    ABB GroupDecember 18, 2014 | Slide 1

    ABB SF 6 Gas ManagementRegional Centre Proposal

  • 8/10/2019 SF6 Presentation Mexico 27082013

    2/22

    ABB GroupDecember 18, 2014 | Slide 2

    SF 6 presentation overview

    Power industry problem

    Significance of ABBs recycling technology

    ABB SF 6 Gas Management Portfolio

    Best practice inventory management

    ABB SF 6 strategy

    Customer benefits

    Summary of SF 6 lifecycle

    Contacts for queries

  • 8/10/2019 SF6 Presentation Mexico 27082013

    3/22

    ABB GroupDecember 18, 2014 | Slide 3

    Power industry problemWhy offer SF 6 management as a service?

    First generation SF 6 equipment now beingreplacedHigh global warmingpotential

    23,900 C0 2 Equiv.Compliant recovery anddisposal required at endof lifeLimited disposal options

    availableCost to businessSafety andenvironmental risk

  • 8/10/2019 SF6 Presentation Mexico 27082013

    4/22

    ABB GroupDecember 18, 2014 | Slide 4

    ABB SF 6 Recycling Plant

  • 8/10/2019 SF6 Presentation Mexico 27082013

    5/22

    ABB SF 6 Recycling Plant

    ABB GroupDecember 18, 2014 | Slide 5

  • 8/10/2019 SF6 Presentation Mexico 27082013

    6/22

    ABB GroupDecember 18, 2014 | Slide 6

    Significance of new technology

    Used SF 6 acceptable for reuse(IEC60480) > 97.0 v/v% pure

    G a s

    C a r

    t

    Technical grade SF 6 (IEC60376) > 99.7 w/w % pure

    Possibility of gas recycling bymanufacturer M

    a n u f a c

    t u r e r

    R e c y c

    l i n g

    I n c i n e r a

    t i o n

    Pure SF 6

    H e a v y

    C o n

    t a m

    i n a

    t i o n

    L i g h t C o n

    t a m

    i n a

    t i o n

    A

    B B

    R e c y c

    l i n g

    P l a

    n t

    ABB Recycling Plant handles alllevels of contaminated gas

    Recycled to > than IEC 60376

  • 8/10/2019 SF6 Presentation Mexico 27082013

    7/22

    ABBs SF 6 management portfolio

    1. SF 6 Disposal

    Disposal of contaminated or unwanted gas and cylinders2. SF 6 Supply

    Supply and recycle of SF 6 and compliant cylinders and cages

    3. Inventory Management cylinder management, SF 6 reporting, waste tracking

    4. Decommissioning Gas reclaim, unit decontamination, material recycling

    5. Training & consultancy Consultancy, class room and practical training

    6. Gas monitoring systems Gas density and trend analysis eg MSM, CBS etc

    7. SF 6 Field Services Gas filling, checks, leak detection and repair, handling

    ABB GroupDecember 18, 2014 | Slide 7

  • 8/10/2019 SF6 Presentation Mexico 27082013

    8/22

    SF6 Gas Management in Australia ABB SF6 Recycling Centre

    Output

    Technical grade SF6

    Processing

    Plant

    Input

    Used SF6

    ABB GroupDecember 18, 2014 | Slide 8

  • 8/10/2019 SF6 Presentation Mexico 27082013

    9/22

    Switchgear Decommissioning

    Our switchgear decommissioning service at ABB Moorebank

    removes SF 6 from equipment, decontaminates and prepares

    equipment for further resource recovery.

  • 8/10/2019 SF6 Presentation Mexico 27082013

    10/22

    Best practice SF 6 inventory managementCylinders and valves

    Colour co-ordinatedcylinders

    Green shoulder technicalgrade gasYellow shoulder used gas

    Special RPV valves fornew SF 6

    Reduce risk ofcompromising purity of

    clean gasCorrosive resistant valvesand cylinders forcontaminated gas

    Improves safety

  • 8/10/2019 SF6 Presentation Mexico 27082013

    11/22

    ABB GroupDecember 18, 2014 | Slide 11

    SF 6 value chain power products industry

    SF 6 recoveryusing gas carts

    MAINTAIN

    Filling, refilling,reclaiming,quality assessment,leak detection,gas sensing,logistics,inventory,reporting

    BUILD

    SF 6 used in

    commissioningnew HV and MVswitchgear andcircuit breakers

    SUPPLY

    SF 6 distributors

    DECOMMISSION

    Decommissionning

    of old switchgear,SF 6 needs to bereclaimed anddisposed of ina compliantmanner

    DISPOSE

    Contaminated

    SF 6 gas isincineratedor processed forreuse by gasdistributors

    High logistic costs and energy consumption

  • 8/10/2019 SF6 Presentation Mexico 27082013

    12/22

    ABB GroupDecember 18, 2014 | Slide 12

    SF 6 value chain power products industryProposed strategy for gas management

    MAINTAIN

    Filling, refilling,reclaiming,

    quality assessment,leak detection,gas sensing,logistics,inventory,reporting

    BUILD

    SF 6 used incommissioningnew HV and MVswitchgear andcircuit breakers

    DECOMMISSION

    Decommissionning

    of old switchgear,SF 6 needs to bereclaimed anddisposed of ina compliantmanner

    DISPOSE

    ContaminatedSF 6 gas isincineratedor processed forreuse by gasdistributors

    ABB / IIE could implement a complete environmental management solution

    ABB / IIESF 6 Recycling Centre

    SUPPLY

    SF 6 distributors

    Amountimported

    is reduced

    Need todispose iseliminated

  • 8/10/2019 SF6 Presentation Mexico 27082013

    13/22

    Customer benefitsLower risk

    Improved safetyperformanceReduced risk of noncompliance to

    regulations Adherence to localstandardsUse of ABBs qualifiedservice techniciansMake reporting toauthorities easier

  • 8/10/2019 SF6 Presentation Mexico 27082013

    14/22

  • 8/10/2019 SF6 Presentation Mexico 27082013

    15/22

    Customer benefits (continued)Decreased carbon footprint

    Support environmental policy objectivesReduction in greenhouse gas emissions

  • 8/10/2019 SF6 Presentation Mexico 27082013

    16/22

    Summary of Proposed SF 6 lifecycle

    Use of SF 6 in electrical equipment

    Decommission, maintainSF 6 switchgear

    Transport used SF 6 to ABB Recycling Centre

    Recycle using ABBs Patented Technology

    Reclaim contaminated,used or unwanted SF 6

    Reuse ABB TechnicalGrade SF 6

    Quality assurancecheck to IEC60376

    Deliver ABB Technical GradeSF 6 to customer

    ABB GroupDecember 18, 2014 | Slide 16

  • 8/10/2019 SF6 Presentation Mexico 27082013

    17/22

    Contacts for more information

    Brett Alexander - SF 6 Operations ManagerTel: + 61 2 9753 [email protected]

    Marcus Marenghi High Voltage Service Manager, AustraliaTel: + 61 2 9753 [email protected]

    ABB GroupDecember 18, 2014 | Slide 17

    mailto:[email protected]:[email protected]:[email protected]:[email protected]
  • 8/10/2019 SF6 Presentation Mexico 27082013

    18/22

  • 8/10/2019 SF6 Presentation Mexico 27082013

    19/22

  • 8/10/2019 SF6 Presentation Mexico 27082013

    20/22

  • 8/10/2019 SF6 Presentation Mexico 27082013

    21/22

    ABB operator manages all processes / activity

    Logistics

    Quality Control

    Inventory management

    Safety

    ABB leases SF6 recycling plant/s only

    On IIE premises

    IIE purchase cylinders and cages

    ABB GroupDecember 18, 2014 | Slide 21

    Option 2: ABB leases a plant to IIE and providesoperator

  • 8/10/2019 SF6 Presentation Mexico 27082013

    22/22

    Option 3: ABB provides complete SF6 gasmanagement service

    IIE outsources SF6 management to ABB.MXABB sets up recycling center for Mexican Market

    MXABB is responsible for:

    LogisticsQuality Control

    Inventory management

    Safety

    Purchase cylinders and cages

    AUABB support setup and plant supply

    ABB GroupDecember 18, 2014 | Slide 22