Levan Babukhadia

12
Levan Babukhadia D Collaboration Meeting, October 11 - 13, 2000, Fermilab http://www-d0.fnal.gov/~blevan Status of the L1 Trigger SUNY at Stony Brook

description

This presentation will probably involve audience discussion, which will create action items. Use PowerPoint to keep track of these action items during your presentation In Slide Show, click on the right mouse button Select “Meeting Minder” Select the “Action Items” tab - PowerPoint PPT Presentation

Transcript of Levan Babukhadia

Page 1: Levan Babukhadia

Levan BabukhadiaLevan Babukhadia

D Collaboration Meeting, October 11 - 13, 2000, FermilabD Collaboration Meeting, October 11 - 13, 2000, Fermilab

http://www-d0.fnal.gov/~blevan

Status of the L1 TriggerStatus of the L1 Trigger

SUNY at Stony BrookSUNY at Stony Brook

Page 2: Levan Babukhadia

DØ Collaboration Meeting, October 11 - 13, 2000, Fermilab Levan Babukhadia

CTPT/FPS ComponentsCTPT/FPS Components– Analog (Fermilab - DØ)

• AFE-8MCM (primarily CFTax): – 10 here, ready by 11/01, 54 more by 12/15, balance 01/30/01

• Crates/Cables on hand, installed when required• Power supplies delayed until new year (partial).

– Mixer ( Fermilab - CD )– Super-sector (1/5th) mid-November– Full Mixer 1/01

– Digital ( Fermilab - DØ )– All MBs here and in testing– Transition boards expecting in ~2 weeks– CTPT DBs (single-wide, 5 Virtex 2.5v FPGAs) by mid-

November – FPS DBs (double-wide, 3 Virtex 2.5v FPGAs) partial order

out– Xilinx/Virtex FPGAs for CTOT on order, others held until

further decision, Virtex vs. Virtex-E– Crates/Cables/PS all here by mid-November

Page 3: Levan Babukhadia

DØ Collaboration Meeting, October 11 - 13, 2000, Fermilab Levan Babukhadia

CTTP/FPS Firmware: CFT/CPS AxialCTTP/FPS Firmware: CFT/CPS Axial

– DFEA (80) : Jamieson Olsen (Kin is gone)• Both L1/L2 firmware in good shape• 4 FPGAs find tracks in 4 Pt and report to 5-th FPGA and to Muon• Backend (5-th) FPGA does CPS cluster finding and track matching

– firmware has to be re-written, concerns on the chip size– expect functional and tested firmware in a couple of months

– CTOC (8) : Juan Lizarazo, now Ricardo Rodrigez • Both L1/L2 firmware completed and tested in testbench• Minor issues and additions will be addressed by Ricardo/Manuel

– CTQD (4) : Pavel Polozov now gone• L2CFT part completed functionally with some minor issue• Needs implementation, L2CPS, and all of this tested in the

hardware

– CTTT (1) : Jerry Blazey• Algorithm/VHDL/Functional/Implementation at ~20%• 2 out of 64 Trigger Terms done through the implementation phase• L1->L3 sender, finish all VHDL, implementation, hardware test

stand

Page 4: Levan Babukhadia

DØ Collaboration Meeting, October 11 - 13, 2000, Fermilab Levan Babukhadia

CTTP/FPS Firmware: CPS StereoCTTP/FPS Firmware: CPS Stereo

– DFES (5) : Qichun Xu, MSU• No link to L1 TM, straight to L2 and L3, thus has time!• Main issue is cluster finding in the large number (~500) of CPS

stereo strips in a sector but having time may save the day...• New MSU student Qichun Xu, just started

– Made a good head-start with an overall algorithms and the cluster finding algorithms in particular

• Start writing VHDL, expect functional code in about 1-2 months

– CPSS (2) : ?!• Nobody yet! Perhaps Qichun will take on this one as

well ...

Page 5: Levan Babukhadia

DØ Collaboration Meeting, October 11 - 13, 2000, Fermilab Levan Babukhadia

CTTP/FPS Firmware: FPSCTTP/FPS Firmware: FPS

– DFEF (32) : Levan Babukhadia• Challenge: cluster finding in 144 FPS strips at the L1 rate• L1 U/V algo developed, coded, and implemented; test stand is

next– L1U and L1V each takes Xilinx/Virtex 400 FPGA (~75%, 63 MHz)

• Develop L2 priority reporting algo to take care of truncation. It is aimed at the 3rd FPGA– Transferring clusters within a DB or find clusters anew?...

– FPSS (4) : Mrinmoy Bhattacharjee• L1 algo developed, coded, and implemented w/o the L3 sender

– fits in one Xilinx/Virtex 400 FPGA (~30%, 66 MHz)• Develop L2 algorithm

– FPTT (1) : Satish Desai• L1 algo developed, coded, and implemented w/o the L3 sender

– fits in one Xilinx/Virtex 400 FPGA (~20%, 64 MHz)• Complete all L1 functionally, test stand by the end of October

Page 6: Levan Babukhadia

DØ Collaboration Meeting, October 11 - 13, 2000, Fermilab Levan Babukhadia

CTPT/FPS Installation/Commissioning

CTPT/FPS Installation/Commissioning

•Assembling test stands for digital/VHDL testing– Hardware: 2 PCs, MBs, 2 Data Pump Boards, PS, cables,

CTPT/FPS DBs» 1 fully stuffed double-wide DB» 10 fully stuffed single-wide DBs

– Personnel: Jamieson Olsen, Brian Connolly (very short time), Ricardo Rodrigez, and a new part-time tech

– Had 1 working test stand but recently moved to DAB3/NE; will be made operational this week

– Aiming at having 2 “single board” bench-tops and 1 “multi-board” test stand (for a one sparse system test -- available now, Jamieson)

• Installing cables/crates on platform•Crates/Cables installed in MCH

Page 7: Levan Babukhadia

DØ Collaboration Meeting, October 11 - 13, 2000, Fermilab Levan Babukhadia

– Components• Scintillator (48) complete• CAFÉ boards (175) on hand• Completing ADC (~12) board layout, ordering parts• Vertex board, FPGA 75% complete, layout commencing• Procuring signal cables (~60) soon• Crate/PS on hand

– Installation/Commissioning• Installed scintillator (4/00) • Cabling awaits FPS, commissioning thereafter

– Software/Firmware• Working on embedded software• Download currently underway• Database under development

– Schedule (on time)• Electronics installed, February 1; Lum Monitoring March 1• And/Or terms, March-April

Luminosity Monitor StatusLuminosity Monitor Status

Page 8: Levan Babukhadia

DØ Collaboration Meeting, October 11 - 13, 2000, Fermilab Levan Babukhadia

– Timing signal generation and distribution• Some work has been done and some tests have been made• Initial implementation will probably cover just the CC racks

– L2/L3 readout complete (by November)• Uses much of the same equipment as the readout from the TF• All circuit boards exist and initial designs of all the FPGAs exist

– Analog input circuit (pick-off) boards (320) • Prototypes of this exist and some testing has been done• 1FTE month to production

– Quadrant Terms

• Circuit board (40) and FPGA design work has been started• No prototypes exist yet• Will not be pushed in the immediate future

– Schedule (late but well before 3/01)• Inactive until TF complete 11/00. Resume within a month• Start with analog pick-offs

L1 Calorimeter Trigger StatusL1 Calorimeter Trigger Status

Page 9: Levan Babukhadia

DØ Collaboration Meeting, October 11 - 13, 2000, Fermilab Levan Babukhadia

L1MU Hardware (4 crates, prod beginning UAz)– Crate Manager (MTCM)

• Production card testing in progress

– Motherboard (MTCxx - Trigger Card) • Production cards beginning fabrication

– Flavor Boards

• Production Trigger Manager (MTM) boards ready for fabrication• Production wire DB (MTC10) design in progress (finish in ~2

weeks) • Preproduction scintillator DB (MTC05) in fabrication

– SLDBs (Gbit/s Serial Links)• Production board testing in progress

Software/Firmware– Download infrastructure in place– Preproduction versions of all firmware exist– No alarms, monitoring

L1 Muon Trigger StatusL1 Muon Trigger Status

Page 10: Levan Babukhadia

DØ Collaboration Meeting, October 11 - 13, 2000, Fermilab Levan Babukhadia

MCEN Hardware (5 crates, in preprod testing BU)– Crate Manager (MCCM)

• Preproduction card layout in progress

– Centroid Finder Cards (MCEN) • Preproduction card testing in progress

– Physics Boards (MCPB)• Preproduction board testing in progress

Infrastructure– Custom VME backplanes completed– Power supplies

• Prototype assembled and tested• VICOR supplies ordered but with 20-22 week lead time

– Platform Services -- on hold pending final cable plant design

– Cabling (~1,600)• Production at Fermilab and NIU in progress

L1 Muon Trigger StatusL1 Muon Trigger Status

Page 11: Levan Babukhadia

DØ Collaboration Meeting, October 11 - 13, 2000, Fermilab Levan Babukhadia

Near Term Commissioning Goals– Mid-August

• Stable operation of one (sparse) L1MU trigger crate and the L1MU MTM crate– still using preproduction cards

– Early October• Add L1CTPT MTM crate to the above

– Mid-October• Begin commissioning production of L1MU crates and cards

Longer Term Commissioning Goals– Begin full crate testing in late Dec or early Jan

• Two octant triggering until then• MCEN cards ~2 months behind above• Temporary power supplies for full crate tests

L1 Muon Trigger StatusL1 Muon Trigger Status

Page 12: Levan Babukhadia

DØ Collaboration Meeting, October 11 - 13, 2000, Fermilab Levan Babukhadia

– All equipment operational and installed• Defective SCL cables are being repaired

– L3 readout• Finish up making readout to L3 available for normal use (by 1/11)

– Master Clock synchronization with the Tevatron beam• This work now starting

– Operational permit• Need to install 5 fuse blocks and write the documentation

– L1 Specific Trigger Fired Mask to L2• Needed to make the Pseudo-Terms work• Deferred until some progress on getting L1 Cal Trigger running

again

– Firmware• Completion of pseudo-terms• Commissioning run-control

– Personnel• Major loss of two engineers. Replacement uncertain

Trigger Framework StatusTrigger Framework Status