PRESUPUESTO ADICIONAL N°02:VEREDAS,ESTACIONAMIENTO Y PAVIMENTACION UBICACIÓN: LOCALIDAD DISTRITO PROVINCIA DEPARTAMENTO DIMENSIONES/ELEMENTOS LONG ANCHO ALTO ESPESOR AREA VOLUMEN N°PART. DESCRIPCION (m) (m) (m) (m) HU.1 OBRAS PROVISIONALES,TRABAJOS PRELIMINARES,SEGURIDAD Y SALUD HU.1.1 TRABAJOS PRELIMINARES HU.1.1.1 LIMPIEZA DEL TERRENO HU.1.1.1.ELIMINACION DE BASURA Y ELEMENTOS SUELTOS Y LIVIANOS PAVIMENTO CALLE NAYLAMP(AREA CAD) 1.00 0.40 420.48 168.19 1.00 ESTACIONAMIENTO(AREA CAD) 1.00 41.15 5.00 0.40 205.75 82.30 1.00 HU.1.2 DEMOLICIONES VEREDAS(AREA CAD) CALLE GRAU-VEREDA 1.00 2.00 0.10 78.65 7.87 1.00 CALLE SUCRE-VEREDA 1.00 2.00 0.10 115.83 11.58 1.00 PASAJE(AQUÍ NO HAY VEREDA EXISTENTE) CALLE NAYLAMP-VEREDA 1.00 2.00 0.10 158.22 15.82 1.00 HU.1.3 TRAZOS,NIVELES Y REPLANTEO HU.1.3.1 TRAZOS,NIVELES Y REPLANTEO PRELIMINAR VEREDAS(AREA CAD) CALLE GRAU-VEREDA 1.00 78.65 1.00 CALLE SUCRE-VEREDA 1.00 115.83 1.00 PASAJE 1.00 130.24 1.00 PAVIMENTO CALLE NAYLAMP(AREA CAD) 1.00 420.48 1.00 ESTACIONAMIENTO(AREA CAD) 1.00 41.15 5.00 205.75 1.00 HU.1.3.2 REPLANTEO DURANTE EL PROCESO 1.00 1.00 VEREDAS(AREA CAD) CALLE GRAU-VEREDA 1.00 78.65 1.00 CALLE SUCRE-VEREDA 1.00 115.83 1.00 PASAJE 1.00 130.24 1.00 PAVIMENTO CALLE NAYLAMP(AREA CAD) 1.00 420.48 1.00 ESTACIONAMIENTO(AREA CAD) 1.00 41.15 5.00 205.75 1.00 HU.2 PISTAS Y VEREDAS HU.2.1 MOVIMIENTO DE TIERRA HU.2.1.1 CORTE CON ELIMINACION LATERAL VEREDAS(AREA CAD) CALLE GRAU-VEREDA 1.00 0.20 78.65 1.00 CALLE SUCRE-VEREDA 1.00 0.20 115.83 1.00 PASAJE 1.00 0.20 130.24 1.00 PAVIMENTO CALLE NAYLAMP(AREA CAD) 1.00 0.40 420.48 1.00 ESTACIONAMIENTO(AREA CAD) 1.00 41.15 5.00 0.40 205.75 1.00 JARDINES(MATERIAL) 1.00 0.20 58.44 11.69 1.00 HU.2.1.3 ELIMINACION DE MATERIAL EXCEDENTE 1.25 ESP. 327.13 1.00 HU.2.2 BASE HU.2.2.1 BASE O AFIRMADO(PAVIMENTO+ESTACIONAMIENTO) ESTACIONAMIENTO 1.00 0.20 205.75 1.00 PAVIMENTO 1.00 0.20 420.48 1.00 HU.2.3 VEREDAS LOSA CALLE GRAU-VEREDA HU.2.3.1 CONCRETO F´C=175KG/CM2 1.00 0.10 78.65 1.00 HU.2.3.2 ENCOFRADO Y DESENCOFRADO DE VEREDAS UÑA 32.93 0.40 13.17 1.00 TRANSVERSALES CADA 3 ML 2.00 0.10 0.20 11.00 HU.2.3.3 SELLADO DE JUNTAS EN VEREDAS 1.00 32.93 1.00 HU.2.3.4 PISO FROTACHADO CEMENTO PULIDO EN VEREDAS 1.00 32.93 2.90 95.50 1.00 UÑA CALLE GRAU-VEREDA HU.2.3.1 CONCRETO F´C=175KG/CM2 1.00 32.93 0.20 0.30 1.98 1.00 LOSA CALLE SUCRE-VEREDA HU.2.3.1 CONCRETO F´C=175KG/CM2 1.00 0.10 115.83 11.58 1.00 HU.2.3.2 ENCOFRADO Y DESENCOFRADO DE VEREDAS UÑA 52.70 0.40 21.08 1.00 TRANSVERSALES CADA 3 ML 2.13 0.10 0.21 17.57 HU.2.3.3 PISO FROTACHADO CEMENTO PULIDO EN VEREDAS 1.00 52.70 2.13 112.25 1.00 HU.2.3.4 SELLADO DE JUNTAS EN VEREDAS 1.00 52.70 1.00 UÑA CALLE SUCRE-VEREDA REPET.ELEM FACTOR CANT. (m 2 ) (m 3 )

description

BUENOOO

Transcript of Metrados Propuesta Final

METRADOS

UBICACIN:LOCALIDADDISTRITOPROVINCIA DEPARTAMENTODIMENSIONES/ELEMENTOSN REPET.ELEMMETRADOFACTOR CANT.LONGANCHO ALTOESPESORAREAVOLUMENNPART.DESCRIPCION(m)(m)(m)(m)(m2)(m3)UNIDADPARCIALTOTALHU.1OBRAS PROVISIONALES,TRABAJOS PRELIMINARES,SEGURIDAD Y SALUDHU.1.1TRABAJOS PRELIMINARESHU.1.1.1LIMPIEZA DEL TERRENOHU.1.1.1.1.ELIMINACION DE BASURA Y ELEMENTOS SUELTOS Y LIVIANOSPAVIMENTO CALLE NAYLAMP(AREA CAD)1.000.40420.48168.191.00(m3)168.19ESTACIONAMIENTO(AREA CAD)1.0041.155.000.40205.7582.301.00(m3)82.30250.49HU.1.2DEMOLICIONESVEREDAS(AREA CAD)CALLE GRAU-VEREDA1.002.000.1078.657.871.00(m3)7.87CALLE SUCRE-VEREDA1.002.000.10115.8311.581.00(m3)11.58PASAJE(AQU NO HAY VEREDA EXISTENTE)CALLE NAYLAMP-VEREDA1.002.000.10158.2215.821.00(m3)15.8235.27HU.1.3TRAZOS,NIVELES Y REPLANTEOHU.1.3.1TRAZOS,NIVELES Y REPLANTEO PRELIMINARVEREDAS(AREA CAD)CALLE GRAU-VEREDA1.0078.651.00(m2)78.65CALLE SUCRE-VEREDA1.00115.831.00(m2)115.83PASAJE1.00130.241.00(m2)130.24PAVIMENTO CALLE NAYLAMP(AREA CAD)1.00420.481.00(m2)420.48ESTACIONAMIENTO(AREA CAD)1.0041.155.00205.751.00(m2)205.75950.95HU.1.3.2REPLANTEO DURANTE EL PROCESO1.001.00(m2)VEREDAS(AREA CAD)CALLE GRAU-VEREDA1.0078.651.00(m2)78.65CALLE SUCRE-VEREDA1.00115.831.00(m2)115.83PASAJE1.00130.241.00(m2)130.24PAVIMENTO CALLE NAYLAMP(AREA CAD)1.00420.481.00(m2)420.48ESTACIONAMIENTO(AREA CAD)1.0041.155.00205.751.00(m2)205.75950.95HU.2PISTAS Y VEREDASHU.2.1MOVIMIENTO DE TIERRAHU.2.1.1CORTE CON ELIMINACION LATERAL VEREDAS(AREA CAD)CALLE GRAU-VEREDA1.000.2078.651.00(m3)15.73CALLE SUCRE-VEREDA1.000.20115.831.00(m3)23.17PASAJE1.000.20130.241.00(m3)26.05PAVIMENTO CALLE NAYLAMP(AREA CAD)1.000.40420.481.00(m3)168.19ESTACIONAMIENTO(AREA CAD)1.0041.155.000.40205.751.00(m3)82.30JARDINES(MATERIAL)1.000.2058.4411.691.00(m3)11.69327.13

HU.2.1.3ELIMINACION DE MATERIAL EXCEDENTE 1.25ESP.327.131.00(m3)408.91408.91

HU.2.2BASEHU.2.2.1BASE O AFIRMADO(PAVIMENTO+ESTACIONAMIENTO)ESTACIONAMIENTO1.000.20205.751.00(m2)205.75PAVIMENTO1.000.20420.481.00(m2)420.48626.23

HU.2.3VEREDASLOSACALLE GRAU-VEREDAHU.2.3.1CONCRETO FC=175KG/CM2 1.000.1078.651.00(m3)7.87HU.2.3.2ENCOFRADO Y DESENCOFRADO DE VEREDAS UA32.930.4013.171.00(m2)13.17TRANSVERSALES CADA 3 ML2.000.100.2011.00(m2)2.2015.37HU.2.3.3SELLADO DE JUNTAS EN VEREDAS1.0032.931.00(m)32.93HU.2.3.4PISO FROTACHADO CEMENTO PULIDO EN VEREDAS1.0032.932.9095.501.00(m2)95.50UACALLE GRAU-VEREDAHU.2.3.1CONCRETO FC=175KG/CM2 1.0032.930.200.301.981.00(m3)1.98LOSACALLE SUCRE-VEREDAHU.2.3.1CONCRETO FC=175KG/CM2 1.000.10115.8311.581.00(m3)11.58HU.2.3.2ENCOFRADO Y DESENCOFRADO DE VEREDAS UA52.700.4021.081.00(m2)21.08TRANSVERSALES CADA 3 ML2.130.100.2117.57(m2)3.6924.77HU.2.3.3PISO FROTACHADO CEMENTO PULIDO EN VEREDAS1.0052.702.13112.251.00(m2)112.25HU.2.3.4SELLADO DE JUNTAS EN VEREDAS1.0052.701.00(m)52.70UACALLE SUCRE-VEREDAHU.2.3.1CONCRETO FC=175KG/CM2 1.0052.700.200.303.161.00(m3)3.16LOSAPASAJEHU.2.3.1CONCRETO FC=175KG/CM2 1.000.10130.2413.021.00(m3)13.02HU.2.3.2ENCOFRADO Y DESENCOFRADO DE VEREDAS UA33.410.4013.361.00(m2)13.36TRANSVERSALES CADA 3 ML3.000.100.3011.14(m2)3.3416.70HU.2.3.3PISO FROTACHADO CEMENTO PULIDO EN VEREDAS1.0033.413.00100.231.00(m2)100.23HU.2.3.4SELLADO DE JUNTAS EN VEREDAS1.0033.411.00(m)33.41UAPASAJEHU.2.3.1CONCRETO FC=175KG/CM2 1.0033.410.200.100.671.00(m3)0.67RESUMENCONCRETO FC=175KG/CM2 (m3)38.28ENCOFRADO Y DESENCOFRADO DE VEREDAS(m2)56.84PISO FROTACHADO CEMENTO PULIDO EN VEREDAS(m2)307.98SELLADO DE JUNTAS EN VEREDAS(m)119.04

HU.2.4PISTASHU.2.4.1PAVIMENTO DE CONCRETO+ESTACIONAMIENTOHU.2.2.3CONCRETO F'C=210KG/CM2 PARA PAVIMENTO+ESTACIONAMIENTO1.00626.231.00(m2)626.23626.23HU.2.2.4ENCOFRADO Y DESENCOFRADO PAOS PAVIMENTO+ESTACIONAMIENTO1.00459.250.2091.851.00(m2)91.8591.85HU.2.4.2SELLADO DE JUNTAS EN PAVIMENTO+ESTACIONAMIENTO1.00459.251.00(m)459.25459.25

HU.2.5SARDINELESHU.2.5.1CONCRETO PARA SARDINEL1.00153.630.150.306.911.00(m3)6.916.91HU.2.5.2ENCOFRADO PARA SARDINEL1.00153.630.2030.731.00(m2)30.7330.73HU.2.5.3TARRAJEO EN CARA INTERIOR Y EXTERIOR DE SARDINELES1.00153.630.1523.041.00(m2)23.0423.04HU.2.5.3SELLADO DE JUNTAS EN SARDINEL1.00153.631.00(m)153.63153.63

HU.2.6BARANDAS DE ESCALERAS DE TUBERIA DE 3"1.0025.481.00(m)25.4825.48

HU.2.7RAMPAS

HU.2.7.1CONCRETO F'C=175KG/CM2 EN RAMPASRAMPA CALLE SUCRE P=10%1.001.502.900.150.331.00(m3)0.33RAMPA CALLE SUCRE P=12%(MARTILLO)1.001.251.000.150.091.00(m3)0.09RAMPA CALLE GRAU P=10%1.001.502.900.150.331.00(m3)0.33RAMPA CALLE GRAU P=10%1.005.202.290.432.541.00(m3)2.54RAMPA CALLE NAYLAMP P=10%(MARTILLO)1.002.301.000.230.261.00(m3)0.26RAMPA CALLE NAYLAMP P=10%1.001.701.000.250.211.00(m3)0.21RAMPA CALLE NAYLAMP P=10%1.003.401.000.490.841.00(m3)0.84RAMPA PASAJE P=6.3%1.003.0010.000.639.451.00(m3)9.4514.05

HU.2.7.2ENCOFRADO PARA RAMPASRAMPA CALLE SUCRE P=10%1.001.490.150.112.00(m2)0.22RAMPA CALLE SUCRE P=12%(MARTILLO)1.001.240.150.092.00(m2)0.18RAMPA CALLE GRAU P=10%1.001.490.150.112.00(m2)0.22RAMPA CALLE GRAU P=10%1.005.180.150.402.00(m2)0.80RAMPA CALLE NAYLAMP P=10%(MARTILLO)1.002.290.230.262.00(m2)0.52RAMPA CALLE NAYLAMP P=10%1.001.680.250.212.00(m2)0.42RAMPA CALLE NAYLAMP P=10%1.003.360.490.822.00(m2)1.64RAMPA PASAJE P=6.3%1.009.980.633.142.00(m2)6.2810.28HU.2.7.3BRUAS DE 2CM CADA 0.15M1.002.905.00(m)14.501.001.004.17(m)4.171.002.905.00(m)14.501.002.2917.33(m)39.691.001.007.67(m)7.671.001.005.67(m)5.671.001.0011.33(m)11.331.0010.0010.00(m)100.00197.53

HU2.8JARDINES(MATERIAL)1.000.2058.4411.691.00(m3)11.6911.69

HU3.0.GRADASHU3.0.1CONCRETO F'C=175KG/CM2 EN GRADAS1.0011.850.250.080.241.00(m3)0.241.002.371.500.150.531.00(m3)0.531.009.680.250.080.191.00(m3)0.191.002.421.200.150.441.00(m3)0.441.006.480.500.230.751.00(m3)0.751.003.241.100.150.531.00(m3)0.532.68

HU3.0.2ENCOFRADO PARA GRADAS1.001.502.373.561.00(m2)3.561.001.202.422.901.00(m2)2.901.001.103.243.562.00(m2)7.1213.58

HU4.0PINTURAHU4.0.1PINTURA PARA VEREDASVEREDASCALLE GRAU-VEREDA1.0032.930.4514.821.00(m2)14.82CALLE SUCRE-VEREDA1.0052.700.4523.721.00(m2)23.72PASAJE1.0033.410.4515.031.00(m2)15.0353.57

HU4.0.2MARCAS EN EL PAVIMENTOPAVIMENTO CALLE NAYLAMP1.0038.100.103.811.00(m2)3.81ESTACIONAMIENTO1.00167.000.1016.701.00(m2)16.7020.51

PRESUPUESTO ADICIONAL N02:VEREDAS,ESTACIONAMIENTO Y PAVIMENTACION

RESUMEN DE METRADOS

METRADO

NPART.DESCRIPCIONUNIDADTOTALHU.1OBRAS PROVISIONALES,TRABAJOS PRELIMINARES,SEGURIDAD Y SALUDHU.1.1TRABAJOS PRELIMINARESHU.1.1.1LIMPIEZA DEL TERRENOHU.1.1.1.1.ELIMINACION DE BASURA Y ELEMENTOS SUELTOS Y LIVIANOS(m3)250.49HU.1.2DEMOLICIONES(m3)35.27HU.1.3TRAZOS,NIVELES Y REPLANTEOHU.1.3.1TRAZOS,NIVELES Y REPLANTEO PRELIMINAR(m2)950.95HU.1.3.2REPLANTEO DURANTE EL PROCESO(m2)950.95HU.2PISTAS Y VEREDASHU.2.1MOVIMIENTO DE TIERRAHU.2.1.1CORTE CON ELIMINACION LATERAL (m3)327.13HU.2.1.3ELIMINACION DE MATERIAL EXCEDENTE (m3)408.91

HU.2.2BASEHU.2.2.1BASE O AFIRMADO(PAVIMENTO+ESTACIONAMIENTO)(m2)626.23HU.2.3VEREDASCONCRETO FC=175KG/CM2 (m2)38.28ENCOFRADO Y DESENCOFRADO DE VEREDAS(m2)56.84PISO FROTACHADO CEMENTO PULIDO EN VEREDAS(m2)307.98SELLADO DE JUNTAS EN VEREDAS(m)119.04

HU.2.4PISTASHU.2.4.1PAVIMENTO DE CONCRETO+ESTACIONAMIENTOHU.2.2.3CONCRETO F'C=210KG/CM2 PARA PAVIMENTO+ESTACIONAMIENTO(m2)626.23HU.2.2.4ENCOFRADO Y DESENCOFRADO PAOS PAVIMENTO+ESTACIONAMIENTO(m2)91.85HU.2.4.2SELLADO DE JUNTAS EN PAVIMENTO+ESTACIONAMIENTO(m)459.25

HU.2.5SARDINELESHU.2.5.1CONCRETO PARA SARDINEL(m3)6.91HU.2.5.2ENCOFRADO PARA SARDINEL(m2)30.73HU.2.5.3TARRAJEO EN CARA INTERIOR Y EXTERIOR DE SARDINELES(m2)23.04HU.2.5.3SELLADO DE JUNTAS EN SARDINEL(m)153.63

HU.2.6BARANDAS DE ESCALERAS DE TUBERIA DE 3"(m)25.48

HU.2.7RAMPASHU.2.7.1CONCRETO F'C=175KG/CM2 EN RAMPAS(m3)14.05HU.2.7.2ENCOFRADO PARA RAMPAS(m2)10.28HU.2.7.3BRUAS DE 2CM CADA 0.15M(m)197.53

HU2.8JARDINES(MATERIAL)(m3)11.69

HU3.0.GRADASHU3.0.1CONCRETO F'C=175KG/CM2 EN GRADAS(m3)2.68HU3.0.2ENCOFRADO PARA GRADAS(m2)13.58HU4.0PINTURAHU4.0.1PINTURA PARA VEREDAS(m2)53.57HU4.0.2MARCAS EN EL PAVIMENTO(m2)20.51

PRESUPUESTOPRESUPUESTO ADICIONAL N 02 : COMPATIBILIZACION DE NIVELES OBRA:CREACION DEL MERCADO DE ABASTOS DEL PUEBLO JVEN SAN MARTINCONTRATISTA:CONSORCIO SAN GABRIELSUPERVISOR:CONSORCIO SAN MARTINLUGAR:DISTRITO, PROVINCIA Y REGION LAMBAYEQUEFECHA:19.02.2015

METRADOPRECIOTOTALNPART.DESCRIPCIONUNIDADTOTALHU.1OBRAS PROVISIONALES,TRABAJOS PRELIMINARES,SEGURIDAD Y SALUDHU.1.1TRABAJOS PRELIMINARESHU.1.1.1LIMPIEZA DEL TERRENOHU.1.1.1.1.ELIMINACION DE BASURA Y ELEMENTOS SUELTOS Y LIVIANOS(m3)250.4920.525,140.10HU.1.2DEMOLICIONES(m3)35.2717.14604.53HU.1.3TRAZOS,NIVELES Y REPLANTEOHU.1.3.1TRAZOS,NIVELES Y REPLANTEO PRELIMINAR(m2)950.952.041,939.94HU.1.3.2REPLANTEO DURANTE EL PROCESO(m2)950.950.75713.21HU.2PISTAS Y VEREDASHU.2.1MOVIMIENTO DE TIERRAHU.2.1.1CORTE CON ELIMINACION LATERAL (m3)327.1315.715,139.21HU.2.1.3ELIMINACION DE MATERIAL EXCEDENTE (m3)408.9120.528,390.83

HU.2.2BASEHU.2.2.1BASE O AFIRMADO(PAVIMENTO+ESTACIONAMIENTO)(m2)626.2315.489,694.04HU.2.3VEREDASHU.2.3.1CONCRETO FC=175KG/CM2 (m2)38.2852.652,015.44HU.2.3.2ENCOFRADO Y DESENCOFRADO DE VEREDAS(m2)56.8434.821,979.17HU.2.3.3PISO FROTACHADO CEMENTO PULIDO EN VEREDAS(m2)307.9836.3611,198.15HU.2.3.4SELLADO DE JUNTAS EN VEREDAS(m)119.043.44409.50

HU.2.4PISTASHU.2.4.1PAVIMENTO DE CONCRETO+ESTACIONAMIENTOHU.2.4.1.1CONCRETO F'C=210KG/CM2 PARA PAVIMENTO+ESTACIONAMIENTO(m2)626.2370.0043,836.10HU.2.4.2.2ENCOFRADO Y DESENCOFRADO PAOS PAVIMENTO+ESTACIONAMIENTO(m2)91.8550.374,626.48HU.2.4.2.3SELLADO DE JUNTAS EN PAVIMENTO+ESTACIONAMIENTO(m)459.253.441,579.82

HU.2.5SARDINELESHU.2.5.1CONCRETO PARA SARDINEL(m3)6.91367.012,536.04HU.2.5.2ENCOFRADO PARA SARDINEL(m2)30.7331.94981.52HU.2.5.3TARRAJEO EN CARA INTERIOR Y EXTERIOR DE SARDINELES(m2)23.0460.241,387.93HU.2.5.4SELLADO DE JUNTAS EN SARDINEL(m)153.633.44528.49

HU.2.6BARANDAS DE ESCALERAS DE TUBERIA DE 3"(m)25.48100.002,548.00

HU.2.7RAMPASHU.2.7.1CONCRETO F'C=175KG/CM2 EN RAMPAS(m3)14.05367.015,156.49HU.2.7.2ENCOFRADO PARA RAMPAS(m2)10.2850.37517.80HU.2.7.3BRUAS DE 2CM CADA 0.15M(m)197.5311.062,184.68

HU2.8JARDINES(MATERIAL)(m3)11.6920.00233.80

HU3.0.GRADASHU3.0.1CONCRETO F'C=175KG/CM2 EN GRADAS(m3)2.68367.01983.59HU3.0.2ENCOFRADO PARA GRADAS(m2)13.5850.37684.02

HU4.0PINTURAHU4.0.1PINTURA PARA VEREDAS(m2)53.574.68250.71HU4.0.2MARCAS EN EL PAVIMENTO(m2)20.5116.00328.16CD115,008.88GG11,500.89U5,750.44SUBTOTAL132,260.212.40%IGV23,806.84CD TOTAL4,784,691.44TOTAL156,067.05