I2PiquesProfundización2

download I2PiquesProfundización2

of 99

Transcript of I2PiquesProfundización2

  • 8/14/2019 I2PiquesProfundizacin2

    1/99

    1

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    PIQUES y CHIMENEAS:Diseo, Construccin y OperacinPIQUES y CHIMENEAS:Diseo, Construccin y Operacin

    Ph. D., P. Eng. TADEUSZ S. [email protected] INTERCADE

    Junio 2008

  • 8/14/2019 I2PiquesProfundizacin2

    2/99

    2

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    2. EXCAVACION DE PIQUES(Conventional Shaft Sinking)

    2. EXCAVACION DE PIQUES(Conventional Shaft Sinking)

    2

  • 8/14/2019 I2PiquesProfundizacin2

    3/99

    3

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    SHAFT SINKINGSHAFT SINKING3

  • 8/14/2019 I2PiquesProfundizacin2

    4/99

    4

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    VARIETY OF SHAFTSVARIETY OF SHAFTS

    Most likely choice:

    Vertical shaft.

    Circular shaft.

    Combination one. Concrete lined

    shaft. Steel sets.

    Other decisions:

    Drill or sink theshaft?

    Shaft diameter. Shaft depth.

    Type of rock.

  • 8/14/2019 I2PiquesProfundizacin2

    5/99

    5

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    In 1987 Shaft Sinkers set an international

    mechanised sinking record (200.4 m in one month at

    Vaal Reefs No 10 shaft). To do this, a shaft sinking

    jumbo - designed and manufactured by the Group

    was employed.

    Shaft Sinkers also holds claim to the deepest shaft

    ever sunk (3 583m below surface at Western Deep

    Levels) .

    as well as the widest (a 19m diameter shaft at the

    Drakensberg Pumped Storage Scheme).

    RECORDS RECORDS

  • 8/14/2019 I2PiquesProfundizacin2

    6/99

    6

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    7

  • 8/14/2019 I2PiquesProfundizacin2

    7/99

    7

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    PREPARATIONSPREPARATIONS

    Determination of geologic and hydrologic

    conditions. Permitting, surveying, documentation.

    Site access.

    Site preparation.

    Prevent flooding!

    Supplies & services.Power, water, compressed air, maintenance,

    storage

    8

  • 8/14/2019 I2PiquesProfundizacin2

    8/99

    8

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    SITE PREPARATIONSITE PREPARATION

    9

  • 8/14/2019 I2PiquesProfundizacin2

    9/99

    9

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    PREPARATIONS PREPARATIONS

    Covered storage for construction materials. A ramp for unloading of heavy machinery ( or

    have a crane available). Installation of shaft sinking equipment.

    Use final headgear?

    Excavation / earthwork needed for shaft

    collar.

    10

  • 8/14/2019 I2PiquesProfundizacin2

    10/99

    10

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    MORE PREPARATIONSMORE PREPARATIONS

    Water

    Use shaft water (industrial water?).

    Wells outside of the shaft drainage cone.

    Industrial (120 m3) & tap (60 m3) water.

    Storm water: control measures. Power

    Substation of up to 2000 kVA.

    Two independent sources of supply!

    Diesel generators (a back-up?).

    11

  • 8/14/2019 I2PiquesProfundizacin2

    11/99

    11

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    OTHERS (SOME)OTHERS (SOME)

    Explosives storage. Fan housing (ventilation).

    Transformer station.

    Lamp / change house.

    Compressor shed.

    Stage hoist building. Office trailer / building.

    Living accommodations?.

    ..

    12

  • 8/14/2019 I2PiquesProfundizacin2

    12/99

    12

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    1Headframe

    2- Winder

    3- Compressor

    4- Fan5- Maintenance

    6- Concrete plant

    7- Open storage

    8- Concrete

    winch

    9- Stage winch

    10-Office

    11-Machine shop

    12-Emergency

    hoist

    13-Water tank14-Transformers

    15-Compressed

    air tank

    16-Genset

    13

  • 8/14/2019 I2PiquesProfundizacin2

    13/99

    13

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    SHAFT BORING SITESHAFT BORING SITE

    14

  • 8/14/2019 I2PiquesProfundizacin2

    14/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    SHAFT SINKING METHODSSHAFT SINKING METHODS

    ConventionalDrill-blast-vent-muck-line cycle.

    Shaft boring. Non-conventional methods

    Rocks with extensive fracture pattern and

    water inflows over 0.5 m3/min.

    Loose, water bearing ground; also weak and

    plastic.Methods include grouting, freezing, & other.

    15

    CONVENTIONAL CONVENTIONAL

  • 8/14/2019 I2PiquesProfundizacin2

    15/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    CONVENTIONAL

    SHAFT SINKING

    CONVENTIONAL

    SHAFT SINKING

    16

  • 8/14/2019 I2PiquesProfundizacin2

    16/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    17

  • 8/14/2019 I2PiquesProfundizacin2

    17/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    CONVENTIONAL SHAFT SINKINGCONVENTIONAL SHAFT SINKING

    18

  • 8/14/2019 I2PiquesProfundizacin2

    18/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Use the permanent (final)headframe?

    Three deck stage

    19

  • 8/14/2019 I2PiquesProfundizacin2

    19/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Example: Three deck stage

    Deck 1: shaft steel sets installation. Decks 2 & 3: stripping, lowering and setting steel concrete

    forms.

    Deck 3: suspension for mucking units.

    Three winch

    stage suspension

    (+ an emergency

    one)

    Weight: 35t

    20

  • 8/14/2019 I2PiquesProfundizacin2

    20/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Crash doors

    Crash beams

    Jack catchers

    21

  • 8/14/2019 I2PiquesProfundizacin2

    21/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    22

  • 8/14/2019 I2PiquesProfundizacin2

    22/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    23

  • 8/14/2019 I2PiquesProfundizacin2

    23/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Five deck stage

    Weight 55 t

    24

  • 8/14/2019 I2PiquesProfundizacin2

    24/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    CONVENTIONAL SINKING

    DRILL-BLAST-VENT-MUCK-LINE

    CONVENTIONAL SINKING

    DRILL-BLAST-VENT-MUCK-LINE Simultaneous sinking and lining.

    All work in the same section of the shaft. Delayed lining.

    Sinking and lining done at the same time

    butin different shaft sections.

    Separate sinking and lining.

    Sinking first and then lining. Center drillhole for mucking ??

    If the access is available!

    25

  • 8/14/2019 I2PiquesProfundizacin2

    25/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    SIMULTANEOUS SINKING AND LININGSIMULTANEOUS SINKING AND LINING

    Sinking and lining done in one work cycle.

    Lining erected upwards (blocks, bricks).Lining lowered downwards.

    (underhanging tubing). No need for temporary rock support.

    Lining can be delayed for up to 10 m (?) incompetent rock.

    26

    PARALLEL SINKING & LINING

  • 8/14/2019 I2PiquesProfundizacin2

    26/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    PARALLEL SINKING & LINING

    ( IN SEPARATE SECTIONS)

    PARALLEL SINKING & LINING

    ( IN SEPARATE SECTIONS)

    High capital cost.

    Long shaft life?

    Used in large diameter

    and deep shafts.

    Temporary rock support

    usually is needed.

    27

    SEQUENTIAL SINKING AND LININGSEQUENTIAL SINKING AND LINING

  • 8/14/2019 I2PiquesProfundizacin2

    27/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    SEQUENTIAL SINKING AND LININGSEQUENTIAL SINKING AND LINING

    Shaft sunk in sections of up to 50 m deep.

    Actual length depends on rock quality. Temporary lining installed during sinking.

    To prevent rock falls & accidents.

    Lining of the section done when the sinkingstops.

    Slow sinking rate.

    Low capital expenditure.

    Suitable for small dia & shallow shafts.

    28

  • 8/14/2019 I2PiquesProfundizacin2

    28/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Begin cycle.

    Lower drill jumbo.

    Dril l out andLoad round

    Raise stage 60 m

    Clear shaft and blast.

    Blow fumes.

    Lower stage

    Lower bucketsLower loader

    Muck .

  • 8/14/2019 I2PiquesProfundizacin2

    29/99

    30

  • 8/14/2019 I2PiquesProfundizacin2

    30/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    31

    SIMPLE TEMPORARY LININGSIMPLE TEMPORARY LINING

  • 8/14/2019 I2PiquesProfundizacin2

    31/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    1- Ring, 2 Rock bolt supporting the ring, 3 Suspending hook for the next

    ring, 4 Iron sheet liners, 5 Fastening wedges, 6 - Permanent lining

    SIMPLE TEMPORARY LININGSIMPLE TEMPORARY LINING

    32

    DEWATERINGDEWATERING

  • 8/14/2019 I2PiquesProfundizacin2

    32/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    DEWATERINGDEWATERING

    Kibbles.

    Submersible pumps.

    Airlifts.

    Combinations of some /all of the above.

    Max. inflow 0.5 m3/min.

    33

    SHAFT COLLARSSHAFT COLLARS33

  • 8/14/2019 I2PiquesProfundizacin2

    33/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    SHAFT COLLARSSHAFT COLLARS

    3434

  • 8/14/2019 I2PiquesProfundizacin2

    34/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    35

  • 8/14/2019 I2PiquesProfundizacin2

    35/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Foundation on :

    Shaft head Circular wall Total depth:

    15 to 25 m

    36

  • 8/14/2019 I2PiquesProfundizacin2

    36/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Force distribution in

    the shaft collar

    35 deg.

    37

  • 8/14/2019 I2PiquesProfundizacin2

    37/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Shaft Collar:(example #1)

    1, 2 heated airways.3 - water pipes.

    4 ladder compart-

    ment access.

    5 power cables.

    6 compressed air.

    7 - Basement for

    pushers.

    38

  • 8/14/2019 I2PiquesProfundizacin2

    38/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Shaft Collar:(example #2)

    1 lining.2 heated air

    channels.

    3 ladder compart-

    ment access.

    4 power cables.

    5 compressed air

    and water pipes.6 Basement.

    39

  • 8/14/2019 I2PiquesProfundizacin2

    39/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Ventilation ShaftCollar:

    1 lining.2 insulation .

    3 ventilation air

    channel.4 safety grate.

    5 ladder.

    6 railing.

    40

  • 8/14/2019 I2PiquesProfundizacin2

    40/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    DIMENSIONING LEVEL ACCESSDIMENSIONING LEVEL ACCESS

    L maximum length

    (transported material)D shaft diameter.

    H clearance

    H = 0.7 (L D)

    Note:For = 450, D = 0.7 D

    41

  • 8/14/2019 I2PiquesProfundizacin2

    41/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    42

    SHAFT BOTTOM DEPTHSHAFT BOTTOM DEPTH

  • 8/14/2019 I2PiquesProfundizacin2

    42/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    SHAFT BOTTOM DEPTHSHAFT BOTTOM DEPTH

    A fixed guides.

    B rope guides.

    1 Fixed guides.

    2 tail rope

    loop.3 - guide rope

    weights.

    4 rope guides.

  • 8/14/2019 I2PiquesProfundizacin2

    43/99

    44

  • 8/14/2019 I2PiquesProfundizacin2

    44/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Time needed to

    Sink 1 m of shaft

    (an example):

    1 Mucking.2 Drilling.

    3 Loading of

    holes..

    4 Total time

    Optimize!Optimize!

    45

    DRILLING PATTERNSDRILLING PATTERNS

  • 8/14/2019 I2PiquesProfundizacin2

    45/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    DRILLING PATTERNS

    Accuracy of excavation (overbreak!).

    Clear rock separation at the hole bottoms. Even and sufficient rock fragmentation.

    Eliminate damage to any shaft installationsor structure.

    Avoid cut-offs of neighboring active holes.

    46

    Drillhole pattern: (a) siltstone, (b) shale, (c) sandstone

  • 8/14/2019 I2PiquesProfundizacin2

    46/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Small diameter, circular shafts

    47

    DRILLHOLE PATTERN IN INCLINEDDRILLHOLE PATTERN IN INCLINED

  • 8/14/2019 I2PiquesProfundizacin2

    47/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    STRATASTRATA

    Inclination

    over 45 deg.

    Wedge holes

    located along

    strike.

    Overbreak

    larger onhanging

    Strata.

    48

  • 8/14/2019 I2PiquesProfundizacin2

    48/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Wedge Cut Pyramid Cut

    Rectangular shafts

  • 8/14/2019 I2PiquesProfundizacin2

    49/99

    50

  • 8/14/2019 I2PiquesProfundizacin2

    50/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Sample drilling pattern

    for a 9 m diameter shaft(wedge cut)

    51

    TREND TOWARDS BURN CUTS & LONGER HOLESTREND TOWARDS BURN CUTS & LONGER HOLES

  • 8/14/2019 I2PiquesProfundizacin2

    51/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    (WITH SUSPENDED DRILL JUMBOS)(WITH SUSPENDED DRILL JUMBOS)

  • 8/14/2019 I2PiquesProfundizacin2

    52/99

    53

    Typical bench cut

  • 8/14/2019 I2PiquesProfundizacin2

    53/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Typical bench cut

    Using 1-3/8 or 1-174 holes

    Roach and Roy, 2007

    54

  • 8/14/2019 I2PiquesProfundizacin2

    54/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Typical bench cut

    Using 1-3/8 or 1-174 holesRoach and Roy, 2007

    55

    BENCH CUT: FEATURESBENCH CUT: FEATURES

  • 8/14/2019 I2PiquesProfundizacin2

    55/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Easier water handling due to availability of asump.

    Bench can be blown clear to check for misfires. The force of the blast is directed into the shaft

    wall.

    Rather than into stage /Galloway minimizingdamage from fly rock.

    Rockbursts are minimized.Shaft bottom has a chance of relieve itself ofthe stress in section.

    56

  • 8/14/2019 I2PiquesProfundizacin2

    56/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Typical cut

    Design(full face circular

    shaft round)

    25-6 / 7.8 m

    diameter

    Shaft

    Roach & Roy, 2007

    57

    Shaft layout

    d ti i

  • 8/14/2019 I2PiquesProfundizacin2

    57/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    and timing

    2 dia holesRoach & Roy, 2007

    58

    MORE ON FULL FACE ROUNDSMORE ON FULL FACE ROUNDS

  • 8/14/2019 I2PiquesProfundizacin2

    58/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Reamer holes one foot longer.Boreholes break fully.

    Provides concave sump.

    59

    BLASTHOLESBLASTHOLES

  • 8/14/2019 I2PiquesProfundizacin2

    59/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Currently at 200 to 250 mm maximum (reamer

    holes).

    Large hole diameter:

    Reduces footage of drilling.

    Reduces consumption of explosives.

    Small hole diameter.

    Hand drilling only. Bulk loading of explosives is becoming common.

    60

    EXPLOSIVESEXPLOSIVES

  • 8/14/2019 I2PiquesProfundizacin2

    60/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Anfo- based slurries and emulsions largely

    replaced the nitroglycerine basedexplosives.

    Safety, bulk loading.

    Consumption is largely independent of

    shaft diameter.

    Consumption decreases with blastholesize.

    61

    LOADING OF EXPLOSIVESLOADING OF EXPLOSIVES

  • 8/14/2019 I2PiquesProfundizacin2

    61/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Bulk explosives allow faster loadingCartridged explosives largely phased-

    out. Pneumatic loading common.

    Several holes loaded at the same time.Shaft extruder vessel employed.

    Loading four holes simultaneously all 76two inch blastholes are loaded within 32

    minutes.

    62

    BULK EMULSION EXPLOSIVESBULK EMULSION EXPLOSIVES

  • 8/14/2019 I2PiquesProfundizacin2

    62/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Less expensive than cartridged ones.

    Faster loading.

    Reduced drilling time.

    Ability to use larger, longer blastholes, thus

    fewer holes. Eliminates misfired holes due to cartridge

    ejection.

    Reduces hazards.

    Vs. detonator sensitive explosives.

    63

    CONSUMPTION OF EXPLOSIVESCONSUMPTION OF EXPLOSIVES

  • 8/14/2019 I2PiquesProfundizacin2

    63/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Depends on physical properties of rock

    20 to 30% less in shales than in hard

    sandstones.

    Still higher in hard, homogeneous rock.

    Depends on hole size (see above) andlength.

    Consumption decreases with increasinghole utilization factor.

    64

    CONSUMPTION OF EXPLOSIVES, kg/m3CONSUMPTION OF EXPLOSIVES, kg/m3

  • 8/14/2019 I2PiquesProfundizacin2

    64/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Hole utilization

    factor, lo/l

    65

    HOLE UTILIZATION FACTORHOLE UTILIZATION FACTOR

  • 8/14/2019 I2PiquesProfundizacin2

    65/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Rock does not fragment at bottom of the

    Blasthole.

    Blasthole utilization factor:F = Lo / L

    Where:Lo utilized length of Blasthole.

    L - drilled length of blasthole.

    F grows with increasing hole diameter.

    There is an optimum F (see below).

    66

  • 8/14/2019 I2PiquesProfundizacin2

    66/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Shale

    Q = 1.1 kg/m3

    Cartridge 32 mm

    67

    Time needed to

  • 8/14/2019 I2PiquesProfundizacin2

    67/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Time needed to

    sink 1 m of shaft

    (an example):

    1 Mucking.2 Drilling.

    3 Loading of

    holes.

    4 Total time.

    Optimize!

    68

  • 8/14/2019 I2PiquesProfundizacin2

    68/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Three-ring connection

    of electric caps:

    1 Cable.

    2 Protecting pipe.

    3, 4 Active antenna.

    5 Passive antenna.

    6 Electric caps

    (in holes).

    7 Supporting sticks.

    69

    NONEL SYSTEM

    REPLACING ELECTRIC DETONATORS

    NONEL SYSTEM

    REPLACING ELECTRIC DETONATORS

  • 8/14/2019 I2PiquesProfundizacin2

    69/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    REPLACING ELECTRIC DETONATORSREPLACING ELECTRIC DETONATORS

    Extremely resistant to accidental

    detonation.By static electricity and stray electric

    currents.

    By radio transmission.

    Flames, friction or impact.

    By now an industry standard.

    Electronic detonators?

    70

    MUCKINGMUCKING70

  • 8/14/2019 I2PiquesProfundizacin2

    70/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Cryderman

    mucker

    71

  • 8/14/2019 I2PiquesProfundizacin2

    71/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    72

    TYPES OF MUCKERSTYPES OF MUCKERS

  • 8/14/2019 I2PiquesProfundizacin2

    72/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Cactus grab.

    Either light or heavy on central pivot.

    Hand-guided while hanging from the platform.

    Muckers.

    Usually rocker muckers, eg Eimco.Driven by an operator.

    Cryderman muckers.

    Scrapers.

    Rectangular & large diameter shafts.

    73

  • 8/14/2019 I2PiquesProfundizacin2

    73/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    74

    WHAT AFFECTS MUCKING EFFICIENCY?WHAT AFFECTS MUCKING EFFICIENCY?

  • 8/14/2019 I2PiquesProfundizacin2

    74/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    75

    TYPICAL CYCLE TIME 4 TO 10 HRSTYPICAL CYCLE TIME 4 TO 10 HRS

  • 8/14/2019 I2PiquesProfundizacin2

    75/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Example: Bechtel, Nevada

    76

    Time needed to

  • 8/14/2019 I2PiquesProfundizacin2

    76/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Sink 1 m of shaft(an example):

    1 Mucking.2 Drilling.

    3 Loading of

    holes.

    4 Total time.

    Optimize!

    77

  • 8/14/2019 I2PiquesProfundizacin2

    77/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    78

    COMMENT(CIM MAGAZINE)

    COMMENT(CIM MAGAZINE)

  • 8/14/2019 I2PiquesProfundizacin2

    78/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    ( )

    1970 to 2007 was the only time period to date

    where sinking rates were not increased

    drastically through some improvement in

    technology.

    One very important aspect of shaft sinking did

    improve, however, and that is safety. Accident

    rates on shaft sinking projects have droppedappreciably over the period.

    79

    CIM: HISTORY OF SHAFT SINKINGCIM: HISTORY OF SHAFT SINKING

  • 8/14/2019 I2PiquesProfundizacin2

    79/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    80

    80

  • 8/14/2019 I2PiquesProfundizacin2

    80/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    (SAMPLE)

    REGULATIONS

    (SAMPLE)

    REGULATIONS

    A good guideline

    for shaft

    sinking operation.

    81

    GENERAL DUTY OF CAREGENERAL DUTY OF CARE

  • 8/14/2019 I2PiquesProfundizacin2

    81/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    An employer, contractor or owner must ensure

    that all shafts in a mine are designed,

    constructed and maintained to safely bear theloads that may reasonably be anticipated to be

    placed on them.

    82

    NOTICENOTICE As soon as is reasonably possible but not later than 90

  • 8/14/2019 I2PiquesProfundizacin2

    82/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    days before a shaft-sinking operation commences, anemployer, contractor or owner must give notice of the

    shaft-sinking operation by submitting to the chief mines

    inspector:(a) the drawings and specifications for:

    (i) the sinking procedure to be used.

    (ii) the shaft lining program.

    (iii) the equipment to be used in the sinking

    rocess, including dump doors; and

    (iv) the shaft collar; and

    (b) the primary and secondary signal systems to

    be used during a shaft-sinking operation.

    83

    SHAFT COLLARSHAFT COLLAR

  • 8/14/2019 I2PiquesProfundizacin2

    83/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    An employer, contractor or owner must ensure thatevery shaft or raise opening at the surface is

    provided with a collar that is:

    a) designed and constructed in accordance withsound engineering practices to prevent any

    person or equipment from falling into the shaft or

    raise.b) made of concrete or equivalent material; and

    c) if reasonably practicable, secured to the

    bedrock.

    84

    DESIGN OF SHAFT SINKING EQUIPMENTDESIGN OF SHAFT SINKING EQUIPMENT

  • 8/14/2019 I2PiquesProfundizacin2

    84/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    An employer, contractor or owner must ensure that theconveyance used in the shaft sinking, its components, the

    hoisting system and mountings, and the crosshead are

    designed, constructed, installed, operated and maintained

    so that the conveyance is capable of transporting workers

    safely.

    2) Without limiting the generality of subsection (1), if a shaft

    is being sunk, an employer, contractor or owner mustensure that:

    a) the conveyance measures at least 1 070

    millimetres from the floor of the conveyance to thetop of the side of the conveyance; and

    b) the suspension members of the conveyance are

    securely attached to the hoist rope.

    85

    MORE .MORE .3) If the distance between the shaft collar and the shaft bottom is

  • 8/14/2019 I2PiquesProfundizacin2

    85/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    greater than 60 metres, the employer or contractor must ensurethat:

    a. the crosshead:

    I. lands on at least two chairs at the bottom

    crosshead stop to prevent distortion of thecrosshead;

    II. is equipped with a safety device for attaching theconveyance to the crosshead so that the

    crosshead cannot jam in the shaft compartmentwithout stopping the conveyance; andIII. is of a type that encloses the conveyance

    unless the shaft compartment is tightlylined and the conveyance is barrel-shaped.

    4)An employer or contractor shall not require or permit persons tobe transported in a conveyance during a shaft-sinking operationunless the requirements of subsections (1) to (3) are met.

    86

    DOORSDOORS

    During a shaft-sinking operation, an employer or

  • 8/14/2019 I2PiquesProfundizacin2

    86/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    contractmust ensure that dump doors meeting therequirements of subsection (2) are installed at theconveyance dumping position.

    2) The dump doors required by subsection (1) must:

    a) prevent the conveyance from being

    dumped while the dump doors are open;b) prevent any material from falling down the shaft

    while the conveyance is being dumped;

    c) be equipped with devices that mechanically latchthe dump doors out of the shaft compartment

    automatically when the dump doors are fully open.

    87

    MOREMORE3) During shaft-sinking operations, an employer or contractor must

    ensure that service doors are:

    ) i t ll d t th ll d

  • 8/14/2019 I2PiquesProfundizacin2

    87/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    a) installed at the collar; and

    b) equipped with devices that mechanically latch the service

    doors out of the shaft compartment automatically when

    the service doors are fully open.4) An employer or contractor must ensure that the doors required

    by subsections (1) and (3) are closed while a conveyance is:

    a) being loaded with tools or materials; orb) being unloaded.

    c) Except when a closed crosshead that provides

    equivalent protection for persons is in use, an employeror contractor must ensure that the doors required by

    subsections (1) and (3) are closed while persons are

    entering or leaving a conveyance.

    88

    SIGNAL LIGHTSSIGNAL LIGHTS

  • 8/14/2019 I2PiquesProfundizacin2

    88/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    An employer or contractor must ensure that dual

    lights are installed at the hoist operator's position

    that activate automatically to indicate to the hoistoperator that:

    (a) the crosshead and conveyance are

    descending together from the dumping

    position; and(b) the dump doors and service doors are

    closed or open.

    89

    MULTI-DECK STAGEMULTI-DECK STAGE

  • 8/14/2019 I2PiquesProfundizacin2

    89/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    If a multi-deck stage is used during a shaft-sinking

    operation, an employer, contractor or owner must

    ensure that:(a) the multi-deck stage is:

    (i) designed by a professional engineer;

    (ii) constructed, installed, operated andmaintained in accordance with the design

    mentioned in subclause (i); and

    (b) any ropes used with the multi-deck stage meet

    the load factor requirements set out in section 160.

    90

    OPEN HOOKS ARE PROHIBITEDOPEN HOOKS ARE PROHIBITED

  • 8/14/2019 I2PiquesProfundizacin2

    90/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    During a shaft-sinking operation, an employer or

    contractor must ensure that no open hooks are

    used to suspend any staging, working platform,

    conveyance or other equipment in the shaft.

    91

    MEANS OF ESCAPEMEANS OF ESCAPE

    Subject to subsection (2) during a shaft sinking operation an

  • 8/14/2019 I2PiquesProfundizacin2

    91/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Subject to subsection (2), during a shaft-sinking operation, anemployer or contractor must ensure that a suitable manway is

    constructed and maintained in the shaft from the collar to the

    sinking stage.

    2) An employer or contractor may install an independently-powered

    escape conveyance in a shaft in place of a manway, but the

    conveyance must be fully operational before the shaft exceeds a

    depth of 30 metres.3) The employer or contractor must provide an auxiliary ladder that:

    a) extends from the permanent ladder or the sinking stage to the

    bottom of the shaft; andb) is located and attached so that it can be promptly lowered to

    any point at which workers are working.

    92

    BEFORE HOISTING A SINKING BUCKETBEFORE HOISTING A SINKING BUCKET

    During shaft sinking operations an employer or contractor must

  • 8/14/2019 I2PiquesProfundizacin2

    92/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    During shaft-sinking operations, an employer or contractor mustensure that:

    (a) a sinking bucket is not moved from the top or bottom

    of a shaft until the worker in charge of the sinking buckethas steadied the sinking bucket;

    (b) a sinking bucket is not moved from the bottom of a

    shaft until the worker in charge of the sinking bucket has

    examined the sinking bucket and has removed any mud

    or other material that may be sticking to it; and

    (c) before a sinking bucket containing loose rock or

    material is moved, no loose rock or material projectsabove the rim of the sinking bucket.

    93

    RIDING IN SINKING BUCKETRIDING IN SINKING BUCKET(1) During shaft-sinking operations, no employer or contractor shall require or

    permit any person:

    (a) to ride on the rim or outside of a sinking bucket; or

  • 8/14/2019 I2PiquesProfundizacin2

    93/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    (a) to ride on the rim or outside of a sinking bucket; or

    (b) subject to subsection (2), to ride in a sinking bucket that

    contains ore, waste or any other materials.

    (2) Small items, including tools, may be carried in a sinking bucket if:

    (a) it is necessary to do so; and

    (b) adequate precautions are taken to ensure the safety of workers

    being transported in the sinking bucket.

    (3) An employer or contractor must ensure that, during shaft-sinking operations:(a) the sinking bucket used to transport workers is in the charge of a

    competent worker authorized by the employer or contractor; and

    (b) no person other than an authorized competent worker gives

    the signals for the movement of a sinking bucket used to transportworkers.

    (4) A worker being transported in a sinking bucket must obey the instructions of

    the authorized competent worker in charge of the sinking bucket.

    94

    LOWERING SINKING BUCKET TO BOTTOM OF

    SHAFT

    LOWERING SINKING BUCKET TO BOTTOM OF

    SHAFT

    S bj i 89 if i ki b k i b i l d h

  • 8/14/2019 I2PiquesProfundizacin2

    94/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Subject to section 89, if a sinking bucket is being lowered to the

    bottom of a shaft during shaft-sinking operations, the employer

    or contractor must ensure that:

    (a) the sinking bucket is stopped at a distance of not lessthan five metres and not more than 10 metres from the

    bottom of the shaft and, beyond that point, lowered

    slowly and only on a separate signal from the worker incharge of the sinking bucket; and

    (b) while the crosshead is being chaired and released,

    the hoist is operated at creep speed only.

    95

    LOWERING WORKERS AFTER BLASTLOWERING WORKERS AFTER BLAST

    During shaft-sinking operations, on the first trip in which workersare

  • 8/14/2019 I2PiquesProfundizacin2

    95/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    are

    transported down a shaft after a blasting operation, theemployer or contractor must ensure that:

    (a) the sinking bucket does not transport more workers thanare necessary to make a proper examination of the parts ofthe shaft that might have been affected by the blast;

    (b) subject to clause (c), the sinking bucket is not lowered

    beyond a point in the shaft beyond which the health or safetyof workers may be endangered and, in any case, is notlowered beyond a point that is less than 15 metres abovethe top of the blasting set or the multi-deck stage; and

    (c) beyond the point mentioned in clause (b), the sinkingbucket is lowered slowly and only on a separate signal fromthe worker in charge of the sinking bucket.

    96

    OVERHEAD PROTECTIONOVERHEAD PROTECTION

    D i h ft i ki ti if k i th h ft i t b

  • 8/14/2019 I2PiquesProfundizacin2

    96/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    During shaft-sinking operations, if work in the shaft is to be

    carried out at more than one elevation at the same time, the

    employer or contractor must ensure that workers in the lower

    elevations are protected from the danger of falling objects ormaterials by installing a secure covering that:

    (a) extends over a sufficient portion of the shaft to afford

    adequate protection to the workers below; and(b) is capable of withstanding the maximum load that may

    reasonably be anticipated.

  • 8/14/2019 I2PiquesProfundizacin2

    97/99

    98

    SINKING SHAFT IN SEDIMENTARY

    STRATA

    SINKING SHAFT IN SEDIMENTARY

    STRATA

    If a shaft is to be sunk in an area underlain by water-bearing or

  • 8/14/2019 I2PiquesProfundizacin2

    98/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    If a shaft is to be sunk in an area underlain by water bearing orbrine-bearing sedimentary strata, the employer, contractor or

    owner must give written notice to the chief mines inspector of

    any intention to drill any hole for the purpose of consolidating ashaft site by a grouting or freezing method.

    (2) A notice required by subsection (1) must:

    (a) be given as soon as is reasonably possible but

    not later than 90 days, before drilling begins;

    (b) include the location of the proposed shaft

    and the number and depth of the holes to be

    drilled; and(c) if subsection (3) applies, include the radius

    and specifications of the pillar to be left around the shaft.

    99

    CONT .CONT .

    3) If a shaft is to be sunk in an area underlain by water

  • 8/14/2019 I2PiquesProfundizacin2

    99/99

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    3) If a shaft is to be sunk in an area underlain by water-

    bearing or brine-bearing sedimentary strata, the

    employer, contractor or owner must ensure that:

    a) a substantial pillar is left around the shaft at each

    working horizon that is adequate to protect the shaft

    from any damage resulting from movement of the

    strata; and

    b) a professional engineer determines the appropriate

    radius and other specifications of the pillar to meet

    the requirements of clause (a).