Datos Previos al Avance de obra
Click here to load reader
-
Upload
rommel-caza -
Category
Documents
-
view
9 -
download
4
description
Transcript of Datos Previos al Avance de obra
![Page 1: Datos Previos al Avance de obra](https://reader037.fdocuments.ec/reader037/viewer/2022100421/55cf8eee550346703b971e07/html5/thumbnails/1.jpg)
HOJA 1 DE 3
Oferente: ING. CARLOS NICOLAS SANTOS LEON
Obra:
15 DÍAS 30 DÍAS 15 DÍAS 30 DÍAS 45 DÍAS 60 DÍAS
11,847.45 0.08 947.80 11,847.45
947.80
1,988.99 1.48 2,943.71 994.50 994.50
1,471.85 1,471.85
7,872.68 3.79 29,837.46 1,968.17 1,968.17 1,968.17 1,968.17
7,459.36 7,459.36 7,459.36 7,459.36
39,363.39 0.25 9,840.85 9,840.85 9,840.85 9,840.85 9,840.85
2,460.21 2,460.21 2,460.21 2,460.21
1,057.84 2.48 2,623.44 352.61 352.61 352.61
874.48 874.48 874.48
1,968.28 8.99 17,694.84 492.07 492.07 492.07 492.07
4,423.71 4,423.71 4,423.71 4,423.71
139,000.02 0.25 34,750.01 34,750.01 34,750.01 34,750.01 34,750.01
8,687.50 8,687.50 8,687.50 8,687.50
93.28 4.31 402.04 93.28
402.04
REPLANTEO Y NIVELACION VIAS
MOVIMIENTOS DE TIERRA
EXCAVACIÓN EN SUELO (VIAS)
MATERIAL DE PRESTAMO IMPORTADO (SIN TRANSPORTE)
TRANSPORTE DE MATERIAL DE PRESTAMO IMPORTADO
EXCAVACION PARA CUNETAS Y ENCAUZAMIENTOS
ESTRUCTURA DE LA VIA
MEJORAMIENTO SUELO SELECCIONADO CANTERA (SIN
TRANSPORTE)
TRANSPORTE DE MATERIAL GRANULAR MEJORAMIENTO
OBRAS DE DRENAJE
EXCAVACIÓN Y RELLENO PARA ESTRUCTURAS MENORES
PRELIMINARES
FORMULARIO 3.8
CÓDIGO DEL PROCESO: COTO-GPM-024-2013
CRONOGRAMA VALORADO DE AVANCE DE OBRA"REHABILITACIÓN DEL CAMINO VECINAL REICITO-RIO PLÁTANO ETAPA 1 DEL CANTÓN 24 DE MAYO"
DESCRIPCION CANTIDADPRECIO
UNITARIO
PRECIO
TOTAL
TIEMPO EN: MESES
1 MES 2 MES 3 MES
"REHABILITACIÓN DEL CAMINO VECINAL REICITO-RIO PLÁTANO ETAPA 1 DEL CANTÓN 24 DE MAYO"
![Page 2: Datos Previos al Avance de obra](https://reader037.fdocuments.ec/reader037/viewer/2022100421/55cf8eee550346703b971e07/html5/thumbnails/2.jpg)
HOJA 2 DE 3
Oferente: ING. CARLOS NICOLAS SANTOS LEON
Obra:
15 DÍAS 30 DÍAS 15 DÍAS 30 DÍAS 45 DÍAS 60 DÍAS
FORMULARIO 3.8
CÓDIGO DEL PROCESO: COTO-GPM-024-2013
CRONOGRAMA VALORADO DE AVANCE DE OBRA"REHABILITACIÓN DEL CAMINO VECINAL REICITO-RIO PLÁTANO ETAPA 1 DEL CANTÓN 24 DE MAYO"
DESCRIPCION CANTIDADPRECIO
UNITARIO
PRECIO
TOTAL
TIEMPO EN: MESES
1 MES 2 MES 3 MES
13.04 32.69 426.28 13.04
426.28
10.00 322.56 3,225.60 10.00
3,225.60
16.00 686.94 10,991.04 16.00
10,991.04
21.31 228.25 4,864.01 21.31
4,864.01
1.64 196.31 321.95 1.64
321.95
42.50 68.70 2,919.75 42.50
2,919.75
147.65 155.89 23,017.16 36.91 36.91 36.91 36.91
5,754.29 5,754.29 5,754.29 5,754.29
549.00 42.12 23,123.88 137.25 137.25 137.25 137.25
5,780.97 5,780.97 5,780.97 5,780.97
33.72 4.31 145.33 33.72
145.33
14.88 32.69 486.43 14.88
486.43
0.68 198.29 134.84 0.68
134.84
42.82 228.25 9,773.67 21.41 21.41
4,886.83 4,886.83
HORMIGÓN SIMPLE CLASE B, f"c= 210 kg/cm2.
TUBERIA DE H.A. DIAMETRO 1200 MM PARA ALCANTARILLAS
TUBERIA DE H.A. DIAMETRO 1800 MM PARA ALCANTARILLAS
HORMIGÓN SIMPLE CLASE B, F"C= 210 kg/cm2
REPLANTILLO DE HORMIGÓN SIMPLE CLASE C, f"c= 180
kg/cm2.
MURO DE GAVION TRIPLE GALVANIZADO
ENROCADO DE PIEDRA BOLA
PIEDRA ESCOLLERA (INCLUYE TRANSPORTE)
RECONSTRUCCION ALCANTARILLA TIPO CAJON 2x2
L=12.00 M
EXCAVACIÓN Y RELLENO PARA ESTRUCTURAS MENORES
PIEDRA BOLA BAJO CIMIENTO
HORMIGÓN SIMPLE CLASE C, f"c= 180 kg/cm2
PIEDRA BOLA BAJO CIMIENTO
![Page 3: Datos Previos al Avance de obra](https://reader037.fdocuments.ec/reader037/viewer/2022100421/55cf8eee550346703b971e07/html5/thumbnails/3.jpg)
HOJA 3 DE 3
Oferente: ING. CARLOS NICOLAS SANTOS LEON
Obra:
15 DÍAS 30 DÍAS 15 DÍAS 30 DÍAS 45 DÍAS 60 DÍAS
FORMULARIO 3.8
CÓDIGO DEL PROCESO: COTO-GPM-024-2013
CRONOGRAMA VALORADO DE AVANCE DE OBRA"REHABILITACIÓN DEL CAMINO VECINAL REICITO-RIO PLÁTANO ETAPA 1 DEL CANTÓN 24 DE MAYO"
DESCRIPCION CANTIDADPRECIO
UNITARIO
PRECIO
TOTAL
TIEMPO EN: MESES
1 MES 2 MES 3 MES
2.40 7.19 17.26 1.20 1.20
8.63 8.63
2,159.98 2.04 4,406.36 1,079.99 1,079.99
2,203.18 2,203.18
3.64 155.89 567.44 3.64
0.04 567.44
SUMAN US$ 183,461.15
13,167.58 39,533.74 46,026.36 35,440.53 24,646.47 24,646.47
7.18% 21.55% 25.09% 19.32% 13.43% 13.43%
13,167.58 52,701.32 98,727.68 134,168.21 158,814.68 183,461.15
Portoviejo viernes, 03 de enero de 2014 7.18% 28.73% 53.81% 73.13% 86.57% 100.00%
OFERENTE:
AVANCE ACUMULADO EN %
ING. CARLOS NICOLAS SANTOS LEON
TUBERIA DE DESAGUE D= 3"
ACERO DE REFUERZO fy= 4200 kg/cm2
ENROCADO DE PIEDRA BOLA
INVERSION MENSUAL
AVANCE PARCIAL EN %
INVERSION ACUMULADA