the databases thatsupport demand forecasts and other suchinformation

  • 8/10/2019 presentasi Manamen Operasional

    26/28

    Wiley 2010 26

    Chapter 13 Highlights

    Planning begins with the development of thestrategic business plan that provides companydirection & objectives for the next two to ten years.

    Sales and operations planning integrates plans fromthe other functional areas and regularly evaluatescompany performance.

    The level aggregate plan maintains the same sizeworkforce and produces the same output eachperiod. Inventories and backorders absorbfluctuations in demand. Chase aggregate planschange the capacity each period to match demand.

  • 8/10/2019 presentasi Manamen Operasional

    27/28

    Wiley 2010 27

    Chapter 13 Highlights cont

    Demand patterns can be smoothed throughpricing incentives, reduced prices for out-of-

    season purchases, or nonprime service times. The difference in aggregate planning for

    companies that do not provide a tangible

    product is that the option to use inventoriesis not available

  • 8/10/2019 presentasi Manamen Operasional

    28/28

    Chapter 13 Homework Hints

    All problems are based on The BackPack Company.

    Problem 13.1: level strategy allowing backorders. Calculatethe production rate and workforce level. Develop the plan,

    calculate the costs, and evaluate the strategy. Problem 13.3-4: chase strategy. 3) Calculate the production

    rate and workforce levels. 4) Develop the plan, calculate thecosts, and evaluate the strategy.

    Problem 13.5: chase strategy with overtime. Calculate theproduction rate and workforce levels. Develop the plan,calculate the costs, and evaluate the strategy.