www.connellfoley .com Alliance of Hazardous Materials Professionals New Jersey Chapter and American Society of Safety Engineers New Jersey Chapter October 27, 2015 Joint Meeting Process Safety Management (PSM) Legal and Regulatory Update Speaker: Steve Barnett, P.E., CIH, MSPH, Esq.; Partner, Law Offices of Connell Foley LLP

Transcript of Barnett presentation 10-27-2015

Page 1: Barnett presentation 10-27-2015

www.connellfoley.com

Alliance of Hazardous Materials Professionals New Jersey Chapter and American Society of

Safety Engineers New Jersey ChapterOctober 27, 2015 Joint Meeting

Process Safety Management (PSM) Legal and Regulatory Update

Speaker: Steve Barnett, P.E., CIH, MSPH, Esq.; Partner, Law Offices of Connell Foley LLP

Page 2: Barnett presentation 10-27-2015

PSM Standard, 29 CFR 1910.119

• Bhopal, India chemical release 1984• Clean Air Act Amendments of 1990 required

OSHA to issue chemical process safety standard

• Standard issued 1992

Page 3: Barnett presentation 10-27-2015

PSM Standard, 29 CFR 1910.119

• October 23, 1989, Phillips Petroleum, Pasadena, Texas• July 19, 1990, BASF, Cincinnati, Ohio• May 1, 1991, IMC, Sterlington, Louisiana• March 23, 2005, BP Refinery, Texas City, Texas• April 2, 2010, Tesoro Refinery, Anacortes, Washington• April 20, 2010, Deepwater Horizon• April 17, 2013, West Fertilizer, West, Texas• June 13, 2013, Williams Olefins, Geismar, Louisiana• November 15, 2014, DuPont, LaPorte, Texas

Page 4: Barnett presentation 10-27-2015

PSM Standard, 29 CFR 1910.119

• 2007 OSHA Petroleum Refinery PSM National Emphasis Program

• 2011 OSHA PSM-Covered Chemical Facility National Emphasis Program

• 645 inspections, 3,100 violations• August 1, 2013 Executive Order 13650

Improving Chemical Facility Safety and Security

Page 5: Barnett presentation 10-27-2015

PSM Standard, 29 CFR 1910.119

• PSM Applicability • Process which involves threshold quantities

listed in Appendix A, or • Process which involves 10,000 pounds of

Category 1 flammable gas or flammable liquid with flashpoint below 100°F on site in one location

Page 6: Barnett presentation 10-27-2015

PSM Standard, 29 CFR 1910.119

• PSM Applicability (cont’d)• Process means any activity involving a highly

hazardous chemical including any use, storage, manufacturing, handling, or the on-site movement of such chemicals, or combination of these activities. For purposes of this definition, any group of vessels which are interconnected and separate vessels which are located such that a highly hazardous chemical could be involved in a potential release shall be considered a single process.

Page 7: Barnett presentation 10-27-2015

PSM Standard, 29 CFR 1910.119

• PSM Applicability (cont’d)• Not applicable to:

Retail facilities Oil or gas well drilling or servicing Normally unoccupied remote facilities

Page 8: Barnett presentation 10-27-2015

PSM Standard, 29 CFR 1910.119

• PSM Requirements• Process Hazard Analysis• Written operating procedures• Employee training and participation• Pre-startup safety reviews• Evaluation of mechanical integrity of equipment• Contractor requirements• Written procedures for management of change• Permit system for hot work• Investigation of incidents involving releases or near misses• Emergency actions plans• Compliance audits at least every 3 years• Trade secret protection

Page 9: Barnett presentation 10-27-2015

West Fertilizer Company, West, Texas

Page 10: Barnett presentation 10-27-2015

West Fertilizer Company, West, Texas

• April 17, 2013 fire and explosion• PHSMA

– September 23, 2011 PHMSA inspection– January 13, 2012 Notice of Probable Violation

• $5,600 offering for transportation anhydrous ammonia with ASME plate illegible and missing NH3 and UN1005 placards

• $4,500 no security plan as per 172.800 for > 3000 kg in one packaging or poisonous by inhalation

– June 12, 2012 Compromise Order and Agreement. Penalties reduced to $5,000 and $250

Page 11: Barnett presentation 10-27-2015

West Fertilizer Company, West, Texas

• Chemical Safety Board investigation ongoing• Reportedly last inspected by OSHA in 1985• 2006 EPA fine of $2,300 for failure to timely file Risk Management

Plan (RMP) pursuant to EPA Clean Air Act rules • Current RMP listed anhydrous but not nitrate because not

required• 400 lbs ammonium nitrate CFATS screening threshold not reported

to DHS • Facility held certificate to handle ammonium nitrate from Texas

State Feed and Fertilizer Control Service• Discussions of state and local fire codes, emergency plans,

communication of information between agencies• August 1, 2013 Executive Order

Page 12: Barnett presentation 10-27-2015

West Fertilizer Company, West, Texas

• August 20, 2013 video safety message by CSB Chair• “CSB has determined that ammonium nitrate storage

falls under a patchwork of U.S. standards and guidance, which does not prohibit many of the conditions found at the West facility. These include the use of combustible wooden storage bins and buildings and a lack of sprinkler systems in case of fire.”

• "The CSB believes it's past time for OSHA and EPA to regulate reactive hazards – including ammonium nitrate – under their process safety rules."

Page 13: Barnett presentation 10-27-2015

Executive Order 13650 – Improving Chemical Facility Safety and Security, August 1, 2013

• Interagency working group and required reports within 90, 180, 270 days (DHS, OSHA, EPA, DOJ, ATF, DOT, USDA)

• Review regulations and enhance coordination of federal, state and local agencies.

• EPA review Risk Management Program (RMP) regulations• OSHA review Process Safety Management (PSM) regulations• DHS review Chemical Facility Anti-Terrorism Standard regulations• ATF review explosives license and permit requirements• Listening sessions, rulemaking, guidance, interpretations,

enforcement

Page 14: Barnett presentation 10-27-2015

OSHA Enforcement Memorandum, PSM Recognized and Generally Accepted Good Engineering Practices (RAGAGEP), June 5, 2015

• PSM-covered processes to comply with RAGAGEP and appropriate internal standards (equipment design, installation, operation, and maintenance; inspection and test practices and frequencies)

• PSM regulation does not define RAGAGEP• June 5 memo requires that internal standards must meet or

exceed published RAGAGEP (published and widely adopted codes, published consensus documents, published non-consensus documents)

• June 5 memo discusses use of shall, must, should, shall not, prohibited, may in published RAGAGEP

Page 15: Barnett presentation 10-27-2015

OSHA Memorandum, PSM Covered Concentrations of Listed Appendix A Chemicals, June 5, 2015• 126 of 137 Appendix A chemicals are listed without reference

to concentration• To date, applicability concentration threshold has been

“commercial grade” or higher• June 5 memo requires employer to determine weight of

substance at 1% concentration and higher• In determining weight, only weight of substance, exclusive of

any solvent, solution or carrier, is counted

Page 16: Barnett presentation 10-27-2015

OSHA Memorandum, PSM and Application of the Retail Exemption, 29

CFR 1910.119(a)(2)(i), July 22, 2015

• Exemption for retail facilities but regulation does not define “retail facility”

• “50 percent test” has applied. 50% of income from direct sales to end user

• July 22 memo limits exemption to facilities in North American Industry Classification System (NAICS) Manual Sector 44-45 - Retail Trade

Page 17: Barnett presentation 10-27-2015

American Petroleum Institute v. OSHA, and American Chemistry Council v. OSHA• Filed August 3, 2015 in United States Court of

Appeals for the District of Columbia, Case No. 15-1252 and 15-1253

• Requesting judicial review of OSHA RAGAGEP memo & OSHA covered concentration memo

• Cases consolidated August 6

Page 18: Barnett presentation 10-27-2015

American Petroleum Institute v. OSHA, and American Chemistry Council v. OSHA• Violate Occupational Safety & Health Act• Promulgated without notice, comment and

publication requirements of the Administrative Procedure Act

• Arbitrary and capricious• Unsupported by substantial evidence• Inconsistent with reasoned decision-making

Page 19: Barnett presentation 10-27-2015

American Petroleum Institute v. OSHA, and American Chemistry Council v. OSHA• Court’s October 19, 2015 briefing schedule– Petitioners’ Brief December 16, 2015– Intervenor for Petitioners’ Brief January 4, 2016– Respondents’ Brief February 3, 2016– Intervenor for Petitioners’ Reply Brief February 17,

2016– Petitioners’ Reply Brief February 17, 2016– Deferred Appendix February 24, 2016– Final Briefs March 9, 2016

Page 20: Barnett presentation 10-27-2015

OSHA Review of PSM regulation

• EPA RMP and OSHA PSM listening sessions, Small Business Regulatory Enforcement Fairness Act of 1996 (SBREFA) panels, advanced notice of proposed rulemaking, notice of proposed rulemaking, final rulemaking

• OSHA will wait until January 2016 to convene SBREFA panel, after EPA convenes its SBREFA panel on RMP

Page 21: Barnett presentation 10-27-2015

OSHA Review of PSM regulation• Incorporate lessons learned from enforcement, incident investigation, and advancements

in industry practices, root cause analysis, process safety metrics, enhanced employee involvement, third-party audits, and emergency response practices.

• Addressing ammonium nitrate hazards through one or both of the following options: 1) covering reactive chemical hazards under the PSM 2) adding ammonium nitrate specifically to the PSM Appendix A highly hazardous chemicals list

• Adding substances or classes of substances to the PSM Appendix A List of Highly Hazardous Chemicals and providing more expedient methods for future updates.

• Expanding coverage and requirements for reactive chemical hazards, which have resulted in many incidents.

• Covering oil and gas drilling and servicing operations that currently are exempt from PSM coverage.

• Continuing harmonization with EPA’s RMP regulation. • Requiring analysis of safer technology and alternatives. • Requiring coordination between chemical facilities and emergency responders to ensure

that emergency responders know how to use chemical information to safely respond to accidental releases, possibly including exercises and drills.