RESUMENMEJORAMIENTO DEL SISTEMA DE ACUEDUCTO SEGN PLAN MAESTRO DEL MUNICIPIO DE ARMERO GUAYABAL DEPARTAMENTO DEL TOLIMAPRESUPUESTO DE LAS OBRASRESUMENCOMPONENTECOSTO DIRECTOBOCATOMA$ 6,830,177DESARENADOR$ 37,890,108ADUCCION Y CONDUCCION$ 71,281,999PLANTA DE TRATAMIENTO$ 125,665,576TANQUE DE ALMACENAMIENTO$ 226,167,819REDES DE DISTRIBUCION$ 4,239,526,108
SUBTOTAL COSTO DIRECTO$ 4,707,361,787
AIU29%$ 1,365,134,918
VALOR TOTAL OBRA$ 6,072,496,705
INTERVENTORIA7%$ 425,074,769
VALOR TOTAL DEL PROYECTO$ 6,497,571,474
POI INIDICADORESCOMPONENTEVALOR OBRASCUMPLIMIENTO INDICADORESPESOS CORRIENTES 20111. CALIDAD2. CONTINUIDAD3. COBERTURA4. IANCBOCATOMA$ 9,427,693$ 9,427,693DESARENADOR$ 52,299,716$ 52,299,716ADUCCION Y CONDUCCION$ 98,390,543$ 98,390,543PLANTA DE TRATAMIENTO$ 173,456,195$ 173,456,195TANQUE DE ALMACENAMIENTO$ 312,179,441$ 312,179,441REDES DE DISTRIBUCION$ 5,851,817,887$ 2,340,727,155$ 3,511,090,732
VALOR TOTAL$ 6,497,571,475$ 235,183,604$ 410,569,984$ 2,340,727,155$ 3,511,090,732
POI ETAPASCOMPONENTEVALOR OBRASFASE 1FASE 2PESOS CORRIENTES 2011BOCATOMA$ 9,427,693$ 9,427,693DESARENADOR$ 52,299,716$ 52,299,716ADUCCION Y CONDUCCION$ 98,390,543$ 98,390,543PLANTA DE TRATAMIENTO$ 173,456,195$ 173,456,195TANQUE DE ALMACENAMIENTO$ 312,179,441$ 312,179,441REDES DE DISTRIBUCION$ 5,851,817,887$ 5,851,817,887
VALOR TOTAL$ 6,497,571,475$ 645,753,588$ 5,851,817,887
RESUMEN (2)MEJORAMIENTO DEL SISTEMA DE ACUEDUCTO SEGN PLAN MAESTRO DEL MUNICIPIO DE ARMERO GUAYABAL DEPARTAMENTO DEL TOLIMAPRESUPUESTO DE LAS OBRASRESUMENFASE 1FASE 2COMPONENTECOSTO DIRECTOBOCATOMA$ 6,830,177$ 6,830,177DESARENADOR$ 37,890,108$ 37,890,108ADUCCION Y CONDUCCION$ 71,281,999$ 71,281,999PLANTA DE TRATAMIENTO$ 125,665,576$ 125,665,576TANQUE DE ALMACENAMIENTO$ 226,167,819$ 226,167,819REDES DE DISTRIBUCION$ 4,239,526,108$ 4,239,526,108
SUBTOTAL COSTO DIRECTO$ 4,707,361,787$ 467,835,679$ 4,239,526,108
AIU29%$ 1,365,134,918$ 135,672,347$ 1,229,462,571
VALOR TOTAL OBRA$ 6,072,496,705$ 603,508,026$ 5,468,988,679
INTERVENTORIA7%$ 425,074,769$ 42,245,562$ 382,829,208
VALOR TOTAL DEL PROYECTO$ 6,497,571,474$ 645,753,588$ 5,851,817,887