Crystal Reports ActiveX Designer - PresupuestoCliente.Rpt

UNIVERSIDAD NACIONAL DEL ALTIPLANO PUNO INGENIERA DE MINAS

ItemDescripcinUnd.MetradoPrecio S.Parcial S.

OBRAS PROVISIONALES800.00

CARTEL DE OBRAUnd1.00800.00800.00

DESARENADOR (04 UND)7,799.00

OBRAS PRELIMINARES97.95

LIMPIEZA DE TERRENO MANUALm243.841.1048.22

TRAZO Y REPLANTEO DE OBRAS DE ARTEm244.401.1249.73

MOVIMIENTO DE TIERRAS809.02

EXCAVACION MANUAL EN TERRENO SUELTO O.A.m344.1210.50463.26

REFINE Y NIVELACION EN TERRENO NORMALm244.401.5367.93

ACARREO DE MATERIAL EXCEDENTE D=30 Mm352.925.25277.83

CONCRETO SIMPLE255.59

SOLADOS CONCRETO f'c=100 kg/cm2 h=2"m243.845.83255.59

CONCRETO ARMADO5,949.64

CONCRETO FC=175 KG/CM2 C/M O.A.m38.24275.312,268.55

ENCOFRADO Y DESENCOFRADO O.A.m249.6032.131,593.65

ACERO DE REFUERZO FY=4200 KG/CM2 C/M 0.A.kg441.324.732,087.44

REVOQUES, ENLUCIDOS Y MOLDURAS686.80

TARRAJEO EN INTERIORESm268.009.84669.12

CURADO DE OBRAS DE ARTEm268.000.2617.68

CONSTRUCCION DE CANAL DE CONDUCCION (3,770.0 ML)225,119.15

OBRAS PRELIMINARES8,897.20

TRAZO Y REPLANTEO DE CANALml3,770.000.853,204.50

NIVELACION Y PLANTILLADO RASANTE DE CANALml3,770.001.515,692.70

MOVIMIENTO DE TIERRAS49,076.72

EXCAVACION Y/O CORTE EN TERRENO SUELTOm31,091.856.306,878.66

ACARREO DE MATERIAL EXCEDENTE D=30 Mm31,419.415.257,451.90

CARGUIO DE MATERIAL DE RELLENOm3164.080.1321.33

TRANSPORTE DE MATERIAL DE RELLENOm3164.083.84630.07

CONFORMACION DE TERRAPLENm3164.089.001,476.72

EXCAVACION DE CAJA DE CANAL EN TIERRA ( A MANO)m31,357.209.4512,825.54

REFINE CAJA CANAL A MANOml3,770.005.2519,792.50

CONCRETO SIMPLE165,567.11

CONCRETO FC=175 KG/CM2 C/MEZm3452.40288.32130,435.97

CERCHAS METLICAS PARA JUNTAS DE DILATACINUnd60.0040.002,400.00

COLOCACION DE CERCHAS SEMICIRCULARESUnd1,508.004.807,238.40

JUNTA FLEXIBLE DE POLIURETANOml2,427.8810.5025,492.74

REVOQUES, ENLUCIDOS Y MOLDURAS1,578.12

CURADO EN CANALES DE CONCRETOm26,069.700.261,578.12

CAMARAS DE CARGA22,155.11

CAMARA DE CARGA 5.0 M3 (03 UND)16,108.36

TRABAJOS PRELIMINARES90.86

LIMPIEZA DE TERRENO MANUALm234.681.1038.15

TRAZO Y REPLANTEO PRELIMINARm234.681.5252.71

MOVIMIENTO DE TIERRAS251.29

EXCAVACION MANUAL EN TERRENO SUELTO O.A.m313.8610.50145.53

REFINE, NIVELACION Y COMPACTACIONm234.680.3211.10

ACARREO DE MATERIAL EXCEDENTE D=30 Mm318.035.2594.66

CONCRETO SIMPLE540.31

SOLADO e=4"m234.6815.58540.31

CONCRETO ARMADO13,325.85

CONCRETO FC=210 KG/CM2 (LOSA DE FONDO Y MUROS)m318.59344.306,400.54

ENCOFRADO Y DESENCOFRADO (LOSA DE FONDO Y MURO)m292.6429.142,699.53

ACERO DE REFUERZO FY=4200 KG/CM2 C/M 0.A.kg893.404.734,225.78

REVOQUES, ENLUCIDOS Y MOLDURAS1,523.65

TARRAJEO CON IMPERMEABILIZANTESm249.2019.66967.27

TARRAJEO EN INTERIORESm244.649.84439.26

TARRAJEO PARA PENDIENTE DE FONDOm212.009.76117.12

PINTURA321.41

ItemDescripcinUnd.MetradoPrecio S.Parcial S.

PINTURA DOS MANOSm244.647.20321.41

VARIOS54.99

PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION)Und3.0018.3354.99

CAMARA DE CARGA 7.0 M3 (01 UND)6,046.75

TRABAJOS PRELIMINARES25.18

LIMPIEZA DE TERRENO MANUALm29.611.1010.57

TRAZO Y REPLANTEO PRELIMINARm29.611.5214.61

MOVIMIENTO DE TIERRAS69.65

EXCAVACION MANUAL EN TERRENO SUELTO O.A.m33.8410.5040.32

REFINE, NIVELACION Y COMPACTACIONm29.610.323.08

ACARREO DE MATERIAL EXCEDENTE D=30 Mm35.005.2526.25

CONCRETO SIMPLE149.72

SOLADO e=4"m29.6115.58149.72

CONCRETO ARMADO4,939.02

CONCRETO FC=210 KG/CM2 (LOSA DE FONDO Y MUROS)m35.25344.301,807.58

ENCOFRADO Y DESENCOFRADO (LOSA DE FONDO Y MURO)m235.3429.141,029.81

ACERO DE REFUERZO FY=4200 KG/CM2 C/M 0.A.kg444.324.732,101.63

REVOQUES, ENLUCIDOS Y MOLDURAS724.32

TARRAJEO CON IMPERMEABILIZANTESm220.6419.66405.78

TARRAJEO EN EXTERIORESm216.7415.67262.32

TARRAJEO PARA PENDIENTE DE FONDOm25.769.7656.22

PINTURA120.53

PINTURA DOS MANOSm216.747.20120.53

VARIOS18.33

PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION)Und1.0018.3318.33

PASE PEATONAL (21 UND)21,561.37

OBRAS PRELIMINARES114.31

TRAZO Y REPLANTEO DE OBRAS DE ARTEm2102.061.12114.31

MOVIMIENTO DE TIERRAS471.56

EXCAVACION MANUAL EN TERRENO SUELTO O.A.m327.2210.50285.81

ACARREO DE MATERIAL EXCEDENTE D=30 Mm335.385.25185.75

CONCRETO20,506.62

CONCRETO FC=140 KG/CM2 + 30% PIEDRA MEDIANA C/M O.A.m349.52227.8311,282.14

CONCRETO FC=175 KG/CM2 C/M O.A.m37.56275.312,081.34

ENCOFRADO Y DESENCOFRADO O.A.m267.2032.132,159.14

ACERO DE REFUERZO FY=4200 KG/CM2 C/M 0.A.kg1,053.704.734,984.00

REVOQUES, ENLUCIDOS Y MOLDURAS468.88

TARRAJEO EN EXTERIORES M / 1:5 e= 1.5 CMm244.109.84433.94

CURADO DE OBRAS DE ARTEm2134.400.2634.94

TOMA LATERAL (21 UND)17,556.37

OBRAS PRELIMINARES57.62

TRAZO Y REPLANTEO DE OBRAS DE ARTEm251.451.1257.62

MOVIMIENTO DE TIERRAS192.10

EXCAVACION MANUAL EN TERRENO SUELTO O.A.m311.0910.50116.45

ACARREO DE MATERIAL EXCEDENTE D=30 Mm314.415.2575.65

CONCRETO5,193.92

CONCRETO FC=175 KG/CM2 C/M O.A.m37.32275.312,015.27

ENCOFRADO Y DESENCOFRADO O.A.m266.4732.132,135.68

ACERO DE REFUERZO FY=4200 KG/CM2 C/M 0.A.kg220.504.731,042.97

REVOQUES, ENLUCIDOS Y MOLDURAS3,912.86

TARRAJEO EN EXTERIORES M / 1:5 e= 1.5 CMm272.249.84710.84

JUNTA WATER STOP DE 6" PROVISION Y COLOCADOml147.8421.523,181.52

CURADO DE OBRAS DE ARTEm278.860.2620.50

CARPINTERIA METALICA8,199.87

COMPUERTA METALICA TIPO TARJETA 0.25 X 0.30 MUnd21.00390.478,199.87

PUENTE VEHICULAR (02 UND)7,969.95

OBRAS PRELIMINARES19.88

TRAZO Y REPLANTEO DE OBRAS DE ARTEm217.751.1219.88

ItemDescripcinUnd.MetradoPrecio S.Parcial S.

MOVIMIENTO DE TIERRAS201.13

EXCAVACION MANUAL EN TERRENO SUELTO O.A.m311.6110.50121.91

ACARREO DE MATERIAL EXCEDENTE D=30 Mm315.095.2579.22

CONCRETO7,547.97

CONCRETO FC=140 KG/CM2 + 30% PIEDRA MEDIANA C/M O.A.m315.61227.833,556.43

CONCRETO FC=210 KG/CM2 C/Mm32.06341.37703.22

ENCOFRADO Y DESENCOFRADO O.A.m252.5432.131,688.11

ACERO DE REFUERZO FY=4200 KG/CM2 C/M 0.A.kg338.314.731,600.21

REVOQUES, ENLUCIDOS Y MOLDURAS200.97

TARRAJEO EN EXTERIORES M / 1:5 e= 1.5 CMm219.399.84190.80

CURADO DE OBRAS DE ARTEm239.130.2610.17

VARIOS13,106.64

CAPACITACION Y ASISTENCIA TECNICAEto1.001,500.001,500.00

SEGURIDAD EN OBRAglb1.002,500.002,500.00

MAESTRO DE OBRAmes3.002,000.006,000.00

PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION)Und8.0018.33146.64

BRIQUETERAUnd1.00140.00140.00

FLETE TERRESTREglb1.002,500.002,500.00

DISEO DE MEZCLAUnd1.00320.00320.00

Costo Directo316,067.59

Gastos Generales (4.22 %)13,348.00

Gastos de Supervisin (4.45 %)14,063.41

Expediente Tcnico (1.90 %)6,000.00

=========================TOTAL PRESUPUESTO 359,479.00SON : TRESCIENTOS CINCUENTA NUEVE MIL CUATROCIENTOS SETENTINUEVE Y 00/100 NUEVOS SOLES