LAKE MEAD WATER INTAKE NO. 3Constructing the highest pressure tunnel in the world
to preserve drinking water supply for two million people
![Page 2: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/2.jpg)
Drought in the Colorado River basin Colorado River supplies 90% of Las Vegas’
water
1983 2013
The Situation
![Page 3: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/3.jpg)
3
Lake Mead dropped 150 feet between
2000 and 2015
![Page 4: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/4.jpg)
HIGH AND LOW LAKE LEVEL ELEVATIONS
![Page 5: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/5.jpg)
Intake No. 1 Out of ServiceIntake No. 2 Out of Service
Saddle Island Elevation 860’
Spillway gates
Elevation 1,000’
Hoover Dam
Dead Pool - Elevation 897’
Spillway Gate - Elevation 1,224’
Elevation 1,050’
INTAKE NO. 3
INTAKE NO. 2
INTAKE NO. 1
Drought Impacts
![Page 6: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/6.jpg)
If the lake level falls below 1,050 feet: Intake No. 1 will be out of service Pumping capacity will be reduced
A new intake system is needed to preserve existing
capacity and water quality if lake levels continue to decline.
Lake Mead Water Level Impacts
![Page 7: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/7.jpg)
Lake Mead Intake No. 3 Approved by SNWA Board of Directors May
2005 Six contracts (originally), $817 Million total
(est)… Deferred Pumping Station - three major contracts $650M estimated construction value
Completion 2015 (2020 with Pumping Station)
![Page 8: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/8.jpg)
Challenges Variable Geology:
Hard, fractured Weak sedimentary Volcanic rock
High tunneling pressures – 17 bar (250 psi)
Intake Structure installed in 350 feet of water
Intake Structure/TBM docking within a 1-ft tolerance after 3 miles of tunneling
Connection to existing operating intakes
![Page 9: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/9.jpg)
Project Location
Lake Mead Las Vegas
![Page 10: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/10.jpg)
Exist Water Treatment
Facility
L3P3 PUMPING STATION
Intake 3
INTAKE TUNNEL
DISCHARGE PIPELINES
INTAKE No. 2 CONNECTOR TUNNEL
Lake Mead Intake No. 3 Contracts
Exist Intake 1
Exist Intake 2
INTAKE No. 2 CONNECTION & MODIFICATIONS
Lake Mead
Saddle Island
![Page 11: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/11.jpg)
Exist Water Treatment
Facility
Intake 3
INTAKE TUNNEL
INTAKE No. 2 CONNECTION
Exist Intake 1
Exist Intake 2
INTAKE No. 2 CONNECTION & MODIFICATIONS
Lake Mead
Saddle Island
![Page 12: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/12.jpg)
Vegas Tunnel Constructors (Design-Build) ~ $450MAccess Shaft• ~ 600’ deep• 30’ finished interior diameter
Tunnel• Launch Chamber ~ 202’ long, 47’ W x 35’ H• Starter Tunnel ~ 450’ long, 27’ W x 25’ H • TBM tunnel
– 20’ finished internal diameter– ~ 14,904’ long– 14” concrete segmental lining
Intake Structure (elev 860)• 96’ high• 16’ diameter riser• Radial inlet
Shafts & TunnelAs deep as the Wynn is tall!
![Page 13: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/13.jpg)
13
Top-Down Shaft Construction Sequence
1) Drill2) Blast3) Excavate4) Map the rock
face5) Initial Support6) Lower Form7) Cast ConcreteRepeat…
![Page 14: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/14.jpg)
Shaft ExcavationCompleted
January 2010
![Page 15: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/15.jpg)
TBM Assembly Chamber
TBM Chamber Excavating Top Heading – Nov 2009
![Page 16: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/16.jpg)
TBM Assembly Chamber
![Page 17: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/17.jpg)
Beginning of inflow in Starter Tunnel - June 28, 2010
Incursion of Unstable Ground
![Page 18: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/18.jpg)
Tunnel Flooding
Flooding EventJune 28th – July 1st, 2010
![Page 19: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/19.jpg)
Area of Tunnel Inflows
Tunnel Realignment
New Alignment
January 2011
![Page 20: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/20.jpg)
20 Realigned Starter Tunnel viewed from Cavern – 03/29/11
![Page 21: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/21.jpg)
Starter Tunnel
CompletedJune 2011
![Page 22: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/22.jpg)
Drilling Jumbo Truck - Hoover Dam Diversion Tunnelshttp://www.usbr.gov/history/photos/dams007.jpg
Back then…
![Page 23: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/23.jpg)
23
Tunnel Boring Machine• 24ft Outside Diameter• 600ft Long Trailing Gear • Total Weight 1500 Metric
Tons• TBM was designed to be
driven in rock with water head up to 17 bar (250 psi)
• Capable of grouting and soil improvement ahead of the face
• Machine designed and fabricated specifically for this project with strict cooperation between SNWA, Design-Builder, and Supplier (Herrenknecht)
![Page 24: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/24.jpg)
Contract 01
TBM TRAILING / SUPPORT GEAR - 585’ long, 1500 tons
TBM
![Page 25: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/25.jpg)
Strand Jacks Used to Handle Weight and Depth
![Page 26: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/26.jpg)
Lowering TBM Down Shaft
![Page 27: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/27.jpg)
27 TBM Lowering September 2011
![Page 28: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/28.jpg)
TBM Positioned At Tunnel Face
December 27, 2011
![Page 29: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/29.jpg)
Local Mfg. of Precast Segments
5 Segments + I keystone = Ring
![Page 30: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/30.jpg)
30 Tunnel Segments delivered to Site
![Page 31: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/31.jpg)
31
![Page 32: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/32.jpg)
Segment Transport
![Page 33: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/33.jpg)
3,000 feet at
13.5 bar WHAT PSI IS 13.5
BAR ?
195.80 PSI
![Page 34: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/34.jpg)
Took a Toll on the Machine
2013 Mar 29
![Page 35: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/35.jpg)
2013/2014 TBM Repairs
3 Repair Stops
4 foot deep niche excavated in front of cutterhead
![Page 36: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/36.jpg)
36
![Page 37: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/37.jpg)
![Page 38: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/38.jpg)
Soft eye
![Page 39: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/39.jpg)
![Page 40: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/40.jpg)
25’ 10”
![Page 41: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/41.jpg)
41 Stainless Steel Riser Assembly
![Page 42: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/42.jpg)
42 Stainless Steel Intake Screen
![Page 43: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/43.jpg)
Intake Riser - Excavation
Spring 2010
![Page 44: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/44.jpg)
44
Preparations for Excavation at lake bottom
• Additional ground investigation• Bathymetry Survey• Excavation and Blasting done from
crane barge• Clam and airlift “Overburden”-
15,000 CY• Overburden was 6 ft of desert soil;
very small silt layer about 6 inch on top.
![Page 45: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/45.jpg)
Shaped Charges Placed on rock surface 7.5 kg / charge Placement structure
30 ft x 30 ft Small blasts at surface – Fish Scare
23,000 charges
![Page 46: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/46.jpg)
46 Rendering of final excavation at lake bottom
![Page 47: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/47.jpg)
Intake Structure Installation
Total Tremie Concrete = 11,300 cy
February and March 2012
![Page 48: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/48.jpg)
Assembled Intake Structure Conveyed to Intake Site
15 Feb 2012
![Page 49: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/49.jpg)
Concrete Batch Plant
![Page 50: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/50.jpg)
Concrete Transport Barge
![Page 51: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/51.jpg)
![Page 52: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/52.jpg)
![Page 53: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/53.jpg)
Intake Structure Tie in
10-ft.
![Page 54: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/54.jpg)
![Page 55: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/55.jpg)
ROV Intake Inspection
![Page 56: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/56.jpg)
Cleaning Seal with ROV
![Page 57: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/57.jpg)
Lowering Bulkhead
![Page 58: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/58.jpg)
Piece of soft eye during hole through
![Page 59: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/59.jpg)
59
Breakthrough on December 10, 2014
![Page 60: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/60.jpg)
60
![Page 61: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/61.jpg)
TBM Removal
![Page 62: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/62.jpg)
TBM Removal
![Page 63: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/63.jpg)
TBM Removal - Completed Apr 27, 2015
![Page 64: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/64.jpg)
![Page 65: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/65.jpg)
![Page 66: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/66.jpg)
Tunnel Steam Cleaner
![Page 67: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/67.jpg)
Remaining Milestones
Intake No. 3 Shafts & Tunnel
Operational October 2015 Final Completion January 2016
![Page 68: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/68.jpg)
600
800
700
900
1100
1000
1200
1300
Intake 3 Tunnel
Inta
ke 3
Inta
ke 1
Connector Tunnel
RMWTF
AMSWTF BROFIPS-1 IPS-2
IPS-2 Pump Operation Limit El. 1000
IPS-1 Pump Operation Limit El. 1050
Lake Elev. (feet above MSL)
Inta
ke 2
Isola
tion
Gate
L3PS
68
Low Lake Level Pumping Station
L3PS was approved by the SNWA on December 10, 2014
![Page 69: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/69.jpg)
L3PS CONTRACT PACKAGES
Mass Excavation - Design-Bid-Build
Pumping Station - CMAR Underground Mechanical and Electrical
Discharge Pipelines – Design-Bid-Build
Electrical Feed & Substation – Design-Bid-Build (by CRC)
![Page 70: Tri State Presentation - 9-24-15](https://reader038.fdocuments.ec/reader038/viewer/2022103105/587a06871a28ab01268b5ab9/html5/thumbnails/70.jpg)
Questions? Questions ?