CONCEPTO UNIDAD CANTIDAD P.U. TOTAL
1.-PREELIMINARES
1.1.-LIMPIEZA Y DESENRAICE DE TERRENO A MANO DE MALEZA A UN METRO DE PROFUNDIDAD
m2 180 $3.39 $610.20
-GRUPO 1 DE CUADRILLA jr 0.0125 $271.50 $3.39
-1/10 DE CABO jr 0.1 $300.00 $30.00
-1 PEON jr 1 $200.00 $200.00
-% HERRAMIENTA MENOR %mo 0.03 $350.00 $10.50
-% MANDO INTERMEDIO %mo 0.08 $350.00 $28.00
-% FACTOR DE SEGURIDAD %mo 0.01 $300.00 $3.00
1.1.-TRAZO Y NIVELACION DE TERRENO, URBANO DE 250 A 750 M2, POR MEDION MANUALES, CON HILO Y NIVEL DE MANGUERA
m2 180 $2.84 $511.66
-CAL tn 0.0004 $1,100.00 $0.44
-HILO DE CAÑAMO O DE PLASTICO pza 0.00167 $25.00 $0.04
-BARROTES DE MADERA pt 0.0145 $13.76 $0.20
-MANGUERA pza 0.00067 $75.00 $0.05
-CUADRILLA 2 TAREAS PESADAS jr 0.00667 $316.50 $2.11
-1/4 DE CABO jr 0.25 $300.00 $75.00
-1 PEON jr 1 $200.00 $200.00
-% HERRAMIENTA MENOR %mo 0.003 $350.00 $1.05
-% MANDO INTERMEDIO %mo 0.08 $350.00 $28.00
-% FACTOR DE SEGURIDAD %mo 0.01 $300.00 $3.00
2.-EXCAVACION
2.1.- EXCAVACIONES m3 60 $68.34 $4,100.18
-PICO DE 5lb pza 0.0013 $150.00 $0.20
-PALA CUADRADA pza 0.00222 $120.00 $0.27
-CUADRILLA 2 TAREAS PESADAS jr 0.25 $271.50 $67.88
-1/4 DE CABO jr 0.1 $300.00 $30.00
-1 PEON jr 1 $200.00 $200.00
-% HERRAMIENTA MENOR %mo 0.01 $300.00 $3.00