 S10 Página  1 Presupuesto AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE ABASTECIMIENTO AGUA POTABLE - HUAYRURPA TA Presupuesto 1201001 S10 S.A.C. 16/02/2015 Costo al Cliente Lugar AYACUCHO - LA MAR - ANCO Precio S/. Parcial S/. Mano de Obra Material Equipo Subcontrato Item Descripción Und. Metrado  92.00 211.86 OBRAS PRELIMINARES 01  303.86 und CARTEL DE OBRA 01.01 1.00 92.00 211.86 303.86  303.86  1 ,302.66 1,368.59  CAPTACION (1) 02  102.41  2,774.05  18.40 10.18 TRABAJOS PRELIMINARES 02.01  0.56  29.28 m2 LIMPIEZA Y DEFORESTACION MANUAL 02.01.01 17.02 6.26 0.19 0.38  6.47 m2 TRAZO Y REPLANTEO 02.01.02 17.02 12.14 10.18 0.37 1.34  22.81  126.35 MOVIMIENTO DE TIERRAS 02.02  3.79  130.15 m3 EXCAVACION PARA ESTRUCTURAS MANUAL 02.02.01 4.12 126.35 3.79 31.59  130.15  412.17 638.71 CONCRETO SIMPLE 02.03  68.81  1,119.90 m3 CONCRETO FC=175 KG/CM2 02.03.01 1.47 140.11 488.43 55.25 465.18  683.81 m3 CONCRETO 1:8+25% P.M 02.03.02 0.24 18.42 44.43 5.95 286.71  68.81 m2 ENCOFRADO Y DESENCOFRADO NORMAL 02.03.03 12.05 253.64 105.85 7.61 30.48  367.28  274.27 68.36 REVOQUES Y ENLUCIDOS 02.04  8.23  350.92 m2 TARRAJEO EN INTERIOR CON IMPERMEABILIZANTE C:A 1 :3 e=1.5cm 02.04.01 6.29 141.86 37.96 4.26 29.27  184.11 m2 TARRAJEO EN EXTERIORES CON CEMENT O-ARENA 1:5 e=1.5 cm 02.04.02 6.29 132.41 30.40 3.97 26.52  166.81  36.04 54.72  FILTROS EN CAPTACION 02.05  0.99  91.74 m3 FILTRO DE ARENA GRUESA 02.05.01 0.31 9.51 23.45 0.19 106.91  33.14 m3 FILTRO DE GRAVA 02.05.02 0.41 26.53 31.27 0.80 142.92  58.60  54.88 211.79  TAPA METALICA 02.06  1.89  268.56 und TAPA METALICA DE 0.40x0.40x1/8" 02.06.01 1.00 12.16 95.00 0.61 107.77  107.77 und TAPA METALICA DE 0.60x0.60x1/8" 02.06.02 1.00 42.72 116.79 1.28 160.79  160.79  44.79 46.67  VARIOS 02.07  1.34  92.78 m2 PINTURA ESMALTE EN EXTERIOR 02.07.01 6.29 44.79 46.67 1.34 14.75  92.78  298.46 252.21  CERCO PERIMETRICO 02.08  14.93  565.60 m CERCO PERIMETRICO CON ALAMBRE DE PUAS 02.08.01 14.10 56.07 30.27 2.81 6.32  89.11 und COLUMNAS DE MADERA CON DADO DE CONCRETO C:H 1:8 02.08.02 7.00 221.03 191.10 11.05 60.46  423.22 und PUERTA DE MADERA ROLLIZA 02.08.03 1.00 21.36 30.84 1.07 53.27  53.27  37.30 85.95  VALVULAS Y ACCESORIOS 02.09  1.87  125.12 und VALVULAS DE BRONCE Y ACCESORIOS SALE Ø 1 1/5" 02.09.01 1.00 37.30 85.95 1.87 125.12  125.12  96 ,664.10 31,809.18  LINEA DE CONDUCCION 03  176,715.80  305,240.73  8 ,771.78 1,128.31 TRABAJOS PRELIMINARES 03.01  633.16  10,562.93 m2 LIMPIEZA Y DEFORESTACION MANUAL 03.01.01 7,237.10 2,663.25 80.33 0.38  2,750.10 m TRAZO, NIVELACION Y REPLANTEO DE ZANJAS 03.01.02 7,234.10 6,108.53 1,128.31 552.83 1.08  7,812.83  76,988.06 5,185.38 MOVIMIENTO DE TIERRAS 03.02  172,482.18  254,716.84 m3 EXCAVACION MANUAL DE ZANJAS EN MATERIAL SUELTO 03.02.01 4,342.28 22,191.66 1,109.45 5.37  23,318.04 m REFINE Y NIVELACION FONDO DE ZANJA PARA TUBERIA 03.02.02 7,237.10 11,094.11 332.18 1.58  11,434.62 m CAMA DE APOYO PARA TUBERIAS E= 0.10 m. 03.02.03 7,237.10 5,551.22 5,185.38 167.18 1.51  10,928.02 03/03/2015 09:13:07a.m. Fecha :

Transcript of s10 impr.pdf

  • S10 Pgina 1

    PresupuestoAMPLIACION Y MEJORAMIENTO DEL SISTEMA DE ABASTECIMIENTO AGUA POTABLE - HUAYRURPATAPresupuesto 1201001

    S10 S.A.C. 16/02/2015Costo alClienteLugar AYACUCHO - LA MAR - ANCO

    Precio S/. Parcial S/.Mano de Obra Material Equipo SubcontratoItem Descripcin Und. Metrado

    92.00 211.86OBRAS PRELIMINARES01 303.86

    undCARTEL DE OBRA01.01 1.00 92.00 211.86 303.86 303.86

    1,302.66 1,368.59 CAPTACION (1)02 102.41 2,774.05

    18.40 10.18TRABAJOS PRELIMINARES02.01 0.56 29.28

    m2LIMPIEZA Y DEFORESTACION MANUAL02.01.01 17.02 6.26 0.19 0.38 6.47

    m2TRAZO Y REPLANTEO02.01.02 17.02 12.14 10.18 0.37 1.34 22.81

    126.35MOVIMIENTO DE TIERRAS02.02 3.79 130.15

    m3EXCAVACION PARA ESTRUCTURAS MANUAL02.02.01 4.12 126.35 3.79 31.59 130.15

    412.17 638.71 CONCRETO SIMPLE02.03 68.81 1,119.90

    m3CONCRETO FC=175 KG/CM202.03.01 1.47 140.11 488.43 55.25 465.18 683.81

    m3CONCRETO 1:8+25% P.M02.03.02 0.24 18.42 44.43 5.95 286.71 68.81

    m2ENCOFRADO Y DESENCOFRADO NORMAL02.03.03 12.05 253.64 105.85 7.61 30.48 367.28

    274.27 68.36REVOQUES Y ENLUCIDOS02.04 8.23 350.92

    m2TARRAJEO EN INTERIOR CON IMPERMEABILIZANTE C:A 1:3 e=1.5cm02.04.01 6.29 141.86 37.96 4.26 29.27 184.11

    m2TARRAJEO EN EXTERIORES CON CEMENTO-ARENA 1:5 e=1.5 cm02.04.02 6.29 132.41 30.40 3.97 26.52 166.81

    36.04 54.72 FILTROS EN CAPTACION02.05 0.99 91.74

    m3FILTRO DE ARENA GRUESA02.05.01 0.31 9.51 23.45 0.19 106.91 33.14

    m3FILTRO DE GRAVA02.05.02 0.41 26.53 31.27 0.80 142.92 58.60

    54.88 211.79 TAPA METALICA02.06 1.89 268.56

    undTAPA METALICA DE 0.40x0.40x1/8"02.06.01 1.00 12.16 95.00 0.61 107.77 107.77

    undTAPA METALICA DE 0.60x0.60x1/8"02.06.02 1.00 42.72 116.79 1.28 160.79 160.79

    44.79 46.67 VARIOS02.07 1.34 92.78

    m2PINTURA ESMALTE EN EXTERIOR02.07.01 6.29 44.79 46.67 1.34 14.75 92.78

    298.46 252.21 CERCO PERIMETRICO02.08 14.93 565.60

    mCERCO PERIMETRICO CON ALAMBRE DE PUAS02.08.01 14.10 56.07 30.27 2.81 6.32 89.11

    undCOLUMNAS DE MADERA CON DADO DE CONCRETO C:H 1:802.08.02 7.00 221.03 191.10 11.05 60.46 423.22

    undPUERTA DE MADERA ROLLIZA02.08.03 1.00 21.36 30.84 1.07 53.27 53.27

    37.30 85.95 VALVULAS Y ACCESORIOS02.09 1.87 125.12

    undVALVULAS DE BRONCE Y ACCESORIOS SALE 1 1/5"02.09.01 1.00 37.30 85.95 1.87 125.12 125.12

    96,664.10 31,809.18 LINEA DE CONDUCCION03 176,715.80 305,240.73

    8,771.78 1,128.31TRABAJOS PRELIMINARES03.01 633.16 10,562.93

    m2LIMPIEZA Y DEFORESTACION MANUAL03.01.01 7,237.10 2,663.25 80.33 0.38 2,750.10

    mTRAZO, NIVELACION Y REPLANTEO DE ZANJAS03.01.02 7,234.10 6,108.53 1,128.31 552.83 1.08 7,812.83

    76,988.06 5,185.38MOVIMIENTO DE TIERRAS03.02 172,482.18 254,716.84

    m3EXCAVACION MANUAL DE ZANJAS EN MATERIAL SUELTO03.02.01 4,342.28 22,191.66 1,109.45 5.37 23,318.04

    mREFINE Y NIVELACION FONDO DE ZANJA PARA TUBERIA03.02.02 7,237.10 11,094.11 332.18 1.58 11,434.62

    mCAMA DE APOYO PARA TUBERIAS E= 0.10 m.03.02.03 7,237.10 5,551.22 5,185.38 167.18 1.51 10,928.02

    03/03/2015 09:13:07a.m.Fecha :

  • S10 Pgina 2

    PresupuestoAMPLIACION Y MEJORAMIENTO DEL SISTEMA DE ABASTECIMIENTO AGUA POTABLE - HUAYRURPATAPresupuesto 1201001

    S10 S.A.C. 16/02/2015Costo alClienteLugar AYACUCHO - LA MAR - ANCO

    Precio S/. Parcial S/.Mano de Obra Material Equipo SubcontratoItem Descripcin Und. Metrado

    m3RELLENO Y COMPACTADO DE ZANJAS CON TIERRA TAMIZADO03.02.04 868.45 3,195.90 53,317.61 65.07 56,510.04

    m3RELLENO Y COMPACTADO CON MAT. PROPIO EN ZANJAS03.02.05 3,039.58 34,955.17 117,555.76 50.18 152,526.12

    4,000.73 24,523.84SUMINISTRO DE TUBERIAS03.03 28,526.34

    mTUBERIA PVC SAP CLASE 7.5 DE 1 1/2"03.03.01 5,031.10 4,000.73 24,523.84 5.67 28,526.34

    6,903.53 971.65 PRUEBA HIDRAULICA03.04 3,600.46 11,434.62

    mPRUEBA HIDRAULICA EN LINEA DE CONDUCCION INCLUIDO DESINFECCION03.04.01 7,237.10 6,903.53 971.65 3,600.46 1.58 11,434.62

    5,235.35 20,558.52 SIFON INVERTIDO04 611.41 26,424.73

    1,820.10 2,783.61 CAMARA DE INGRESO04.01 289.32 4,894.51

    m2LIMPIEZA DE TERRENO MANUAL04.01.01 40.00 184.00 5.52 4.74 189.60

    m2TRAZO Y REPLANTEO04.01.02 40.00 28.51 23.94 0.86 1.34 53.60

    m3EXACAVACION EN TERRENO NORMAL04.01.03 6.10 224.48 11.22 38.64 235.70

    m3RELLENO CON MATERIAL PROPIO04.01.04 0.72 16.56 0.50 23.69 17.06

    m3ELIMINACION DE MATERIAL EXCEDENTE A 30 M04.01.05 6.72 123.65 3.71 18.95 127.34

    m2SOLADO DE CONCRETO C:H 1:10 e=3"04.01.06 5.17 7.36 82.15 10.24 19.28 99.68

    m2ENCOFRADO Y DESENCOFRADO NORMAL04.01.07 26.09 549.18 229.21 16.48 30.48 795.22

    m3CONCRETO FC=175 KG/CM204.01.08 0.41 39.07 136.23 15.41 465.18 190.72

    m3CONCRETO FC=210 KG/CM204.01.09 2.69 256.39 820.93 208.04 477.83 1,285.36

    kgACERO ESTRUTURAL FY=4200 KG/CM204.01.10 98.99 88.60 397.80 5.84 4.98 492.97

    m2TARRAJEO EN INTERIORES Y EXTERIORES (C:A - 1:5)04.01.11 12.69 180.70 61.35 5.42 19.51 247.58

    glbACCESORIOS EN CAMARA DE INGRESO04.01.12 1.00 121.60 1,032.00 6.08 1,159.68 1,159.68

    1,488.03 2,693.93 CAMARA DE SALIDA04.02 263.85 4,447.27

    m2TRAZO Y REPLANTEO04.02.01 40.00 28.51 23.94 0.86 1.34 53.60

    m2LIMPIEZA DE TERRENO MANUAL04.02.02 40.00 184.00 5.52 4.74 189.60

    m3RELLENO CON MATERIAL PROPIO04.02.03 0.20 4.60 0.14 23.69 4.74

    m2SOLADO DE CONCRETO C:H 1:10 e=3"04.02.04 1.84 12.77 29.23 3.94 24.97 45.94

    m3ELIMINACION DE MATERIAL EXCEDENTE A 30 M04.02.05 8.43 155.11 4.65 18.95 159.75

    m2ENCOFRADO Y DESENCOFRADO NORMAL04.02.06 20.42 429.84 179.39 12.90 30.48 622.40

    m3CONCRETO FC=210 KG/CM204.02.07 2.50 238.28 762.94 193.34 477.83 1,194.58

    m3CONCRETO FC=175 KG/CM204.02.08 0.69 65.76 229.26 25.94 465.18 320.97

    kgACERO ESTRUTURAL FY=4200 KG/CM204.02.09 95.06 85.09 382.01 5.61 4.98 473.40

    glbACCESORIOS EN CAMARA DE SALIDA04.02.10 1.00 121.60 1,032.00 6.08 1,159.68 1,159.68

    m2TARRAJEO EN INTERIORES Y EXTERIORES (C:A - 1:5)04.02.11 11.41 162.47 55.16 4.87 19.51 222.61

    1,927.22 15,080.98SIFON04.03 58.24 17,082.95

    mTUBERIA PVC SAP C-10 48mm04.03.01 1,534.40 1,340.49 8,613.20 40.51 6.52 10,004.29

    mTUBERIA PVC SAP C-15 48 MM04.03.02 671.60 586.73 6,467.78 17.73 10.54 7,078.66

    335.53 512.53 CONSTRUCCION DE CAMARA DE REUNION05 31.10 879.44

    1.55 0.60TRABAJOS PRELIMINARES05.01 0.04 2.20

    03/03/2015 09:13:07a.m.Fecha :

  • S10 Pgina 3

    PresupuestoAMPLIACION Y MEJORAMIENTO DEL SISTEMA DE ABASTECIMIENTO AGUA POTABLE - HUAYRURPATAPresupuesto 1201001

    S10 S.A.C. 16/02/2015Costo alClienteLugar AYACUCHO - LA MAR - ANCO

    Precio S/. Parcial S/.Mano de Obra Material Equipo SubcontratoItem Descripcin Und. Metrado

    m2LIMPIEZA Y DEFORESTACION MANUAL05.01.01 2.25 0.83 0.02 0.38 0.86

    m2TRAZO Y REPLANTEO05.01.02 1.00 0.72 0.60 0.02 1.34 1.34

    22.08MOVIMIENTO DE TIERRAS05.02 0.66 22.74

    m3EXCAVACION PARA ESTRUCTURAS MANUAL05.02.01 0.72 22.08 0.66 31.59 22.74

    187.50 349.14OBRAS DE CONCRETO05.03 26.67 563.59

    m3CONCRETO FC=175 KG/CM205.03.01 0.58 55.29 192.71 21.81 465.18 269.80

    m2ENCOFRADO Y DESENCOFRADO NORMAL05.03.02 5.10 107.35 44.80 3.22 30.48 155.45

    kgACERO ESTRUTURAL FY=4200 KG/CM205.03.03 27.78 24.86 111.63 1.64 4.98 138.34

    97.65 31.89REVOQUES Y ENLUCIDOS05.04 2.93 132.48

    m2TARRAJEO EN INTERIOR CON IMPERMEABILIZANTE C:A 1:3 e=1.5cm05.04.01 2.40 42.72 14.48 1.28 24.36 58.46

    m2TARRAJEO EN EXTERIORES CON CEMENTO-ARENA 1:505.04.02 3.60 54.93 17.41 1.65 20.56 74.02

    12.16 116.79 TAPA METALICA05.06 0.36 129.31

    undTAPA METALICA DE 0.60x0.60x1/8"05.06.01 1.00 12.16 116.79 0.36 129.31 129.31

    14.59 14.11 VARIOS05.07 0.44 29.12

    m2PINTURA EN EXTERIORES05.07.01 3.60 14.59 14.11 0.44 8.09 29.12

    1,435.95 827.35VALVULA DE PURGA (04 UNIDADES)06 56.47 2,320.05

    1.55 0.86TRABAJOS PRELIMINARES06.01 0.05 2.48

    m2LIMPIEZA Y DEFORESTACION MANUAL06.01.01 1.44 0.53 0.02 0.38 0.55

    m2TRAZO Y REPLANTEO06.01.02 1.44 1.02 0.86 0.03 1.34 1.93

    23.92MOVIMIENTO DE TIERRAS06.02 0.72 24.64

    m3EXCAVACION PARA ESTRUCTURAS MANUAL06.02.01 0.78 23.92 0.72 31.59 24.64

    247.32 232.18OBRAS DE CONCRETO06.03 19.84 499.48

    m3CONCRETO FC=140 KG/CM206.03.01 0.51 48.61 149.26 13.88 415.20 211.75

    m2ENCOFRADO Y DESENCOFRADO NORMAL06.03.02 9.44 198.71 82.92 5.96 30.48 287.73

    122.05 38.67REVOQUES Y ENLUCIDOS06.04 3.66 164.48

    m2TARRAJEO EN EXTERIORES CON CEMENTO-ARENA 1:506.04.01 8.00 122.05 38.67 3.66 20.56 164.48

    1,041.11 555.64 VARIOS06.05 32.20 1,628.97

    glbACCESORIOS VALVULA DE PURGA EN RED DE DISTRIBUCION06.05.01 4.00 972.80 159.81 29.18 290.45 1,161.80

    undTAPA METALICA DE 0.40x0.40x1/8"06.05.02 4.00 48.64 380.00 2.43 107.77 431.08

    m3FILTRO DE GRAVA06.05.03 0.06 3.88 4.58 0.12 142.92 8.58

    m2EMPEDRADO A LA SALIDA DE LA TUBERIA06.05.04 1.00 15.79 11.25 0.47 27.51 27.51

    7,676.69 6,137.10 CONSTRUCION DE RESERVORIO DE 15 M307 621.61 14,437.10

    49.99 27.67TRABAJOS PRELIMINARES07.01 1.51 79.53

    m2LIMPIEZA Y DEFORESTACION MANUAL07.01.01 46.24 17.02 0.51 0.38 17.57

    m2TRAZO Y REPLANTEO07.01.02 46.24 32.97 27.67 1.00 1.34 61.96

    1,676.71MOVIMIENTO DE TIERRAS07.02 49.19 1,725.86

    m3EXCAVACION PARA ESTRUCTURAS MANUAL07.02.01 29.16 894.25 26.83 31.59 921.16

    03/03/2015 09:13:07a.m.Fecha :

  • S10 Pgina 4

    PresupuestoAMPLIACION Y MEJORAMIENTO DEL SISTEMA DE ABASTECIMIENTO AGUA POTABLE - HUAYRURPATAPresupuesto 1201001

    S10 S.A.C. 16/02/2015Costo alClienteLugar AYACUCHO - LA MAR - ANCO

    Precio S/. Parcial S/.Mano de Obra Material Equipo SubcontratoItem Descripcin Und. Metrado

    m2REFINE,NIVELACION Y COMPACTACION07.02.02 24.30 111.78 2.24 4.69 113.97

    m3ELIMINACION DE MATERIAL EXCEDENTE A 30 M07.02.03 36.45 670.68 20.12 18.95 690.73

    2,492.90 4,170.02OBRAS DE CONCRETO07.03 446.42 7,110.42

    m2ENCOFRADO Y DESENCOFRADO NORMAL07.03.02 69.98 1,473.03 614.77 44.19 30.48 2,132.99

    m3CONCRETO FC=175 KG/CM207.03.03 10.70 1,019.87 3,555.25 402.23 465.18 4,977.43

    1,776.82 558.15REVOQUES Y ENLUCIDOS07.04 53.31 2,389.00

    m2TARRAJEO EN INTERIOR CON IMPERMEABILIZANTE C:A 1:3 e=1.5cm07.04.01 33.00 744.25 199.15 22.33 29.27 965.91

    m2TARRAJEO EN EXTERIORES CON CEMENTO-ARENA 1:507.04.02 47.52 724.98 229.73 21.75 20.56 977.01

    m2MORTERO 1:5 E=1.5 CM PARA PENDIENTES DE FONDO07.04.03 12.96 307.59 129.27 9.23 34.42 446.08

    200.76 250.52 CARPINTERIA METALICA07.05 5.90 457.18

    undTAPA METALICA DE 0.80x0.80x1/8"07.05.01 1.00 42.72 50.00 1.28 94.00 94.00

    undESCALERA DE GATO - DISEO DE 1/2"07.05.02 1.00 151.96 98.50 4.56 255.02 255.02

    undVENTILACION C/TUBERIA DE ACERO S/DISEO DE 3"07.05.03 1.00 6.08 102.02 0.06 108.16 108.16

    436.64 435.52 VARIOS07.06 13.10 885.16

    m2PINTURA ESMALTE EN EXTERIOR07.06.01 25.92 184.58 192.29 5.54 14.75 382.32

    m2EMPEDRADO PERIMETRAL07.06.02 18.24 241.38 205.20 7.24 24.88 453.81

    undHIPOCLORADOR DE FLUJO DIFUSION07.06.03 1.00 10.68 38.03 0.32 49.03 49.03

    1,042.87 695.22 CERCO PERIMETRICO07.07 52.18 1,789.95

    mCERCO PERIMETRICO CON ALAMBRE DE PUAS07.07.01 169.56 674.17 364.08 33.74 6.32 1,071.62

    undCOLUMNAS DE MADERA CON DADO DE CONCRETO C:H 1:807.07.02 11.00 347.34 300.30 17.37 60.46 665.06

    undPUERTA DE MADERA ROLLIZA07.07.03 1.00 21.36 30.84 1.07 53.27 53.27

    300.00 1,189.63 CASETA DE VALVULAS08 20.17 1,510.02

    18.40MOVIMIENTO DE TIERRAS08.01 0.55 18.95

    m3EXCAVACION PARA ESTRUCTURAS MANUAL08.01.01 0.60 18.40 0.55 31.59 18.95

    126.86 214.79OBRAS DE CONCRETO08.02 14.43 356.29

    m2SOLADO H=5 CM ( C:A -1:10)08.02.01 1.10 6.44 15.64 0.19 20.25 22.28

    m3CONCRETO FC=175 KG/CM208.02.02 0.29 27.64 96.35 10.90 465.18 134.90

    m2ENCOFRADO Y DESENCOFRADO NORMAL08.02.03 3.66 77.05 32.16 2.31 30.48 111.56

    kgACERO FY=4200 KG/CM208.02.04 17.58 15.73 70.64 1.03 4.98 87.55

    64.81 18.86REVOQUES Y ENLUCIDOS08.03 1.95 85.65

    m2TARRAJEO EN EXTERIORES CON CEMENTO-ARENA 1:508.03.01 2.03 30.97 9.81 0.93 20.56 41.74

    m2TARRAJEO EN INTERIOR CON IMPERMEABILIZANTE C:A 1:3 e=1.5cm08.03.02 1.50 33.84 9.05 1.02 29.27 43.91

    69.42 934.61SUMINISTRO DE ACCESORIOS EN CASETA VALVULAS DE RESERVORIO08.04 2.62 1,006.65

    glbSUMINISTRO DE ACCESORIOS EN CASETA DE VALVULAS 1 1/2"08.04.01 1.00 26.70 817.82 1.34 845.86 845.86

    undTAPA METALICA DE 0.60x0.60x1/8"08.04.02 1.00 42.72 116.79 1.28 160.79 160.79

    20.51 21.37 PINTURA08.05 0.62 42.48

    m2PINTURA ESMALTE EN EXTERIOR08.05.01 2.88 20.51 21.37 0.62 14.75 42.48

    03/03/2015 09:13:07a.m.Fecha :

  • S10 Pgina 5

    PresupuestoAMPLIACION Y MEJORAMIENTO DEL SISTEMA DE ABASTECIMIENTO AGUA POTABLE - HUAYRURPATAPresupuesto 1201001

    S10 S.A.C. 16/02/2015Costo alClienteLugar AYACUCHO - LA MAR - ANCO

    Precio S/. Parcial S/.Mano de Obra Material Equipo SubcontratoItem Descripcin Und. Metrado

    46,230.70 8,755.51LINEA DE ADUCCION Y DISTRIBUCION09 40,148.25 95,190.06

    2,438.99 313.77TRABAJOS PRELIMINARES09.01 176.07 2,937.07

    m2LIMPIEZA Y DEFORESTACION MANUAL09.01.01 2,011.69 740.30 22.33 0.38 764.44

    mTRAZO, NIVELACION Y REPLANTEO DE ZANJAS09.01.02 2,011.69 1,698.69 313.77 153.74 1.08 2,172.63

    39,278.93 1,441.38MOVIMIENTO DE TIERRAS09.02 38,931.38 79,668.64

    m3EXCAVACION MANUAL DE ZANJAS09.02.01 1,207.01 11,813.79 354.50 10.08 12,166.66

    mREFINE Y NIVELACION FONDO DE ZANJA PARA TUBERIA09.02.02 2,011.69 9,253.77 277.61 4.74 9,535.41

    mCAMA DE APOYO PARA TUBERIAS09.02.03 2,011.69 9,253.77 1,441.38 277.61 5.46 10,983.83

    m3RELLENO Y COMPACTADO DE ZANJAS, CON MATERIAL ZARANDEADO09.02.04 193.12 1,184.40 11,880.07 67.65 13,064.57

    m3RELLENO Y COMPACTADO CON MAT. PROPIO EN ZANJAS09.02.05 675.93 7,773.20 26,141.59 50.18 33,918.17

    2,380.21 6,631.77SUMINISTRO DE TUBERIAS09.03 71.79 9,110.78

    mTUBERIA PVC SAP CLASE 7.5 DE 1 1/2"09.03.01 312.50 477.50 1,233.58 14.34 5.53 1,728.13

    mTUBERIA PVC SAP CLASE 7.5 DE 1"09.03.02 500.00 436.82 1,973.73 13.20 4.86 2,430.00

    mTUBERIA PVC SAP CLASE7.5 DE 3/4"09.03.03 1,199.19 1,465.89 3,424.46 44.25 4.13 4,952.65

    1,918.97 192.92 PRUEBA HIDRAULICA09.04 962.60 3,077.89

    mPRUEBA HIDRAULICA Y DESINFECCION DE SISTEMA09.04.01 2,011.69 1,918.97 192.92 962.60 1.53 3,077.89

    213.60 175.67 ACCESORIOS09.05 6.41 395.68

    glbACCESORIOS PVC SAP EN LA LINEA ADUCCION Y DISTRIBUCION09.05.01 1.00 213.60 175.67 6.41 395.68 395.68

    2,704.06 2,582.07CAMARA ROMPE PRESION T-VI (07 UND)10 174.91 5,461.66

    9.25 3.60TRABAJOS PRELIMINARES10.01 0.28 13.17

    m2LIMPIEZA Y DEFORESTACION MANUAL10.01.01 13.50 4.97 0.15 0.38 5.13

    m2TRAZO Y REPLANTEO10.01.02 6.00 4.28 3.60 0.13 1.34 8.04

    224.48MOVIMIENTO DE TIERRAS10.02 6.74 231.24

    m3EXCAVACION PARA ESTRUCTURAS MANUAL10.02.01 7.32 224.48 6.74 31.59 231.24

    972.20 1,195.44OBRAS DE CONCRETO10.03 122.95 2,291.09

    m3CONCRETO FC=175 KG/CM210.03.01 2.70 257.35 897.11 101.50 465.18 1,255.99

    m2ENCOFRADO Y DESENCOFRADO NORMAL10.03.02 33.96 714.85 298.33 21.45 30.48 1,035.10

    777.99 191.62REVOQUES Y ENLUCIDOS10.04 23.34 993.12

    m2TARRAJEO EN INTERIOR CON IMPERMEABILIZANTE C:A 1:3 e=1.5cm10.04.01 15.12 341.01 91.25 10.23 29.27 442.56

    m2TARRAJEO EN EXTERIORES CON CEMENTO-ARENA 1:5 e=1.5 cm10.04.02 20.76 436.98 100.37 13.11 26.52 550.56

    313.26 275.63VALVULAS Y ACCESORIOS10.05 9.40 598.29

    glbACCESORIOS CAMARA ROMPE PRESION TIPO 6 E 1 1/2" S 1 1/2"10.05.01 7.00 313.26 275.63 9.40 85.47 598.29

    299.04 817.53 TAPA METALICA10.06 8.97 1,125.53

    undTAPA METALICA DE 0.60x0.60x1/8"10.06.01 7.00 299.04 817.53 8.97 160.79 1,125.53

    107.84 98.25 VARIOS10.07 3.23 209.22

    m2PINTURA EN EXTERIORES10.07.01 20.76 84.16 81.37 2.52 8.09 167.95

    m2EMPEDRADO A LA SALIDA DE LA TUBERIA10.07.02 1.50 23.68 16.88 0.71 27.51 41.27

    03/03/2015 09:13:07a.m.Fecha :

  • S10 Pgina 6

    PresupuestoAMPLIACION Y MEJORAMIENTO DEL SISTEMA DE ABASTECIMIENTO AGUA POTABLE - HUAYRURPATAPresupuesto 1201001

    S10 S.A.C. 16/02/2015Costo alClienteLugar AYACUCHO - LA MAR - ANCO

    Precio S/. Parcial S/.Mano de Obra Material Equipo SubcontratoItem Descripcin Und. Metrado

    363.73 716.37VALVULA DE CONTROL (5 UNIDADES)11 24.31 1,104.58

    9.56 1.08TRABAJOS PRELIMINARES11.01 0.29 10.94

    m2LIMPIEZA DE TERRENO MANUAL11.01.01 1.80 8.28 0.25 4.74 8.53

    m2TRAZO Y REPLANTEO11.01.02 1.80 1.28 1.08 0.04 1.34 2.41

    30.05MOVIMIENTO DE TIERRAS11.02 0.90 30.96

    m3EXCAVACION PARA ESTRUCTURAS MANUAL11.02.01 0.98 30.05 0.90 31.59 30.96

    258.15 234.19OBRAS DE CONCRETO11.03 19.92 512.40

    m3CONCRETO FC=140 KG/CM211.03.01 0.50 47.66 146.34 13.60 415.20 207.60

    m2ENCOFRADO Y DESENCOFRADO NORMAL11.03.02 10.00 210.49 87.85 6.32 30.48 304.80

    65.97 481.10REVOQUES Y ENLUCIDOS11.04 3.20 550.28

    undTAPA METALICA DE 0.40x0.40x1/8"11.04.01 5.00 60.80 475.00 3.04 107.77 538.85

    m3FILTRO DE GRAVA11.04.02 0.08 5.17 6.10 0.16 142.92 11.43

    4,466.58 9,320.57CONEXIONES DOMICILIARIAS (94 UNIDADES)12 174.65 13,962.00

    2,858.17MOVIMIENTO DE TIERRAS12.01 85.75 2,944.19

    m3EXCAVACION PARA ESTRUCTURAS MANUAL12.01.01 93.20 2,858.17 85.75 31.59 2,944.19

    309.39 471.34OBRAS DE CONCRETO12.02 49.93 830.77

    m3CONCRETO FC=175 KG/CM212.02.01 1.17 111.52 388.75 43.99 465.18 544.26

    m2ENCOFRADO Y DESENCOFRADO NORMAL12.02.02 9.40 197.87 82.59 5.94 30.48 286.51

    1,299.02 8,849.23SUMINISTRO DE ACCESORIOS12.03 38.97 10,187.04

    glbCONEXION A RED DE DISTRIBUCION D= 1 1/2"12.03.01 13.00 359.18 1,141.76 10.78 116.29 1,511.77

    glbCONEXION A RED DE DITRIBUCION D= 3/412.03.02 52.00 444.29 5,037.37 13.32 105.67 5,494.84

    glbCONEXION A RED DE DISTRIBUCION 1"12.03.03 29.00 495.55 2,670.10 14.87 109.67 3,180.43

    COSTO DIRECTO 469,608.28