VALORIZACION

19
VALORIZACION AL 25% OBRA: CERCO DE ALBAÑILERIA ITEM DESCRIPCION UNIDAD METRADO ANTERIOR ACTUAL CANTID. IMPORT. CANTID. IMPORT. 1.00 MOVIMIENTO DE TIERRA 1.01 EXCAVACION DE ZANJAS m3 21.76 7.73 168.26 21.76 168.26 1.02 3.02 33.93 102.45 3.02 102.45 1.03 ELIMINACION DE MATERIAL EXCEDENTE m3 22.48 25.86 581.40 22.48 581.40 2.00 CONCRETO CICLOPEO 2.01 CIMIENTO CORRIDO 1:10 + 30% P.G. m3 17.41 160.00 2785.58 8.71 1392.79 2.02 SOBRECIMIENTO 2.02.1 CONCRETO 1:8 +25% P.M. m3 2.41 232.76 560.96 2.02.2 ENCOFRADO Y DESENCOFRADO m2 35.01 39.38 1378.90 3.00 CONCRETO ARMADO 3.01 COLUMNAS 3.01.1 CONCRETO f'c = 210 kg/cm2 m3 1.89 366.76 693.17 3.01.2 ENCOFRADO Y DESENCOFRADO m2 46.62 33.88 1579.52 3.01.2 ACERO fy = 4200 kg/cm2 kg 1850 4.48 8292.78 925.00 4146.39 3.02 VIGAS 3.02.1 CONCRETO f'c = 210 kg/cm2 m3 1.50 335.80 503.69 3.02.2 ENCOFRADO Y DESENCOFRADO m2 25.49 29.60 754.52 3.02.2 ACERO fy = 4200 kg/cm2 kg 1500 4.35 6527.01 375.00 1631.75 4.00 MURO DE ALBAÑILERIA 4.01 m2 164.54 49.78 8191.00 COSTO DIRECTO 32119.25 8023.05 GASTOS GENERALES+ UTILIDAD (25%) 8029.81 2005.76 SUBTOTAL 40149.07 10028.81 PRECIO UNITARIO PRECIO PARCIAL RELLENO COMPACTADO CON MATERIAL PROPIO MURO DE LADRILLOS CORRIENTES (6X12X23) cm , EN APARAJEO DE SOGA

description

seminario

Transcript of VALORIZACION

Page 1: VALORIZACION

VALORIZACION AL 25%OBRA: CERCO DE ALBAÑILERIA

ITEM DESCRIPCION UNIDAD METRADOANTERIOR ACTUAL ACUMULADO

CANTID. IMPORT. CANTID. IMPORT. CANTID. IMPORT.1.00 MOVIMIENTO DE TIERRA

1.01 EXCAVACION DE ZANJAS m3 21.76 7.73 168.26 21.76 168.26 21.76 168.26

1.02 3.02 33.93 102.45 3.02 102.45 3.02 102.45

1.03 ELIMINACION DE MATERIAL EXCEDENTE m3 22.48 25.86 581.40 22.48 581.40 22.48 581.402.00 CONCRETO CICLOPEO

2.01 CIMIENTO CORRIDO 1:10 + 30% P.G. m3 17.41 160.00 2785.58 8.71 1392.79 8.71 1392.792.02 SOBRECIMIENTO

2.02.1 CONCRETO 1:8 +25% P.M. m3 2.41 232.76 560.962.02.2 ENCOFRADO Y DESENCOFRADO m2 35.01 39.38 1378.90

3.00 CONCRETO ARMADO3.01 COLUMNAS

3.01.1 CONCRETO f'c = 210 kg/cm2 m3 1.89 366.76 693.173.01.2 ENCOFRADO Y DESENCOFRADO m2 46.62 33.88 1579.523.01.2 ACERO fy = 4200 kg/cm2 kg 1850 4.48 8292.78 925.00 4146.39 925.00 4146.39

3.02 VIGAS3.02.1 CONCRETO f'c = 210 kg/cm2 m3 1.50 335.80 503.693.02.2 ENCOFRADO Y DESENCOFRADO m2 25.49 29.60 754.523.02.2 ACERO fy = 4200 kg/cm2 kg 1500 4.35 6527.01 375.00 1631.75 375.00 1631.75

4.00 MURO DE ALBAÑILERIA

4.01 m2 164.54 49.78 8191.00

COSTO DIRECTO 32119.25 8023.05 8023.05GASTOS GENERALES+ UTILIDAD (25%) 8029.81 2005.76 2005.76

SUBTOTAL 40149.07 10028.81 10028.81

PRECIO UNITARIO

PRECIOPARCIAL

RELLENO COMPACTADO CON MATERIAL PROPIO

MURO DE LADRILLOS CORRIENTES (6X12X23) cm , EN APARAJEO DE SOGA

Page 2: VALORIZACION

SALDOCANTID. IMPORT.

100.00

100.00

100.00

50.00

2.41 560.9635.01 1378.90

1.89 693.1746.62 1579.52

50.00

1.50 503.6925.49 754.52

25.00

164.54 8191.00

13661.763415.44

17077.21

%AVANCE

Page 3: VALORIZACION

VALORIZACION AL 50%OBRA: CERCO DE ALBAÑILERIA

ITEM DESCRIPCION UNIDAD METRADO

1.00 MOVIMIENTO DE TIERRA1.01 EXCAVACION DE ZANJAS m3 21.76 7.73 168.26

1.02 3.02 33.93 102.45

1.03 ELIMINACION DE MATERIAL EXCEDENTE m3 22.48 25.86 581.402.00 CONCRETO CICLOPEO

2.01 CIMIENTO CORRIDO 1:10 + 30% P.G. m3 17.41 160.00 2785.582.02 SOBRECIMIENTO

2.02.1 CONCRETO 1:8 +25% P.M. m3 2.41 232.76 560.962.02.2 ENCOFRADO Y DESENCOFRADO m2 35.01 39.38 1378.90

3.00 CONCRETO ARMADO3.01 COLUMNAS

3.01.1 CONCRETO f'c = 210 kg/cm2 m3 1.89 366.76 693.173.01.2 ENCOFRADO Y DESENCOFRADO m2 46.62 33.88 1579.523.01.2 ACERO fy = 4200 kg/cm2 kg 1850 4.48 8292.78

3.02 VIGAS3.02.1 CONCRETO f'c = 210 kg/cm2 m3 1.50 335.80 503.693.02.2 ENCOFRADO Y DESENCOFRADO m2 25.49 29.60 754.523.02.2 ACERO fy = 4200 kg/cm2 kg 1500 4.35 6527.01

4.00 MURO DE ALBAÑILERIA

4.01 m2 164.54 49.78 8191.00

COSTO DIRECTO 32119.25GASTOS GENERALES+ UTILIDAD (25%) 8029.81

SUBTOTAL 40149.07

PRECIO UNITARIO

PRECIOPARCIAL

RELLENO COMPACTADO CON MATERIAL PROPIO

MURO DE LADRILLOS CORRIENTES (6X12X23) cm , EN APARAJEO DE SOGA

Page 4: VALORIZACION

VALORIZACION AL 50%

ANTERIOR ACTUAL ACUMULADO SALDOCANTID. IMPORT. CANTID. IMPORT. CANTID. IMPORT. CANTID. IMPORT.

21.76 168.26 100.00

3.02 102.45 100.00

22.48 581.40 100.00

8.71 1392.79 8.71 1392.79 17.41 2785.58 100.00

2.41 560.96 2.41 560.96 100.0035.01 1378.90 35.01 1378.90 100.00

1.32 485.22 1.32 485.22 70.0046.62 1579.52 46.62 1579.52 100.00

925.00 4146.39 925.00 4146.39 1850.00 8292.78 100.00

1.50 503.6925.49 754.52

375.00 1631.75 750.00 3263.51 1125.00 4895.26 75.00

164.54 8191.00

7170.93 12807.28 20830.33 9449.221792.73 3201.82 5207.58 2362.308963.67 16009.10 26037.92 11811.52

%AVANCE

Page 5: VALORIZACION

VALORIZACION AL 75%OBRA: CERCO DE ALBAÑILERIA

ITEM DESCRIPCION UNIDAD METRADO

1.00 MOVIMIENTO DE TIERRA1.01 EXCAVACION DE ZANJAS m3 21.76 7.73 168.26

1.023.02 33.93 102.45

1.03 ELIMINACION DE MATERIAL EXCEDENTE m3 22.48 25.86 581.402.00 CONCRETO CICLOPEO

2.01 CIMIENTO CORRIDO 1:10 + 30% P.G. m3 17.41 160.00 2785.582.02 SOBRECIMIENTO

2.02.1 CONCRETO 1:8 +25% P.M. m3 2.41 232.76 560.962.02.2 ENCOFRADO Y DESENCOFRADO m2 35.014 39.38 1378.90

3.00 CONCRETO ARMADO3.01 COLUMNAS

3.01.1 CONCRETO f'c = 210 kg/cm2 m3 1.89 366.76 693.173.01.2 ENCOFRADO Y DESENCOFRADO m2 46.62 33.88 1579.523.01.2 ACERO fy = 4200 kg/cm2 kg 1850 4.48 8292.78

3.02 VIGAS3.02.1 CONCRETO f'c = 210 kg/cm2 m3 1.50 335.80 503.693.02.2 ENCOFRADO Y DESENCOFRADO m2 25.49 29.60 754.523.02.2 ACERO fy = 4200 kg/cm2 kg 1500 4.35 6527.01

4.00 MURO DE ALBAÑILERIA

4.01m2 164.54 49.78 8191.00

COSTO DIRECTO 32119.25GASTOS GENERALES+ UTILIDAD (25%) 8029.81

SUBTOTAL 40149.07

PRECIO UNITARIO

PRECIOPARCIAL

RELLENO COMPACTADO CON MATERIAL PROPIO

MURO DE LADRILLOS CORRIENTES (6X12X23) cm , EN APARAJEO DE SOGA

Page 6: VALORIZACION

VALORIZACION AL 75%

ANTERIOR ACTUAL ACUMULADO SALDOCANTID. IMPORT. CANTID. IMPORT. CANTID. IMPORT. CANTID. IMPORT.

21.76 168.26 100.00

3.02 102.45 100.00

22.48 581.40 100.00

17.41 2785.58 100.00

2.41 560.96 100.0035.01 1378.90 100.00

1.32 485.22 0.57 207.95 1.89 693.17 100.0046.62 1579.52 100.00

1850.00 8292.78 100.00

1.50 503.6925.49 754.52

1125.00 4895.26 375.00 1631.75 1500.00 6527.01 100.00

164.54 8191.00 100.00

5380.48 1839.70 30861.04 1258.211345.12 459.93 7715.26 314.556725.60 2299.63 38576.30 1572.77

%AVANCE

Page 7: VALORIZACION

VALORIZACION AL 100%OBRA: CERCO DE ALBAÑILERIA

ITEM DESCRIPCION UNIDAD METRADO

1.00 MOVIMIENTO DE TIERRA1.01 EXCAVACION DE ZANJAS m3 21.76 7.73

1.023.02 33.93

1.03 ELIMINACION DE MATERIAL EXCEDENTE m3 22.48 25.862.00 CONCRETO CICLOPEO

2.01 CIMIENTO CORRIDO 1:10 + 30% P.G. m3 17.41 160.002.02 SOBRECIMIENTO

2.02.1 CONCRETO 1:8 +25% P.M. m3 2.41 232.762.02.2 ENCOFRADO Y DESENCOFRADO m2 35.014 39.38

3.00 CONCRETO ARMADO3.01 COLUMNAS

3.01.1 CONCRETO f'c = 210 kg/cm2 m3 1.89 366.763.01.2 ENCOFRADO Y DESENCOFRADO m2 46.62 33.883.01.2 ACERO fy = 4200 kg/cm2 kg 1850 4.48

3.02 VIGAS3.02.1 CONCRETO f'c = 210 kg/cm2 m3 1.50 335.803.02.2 ENCOFRADO Y DESENCOFRADO m2 25.49 29.603.02.2 ACERO fy = 4200 kg/cm2 kg 1500 4.35

4.00 MURO DE ALBAÑILERIA

4.01m2 164.54 49.78

COSTO DIRECTOGASTOS GENERALES+ UTILIDAD (25%)

SUBTOTAL

PRECIO UNITARIO

RELLENO COMPACTADO CON MATERIAL PROPIO

MURO DE LADRILLOS CORRIENTES (6X12X23) cm , EN APARAJEO DE SOGA

Page 8: VALORIZACION

VALORIZACION AL 100%

ANTERIOR ACTUAL ACUMULADO SALDOCANTID. IMPORT. CANTID. IMPORT. CANTID. IMPORT. CANTID. IMPORT.

168.26 21.76 168.26 100.00

102.453.02 102.45 100.00

581.40 22.48 581.40 100.00

2785.58 17.41 2785.58 100.00

560.96 2.41 560.96 100.001378.90 35.01 1378.90 100.00

693.17 1.89 693.17 100.001579.52 46.62 1579.52 100.008292.78 1850.00 8292.78 100.00

503.69 1.50 503.69 100.00754.52 25.49 754.52 100.00

6527.01 1500.00 6527.01 100.00

8191.00164.54 8191.00 100.00

32119.25 0.00 0.00 32119.25 0.008029.81 0.00 0.00 8029.81 0.00

40149.07 0.00 0.00 40149.07 0.00

PRECIOPARCIAL

%AVANCE

Page 9: VALORIZACION

costo unitarioPARTIDA: EXCAVACION ZANJASUNIDAD: m3CUADRILLA: 0.1 capataz + 4 peonesRENDIMIENTO: 14 m3/diadescripcion unidad cantidad precio costo parcialcapataz h-h 0.057 13.10 0.75peon h-h 0.571 13.10 7.49herramientas estimado 0.03 8.23 0.25

costo total 7.73

PARTIDA: RELLENO COMPACTADO CON MATERIAL PROPIOUNIDAD: m3CUADRILLA: 0.1 capataz + 1 peonRENDIMIENTO: 3.5 m3/diadescripcion unidad cantidad precio costo parcialcapataz h-h 0.229 13.10 2.99peon h-h 2.286 13.10 29.94herramientas estimado 0.03 32.94 0.99

costo total 33.93

PARTIDA: ELIMINACION DE MATERIAL EXCEDENTEUNIDAD: m3CUADRILLA: 2 peones + 1 volqueteRENDIMIENTO: 30 m3/diadescripcion unidad cantidad precio costo parcialpeon h-h 0.533 13.10 6.99volquete h-m 0.267 70.00 18.67herramientas estimado 0.03 6.99 0.21

costo total 25.86

PARTIDA: CONCRETO CIMIENTO CORRIDOUNIDAD: m3

RENDIMIENTO: 25 m3/diaMEZCLA: 1:10 + 30% PM a/c =0.80 descripcion unidad cantidad precio costo parcialoperario h-h 0.640 15.00 9.60oficial h-h 0.320 14.20 4.54peon h-h 2.560 13.10 33.54operador de equipo liviano h-h 0.640 14.20 9.09cemento bolsa 2.900 17.60 51.04hormigon m3 0.830 33.60 27.89piedra m3 0.480 30.00 14.40agua m3 0.100 10.00 1.00mezcladora h-m 0.320 12.50 4.00

CUADRILLA: 2 OPERARIO + 1 OFICIAL + 8 peones + 2 OPERADORES DE EQUIPOS LIVIANOS + 1 MEZCLADORA + 1 VIBRADOR

Page 10: VALORIZACION

vibradora h-m 0.320 10.00 3.20herramientas estimado 0.03 56.77 1.70

costo total 160.00

PARTIDA:CONCRETO DE SOBRECIMIENTO UNIDAD: m3

RENDIMIENTO: 13 m3/diaMEZCLA: 1:8 + 25% PM a/c =0.80 descripcion unidad cantidad precio costo parcialoperario h-h 0.615 15.00 9.23oficial h-h 1.231 14.20 17.48peon h-h 4.923 13.10 64.49operador de equipo liviano h-h 1.231 14.20 17.48cemento bolsa 3.700 17.60 65.12hormigon m3 0.850 33.60 28.56piedra m3 0.400 30.00 12.00agua m3 0.130 10.00 1.30mezcladora h-m 0.615 12.50 7.69vibradora h-m 0.615 10.00 6.15herramientas estimado 0.03 108.68 3.26

costo total 232.76

CUADRILLA: 1 OPERARIO + 2 OFICIAL + 8 peones + 2 OPERADORES DE EQUIPOS LIVIANOS + 1 MEZCLADORA + 1 VIBRADOR

Page 11: VALORIZACION

PARTIDA: MURO DE ALBAÑILERIAUNIDAD: m2 aparajeo de sogaCUADRILLA: 1 OPERARIO + 1/2 peon RENDIMIENTO: 9 m2/diaMEZCLA: 1:5 a/c =0.75 JUNTA: 1.5cm descripcion unidad cantidad precio costo parcialoperario h-h 0.889 15.00 13.33peon h-h 0.444 13.10 5.82ladrillos unidad 57.14 0.45 25.713cemento bolsa 0.195 17.60 3.432arena m3 0.027 23.00 0.621agua m3 0.006 10.00 0.06andamio de madera pie2 0.050 4.50 0.225herramientas estimado 0.03 19.16 0.57

costo total 49.78

PARTIDA: CONCRETO DE COLUMNAUNIDAD: m3 f´c= 210 kg/cm2

RENDIMIENTO: 10 m3/diaMEZCLA: 1:2.1:2.3 a/c =0.67 descripcion unidad cantidad precio costo parcialoperario h-h 1.600 15.00 24.00oficial h-h 0.800 14.20 11.36peon h-h 8.000 13.10 104.80operador de equipo liviano h-h 1.600 14.20 22.72cemento bolsa 8.400 17.60 147.84arena m3 0.500 23.00 11.5grava m3 0.550 35.00 19.25agua m3 0.240 10.00 2.4mezcladora h-m 0.800 12.50 10.00

vibradora h-m 0.800 10.00 8.00herramientas estimado 0.03 162.88 4.89

costo total 366.76

PARTIDA: ENCOFRADO Y DESENCOFRADO DE COLUMNA UNIDAD: m2 CUADRILLA: 1 OPERARIO + 1 OFICIAL RENDIMIENTO: 10 m3/diadescripcion unidad cantidad precio costo parcialoperario h-h 0.800 15.00 12.00oficial h-h 0.800 14.20 11.36madera tornillo pie2 1.880 4.50 8.46clavos # 16 kg 0.200 3.40 0.68

CUADRILLA: 2 OPERARIO + 1 OFICIAL + 10 peon + 2 OPERADORES DE EQUIPOS LIVIANOS + 1 MEZCLADORA + 1 VIBRADOR

Page 12: VALORIZACION

alambre # 8 kg 0.200 3.40 0.68herramientas estimado 0.03 23.36 0.70

costo total 33.88

PARTIDA: ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO

UNIDAD: m2

CUADRILLA: 1 OPERARIO + 1 OFICIAL RENDIMIENTO: 14 m3/diadescripcion unidad cantidad precio costo parcialoperario h-h 0.571 15.00 8.57oficial h-h 0.571 14.20 8.11madera tornillo pie2 4.630 4.50 20.84clavos # 16 kg 0.200 3.40 0.68alambre # 8 kg 0.200 3.40 0.68herramientas estimado 0.03 16.69 0.50

costo total 39.38

PARTIDA: ACERO DE REFUERZO PARA COLUMNAUNIDAD: KG CUADRILLA: 1 OPERARIO + 1 OFICIAL RENDIMIENTO: 220 KG/diadescripcion unidad cantidad precio costo parcialoperario h-h 0.036 15.00 0.55oficial h-h 0.036 14.20 0.52acero corrugado kg 1.070 2.80 3.00alambre # 16 kg 0.030 3.40 0.10cizalla para corte de fierro h-m 0.036 8.00 0.29herramientas estimado 0.03 1.06 0.03

costo total 4.48

PARTIDA: CONCRETO DE VIGAUNIDAD: m3 f´c= 210 kg/cm2

RENDIMIENTO: 12 m3/diaMEZCLA: 1:2.1:2.3 a/c =0.67 descripcion unidad cantidad precio costo parcialoperario h-h 1.333 15.00 20.00oficial h-h 0.667 14.20 9.47peon h-h 6.667 13.10 87.33operador de equipo liviano h-h 1.333 14.20 18.93cemento bolsa 8.400 17.60 147.84arena m3 0.500 23.00 11.5grava m3 0.550 35.00 19.25agua m3 0.240 10.00 2.4mezcladora h-m 0.667 12.50 8.33

CUADRILLA: 2 OPERARIO + 1 OFICIAL + 10 peon + 2 OPERADORES DE EQUIPOS LIVIANOS + 1 MEZCLADORA + 1 VIBRADOR

Page 13: VALORIZACION

vibradora h-m 0.667 10.00 6.67herramientas estimado 0.03 135.73 4.07

costo total 335.80

PARTIDA: ENCOFRADO Y DESENCOFRADO DE VIGAUNIDAD: m2 CUADRILLA: 1 OPERARIO + 1 OFICIAL RENDIMIENTO: 12 m3/diadescripcion unidad cantidad precio costo parcialoperario h-h 0.667 15.00 10.00oficial h-h 0.667 14.20 9.47madera tornillo pie2 1.820 4.50 8.19clavos # 16 kg 0.200 3.40 0.68alambre # 8 kg 0.200 3.40 0.68herramientas estimado 0.03 19.47 0.58

costo total 29.60

PARTIDA: ACERO DE REFUERZO PARA VIGAUNIDAD: KG CUADRILLA: 1 OPERARIO + 1 OFICIAL RENDIMIENTO: 250 KG/diadescripcion unidad cantidad precio costo parcialoperario h-h 0.032 15.00 0.48oficial h-h 0.032 14.20 0.45acero corrugado kg 1.070 2.80 3.00alambre # 16 kg 0.030 3.40 0.10cizalla para corte de fierro h-m 0.036 8.00 0.29herramientas estimado 0.03 0.93 0.03

costo total 4.35