Mano de Obra Total Precio Pintado Fisma

Post on 16-Feb-2016

215 views 0 download

description

Mano de Obra Total Precio Pintado Fisma

Transcript of Mano de Obra Total Precio Pintado Fisma

COSTO DE METRADOS DE MANO DE OBRA PINTURA‐

AULA 5(TERCER PISO) Und METRADO PREC.UNIT PRECIO

PARED m2 77.1939 2 154.4

VIGA m2 11.12 3 33.36

COLUMNA m2 7.9 3 23.7

AULA 4(TERCER PISO)

PARED m2 76.1939 2 152.4

VIGA m2 14.4 3 43.2

COLUMNA m2 12.22 3 36.66

AULA 3(TERCER PISO)

PARED m2 78.216 2 156.432

VIGA m2 13.21 3 39.63

COLUMNA m2 12.21 3 36.63

CIELO RAZO m2 58.5 2.5 146.3

AULA 2(TERCER PISO)

PARED m2 77.1939 2 154.38

VIGA m2 11.12 3 33.36

COLUMNA m2 6.8 3 20.4

CIELO RAZO m2 58.5 2.5 146.3

AULA 1(TERCER PISO)

PARED m2 77.1939 2 154.4

VIGA m2 11.12 3 33.4

COLUMNA m2 6.8 3 20.4

CIELO RAZO m2 58.5 2.5 146.3

SALA COMP.(2do PISO)

PARED m2 35.77 2 71.54

VIGA m2 6.91 3 20.73

COLUMNA m2 2.52 3 7.56

BIBLIOTECA.(2do PISO)

PARED m2 42.446 2 84.9

VIGA m2 6.36 3 19.1

COLUMNA m2 9.69 3 29.1

BAÑ.PROF(V)(1er PISO)

PARED m2 7.95 2 15.9

VIGA m2 0.4563 3 1.3689

BAÑ.PROF(M)(1er PISO)

PARED m2 7.38 2 14.76

VIGA m2 0.9975 3 2.9925

COLUMNA m2 0.962 3 2.886

SALA PROFES(1er PISO)

PARED m2 25.61 2 51.22

VIGA m2 8.56 3 25.68

COLUMNA m2 3.52 3 10.56

SALON DIRECTORA(1er PISO)

PARED m2 31.45 2 62.9

VIGA m2 5.9 3 17.7

COLUMNA m2 2.95 3 8.85

AUDITORIO(1er PISO)

PARED m2 101.2 2 202.4

VIGA m2 54.92 5 274.6

COLUMNA m2 14.29 3 42.87

CIELO RAZO(ESCARCH) m2 110.95 5 554.75

PRECIO TOTAL 3054.0194