COBRA PRESENTATION

13
Date: - 13/7/2015 1 PROJECT NO. P29148 CONTRACT NO. 15642.01/EC10874

Transcript of COBRA PRESENTATION

Page 1: COBRA  PRESENTATION

Date: - 13/7/20151

PROJECT NO. P29148 CONTRACT NO. 15642.01/EC10874

Page 2: COBRA  PRESENTATION

2Date: - 13/7/2015

Page 3: COBRA  PRESENTATION

3

As part of sustaining current oil production & achieving 70 MBOPD in ADCO’S shah Field, Located 180 KM South- West of Abu Dhabi city, 8 No’s New ESP Wells will be drilled over the period 2015 – 2016. Electrical Power Supply has to be provided near the Well head to run Electrical Submersible Pumps (ESPs), Container mounted Substations (called Power Skids) will be provided by other contractors. And for this purpose these wells shall be Powered from the Existing 33KV Overhead line network. Through this, a New Spur lines to be constructed under this project

Date: - 13/7/2015

Page 4: COBRA  PRESENTATION

4

2. Project Objectives

To construct New Spur Lines and/or provide 33 KV Power Cables, Tapped-Off from the Existing main 33 KV Lines to 8 Power Skids Provided by Others.

Date: - 13/7/2015

Page 5: COBRA  PRESENTATION

5

3. Scope

Date: - 13/7/2015

The construction of Eight new tap-off 33 KV overhead lines in Shah Field to provide power supply for new 8 nos. ESP (Electrical submersible pump) wells to be drilled out of the following wells & 1 No 33KV overhead line Link between (Sy-80 & Sy-15) also mentioned below:

Sy-85, Sy-86, Sy-87, Sy-88, Sy-89, Sy-90, Sy-91, Sy-92,

OHL Link (Sy-80 & Sy-15).

Page 6: COBRA  PRESENTATION

6Date: - 13/7/2015

The existing 33 KV overhead lines will be tapped-off and overhead lines (wooden poles) / Underground power cables shall be run for the eight wells up to proposed power skid locations, and 33KV overhead line Link between Sy-80 & Sy-15 as per details provided in the tender document.

Page 7: COBRA  PRESENTATION

7

4. Scope of work

Carry out all necessary modifications for tapping-off from the existing overhead lines through the most practical shortest route.

Date: - 13/7/2015

The Scope of work under this project shall be implemented based on specifications, technical schedules, existing Overhead Line field layout & typical (sample) drawings. Cobra scope of work shall include but not limited to the following.

Page 8: COBRA  PRESENTATION

8

Provision of Topographical (as minimum for every angle pole structure) Survey for routing the main 33 KV overhead line, including line profile & pole spotting.

Extension of overhead line to Power Skid location including supply, installation of overhead line materials such as Wooden poles, Switches, Arrestors, 33KV ACSR Conductors, OPGW, FOC, Cross arms, Stay wires etc. Including all necessary materials for erection, testing & pre-commissioning, completion & warranty of the 33 KV overhead line (Single Circuit). The extended line shall be started at the Tap-off Point & shall end with terminal Pole (G1 Type). 100 Meter away form the Power Skid location ( to be co-ordinated with ADCO). The oil well will be approximately 50-100 Meter away from the Power Skid.

The line route shall be subject to ADCO approval. Each extended line will be started with an Line Isolator Switch with

Earth Switch & Ends with Fused Switch with Earth Switch.

Date: - 13/7/2015

Page 9: COBRA  PRESENTATION

9

Supply, installation, termination & testing including the termination kits for the following Cable’s: Single Core, 70 Sq.mm ( From end terminal pole to Power Skid) & 300 Sq.mm ( for Road crossing), 19/33 KV stranded copper conductor, XLPE, copper screening, AWA, PVC sheathed & Fibre Optic Cable. Cables shall be as per technical schedule.

Provision for Track crossing or Road crossing or Rig crossing as required by rote survey.

A separate external earthing cable of minimum 70 Sq.mm shall be laid & connected at both ends to the earthing of the terminal pole structure/Transformer & subsequently to overhead earth wire.

Tap-off /Tie ins to existing line. Installation of at least one Deep earth well (2 m below summer water

table) shall be provided for each branch line

Date: - 13/7/2015

Page 10: COBRA  PRESENTATION

10

Supply, installation, testing of OPGW Junction Boxes mounted on Tap-off point pole & terminal pole (G1 Type).

Supply, installation, termination & testing of Under ground Fibre Optic Cable between terminal pole Junction Box & Power Skid.

Earthing/Bonding for pole support, pole mounted equipment & OPGW ( Including earth mats, earth rods & connecting) shall be as per specification for 33 KV overhead line works.

A Fault current indicator shall be installed at the tapping point of the New extension line.

Full compliance to ADCO HSE manual Vol-10 & ADCO road safety manual Vol 10/3 shall be guaranteed.

Submission of Drawings & technical documentation during Engineering, supply, construction as per technical specification Cobra shall compile ‘as built’ mark-ups of Drawings & documents for final preparation of master Drawings to be handed over to ADCO, on completion of work.

Date: - 13/7/2015

Page 11: COBRA  PRESENTATION

11Date: - 13/7/2015

5. Organization chart

AREA MANAGERCARLOS NAVARRO

Project ManagerSUHAS AHER

Administration Staff (Abu Dhabi)

Construction Crew

Site EngineerK. SIVA

Sub-contractor

Engg. / QualityDept - Madrid.

HSE Officers Roshin/A.N Mohanan

Site EngineerSUMAN CH

Page 12: COBRA  PRESENTATION

12Date: - 13/7/2015

6. Planning Package L-2

SUPPLY & CONSTRUCTION WORKS FOR 33 KV OHL AT SHAH ESP TIE-INS ( CONTRACT NO: 15642.01/EC/10874) PROJECT PLANNING LEVEL - 2 (Rev.0)(CONSTRUCTION) VO2

SR Task Name Duration Schedule Start Schedule End

Construction of 33 KV OHL For Shah ESP 482 days 07 -June- 2015 30 –Sep- 20161 VARIATION ORDER ISSUANCE 001 day 07 –June- 2015 07 –June- 2015 2 PROFILE SURVEY & ENGINEERING DRWAING PREPARATION 80 days 08 –June- 2015 26 –Aug- 20153 PROCUREMENT OF MATERIALS 180 days 08 –June- 2015 04 –Dec- 20154 33 KV OHL INSTALATION TO WELL # (Sy-86) 65 days 01 –July- 2015 03 –Sep- 20155 33 KV OHL INSTALATION TO WELL # (Sy-85) 55 days 04 –Sep- 2015 28 –Oct- 20156 33 KV OHL INSTALATION LINK BETWEEN Sy-80 & Sy-15 60 days 29 –Oct- 2015 27 –Dec- 20157 33 KV OHLINSTALATION TO WELL # (Sy-87) 25 days 28 –Dec- 2015 21 –Jan- 2016 8 33 KV OHLINSTALATION TO WELL # (Sy-88) 30 days 22 –Jan- 2016 20 –Feb- 20169 33 KV OHLINSTALATION TO WELL # (Sy-89) 30 days 21 –Feb- 2016 21 –Mar- 2016 10 33 KV OHLINSTALATION TO WELL # (Sy-92) 30 days 22 –Mar- 2016 20 –Apr- 201611 33 KV OHLINSTALATION TO WELL # (Sy-90) 30 days 21 –Apr- 2016 20 –May- 201612 33 KV OHLINSTALATION TO WELL # (Sy-91) 32 days 21 –May- 2016 21 –June- 201613 EARTH WELL DRILLING 8 LOCATIONS 101 days 22 –June- 2016 30 –Sep- 2016

Page 13: COBRA  PRESENTATION

13Date: - 13/7/2015

THANK YOU