3.- Replanteo de Muros CC y CA - RUR ,URB

44
ENTIDAD: MTC-PROVIAS NACIONAL. OBRA: REHABILITACION Y MEJORAMIENTO DE LA CARRETERA QUINUA-SAN FRANCISCO TRAMO 2: KM. 78+500-KM.172+420 ( SAN FRANCISCO ). CONTRATISTA: CONSORCIO VIAL QUINUA. SUPERVISOR: CONSORCIO SUPERVISOR LA QUINUA CONSORCIO OBRAS REPLANTEO D PROYECTO REPLAN PROG. FINAL km 1 79+340.000 79+365.000 25.00 79+340.000 79+345.000 79+350.000 79+355.000 79+360.000 2 80+347.000 80+366.000 19.00 80+345.000 80+350.000 80+355.000 80+360.000 3 80+645.000 80+671.000 26.00 80+645.000 80+650.000 80+655.000 80+660.000 80+665.000 80+668.000 4 82+174.000 82+186.000 12.00 82+174.000 82+179.000 82+182.500 5 83+231.000 83+259.000 28.00 83+231.000 83+236.000 83+241.000 83+246.000 83+251.000 83+256.000 6 84+986.500 85+003.000 16.50 84+982.000 84+985.000 84+988.500 84+993.500 7 85+116.000 85+120.000 4.00 85+116.000 85+118.000 95+241.000 95+246.000 N o LOG. PROYECTO (m) ALTURA DE MURO (m) PROYECTO PROG. INICIAL km PROG. INICIAL

description

3.- Replanteo de Muros CC y CA - RUR ,URB

Transcript of 3.- Replanteo de Muros CC y CA - RUR ,URB

ENTIDAD: MTC-PROVIAS NACIONAL.

OBRA: REHABILITACION Y MEJORAMIENTO DE LA CARRETERA QUINUA-SAN FRANCISCO

TRAMO 2: KM. 78+500-KM.172+420 ( SAN FRANCISCO ).

CONTRATISTA: CONSORCIO VIAL QUINUA.

SUPERVISOR: CONSORCIO SUPERVISOR LA QUINUA

CONSORCIO SUPERVISION LA QUINUA OBRAS DE ARTE Y DRENAJE

REPLANTEO DE MUROS DE C.C. ZONA RURAL

PROYECTO REPLANTEO

PROG. FINAL km

1 79+340.000 79+365.000 25.00

79+340.000

79+345.000

79+350.000

79+355.000

79+360.000

2 80+347.000 80+366.000 19.00

80+345.000

80+350.000

80+355.000

80+360.000

3 80+645.000 80+671.000 26.00

80+645.000

80+650.000

80+655.000

80+660.000

80+665.000

80+668.000

4 82+174.000 82+186.000 12.00

82+174.000

82+179.000

82+182.500

5 83+231.000 83+259.000 28.00

83+231.000

83+236.000

83+241.000

83+246.000

83+251.000

83+256.000

6 84+986.500 85+003.000 16.50

84+982.000

84+985.000

84+988.500

84+993.500

7 85+116.000 85+120.000 4.00 85+116.000

85+118.000

8 95+241.000 95+264.000 23.00

95+241.000

95+246.000

No

LOG. PROYECTO (m)

ALTURA DE MURO (m) PROYECTO PROG. INICIAL

kmPROG.

INICIAL

8 95+241.000 95+264.000 23.00 95+251.000

95+256.000

95+261.000

9 95+430.000 95+446.000 16.00

95+430.000

95+435.000

95+439.500

95+442.500

10 95+461.000 95+477.000 16.00

95+461.000

95+465.000

95+469.000

95+473.000

11 95+552.000 95+562.000 10.00 95+552.000

95+557.000

12 95+775.000 95+802.000 27.00

95+775.000

95+780.000

95+785.000

95+790.000

95+795.000

95+800.000

13 95+808.000 95+827.000 19.00

95+812.000

95+817.000

95+822.000

95+827.000

14 95+894.000 95+918.000 24.00

95+894.000

95+899.000

95+904.000

95+909.000

95+914.000

15 95+992.000 96+001.000 9.00 95+992.000

95+997.000

16 97+005.000 97+011.000 6.00 97+005.000

17 99+250.000 99+263.000 13.00

99+250.000

99+255.000

99+260.000

18 101+300.000 101+315.000 15.00

101+299.540

101+302.540

101+307.540

101+309.540

101+312.540

19 102+088.000 102+095.000 7.00

20 102+525.000 102+534.000 9.00 102+530.000

102+533.000

21 103+422.000 103+431.000 9.00 103+420.000

21 103+422.000 103+431.000 9.00 103+424.000

22 103+800.000 103+812.000 12.00 103+797.000

103+802.000

23 104+949.000 104+951.000 2.00 104+949.000

104+951.000

24 105+205.000 105+231.000 26.00

105+200.000

105+205.000

105+210.000

105+215.000

105+220.000

25 105+570.000 105+576.000 6.00 105+570.000

105+573.000

26 106+384.000 106+391.000 7.00

106+385.000

106+387.000

106+390.000

27 106+444.000 106+459.000 15.00

106+444.000

106+447.000

106+450.000

106+453.000

106+456.000

28 109+647.000 109+657.000 10.00 109+655.000

109+660.000

29 109+793.000 109+804.000 11.00

109+793.000

109+797.000

109+801.000

109+805.000

30 109+838.000 109+843.000 5.00 109+835.000

31 112+912.000 112+924.000 12.00

112+915.000

112+918.000

112+924.000

32 117+007.000 117+026.000 19.00

117+007

117+012

117+017

117+022

33 118+992.000 119+007.000 15.00

118+994

118+999

119+004

34 121+020.000 121+030.000 10.00 121+024

121+029

35 121+105.000 121+110.000 5.00 121+101.5

36 121+502.000 121+510.000 8.00 121+502

121+506

37 122+633.000 122+658.000 25.00

122+630.000

37 122+633.000 122+658.000 25.00

122+635.000

122+640.000

122+645.000

122+650.000

38 125+285.000 125+296.000 11.00

125+285.000

125+290.000

125+294.000

39 125+338.000 125+348.000 10.00

125+338.000

125+343.000

125+346.000

40 125+863.000 125+875.000 12.00

125+870.000

125+874.000

125+878.000

41 126+739.000 126+752.000 13.00

126+739

126+744

126+748

42 130+659.000 130+662.000 3.00 130+659.000

43 132+014.000 132+059.000 45.00

132+014.000

132+018.000

132+022.000

132+027.000

132+032.000

132+037.000

132+042.000

132+047.000

44 142+489.000 142+529.000 40.00

142+479.000

142+484.000

142+489.000

142+494.000

142+499.000

142+504.000

142+509.000

142+514.000

45 142+625.000 142+655.000 30.00

MC.C 142+632.000

MC.A 142+635.000

MC.A 142+639.000

MC.A 142+647.000

MC.C 142+652.000

46 144+508.000 144+524.000 16.00

144+505.000

144+510.000

144+515.000

47 144+614.000 144+657.000 43.00

48 148+146.000 148+152.000 6.00 148+146.000

48 148+146.000 148+152.000 6.00 148+150.000

49 155+336.000 155+341.000 5.00 155+355.000

50 155+399.000 155+405.000 6.00 155+394.000

155+398.000

51 157+230.000 157+244.000 14.00

157+230.000

157+235.000

157+240.000

52 162+017.000 162+032.000 15.00

162+020.000

162+026.000

162+031.000

53

168+192.000 168+243.000 51.00

168+175.000

168+180.000

168+185.000

168+190.000

168+195.000

168+212.000 168+217.000 5.00

168+200.000

168+205.000

168+210.000

168+215.000

168+220.000

replanteado Y revisado pero desaprovado para nueva presentacionprogresivas de replanteo que varian del proyectoprogresivas de replanteo que varian del proyecto en presentacion_separados

CONSORCIO SUPERVISION LA QUINUA OBRAS DE ARTE Y DRENAJE

REPLANTEO DE MUROS DE C.C. ZONA RURAL

REPLANTEO

OBSERVACIONAUTORIZACIONES DE TRABAJO

PROG. FINAL FECHA AUT. N° DE AUT.

79+345.000 5.00 1.50

Aprobado 5/27/2013 AUT. N° 56779+350.000 5.00 1.50

79+355.000 5.00 1.50

79+360.000 5.00 1.50

79+365.000 5.00 1.50

80+350.000 5.00 1.50

Aprobado80+355.000 5.00 1.50

80+360.000 5.00 1.50

80+364.000 4.00 1.50

80+650.000 5.00 1.50

Aprobado

80+655.000 5.00 1.50

80+660.000 5.00 1.50

80+665.000 5.00 1.50

80+668.000 3.00 1.50

80+671.000 3.00 1.50

82+179.000 5.00 1.50

Aprobado82+182.500 3.50 1.50

82+186.000 3.50 1.50

83+236.000 5.00 1.50

Aprobado

83+241.000 5.00 1.50

83+246.000 5.00 1.50

83+251.000 5.00 1.50

83+256.000 5.00 1.50

83+259.000 3.00 1.50

84+985.000 3.00 1.50

Aprobado 84+988.500 3.50 2.00

84+993.500 5.00 1.50

84+998.500 5.00 1.50

85+118.000 2.00 1.50 Aprobado

85+120.000 2.00 1.50

95+246.000 5.00 2.00

Aprobado 11/20/2012 AUT. N° 33795+251.000 5.00 2.00

LOG. REPLANTEO (m)

ALTURA DE MURO (m) REPLANTEO

95+256.000 5.00 2.00 Aprobado 11/20/2012 AUT. N° 33795+261.000 5.00 2.00

95+264.000 3.00 2.00

95+435.000 5.00 2.00

Aprobado 12/11/2012 AUT. N° 36795+439.500 4.50 2.00

95+442.500 3.00 3.50

95+446.000 3.50 2.00

95+465.000 4.00 2.00

Aprobado 12/11/2012 AUT. N° 36895+469.000 4.00 2.00

95+473.000 4.00 2.00

95+477.000 4.00 2.00

95+557.000 5.00 2.00 Aprobado

95+562.000 5.00 2.00

95+780.000 5.00 2.00

Aprobado 12/11/2012 AUT. N° 369

95+785.000 5.00 2.00

95+790.000 5.00 2.00

95+795.000 5.00 2.50

95+800.000 5.00 2.50

95+802.000 2.00 2.00

95+817.000 5.00 2.00

Aprobado 12/11/2012 AUT. N° 37095+822.000 5.00 2.00

95+827.000 5.00 2.00

95+831.000 4.00 2.00

95+899.000 5.00 2.50

Aprobado 1/22/2013 AUT. N° 38695+904.000 5.00 2.50

95+909.000 5.00 2.50

95+914.000 5.00 2.00

95+918.000 4.00 2.00

95+997.000 5.00 2.00 Aprobado 1/23/2013 AUT. N° 385

96+001.000 4.00 2.00

97+011.330 6.00 1.50 Aprobado 6/2/2013 AUT. N° 57399+255.000 5.00 1.50

Aprobado 6/2/2013 AUT. N° 57499+260.000 5.00 1.50

99+262.280 3.00 1.50

101+302.540 3.00 2.50

Aprobado 6/13/2013 AUT. N° 588101+307.540 5.00 3.00

101+309.540 2.00 3.00

101+312.540 3.00 3.00

101+315.000 2.00 2.50

102+533.000 3.00 1.50 Aprobado 6/13/2013 AUT. N° 589

102+539.000 6.00 2.00

103+424.000 4.00 1.50 Aprobado 6/13/2013 AUT. N° 590

103+429.180 5.00 1.50 Aprobado 6/13/2013 AUT. N° 590

103+802.000 5.00 2.00 Aprobado

103+807.000 5.00 2.00

104+951.000 2.00 2.50 Aprobado 6/13/2013 AUT. N° 591

104+955.060 4.06 3.00

105+205.000 5.00 2.00

Aprobado105+210.000 5.00 2.00

105+215.000 5.00 1.50

105+220.000 5.00 2.00

105+229.600 9.00 2.00

105+573.000 3.00 2.00 Aprobado

105+576.000 3.00 2.00

106+387.000 2.00 2.00

Aprobado106+390.000 3.00 1.50

106+392.000 2.00 2.00

106+447.000 3.00 1.50

Aprobado106+450.000 3.00 1.50

106+453.000 3.00 1.50

106+456.000 3.00 1.50

106+458.060 3.00 1.50

109+660.000 5.00 2.00 Aprobado

109+665.000 5.00 2.00

109+797.000 4.00 1.50

Aprobado 109+801.000 4.00 1.50

109+805.000 4.00 1.50

109+809.00 4.00 1.50

109.840.28 5.00 1.50 Aprobado 7/8/2013 AUT. N° 644 112+918.000 3.00 2.50

Aprobado 112+924.000 6.00 2.50

112+930.000 6.00 1.50

117+012 5.00 1.50

Aprobado117+017 5.00 1.50

117+022 5.00 1.50

117+026 4.00 1.50

118+999 5.00 1.50

Aprobado 3/13/2015 AUT. N°927 119+004 5.00 2.00

119+009 5.00 2.00

121+029 5.00 3.00 Aprobado 6/11/2015 AUT. N°1078

121+034 5.00 3.00

121+106.5

121+506 4.00 1.50 Aprobado 6/16/2015 AUT. N°1096

121+510 4.00 1.50

122+635.000 5.00 1.50

Aprobado

122+640.000 5.00 2.00

Aprobado122+645.000 5.00 2.00

122+650.000 5.00 2.00

122+655.000 5.00 2.00

125+290.000 5.00 1.50

Aprobado125+294.000 4.00 1.50

125+298.000 4.00 1.50

125+343.000 5.00 2.00

Aprobado 5/29/2015 AUT. N°1053 125+346.000 3.00 2.00

125+348.000 2.00 1.50

125+874.000 4.00 2.00

Aprobado 5/29/2015 AUT. N°1057 125+878.000 4.00 2.00

125+882.000 4.00 2.00

126+744 5.00 2.00

Aprobado126+748 4.00 2.00

126+752 4.00 2.00

130+662.000 3.00 1.50 Aprobado132+018.000 4.00 2.50

Aprobado 7/14/2015 AUT. N° 1160

132+022.000 4.00 3.00

132+027.000 5.00 5.00

132+032.000 5.00 5.00

132+037.000 5.00 6.00

132+042.000 5.00 4.50

132+047.000 5.00 4.50

132+059.000 3.00 3.00

142+484.000 5.00 2.50

Aprobado 9/18/2014 AUT. N° 695

142+489.000 5.00 2.50

142+494.000 5.00 2.50

142+499.000 5.00 2.50

142+504.000 5.00 2.50

142+509.000 5.00 2.50

142+514.000 5.00 2.50

142+519.000 5.00 2.50

142+635.000 3.00 1.50

Aprobado 9/18/2014 AUT. N° 696

142+639.000 4.00 3.50

142+647.000 8.00 6.00

142+652.000 5.00 4.50

142+655.000 3.00 2.00

144+510.000 5.00 1.50

Aprobado144+515.000 5.00 3.50

144+518.000 3.00 2.00

148+150.000 4.00 3.00 Aprobado 9/20/2014 AUT. N°706

148+152.000 2.00 2.00 Aprobado 9/20/2014 AUT. N°706

155+360.000 5.00 1.50 Aprobado 4/22/2013 AUT. N° 480

155+398.000 4.00 2.00 Aprobado 4/18/2013 AUT. N° 466

155+401.000 3.00 1.50

157+235.000 5.00 2.00

Aprobado 4/2/2013 AUT. N° 459157+240.000 5.00 1.50

157+244.000 4.00 1.50

162+026.000 6.00 3.00

Aprobado162+031.000 5.00 3.00

162+035.000 4.00 3.00

168+180.000 5.00 1.50

Aprobado 4/2/2013 AUT. N° 460168+185.000 5.00 1.50

168+190.000 5.00 2.00

168+195.000 5.00 2.50

168+200.000 5.00 2.00

168+205.000 5.00 1.50

Aprobado 4/18/2013 AUT. N° 465168+210.000 5.00 1.50

168+215.000 5.00 1.50

168+220.000 5.00 1.50

168+226.000 6.00 1.50

replanteado Y revisado pero desaprovado para nueva presentacion

progresivas de replanteo que varian del proyecto en presentacion_separados

CONSORCIO SUPERVISION LA QUINUA OBRAS DE ARTE Y DRENAJE

REPLANTEO DE MUROS DE C.C. ZONA RURAL

CVQ-0353: F=06-11-12 CSQ-0088: F=09-11-12

CVQ-0243: F=08-09-12 CSQ-0061: F=12-09-12

CVQ-0233: F=06-09-12 CSQ-0059: F=07-09-12

CVQ-0233: F=06-09-12 CSQ-0059: F=07-09-12

CVQ-0353: F=06-11-12 CSQ-0088: F=09-11-12

CVQ-0203: F=22-04-15 CSQ-0046: F=23-04-15

CVQ-0233: F=06-09-12 CSQ-0059: F=07-09-12

CVQ-0363: F=09-11-12 CSQ-0091: F=12-11-12

CARTA PRESENTADA POR EL CONTRATISTA

INORME - SUPERVISOR (ESPECIALISTA EOAD)

CVQ-0363: F=09-11-12 CSQ-0091: F=12-11-12

CVQ-0363: F=09-11-12 CSQ-0091: F=12-11-12

CVQ-0363: F=09-11-12 CSQ-0091: F=12-11-12

CVQ-0363: F=09-11-12 CSQ-0091: F=12-11-12

CVQ-0369: F=13-11-12 CSQ-0096: F=26-11-12

CVQ-0369: F=13-11-12 CSQ-0096: F=26-11-12

CVQ-0369: F=13-11-12 CSQ-0096: F=26-11-12

CVQ-0369: F=13-11-12 CSQ-0096: F=26-11-12

CVQ-0210: F=13-05-13 CSQ-0061: F=14-05-13

CVQ-0228: F=24-05-13 CSQ-0074: F=24-05-13

CVQ-0251: F=01-06-13 CSQ-0082: F=04-06-13

CVQ-0251: F=01-06-13 CSQ-0082: F=04-06-13

CVQ-0259: F=04-06-13 CSQ-0086: F=05-06-13

CVQ-0259: F=04-06-13 CSQ-0086: F=05-06-13

CVQ-300: F=26-06-13 CSQ-0102: F=27-06-13

CVQ-0259: F=04-06-13 CSQ-0086: F=05-06-13

CVQ-0269: F=10-06-13 CSQ-0089: F=11-06-13

CVQ-0269: F=10-06-13 CSQ-0089: F=11-06-13

CVQ-0269: F=10-06-13 CSQ-0089: F=11-06-13

CVQ-0269: F=10-06-13 CSQ-0089: F=11-06-13

CVQ-0283: F=17-06-13 CSQ-0096: F=19-06-13

CVQ-0283: F=17-06-13 CSQ-0096: F=19-06-13

CVQ-0283: F=17-06-13 CSQ-0096: F=19-06-13

CVQ-0042: F=29-01-15 CSQ-0015: F=03-02-15

CVQ-0242: F=31-05-13 CSQ-0080: F=31-05-13

CVQ-0242: F=31-05-13 CSQ-0080: F=31-05-13

CVQ-0242: F=31-05-13 CSQ-0080: F=31-05-13

CVQ-515

CVQ-0242: F=31-05-13 CSQ-0080: F=31-05-13

CVQ-0226: F=22-05-13 CSQ-0073: F=24-05-13

CVQ-0226: F=22-05-13 CSQ-0073: F=24-05-13

CVQ-0322: F=11-07-13 CSQ-0112: F=18-07-13

CVQ-0243: F=08-09-12 CSQ-0061: F=12-09-12

CVQ-0322: F=11-07-13 CSQ-0112: F=18-07-13

CVQ-0242: F=31-05-13 CSQ-0080: F=31-05-12

CVQ-0223: F=03-09-12 CSQ-0056: F=04-09-12

CVQ-0353: F=06-11-12 CSQ-0088: F=09-11-12

CVQ-0353: F=06-11-12 CSQ-0088: F=09-11-12

CVQ-0104: F=27-09-14 CSQ-0024: F=27-09-14

CVQ-0353: F=06-11-12 CSQ-0088: F=09-11-12

CVQ-0353: F=06-11-12 CSQ-0088: F=09-11-12

CVQ-0353: F=06-11-12 CSQ-0088: F=09-11-12

CVQ-0353: F=06-11-12 CSQ-0088: F=09-11-12

CVQ-0353: F=06-11-12 CSQ-0088: F=09-11-12

CVQ-0353: F=06-11-12 CSQ-0088: F=09-11-12

CVQ-0251: F=01-06-13 CSQ-0082: F=04-06-13

CVQ-0157: F=10-04-13 CSQ-0143: F=11-04-13

CVQ-0181: F=26-04-13 CSQ-0050: F=29-04-13

OBSERVACION - INFORMES

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

cambio por informe 0056 CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

Cambio x CSQ-0056: F=04-09-12

CVQ-0183: F=13-11-14

METRADO PRESENTADOS CON

CARTA:

carta 0156-13 , informe 044_adicionales adicional_intercalado

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

adicional_intercalado

MC Adic-Proy Km 105+562 - 105+581(L=19metros)

Adic. 1 metro(109+657-109+658)_intercalado MC Km 109+647 - 109+658

Adic. 1 metro(109+804-109+805)_intercalado MC Km 109+793 - 109+805

cambio x informe 0115; 18-07-13 RCDO v2 incremento de longitud y altura

adicional_intercalado

CVQ-0183: F=13-11-14

cambio x informe 61;12-09-12_RCDOCVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

cambio por informe 0065

cambio por informe 0065

cambio por informe 0065

cambio x informe 59; 07-09-12

cambio por informe 0065; Version III cambio por informe 0088-CVQ N°0353 06.11.12 MC.C - MC.A - MC.C

cambio por informe 0065 adicional_intercalado

CVQ-0183: F=13-11-14

CVQ-0183: F=13-11-14

cambio por informe 0066 CVQ-0183: F=13-11-14

cambio x informe 88;09-11-12 CVQ-0183: F=13-11-14

cambio por informe 0088 CVQ-0183: F=13-11-14

cambio por informe 0088 CVQ-0183: F=13-11-14

cambio por informe 0065 adicional_intercalado

cambio por informe 0065 adicional_intercalado

cambio por informe 0065 adicional_intercalado

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

METRADO APROBADOS CON

INFORME:

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12 ACTUALIZAR PLANO DE REPL.

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12 ACTUALIZAR PLANO DE REPL.

CSQ-0044: F=17-11-12 ACTUALIZAR PLANO DE REPL.

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

ENTIDAD: MTC-PROVIAS NACIONAL.

OBRA: REHABILITACION Y MEJORAMIENTO DE LA CARRETERA QUINUA-SAN FRANCISCO

TRAMO 2: KM. 78+500-KM.172+420 ( SAN FRANCISCO ).

CONTRATISTA: CONSORCIO VIAL QUINUA.

SUPERVISOR: CONSORCIO SUPERVISOR LA QUINUA

CONSORCIO SUPERVISION LA QUINUA OBRAS DE ARTE Y DRENAJE

REPLANTEO DE MUROS DE C.C. ZONA URBANA

PROYECTO

PROG. INICIAL km PROG. FINAL km

TE-60 85+298.000 85+308.000 10.00

TE-61 85+339.000 85+369.000 30.00

TE-62 85+445.000 85+465.000 20.00

TE-63 85+541.000 85+576.000 35.00

TE-64 85+602.000 85+616.000 14.00

TE-65 93+060.000 93+100.000 40.00

No LOG. PROYECTO (m)

ALTURA DE MURO (m) PROYECTO

TE-65 93+060.000 93+100.000 40.00

TE-66 96+220.000 96+238.000 18.00

TE-67 96+389.000 96+404.000 15.00 TE-68 96+422.000 96+442.000 20.00

TE-69 96+454.000 96+461.000 7.00 TE-70 96+468.000 96+476.000 8.00

TE-71 112+385.000 112+400.000 15.00

TE-72 112+476.000 112+535.000 59.00

TE-73 112+628.000 112+643.000 15.00

TE-74 112+663.000 112+720.000 57.00

TE-74 112+663.000 112+720.000 57.00

TE-75 148+667.000 148+678.000 11.00

TE-76 149+753.000 149+780.000 27.00

TE-77 149+989.000 150+009.000 20.00 TE-77A 158+937.000 158+956.000 19.00 TE-77B 159+592.000 159+603.000 11.00

TE-78 159+699.000 159+712.000 13.00

TE-79 164+856.000 164+887.000 31.00

TE-80 164+971.000 164+999.000 28.00

REHABILITACION Y MEJORAMIENTO DE LA CARRETERA QUINUA-SAN FRANCISCO

CONSORCIO SUPERVISION LA QUINUA OBRAS DE ARTE Y DRENAJE

REPLANTEO DE MUROS DE C.C. ZONA URBANA

REPLANTEO

OBSERVACION

PROG. INICIAL PROG. FINAL

85+298.00 85+303.00 5.00 1.00Aprobado

85+303.00 85+308.00 5.00 1.0085+339.00 85+344.00 5.00 1.50

Aprobado

85+344.00 85+349.00 5.00 1.5085+349.00 85+354.00 5.00 2.0085+354.00 85+359.00 5.00 2.0085+359.00 85+364.00 5.00 2.0085+364.00 85+369.00 5.00 2.0085+369.00 85+374.00 5.00 1.5085+445.00 85+450.00 5.00 1.50

Aprobado85+450.00 85+455.00 5.00 2.0085+455.00 85+460.00 5.00 2.0085+460.00 85+465.00 5.00 1.0085+541.00 85+543.00 2.00 2.00

Aprobado

85+543.00 85+548.00 5.00 2.5085+548.00 85+552.00 4.00 3.0085+552.00 85+557.00 5.00 3.5085+557.00 85+562.00 5.00 3.0085+562.00 85+567.00 5.00 2.5085+567.00 85+572.00 5.00 2.0085+572.00 85+576.00 4.00 1.5085+602.00 85+604.00 2.00 1.50

Aprobado85+604.00 85+608.00 4.00 1.5085+608.00 85+612.00 4.00 1.5085+612.00 85+616.00 4.00 1.5093+060.00 93+065.00 5.00 2.00

Aprobado

93+065.00 93+070.00 5.00 2.5093+070.00 93+075.00 5.00 3.0093+075.00 93+080.00 5.00 3.0093+080.00 93+085.00 5.00 3.0093+085.00 93+090.00 5.00 3.0093+090.00 93+095.00 5.00 2.50

LOG. REPLANTEO (m)

ALTURA DE MURO (m) REPLANTEO

93+095.00 93+100.00 5.00 2.00

Aprobado

96+220.00 96+225.00 5.00 2.50

Aprobado96+225.00 96+230.00 5.00 2.5096+230.00 96+234.00 4.00 2.0096+234.00 96+238.00 4.00 2.00

96+382 96+387.00 5.00 1.50

Aprobado

96+387 96+391.00 4.00 1.5096+391 96+396.00 5.00 1.5096+396 96+401.00 5.00 1.5096+401 96+406.00 5.00 1.5096+406 96+410.00 4.00 1.5096+410 96+415.00 5.00 1.5096+415 96+420.00 5.00 2.0096+420 96+427.00 7.00 2.5096+427 96+432.00 5.00 2.5096+432 96+437.00 5.00 2.5096+437 96+443.00 6.00 2.0096+443 96+447.00 4.00 1.5096+452 96+457.00 5.00 2.00

Aprobado96+457 96+462.00 5.00 2.0096+462 96+467.00 5.00 2.0096+467 96+471.00 4.00 2.0096+471 96+475.00 4.00 2.00

112+382.70 112+387.70 5.00 2.00Aprobado112+387.70 112+392.70 5.00 2.00

112+392.70 112+397.70 5.00 2.00112+478.00 112+483.00 5.00 1.00

Aprobado

112+483.00 112+488.00 5.00 1.00112+488.00 112+493.00 5.00 1.50112+493.00 112+498.00 5.00 2.50112+498.00 112+503.00 5.00 2.50112+503.00 112+508.00 5.00 2.00112+508.00 112+513.00 5.00 2.00112+513.00 112+518.00 5.00 2.50112+518.00 112+523.00 5.00 2.50112+523.00 112+528.00 5.00 2.50112+528.00 112+533.00 5.00 2.50112+533.00 112+537.00 4.00 2.50112+628.00 112+633.00 5.00 2.00

Aprobado112+633.00 112+638.00 5.00 2.00112+638.00 112+643.00 5.00 2.00112+664.00 112+669.00 5.00 2.00

Aprobado

112+669.00 112+674.00 5.00 2.50112+674.00 112+679.00 5.00 3.00112+679.00 112+684.00 5.00 3.00

112+684.00 112+689.00 5.00 3.00Aprobado

112+689.00 112+694.00 5.00 3.00112+694.00 112+699.00 5.00 2.50112+699.00 112+704.00 5.00 2.50112+704.00 112+709.00 5.00 2.50112+709.00 112+715.00 6.00 2.50148+669.00 148+673.00 4.00 2.50

Aprobado148+673.00 148+677.00 4.00 3.50148+677.00 148+681.00 4.00 3.50149+753.00 149+757.00 4.00 4.00

Aprobado149+757.00 149+762.00 5.00 5.50149+762.00 149+767.00 5.00 5.50149+767.00 149+771.00 4.00 5.00149+771.00 149+774.00 3.00 4.00

158+937.00 158+956.00 19.00 Aprobado

159+699.00 159+703.00 4.00 2.00 Aprobado 159+703.00 159+708.00 5.00 2.50

159+708.00 159+712.00 4.00 2.00164+857.00 164+862.00 5.00 1.50

Aprobado

164+862.00 164+867.00 5.00 2.00164+867.00 164+872.00 5.00 2.00164+872.00 164+877.00 5.00 2.00164+877.00 164+882.00 5.00 2.50164+882.00 164+886.00 4.00 3.00164+973.50 164+978.50 5.00 3.50

Aprobado

164+978.50 164+983.50 5.00 2.50164+983.50 164+988.50 5.00 2.00164+988.50 164+993.50 5.00 2.00164+993.50 164+997.50 4.00 1.50164+997.50 165+001.50 4.00 1.50

AUTORIZACIONES DE TRABAJO PRESENTA CONTRATISTA APROBACION SUPERVISOR

FECHA AUT. N° DE AUT. FECHA FECHA

CVQ-0200: F=09-05-13 CSQ-0057: F=10-05-13

CVQ-0200: F=09-05-13 CSQ-0057: F=10-05-13

CVQ-0200: F=09-05-13 CSQ-0057: F=10-05-13

CVQ-0200: F=09-05-13 CSQ-0057: F=10-05-13

10/2/2015 AUT. N° 1486 CVQ-0214: F=15-05-13 CSQ-0063: F=17-05-13

3/13/2015 AUT. N° 926 CVQ-0226: F=22-05-13 CSQ-0073: F=24-05-13

3/13/2015 AUT. N° 926 CVQ-0226: F=22-05-13 CSQ-0073: F=24-05-13

6/16/2015 AUT. N° 1101 CVQ-0278: F=26-05-15 CSQ-0061: F=28-05-15

6/10/2015 AUT. N° 1074 CVQ-0285: F=29-05-15 CSQ-0066: F=01-06-15

CVQ-0293: F=01-06-15 CSQ-0069: F=02-06-15

10/2/2015 AUT. N°1487 CVQ-0203: F=22-04-15 CSQ-0046: F=23-04-15

10/2/2015 AUT. N° 1492 CVQ-0203: F=22-04-15 CSQ-0046: F=23-04-15

10/2/2015 AUT. N° 1489 CVQ-0280: F=26-05-15 CSQ-0065: F=01-06-15

10/2/2015 AUT. N° 1490 CVQ-0280: F=26-05-15 CSQ-0065: F=01-06-15

10/2/2015 AUT. N° 1490 CVQ-0280: F=26-05-15 CSQ-0065: F=01-06-15

9/20/2014 AUT. N° 707 CVQ-0294: F=24-06-13 CSQ-0099: F=26-06-13

9/28/2014 AUT. N° 717 CVQ-0316: F=05-07-13 CSQ-0107: F=05-07-13

CVQ-0214: F=15-05-13 CSQ-0063: F=17-05-13

CVQ-0086: F=18-02-15 CSQ-0021: F=20-02-15

11/25/2014 AUT. N° 807 CVQ-0294: F=24-06-13 CSQ-0099: F=26-06-13

CVQ-0294: F=24-06-13 CSQ-0099: F=26-06-13

OBSERVACION - INFORMES

MURO ADIC. - PROY

METRADO PRESENTADOS CON

CARTA:

SE VA ANULAR PARA CONSTRUCCIONDE MURO SECO

SE VA ANULAR PARA CONSTRUCCIONDE MURO SECO

MURO ADIC.2 y CONTRACTUAL L/DER KM.96+382-KM.96+389 =

ADIC.2 KM.96+389-KM.96+404 = PROY. KM.96+404-KM.96+422 = ADIC.2 KM.96+422-KM.96+442 = PROY.

KM.96+442-KM.96+447 = ADIC.2

MURO ADIC.2 y CONTRACTUAL L/DER KM.96+452-KM.96+454 =

ADIC.2 KM.96+454-KM.96+461 = PROY. KM.96+462-KM.96+468 = ADIC.2 KM.96+468-KM.96+476 = PROY.

CVQ-0183: F=13-11-14

adic._Proy Km 158+956-158+964 MC-URB(ruCVQ-0183: F=13-11-14

Cambio x informe 99;26-06-13 modificado_(Muro C.A.)

METRADO APROBADOS CON

INFORME:

CSQ-0044: F=17-11-12

CSQ-0044: F=17-11-12

ENTIDAD: MTC-PROVIAS NACIONAL.

OBRA: REHABILITACION Y MEJORAMIENTO DE LA CARRETERA QUINUA-SAN FRANCISCO

TRAMO 2: KM. 78+500-KM.172+420 ( SAN FRANCISCO ).

CONTRATISTA: CONSORCIO VIAL QUINUA.

SUPERVISOR: CONSORCIO SUPERVISOR LA QUINUA

CONSORCIO SUPERVISION LA QUINUA OBRAS DE ARTE Y DRENAJEREPLANTEO DE MUROS DE C.A.

PROYECTO REPLANTEO

PROG. INICIAL km PROG. INICIAL

1.0 85+003.000 85+008.000 5.00 84+998.500

2.0 95+439.000 95+441.000 2.00

3.0 118+998.000 119+002.000 4.00

4.0 132+023.000 132+056.000 33.00

5.0 142+627.000 142+650.000 23.00

6.0 144+501.000 144+508.000 7.00

7.0 144+657.000 144+660.000 3.00

8.0 168+212.000 168+217.000 5.00 168+200.000

No LOG. PROYECTO (m)

ALTURA DE MURO (m) PROYECTO PROG. INICIAL

km

CONSORCIO SUPERVISION LA QUINUA OBRAS DE ARTE Y DRENAJEREPLANTEO DE MUROS DE C.A.

REPLANTEO

OBSERVACIONAUTORIZACIONES DE TRABAJO

PROG. FINAL FECHA AUT. N° DE AUT.

85+003.500 5.00 3.50 Aprobado -

-

-

-

-

168+226.000 26.00 Aprobado

LOG. REPLANTEO (m)

ALTURA DE MURO (m) REPLANTEO

PRESENTA CONTRATISTA APROBACION SUPERVISOR

FECHA FECHA

CVQ-0203: F=22-04-15 Q-0046: F=23-04-15

CVQ-0353: F=08-11-12 CSQ-0088: F=09-11-12

OBSERVACION - INFORMES

Cambio x CSQ-0056: F=04-09-12

OJO: CVQ-0353: F=06-11-12 ; CSQ-0088: F=09-11-12 MC.C - MC.A - MC.C

PROG. CONSIDERADO CON C°C°