RESUMEN COSTO TOTAL PROYECTO : RECONSTRUCCION DE LA I.E.I. Nº 427 JESUS DIVINA MISERICORDIA DEL DISTRITO DE CIUDAD NUEVA - TACNA FECHA - MAYO DE 2010 LUGAR : TACNA-TACNA-TACNA ASIGNACION GENERICA O ESPECIFICA ESPECIFICA DESCRIPCION MES SUB TOTAL TOTAL MES 01 MES 02 MES 03 PRESUPUESTO DE OBRA 660,597.32 COSTO DIRECTO DE INFRAESTRUCTURA 160,359.95 225,186.49 125,378.94 510,925.38 SUB TOTAL 160,359.95 225,186.49 125,378.94 510,925.38 510,925.38 GASTOS GENERALES 10.00% 22,123.71 14,484.41 14,484.41 51,092.54 51,092.54 GASTOS DE SUPERVISION 3.00% 6,392.59 4,467.59 4,467.59 15,327.76 15,327.76 GASTOS DE LIQUIDACION 1.50% 0.00 0.00 7,663.88 7,663.88 7,663.88 GASTOS ADMINISTRATIVOS 3.00% 5,109.25 5,109.25 5,109.25 15,327.76 15,327.76 EXPEDIENTE TECNICO 19,500.00 0.00 0.00 19,500.00 19,500.00 MOBILIARIO Y EQUIPAMIENTO 0.00 0.00 40,760.00 40,760.00 40,760.00 TOTAL PRESUPUESTO 213,485.51 249,247.74 197,864.07 660,597.32 660,597.32 PRESUPUESTO TOTAL POR MES 213,485.51 249,247.74 197,864.07 660,597.32 660,597.32 TACNA REGIONAL GOBIERNO Desarrollo para todos

description

Presupuesto Dm

Transcript of Presupuesto Dm

Page 1: Presupuesto Dm

RESUMEN COSTO TOTAL

PROYECTO : RECONSTRUCCION DE LA I.E.I. Nº 427 JESUS DIVINA MISERICORDIA DEL DISTRITO DE CIUDAD NUEVA - TACNA

FECHA - MAYO DE 2010

LUGAR : TACNA-TACNA-TACNA

ASIGNACION GENERICA O ESPECIFICA

ESPECIFICA DESCRIPCIONMES

SUB TOTAL TOTALMES 01 MES 02 MES 03

PRESUPUESTO DE OBRA 660,597.32

COSTO DIRECTO DE INFRAESTRUCTURA 160,359.95 225,186.49 125,378.94 510,925.38

SUB TOTAL 160,359.95 225,186.49 125,378.94 510,925.38 510,925.38

GASTOS GENERALES 10.00% 22,123.71 14,484.41 14,484.41 51,092.54 51,092.54

GASTOS DE SUPERVISION 3.00% 6,392.59 4,467.59 4,467.59 15,327.76 15,327.76

GASTOS DE LIQUIDACION 1.50% 0.00 0.00 7,663.88 7,663.88 7,663.88

GASTOS ADMINISTRATIVOS 3.00% 5,109.25 5,109.25 5,109.25 15,327.76 15,327.76

EXPEDIENTE TECNICO 19,500.00 0.00 0.00 19,500.00 19,500.00

MOBILIARIO Y EQUIPAMIENTO 0.00 0.00 40,760.00 40,760.00 40,760.00

TOTAL PRESUPUESTO 213,485.51 249,247.74 197,864.07 660,597.32 660,597.32

PRESUPUESTO TOTAL POR MES 213,485.51 249,247.74 197,864.07 660,597.32 660,597.32

TACNAREGIONALGOBIERNO

Desarrollo para todos

Page 2: Presupuesto Dm

GASTOS INDIRECTOS

PROYECTO : RECONSTRUCCION DE LA I.E.I. Nº 427 JESUS DIVINA MISERICORDIA DEL DISTRITO DE CIUDAD NUEVA - TACNAFECHA - MAYO DE 2010LUGAR : TACNA-TACNA-TACNA

ESPECIFICA DESCRIPCION UND CANT. P.U PARCIAL MESES

SUB TOTAL TOTALMES 01 MES 02 MES 03

GASTOS GENERALES 51,092.54

2.6.22.23 COSTO DE CONSTRUCCION POR ADM. DIRECTA - PERSONAL 10,500.00 10,500.00 10,500.00 31,500.00

PERSONALINGENIERO RESIDENTE MES 3 4,200.00 12,600 4,200.00 4,200.00 4,200.00 12,600.00ASISTENTE TECNICO MES 3 2,300.00 6,900 2,300.00 2,300.00 2,300.00 6,900.00ASISTENTE ADMINISTRATIVO MES 3 1,600.00 4,800 1,600.00 1,600.00 1,600.00 4,800.00ALMACENERO MES 3 1,200.00 3,600 1,200.00 1,200.00 1,200.00 3,600.00GUARDIAN MES 3 1,200.00 3,600 1,200.00 1,200.00 1,200.00 3,600.00

2.6.22.24 COSTO DE CONSTRUCCION POR ADM. DIRECTA - BIENES 330.50 330.50 330.50 991.50

COMBUSTIBLES110 GASOLINA DE 84 OCTANOS GLN 65 9.80 637 212.33 212.33 212.33 637.00110 PETROLEO GLN 35 8.70 305 101.50 101.50 101.50 304.506 LUBRICANTES, FILTROS GLN 1 50.00 50 16.67 16.67 16.67 50.00

2.6.22.25 COSTO DE CONSTRUCCION POR ADM. DIRECTA - SERVICIOS 318.33 233.33 233.33 785.00

VARIOSSERVICIO ENSAYO A LA COMPRESION UND 15 40.00 600 200.00 200.00 200.00 600.00SERVICIO ENSAYO DE COMPACTACION UND 1 25.00 25 25.00 25.00SERVICIO PROCTOR MODIFICADO UND 1 60.00 60 60.00 60.00SERVICIO DE FOTOCOPIADO Y ANILLADO UND 1 100.00 100 33.33 33.33 33.33 100.00

2.6.22.26 COSTO DE CONSTRUCCION POR ADM. DIRECTA - OTROS 3,040.00 0.00 0.00 3,040.00

IMPLEMENTOS DE SEGURIDAD15 ZAPATOS DE SEGURIDAD PAR 2 150.00 300 300.00 300.00

BOTAS PAR 18 50.00 900 900.00 900.00CASCOS PAR 16 35.00 560 560.00 560.00CHALECOS UND 16 30.00 480 480.00 480.00MAMELUCOS UND 16 50.00 800 800.00 800.00

2.6.22.26 COSTO DE CONSTRUCCION POR ADM. DIRECTA - OTROS 200.00 200.00 200.00 600.00

PRACTICANTE MES 3 200.00 600 200.00 200.00 200.00 600.00

TACNAREGIONALGOBIERNO

Desarrollo para todos

Page 3: Presupuesto Dm

GASTOS INDIRECTOS

PROYECTO : RECONSTRUCCION DE LA I.E.I. Nº 427 JESUS DIVINA MISERICORDIA DEL DISTRITO DE CIUDAD NUEVA - TACNAFECHA - MAYO DE 2010LUGAR : TACNA-TACNA-TACNA

ESPECIFICA DESCRIPCION UND CANT. P.U PARCIAL MESES

SUB TOTAL TOTALMES 01 MES 02 MES 03

TACNAREGIONALGOBIERNO

Desarrollo para todos

2.6.22.26 COSTO DE CONSTRUCCION POR ADM. DIRECTA - OTROS 735.58 95.58 95.58 926.74

BIENES DE CONSUMOMEMORIA PORTATIL UND 2 120.00 240 240.00 240.00MATERIALES PARA MANTENIMIENTO Y REPUESTOS GLB 1 250.00 250 250.00 250.00TINTA PARA IMPRESORA A COLORES UND 2 60.00 120 120.00 120.00CINTA PARA IMPRESORA UND 1 30.00 30 30.00 30.00CARTUCHO PARA PLOTER UND 0 200.00 - 0.00 0.00CAJA CHICA GLB 1 286.74 287 95.58 95.58 95.58 286.74

2.6.22.26 COSTO DE CONSTRUCCION POR ADM. DIRECTA - OTROS 150.00 0.00 0.00 150.00

MEDICINASMEDICINAS GLB 1 150.00 150 150.00 150.00

. 2.6.22.26 COSTO DE CONSTRUCCION POR ADM. DIRECTA - OTROS 874.30 0.00 0.00 874.30

MATERIALES DE ESCRITORIOPAPEL CARBON COLOR AZUL PQTE 1 18.00 18 18.00 18.00CUADERNO ESPIRAL 200 HOJAS REFORZADO UND 1 35.00 35 35.00 35.00CUADERNO EMPASTADO 100 HOJAS UND 1 10.00 10 10.00 10.00AGENDA 2009 UND 1 10.00 10 10.00 10.00LAPICERO CJA 2 3.00 6 6.00 6.00PERFORADOR UND 1 40.00 40 40.00 40.00PAPEL AUTOCOPIATIVOS CON 4 COPIAS MLL 0.25 400.00 100 100.00 100.00PAPEL FORMATO A4 80GR MLL 3 22.00 66 66.00 66.00CUADERNO DE OBRA DE 100 FOLIOS AUTOCOPIATIVO 0UND 3 35.00 105 105.00 105.00PORTAMINAS UND 5 2.50 13 12.50 12.50TARJETA DE CONTROL VISIBLE MLL 0.5 100.00 50 50.00 50.00RESALTADOR DE COLORES CJA 1 15.00 15 15.00 15.00ARCHIVADORES GRANDE UND 3 4.00 12 12.00 12.00ARCHIVADORES CHICO UND 3 2.00 6 6.00 6.00PAPEL PARA PLOTER ROLLO UND 1 70.00 70 70.00 70.00ESCALIMETRO UND 2 15.00 30 30.00 30.00JUEGO DE ESCUADRAS GRANDES JGO 2 30.00 60 60.00 60.00PERFORADOR UND 1 30.00 30 30.00 30.00

Page 4: Presupuesto Dm

GASTOS INDIRECTOS

PROYECTO : RECONSTRUCCION DE LA I.E.I. Nº 427 JESUS DIVINA MISERICORDIA DEL DISTRITO DE CIUDAD NUEVA - TACNAFECHA - MAYO DE 2010LUGAR : TACNA-TACNA-TACNA

ESPECIFICA DESCRIPCION UND CANT. P.U PARCIAL MESES

SUB TOTAL TOTALMES 01 MES 02 MES 03

TACNAREGIONALGOBIERNO

Desarrollo para todos

ENGRAMPADOR TIPO ALICATE UND 1 50.00 50 50.00 50.00FOLEADOR UND 1 50.00 50 50.00 50.00CD REGRABABLES C/CAJA UND 50 0.60 30 30.00 30.00CD RECORDABLE UND 5 0.60 3 3.00 3.00POST IT X 320 HJS 3" X 3" UND 1 9.80 10 9.80 9.80FILE DE COLOR UND 50 0.40 20 20.00 20.00FASTER X 50 UND CJA 1 5.00 5 5.00 5.00CLIPS MARIPOSA X 50 UND CJA 1 3.00 3 3.00 3.00CLIPS CJA 1 2.00 2 2.00 2.00SET DE ESCRITORIO UND 1 20.00 20 20.00 20.00PLUMON PARA PIZARRA CRILICA UND 2 3.00 6 6.00 6.00

2.6.22.26 COSTO DE CONSTRUCCION POR ADM. DIRECTA - OTROS 2,850.00 0.00 0.00 2,850.00

BIENES DURADEROSCOMPUTADORA CORE 2 DUO UND 1 2,500.00 2,500 2,500.00 2,500.00ESCRITORIO UND 1 350.00 350 350.00 350.00

2.6.22.26 COSTO DE CONSTRUCCION POR ADM. DIRECTA - OTROS 2,750.00 2,750.00 2,750.00 8,250.00

ALQUILER DE BIENES ALQUILER DE CAMIONETA DIA 75 110.00 8,250 2,750.00 2,750.00 2,750.00 8,250.00

2.6.22.26 COSTO DE CONSTRUCCION POR ADM. DIRECTA - OTROS 150.00 150.00 150.00 450.00

PAGO A ELECTROSURENERGIA ELECTRICA MES 3 150.00 450 150.00 150.00 150.00 450.00

2.6.22.26 COSTO DE CONSTRUCCION POR ADM. DIRECTA - OTROS 150.00 150.00 150.00 450.00

PAGO A EMAPAAGUA MES 3 150.00 450 150.00 150.00 150.00 450.00

2.6.22.26 COSTO DE CONSTRUCCION POR ADM. DIRECTA - OTROS 75.00 75.00 75.00 225.00

TELEFONIA MOVILNEXTEL MES 3 75.00 225 75.00 75.00 75.00 225.00

Page 5: Presupuesto Dm

GASTOS INDIRECTOS

PROYECTO : RECONSTRUCCION DE LA I.E.I. Nº 427 JESUS DIVINA MISERICORDIA DEL DISTRITO DE CIUDAD NUEVA - TACNAFECHA - MAYO DE 2010LUGAR : TACNA-TACNA-TACNA

ESPECIFICA DESCRIPCION UND CANT. P.U PARCIAL MESES

SUB TOTAL TOTALMES 01 MES 02 MES 03

TACNAREGIONALGOBIERNO

Desarrollo para todos

Page 6: Presupuesto Dm

GASTOS INDIRECTOS

PROYECTO : RECONSTRUCCION DE LA I.E.I. Nº 427 JESUS DIVINA MISERICORDIA DEL DISTRITO DE CIUDAD NUEVA - TACNAFECHA - MAYO DE 2010LUGAR : TACNA-TACNA-TACNA

ESPECIFICA DESCRIPCION UND CANT. P.U PARCIAL MESES

SUB TOTAL TOTALMES 01 MES 02 MES 03

TACNAREGIONALGOBIERNO

Desarrollo para todos

GASTOS DE SUPERVISION 15,327.76

2.6.22.23 COSTO DE CONSTRUCCION POR ADM. DIRECTA - PERSONAL 3,250.00 3,250.00 3,250.00 9,750.00

0.5 ING. SUPERVISOR MES 3 4,200.00 6,300 2,100.00 2,100.00 2,100.00 6,300.000.5 ASISTENTE SUPERVISION MES 3 2,300.00 3,450 1,150.00 1,150.00 1,150.00 3,450.00

2.6.22.24 COSTO DE CONSTRUCCION POR ADM. DIRECTA - BIENES 810.00 810.00 810.00 2,430.00

COMBUSTIBLES110 GASOLINA DE 84 OCTANOS GLN 36 12.50 450 150.00 150.00 150.00 450.006 ALQUILER DE CAMIONETA DIA 18 110.00 1,980 660.00 660.00 660.00 1,980.00

2.6.22.25 COSTO DE CONSTRUCCION POR ADM. DIRECTA - SERVICIOS 1,000.00 0.00 0.00 1,000.00

VARIOSSERVICIOS DE TERCEROS UND 1 1,000.00 1,000 1,000.00 1,000.00

2.6.22.26 COSTO DE CONSTRUCCION POR ADM. DIRECTA - OTROS 765.00 0.00 0.00 765.00

IMPLEMENTOS DE SEGURIDAD15 ZAPATOS DE SEGURIDAD PAR 2 150.00 300 300.00 300.00

OTROS IMPLEMENTOS GLB 1 165.00 165 165.00 165.00CASACAS UND 2 150.00 300 300.00 300.00

2.6.22.26 COSTO DE CONSTRUCCION POR ADM. DIRECTA - OTROS 267.59 107.59 107.59 482.76

BIENES DE CONSUMOMEMORIA PORTATIL 8GB (USB) UND 2 80.00 160 160.00 160.00CAJA CHICA GLB 1 322.76 323 107.59 107.59 107.59 322.76

2.6.22.26 COSTO DE CONSTRUCCION POR ADM. DIRECTA - OTROS 200.00 200.00 200.00 600.00

MATERIALES DE ESCRITORIOMATERIALES DE ESCRITORIO GLB 1 600.00 600 200.00 200.00 200.00 600.00

2.6.22.26 COSTO DE CONSTRUCCION POR ADM. DIRECTA - OTROS 100.00 100.00 100.00 300.00

BIENES DURADEROS

Page 7: Presupuesto Dm

GASTOS INDIRECTOS

PROYECTO : RECONSTRUCCION DE LA I.E.I. Nº 427 JESUS DIVINA MISERICORDIA DEL DISTRITO DE CIUDAD NUEVA - TACNAFECHA - MAYO DE 2010LUGAR : TACNA-TACNA-TACNA

ESPECIFICA DESCRIPCION UND CANT. P.U PARCIAL MESES

SUB TOTAL TOTALMES 01 MES 02 MES 03

TACNAREGIONALGOBIERNO

Desarrollo para todos

OTROS GASTOS GLB 1 300.00 300 100.00 100.00 100.00 300.00

Page 8: Presupuesto Dm

GASTOS INDIRECTOS

PROYECTO : RECONSTRUCCION DE LA I.E.I. Nº 427 JESUS DIVINA MISERICORDIA DEL DISTRITO DE CIUDAD NUEVA - TACNAFECHA - MAYO DE 2010LUGAR : TACNA-TACNA-TACNA

ESPECIFICA DESCRIPCION UND CANT. P.U PARCIAL MESES

SUB TOTAL TOTALMES 01 MES 02 MES 03

TACNAREGIONALGOBIERNO

Desarrollo para todos

GASTOS DE LIQUIDACION 7,663.88

2.6.22.23 COSTO DE CONSTRUCCION POR ADM. DIRECTA - PERSONAL 0.00 0.00 4,200.00 4,200.00

ING. LIQUIDADOR MES 1 4,200.00 4,200 4,200.00 4,200.00

2.6.22.24 COSTO DE CONSTRUCCION POR ADM. DIRECTA - BIENES 0.00 0.00 295.00 295.00

COMBUSTIBLES110 GASOLINA DE 84 OCTANOS GLN 6 12.50 75 75.00 75.006 ALQUILER DE CAMIONETA DIAS 2 110.00 220 220.00 220.00

2.6.22.25 COSTO DE CONSTRUCCION POR ADM. DIRECTA - SERVICIOS 0.00 0.00 2,061.09 2,061.09

VARIOSSERVICIOS DE TERCEROS (LIQUIDACION) UND 1 1,800.00 1,800.00 1,800.00 1,800.00CAJA CHICA GLB 1 261.09 261.09 0.00 261.09 261.09

2.6.22.26 COSTO DE CONSTRUCCION POR ADM. DIRECTA - OTROS 0.00 0.00 160.00 160.00

BIENES DE CONSUMOMEMORIA PORTATIL 8GB (USB) UND 2 80.00 160 160.00 160.00

2.6.22.26 COSTO DE CONSTRUCCION POR ADM. DIRECTA - OTROS 0.00 0.00 500.00 500.00

MATERIALES DE ESCRITORIOMATERIALES DE ESCRITORIO GLB 1 500.00 500 500.00 500.00

2.6.22.26 COSTO DE CONSTRUCCION POR ADM. DIRECTA - OTROS 0.00 0.00 447.79 447.79

BIENES DURADEROSALQUILER DE COMPUTADORA GLB 1 447.79 448 447.79 447.79

TOTALES 74,084.18 43,282.60 24,154.00 39,481.76 74,084.18 106,918.36

Page 9: Presupuesto Dm

COSTO DIRECTO DE INFRAESTRUCTURA

PROYECTO : RECONSTRUCCION DE LA I.E.I. Nº 427 JESUS DIVINA MISERICORDIA DEL DISTRITO DE CIUDAD NUEVA - TACNA FECHA - MAYO DE 2010 LUGAR : TACNA-TACNA-TACNA

ESPECIFICA DESCRIPCION UND P.U. PROGRAMADO MESES

SUB TOTAL TOTAL METRADO COSTO MES 01 MES 02 MES 03

2.6.22.23 COSTO DE CONSTRUCCION POR ADM. DIRECTA - PERSONAL 162,133.53 REMUNERACION BRUTA DEL OBRERO EVENTUAL 54,205.95 53,963.79 53,963.79 162,133.53

TOPOGRAFO HH 11.04 21.94 242.16 242.16 - - 242.16 CAPATAZ HH 11.15 885.70 10,109.36 3,369.79 3,369.79 3,369.79 10,109.36 OPERARIO HH 11.04 5,696.70 64,310.23 21,436.74 21,436.74 21,436.74 64,310.23 OFICIAL HH 9.84 2,288.86 22,990.99 7,663.66 7,663.66 7,663.66 22,990.99 PEON HH 8.88 7,122.89 64,480.79 21,493.60 21,493.60 21,493.60 64,480.79

2.6.22.24 COSTO DE CONSTRUCCION POR ADM. DIRECTA - BIENES 316,042.02 91,086.04 161,427.37 63,528.62 316,042.02

ALAMBRE NEGRO RECOCIDO # 16 KG 4.50 549.88 2,456.30 818.77 818.77 818.77 2,456.30 ALAMBRE NEGRO RECOCIDO # 8 KG 4.50 119.31 536.96 178.99 178.99 178.99 536.96 CLAVOS PARA MADERA C/C 2" KG 4.30 53.76 231.95 77.32 77.32 77.32 231.95 CLAVOS PARA MADERA C/C 3" KG 4.30 258.63 1,117.46 372.49 372.49 372.49 1,117.46 PERNO DE 1/2"x12" CON TUERCA UND 3.20 18.30 58.32 58.32 - - 58.32 PERNOS HEXAGONALES DE 3/4" x 3 1/2" PZA 4.20 9.00 37.80 37.80 - - 37.80 FIERRO LISO DE 1/4" KG 3.50 15.87 55.55 55.55 - - 55.55 FIERRO LISO 1/2" M 3.50 109.89 384.62 384.62 - - 384.62 POLEA METALICA DE DIAMETRO 3" X 1/2" UND 12.50 2.00 25.00 25.00 - - 25.00 CLAVOS CON CABEZA PROMEDIO KG 3.60 1.31 4.90 4.90 - - 4.90 TUBO ACERO NEGRO REDONDO 2 1/2" x 2mm x 6 PZA 300.00 10.55 3,164.25 3,164.25 - - 3,164.25 ACERO FY=4,200 KG/CM2 KG 3.00 12,622.31 37,866.94 12,622.31 12,622.31 12,622.31 37,866.94 ARENA FINA M3 35.00 130.64 4,576.11 1,525.37 1,525.37 1,525.37 4,576.11 THOR GEL(CAJA DE 5 KG) KG 95.00 12.00 1,140.00 1,140.00 - - 1,140.00 ARENILLA M3 35.00 31.83 1,113.74 371.25 371.25 371.25 1,113.74 TIERRA DE CHACRA M3 25.00 29.67 743.08 247.69 247.69 247.69 743.08 PIEDRA CHANCADA DE 1/2" M3 50.00 118.78 5,939.03 1,979.68 1,979.68 1,979.68 5,939.03 PIEDRA GRANDE DE 8" M3 40.00 27.31 1,091.79 363.93 363.93 363.93 1,091.79 AFIRMADO M3 30.00 107.28 3,218.27 1,072.76 1,072.76 1,072.76 3,218.27 ARENA GRUESA M3 25.00 103.95 2,600.95 866.98 866.98 866.98 2,600.95 CONFITILLO M3 30.00 0.40 12.10 4.03 4.03 4.03 12.10 PIEDRA MEDIANA M3 25.00 7.85 196.49 65.50 65.50 65.50 196.49 PIEDRA LAJA M2 55.00 9.92 545.16 181.72 181.72 181.72 545.16 CONDUCTOR DE COBRE DESNUDO 16 MM2 M 8.70 4.00 34.80 - 34.80 - 34.80 CONECTOR UND 8.00 4.00 32.00 - 32.00 - 32.00 CONDUCTOR TW SOLIDO 2.5mm2 M 1.85 550.91 1,021.59 - 1,021.59 - 1,021.59 CONDUCTOR TW SOLIDO 4 mm2 M 2.35 246.16 578.36 - 578.36 - 578.36 CONDUCTOR CABLEADO 2.5 mm2 THW M 2.10 123.09 258.12 - 258.12 - 258.12 CONDUCTOR CABLEADO 4.0 mm2 THW M 2.50 33.48 83.85 - 83.85 - 83.85 CONDUCTOR CABLEADO 6 mm2 THW M 3.20 66.95 214.50 - 214.50 - 214.50 GANCHO GALVANIZADO 100mm UND 4.40 54.22 238.57 - 238.57 - 238.57 INODORO BABY DE LOSA DE PRIMERA PARA NIÑOS PZA 270.00 2.00 540.00 - 540.00 - 540.00 LAVATORIO DE LOSA BLANCA 1ra (incl. accesorios) UND 150.00 2.00 300.00 - 300.00 - 300.00 INODORO DE LOZA BLANCO TQUE. BAJO inc. accesorios UND 180.00 2.00 360.00 - 360.00 - 360.00 LLAVE DUCHA CROMADA UND 45.00 1.00 45.00 - 45.00 - 45.00 PRUEBA HIDRAULICA PARA RED DE DESAGUE GLB 750.00 1.00 750.00 - - 750.00 750.00 REGISTRO DE BRONCE DE 4" UND 15.00 5.00 75.00 - 75.00 - 75.00 SUMIDERO CROMADO DE 2" UND 6.00 8.00 48.00 - 48.00 - 48.00 GRIFO DE BRONCE 1/2" UND 15.00 11.00 165.00 - 165.00 - 165.00 PRUEBA HIDRAULICA GENERAL GLB 750.00 1.00 750.00 250.00 250.00 250.00 750.00 FAROLA CONICAS TRANSPARENTES UND 100.00 13.00 1,300.00 - 1,300.00 - 1,300.00 TABLERO DE DISTRIBUCION METALICO P/4 LLAVES PZA 350.00 2.00 700.00 - 700.00 - 700.00 INTERRUPTOR TERMOMAGNETIC DE 3x175Ax380V UND 630.00 1.00 630.00 - 630.00 - 630.00 INTERRUPTOR TERMOMAGNETICO 2x20 A. UND 40.00 1.00 40.00 - 40.00 - 40.00 INTERRUPTOR TERMOMAGNETICO 2x30 A. UND 45.00 1.00 45.00 - 45.00 - 45.00 INTERRUPTOR TERMOMAGNETICO 3x40 A. UND 150.00 1.00 150.00 - 150.00 - 150.00 CAJA DE PASE GALVANIZADA DE 4" X 4"X 2" PZA 8.50 8.00 68.00 - 68.00 - 68.00 CAJA OCTOGONAL GALV. 4" X 2 1/8 " UND 2.00 35.00 70.00 35.00 35.00 - 70.00 CAJA RECTANGULAR GALV. LIV. 2"x4" UND 2.00 38.00 76.00 38.00 38.00 - 76.00 ROSETA RJ45 PZA 3.00 2.00 6.00 3.00 3.00 - 6.00 PLACA DE SALIDA DE TELEVISION Y TELEFONO UND 6.00 2.00 12.00 6.00 6.00 - 12.00 INTERRUPTOR SIMPLE UND 10.00 8.00 80.00 40.00 40.00 - 80.00 TOMACORRIENTE DOBLE C/PTA A TIERRA UND 12.00 23.00 276.00 - 276.00 - 276.00 INTERRUPTOR DOBLE UND 12.00 5.00 60.00 - 60.00 - 60.00 ARTEFACTO FLUORESCENTE RECTO TPR 3 X 36 W UND 150.00 8.00 1,200.00 - 1,200.00 - 1,200.00 ARTEFACTO FLUORESCENTE TIPO BE 1X36W UND 105.00 1.00 105.00 - 105.00 - 105.00 ARTEFACTO FLUORESCENTE RECTO TPR 2 x 36 W UND 120.00 11.00 1,320.00 - 1,320.00 - 1,320.00 ARTEFACTO FLUORESCENTE CIRCULAR TPC 1 X 32 W UND 85.00 9.00 765.00 - 765.00 - 765.00 BRAQUETE 32 W UND 75.00 1.00 75.00 - 75.00 - 75.00 ASFALTO RC-250 GLN 8.00 35.61 284.94 142.47 142.47 - 284.94 LADRILLO K.K. DE ARCILLA 14X24X10 CM. UND 1.05 12,248.18 12,860.61 4,286.87 4,286.87 4,286.87 12,860.61 LADRILLO PASTELERO 20X20X3 CM UND 1.22 6,409.00 7,818.98 2,606.33 2,606.33 2,606.33 7,818.98 LADRILLO DE TECHO 30x30x15 cm UND 2.03 1,790.25 3,631.65 1,210.55 1,210.55 1,210.55 3,631.65 CONDUCTOR 2x1x10 MM2 NYY M 15.70 46.35 727.65 - 363.83 363.83 727.65 CONDUCTOR 2x1x6 MM2 NYY M 8.80 90.64 797.28 - 398.64 398.64 797.28 CEMENTO PORTLAND TIPO I (42.5KG) BOL 23.00 1,883.43 43,320.63 14,440.21 14,440.21 14,440.21 43,320.63 PLANCHA DE FIBROCEMENTO 1.83 x 1.10 m x 5 mm PLN 35.90 30.63 1,099.58 - 1,099.58 - 1,099.58

TACNAREGIONALGOBIERNO

Desarrollo para todos

Page 10: Presupuesto Dm

COSTO DIRECTO DE INFRAESTRUCTURA

PROYECTO : RECONSTRUCCION DE LA I.E.I. Nº 427 JESUS DIVINA MISERICORDIA DEL DISTRITO DE CIUDAD NUEVA - TACNA FECHA - MAYO DE 2010 LUGAR : TACNA-TACNA-TACNA

ESPECIFICA DESCRIPCION UND P.U. PROGRAMADO MESES

SUB TOTAL TOTAL METRADO COSTO MES 01 MES 02 MES 03

TACNAREGIONALGOBIERNO

Desarrollo para todos

TAPA DE CONCRETO 12'' X 24'' UND 38.00 4.00 152.00 - 152.00 - 152.00 CAJA PREFABRICADA DE CONCRETO C/TAPA UND 35.00 4.00 140.00 - 140.00 - 140.00 CAJA CONCRETO SIMPLE PARA VALVULAS UND 35.00 2.00 70.00 - 70.00 - 70.00 CERAMICO DE 20 x 30 cm. M2 32.00 136.77 4,376.41 - 4,376.41 - 4,376.41 CERAMICO DE 30 x 30 cm. M2 32.00 233.35 7,467.02 - 7,467.02 - 7,467.02 CERAMICO BLANCO DE 20 x 30 cm M2 32.00 58.88 1,883.95 - 1,883.95 - 1,883.95 CERRADURA DE TRES GOLPES UND 65.00 10.00 650.00 - 650.00 - 650.00 CERRADURA "SAPITO" DE BRONCE UND 5.50 55.00 302.50 - 302.50 - 302.50 BISAGRA ALUMINIZADA 2 1/2"x2 1/2" UND 3.50 110.00 385.00 - 385.00 - 385.00 BISAGRA ALUMINIZADA 4"x4" UND 5.00 68.00 340.00 - 340.00 - 340.00 CERRADURA DE PERILLA UND 30.00 2.00 60.00 - 60.00 - 60.00 TAPIZ DE GOMA M2 12.50 44.30 553.95 - 553.95 - 553.95 CAL ( BOLSA X 20 KG) BOL 38.00 16.98 645.06 - 645.06 - 645.06 CINTA AISLANTE RLL 3.00 5.00 15.00 - 15.00 - 15.00 CINTA AISLANTE UND 3.00 28.77 86.22 - 86.22 - 86.22 CINTA TEFLON RLL 1.50 43.19 65.61 - 65.61 - 65.61 CESPED M2 6.50 441.34 2,870.88 - 2,870.88 - 2,870.88 SOLDADURA CELLOCORD KG 14.50 874.61 12,681.85 - 12,681.85 - 12,681.85 ACCESORIOS DIVERSOS GLB 160.00 54.22 8,675.20 - 8,675.20 - 8,675.20 ESPUMA PLASTICA DURA A/DENSIDAD 2X1M e=2" UND 90.00 3.10 279.44 - 279.44 - 279.44 JEBE MICROPOROSO M 180.00 1.21 217.40 - 217.40 - 217.40 CINTA BANDIT 1/2" PZA 3.00 0.50 1.50 - 1.50 - 1.50 PRESILLO PARA CINTA BANDIT CJA 1.50 8.00 12.00 - 12.00 - 12.00 TEROKAL GLN 45.00 0.29 13.08 - 13.08 - 13.08 YESO EN BOLSA DE 20 Kg BLS 11.60 33.90 393.50 - 393.50 - 393.50 PORCELANA KG 5.00 90.53 452.17 - 452.17 - 452.17 ADITIVO PLASTIFICANTE Y REDUCTOR DE AGUA GLN 75.00 14.80 1,110.70 - 1,110.70 - 1,110.70 SOLVENTE SC-55 PARA LACA PROTECTORA GLN 78.00 23.24 1,812.11 - 1,812.11 - 1,812.11 PINTURA BARNIZ GLN 45.00 4.05 182.26 - 182.26 - 182.26 RODOPLAST PARA BORDE DE MAYOLICAS M 3.00 32.01 96.00 - 96.00 - 96.00 LAVADERO A.INOX.19"x37"C/ESC. P. SAT.C/A UND 185.00 2.00 370.00 - 370.00 - 370.00 PEGAMENTO PARA CERAMICO ( Bolsa 25 Kg.) BOL 23.00 77.05 1,772.41 - 1,772.41 - 1,772.41 PEGAMENTO PARA PVC GLN 85.00 5.57 475.49 - 475.49 - 475.49 TEROKAL GLN 65.00 1.23 80.15 - 80.15 - 80.15 SOLDADURA CELLOCORD P 3/16" KG 16.00 49.95 798.95 - 798.95 - 798.95 PLASTICA ESPESOR 0.1 mm M2 1.80 42.58 76.64 - 76.64 - 76.64 GABINETE METALICO UND 60.00 1.00 60.00 - 60.00 - 60.00 GRIFO DE RIEGO 3/4" UND 25.00 2.00 50.00 - 50.00 - 50.00 MEDIDOR TRIFASICO DE ENERGIA ELECTRICA UND 330.00 1.00 330.00 - 330.00 - 330.00 LIJA UND 1.50 1.50 2.25 - 2.25 - 2.25 TRANSPORTE DE EQUIPO GLB 800.00 1.00 800.00 266.67 266.67 266.67 800.00 TRANSPORTE DE MATERIALES GLB 4,200.00 1.00 4,200.00 1,400.00 1,400.00 1,400.00 4,200.00 GASOLINA 84 OCTANOS GLN 9.50 37.39 356.56 - 356.56 - 356.56 HORMIGON M3 33.00 64.95 2,142.33 714.11 714.11 714.11 2,142.33 LIJA PARA FIERRO PLG 1.80 87.27 156.72 - 156.72 - 156.72 HOJA DE SIERRA PZA 5.50 168.76 928.18 - 928.18 - 928.18 LIJA PARA CONCRETO HJA 1.80 144.54 258.35 - 258.35 - 258.35 COLA SINTETICA GLN 26.20 3.97 103.86 - 103.86 - 103.86 LIJA PARA MADERA UND 1.50 46.88 70.38 - 70.38 - 70.38 AGUA M3 5.00 118.76 600.26 - 600.26 - 600.26 ESTERA DE 2.00 X 3.00 M. UND 28.00 17.25 483.04 - 483.04 - 483.04 PRUEBAS ELECTRICAS UND 750.00 1.00 750.00 - 750.00 - 750.00 ESTIMADO EST 35.00 6.00 210.00 - 210.00 - 210.00 REPOSTERO DE MADERA UND 2,000.00 1.00 2,000.00 - 2,000.00 - 2,000.00 MOSTRADOR DE MADERA SEGUN MEDIDA UND 1,500.00 1.00 1,500.00 - 1,500.00 - 1,500.00 ROPERO DE MADERA SEGUN MEDIDA GLB 3,200.00 1.00 3,200.00 - 3,200.00 - 3,200.00 MADERA TORNILLO P2 5.50 4,966.24 27,315.63 9,105.21 9,105.21 9,105.21 27,315.63 MADERA CEDRO P2 9.50 1,169.40 11,108.49 3,702.83 3,702.83 3,702.83 11,108.49 REGLA DE MADERA P2 10.50 12.45 129.51 43.17 43.17 43.17 129.51 PALOS DE EUCALIPTO 2.5 M PZA 8.50 17.25 146.88 - 146.88 - 146.88 PERGOLA DE MADERA SEGUN DISEÑO UND 1,850.00 1.00 1,850.00 - 1,850.00 - 1,850.00 TRIPLAY DE 4'x8'x 19 mm PLN 135.00 4.25 573.99 191.33 191.33 191.33 573.99 TRIPLAY DE 4'x8'x 4 mm PLN 32.00 73.81 2,361.95 787.32 787.32 787.32 2,361.95 MALLA RASCHELL M2 3.50 440.60 1,544.25 - - 1,544.25 1,544.25 MALLA ELECTROSOLDADA DE 2" X 2" No.12 M2 15.00 177.20 2,657.97 1,328.99 1,328.99 - 2,657.97 ANGULO 1"x1"x3/16" x 6m PZA 40.00 78.25 3,130.28 1,565.14 1,565.14 - 3,130.28 ANGULO ACERO 1 1/2" x 1 1/2" x 1/8" x 6m PZA 72.00 59.07 4,252.75 2,126.38 2,126.38 - 4,252.75 PUERTA METALICA EN INGRESO, INC PINTADO Y COLOCADO M2 3,200.00 2.00 6,400.00 3,200.00 3,200.00 - 6,400.00 AGUARRAZ GLN 16.50 0.37 6.32 3.16 3.16 - 6.32 PINTURA LATEX GLN 35.00 48.63 1,703.18 851.59 851.59 - 1,703.18 PINTURA ESMALTE SINTETICO GLN 45.00 0.86 38.88 19.44 19.44 - 38.88 PINTURA ANTICORROSIVA GLN 45.00 6.67 300.73 150.37 150.37 - 300.73 PINTURA ESMALTE GLN 45.00 9.15 411.43 205.72 205.72 - 411.43 LACA PROTECTORA ENCOFRADO P/CONCRETO CARAVISTA GLN 148.00 25.24 3,737.32 1,868.66 1,868.66 - 3,737.32 SELLADOR BLANCO PARA MUROS GLN 28.00 0.60 17.09 8.55 8.55 - 17.09 PINTURA IMPRIMANTE GLN 30.00 142.66 4,282.51 2,141.26 2,141.26 - 4,282.51 ARANDELA PLASTICA UND 0.95 135.55 129.04 64.52 64.52 - 129.04 CALAMINA PLN 25.00 23.52 588.00 294.00 294.00 - 588.00 TUBO GALVANIZADO DE 2" x 6 m. UND 160.00 20.33 3,252.80 1,626.40 1,626.40 - 3,252.80

Page 11: Presupuesto Dm

COSTO DIRECTO DE INFRAESTRUCTURA

PROYECTO : RECONSTRUCCION DE LA I.E.I. Nº 427 JESUS DIVINA MISERICORDIA DEL DISTRITO DE CIUDAD NUEVA - TACNA FECHA - MAYO DE 2010 LUGAR : TACNA-TACNA-TACNA

ESPECIFICA DESCRIPCION UND P.U. PROGRAMADO MESES

SUB TOTAL TOTAL METRADO COSTO MES 01 MES 02 MES 03

TACNAREGIONALGOBIERNO

Desarrollo para todos

TUBO GALVANIZADO DE 3" x 6 m. UND 235.00 0.33 77.55 38.78 38.78 - 77.55 TUBO GALVANIZADO DE 4" x 6 m. UND 315.00 0.33 103.95 51.98 51.98 - 103.95 TUBERIA F°G° 1/2" M 9.60 1.28 12.31 6.16 6.16 - 12.31 POSTES ORNAMENTALES UND 300.00 13.00 3,900.00 1,950.00 1,950.00 - 3,900.00 PLANCHA ACERO LAF 1.20 x 1200 x 2400 mm. (1/8") PZA 825.00 0.08 69.19 34.60 34.60 - 69.19 ESTRUCTURA DE FIBRA DE VIDRIO UND 1,500.00 6.00 9,000.00 4,500.00 4,500.00 - 9,000.00 VARILLA DE COBRE d=1/2" DE 2.5m UND 210.00 4.00 840.00 420.00 420.00 - 840.00 TUBERIA PVC SAP CLASE 10 3/4'' M 4.60 6.40 29.44 14.72 14.72 - 29.44 REDUCCION R PVC SAP P/AGUA 3/4" A 1/2" UND 2.50 3.00 7.50 3.75 3.75 - 7.50 UNION UNIVERSAL PVC SAP DE 1/2" UND 3.50 8.00 28.00 14.00 14.00 - 28.00 CODO DE 90°C/R PVC SAP P/AGUA DE 1/2" UND 1.30 66.00 85.80 42.90 42.90 - 85.80 TEE PVC SAP DE 1/2" C/R PARA AGUA UND 1.60 60.00 96.00 48.00 48.00 - 96.00 TEE PVC SAP P/AGUA DE 3/4" UND 2.20 4.00 8.80 4.40 4.40 - 8.80 CODO DE 90 PVC SAL DE 2" UND 4.50 21.00 94.50 47.25 47.25 - 94.50 CODO DE 90 PVC SAL DE 4" UND 6.00 5.00 30.00 15.00 15.00 - 30.00 TEE SANITARIA SIMPLE PVC SAL DE 4" UND 8.00 5.00 40.00 20.00 20.00 - 40.00 UNION UNIVERSAL PVC SAP 3/4" PZA 8.00 4.00 32.00 16.00 16.00 - 32.00 TRAMPA "P" PVC SAL DE 2" UND 11.50 11.00 126.50 63.25 63.25 - 126.50 CODO DE 90° PVC SAP P/AGUA DE 3/4" UND 2.10 14.00 29.40 14.70 14.70 - 29.40 CODO PVC SAP 3/4" X 90° PZA 2.10 6.92 14.54 7.27 7.27 - 14.54 CODO PVC AGUA,ROSCADO, DE 90 X 1/2 UND 1.50 4.00 6.00 3.00 3.00 - 6.00 CODO PVC SAP 1/2" X 90° UND 1.20 38.06 45.65 22.83 22.83 - 45.65 TUBO PVC SAL 2" X 3M PZA 9.00 20.48 184.22 92.11 92.11 - 184.22 TUBO PVC SAL 4" X 3M PZA 20.00 28.85 577.01 288.51 288.51 - 577.01 TEE PVC SAL 2" X 2" PZA 5.00 2.00 10.00 5.00 5.00 - 10.00 TEE PVC SAL 4" X 4" PZA 8.50 7.00 59.50 29.75 29.75 - 59.50 YEE PVC SAL DE 4" X 2" PZA 7.00 7.00 49.00 24.50 24.50 - 49.00 TUBO PVC SAP (ELECTRICA) D=20 mm x 3 m UND 9.40 110.47 1,038.36 519.18 519.18 - 1,038.36 TUBO PVC SAP (ELECTRICA) D=35 mm x 3 m UND 21.50 52.85 1,137.03 568.52 568.52 - 1,137.03 TUBO PVC SAP (ELECTRICA) SAP 50 mm PZA 30.50 1.10 33.55 16.78 16.78 - 33.55 TUBERIA PVC-CLASE 10 SP 3/4" x 5m. M 4.60 245.87 1,130.70 565.35 565.35 - 1,130.70 TUBERIA PVC-CLASE 10 SP 1/2" x 5m. M 2.80 96.53 270.25 135.13 135.13 - 270.25 TUBO PVC SAP (ELECTRICA) D=25 mm x 3 m UND 9.50 1.40 13.32 6.66 6.66 - 13.32 CURVA PVC SEL 3/4" PZA 0.80 64.40 51.52 25.76 25.76 - 51.52 UNION SIMPLE PVC-SEL 3/4" UND 0.50 46.00 23.00 11.50 11.50 - 23.00 UNION SIMPLE PVC-SAP CLASE 10 SP-1/2" UND 0.80 18.47 14.58 7.29 7.29 - 14.58 UNION SIMPLE PVC-SAP CLASE 10 SP-3/4" UND 1.00 22.99 22.99 11.50 11.50 - 22.99 CONEXION A TUBERIA EXTERNA EXISTENTE GLB 550.00 1.00 550.00 275.00 275.00 - 550.00 VALVULA COMPUERTA DE BRONCE DE 1/2" UND 30.00 4.00 120.00 60.00 60.00 - 120.00 VALVULA COMPUERTA DE BRONCE DE 3/4" UND 38.00 2.00 76.00 38.00 38.00 - 76.00 REGISTRO DE BRONCE DE 2" PZA 6.00 2.00 12.00 6.00 6.00 - 12.00 VIDRIO SEMIDOBLE P2 4.20 513.24 2,155.60 718.53 718.53 718.53 2,155.60

2.6.22.26 COSTO DE CONSTRUCCION POR ADM. DIRECTA - SERVICIOS 32,750.32 15,068.13 9,795.50 7,886.70 32,750.32

MIRA TOPOGRAFICA HE 2.15 47.17 45.40 45.40 - - 45.40 CIZALLA P/FIERRO CONST. HASTA 1" UND 4.00 199.76 226.91 75.64 75.64 75.64 226.91 WINCHA DE 30 MTS. PZA 50.00 38.50 45.40 45.40 - - 45.40 JALON HE 2.15 94.71 90.81 90.81 - - 90.81 WINCHE ELECTRICO HM 10.00 95.50 95.46 31.82 31.82 31.82 95.46 VOLQUETE DE 10 M3 HM 125.00 7,203.75 7,206.04 2,402.01 2,402.01 2,402.01 7,206.04 CAMION CISTERNA 4X2 (AGUA) 2,000 GAL. HM 68.00 35.36 35.16 11.72 11.72 11.72 35.16 ESMERIL ELECTRICO R. HM 4.50 216.95 217.70 72.57 72.57 72.57 217.70 ANDAMIO METALICO HM 4.40 1,234.20 1,234.20 411.40 411.40 411.40 1,234.20 COMPRESORA NEUMATICA 150 HP 380-590 PCM HM 90.00 3,507.30 3,507.24 3,507.24 - - 3,507.24 COMPACTADOR VIBR. TIPO PLANCHA 4 HP HM 20.00 2,869.00 2,868.74 956.25 956.25 956.25 2,868.74 CARGADOR S/LLANTAS 100-125 HP 2.25 YD3 HM 155.00 2,097.15 2,095.75 1,047.88 1,047.88 - 2,095.75 MARTILLO NEUMATICO DE 25 Kg. HM 18.00 1,250.82 1,250.81 1,250.81 - - 1,250.81 VIBRADOR DE CONCRETO 4 HP 2.40" HM 15.00 978.45 978.45 326.15 326.15 326.15 978.45 MOTOSOLDADORA DE 250 AMP. HM 18.00 1,721.88 1,721.85 860.93 860.93 - 1,721.85 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 HM 25.00 4,525.50 4,526.40 1,508.80 1,508.80 1,508.80 4,526.40 TEODOLITO HM 15.00 329.10 332.97 332.97 - - 332.97 HERRAMIENTAS MANUALES %MO - - 6,271.03 2,090.34 2,090.34 2,090.34 6,271.03

COSTO DIRECTO 510,925.38 160,359.95 225,186.49 125,378.94 510,925.38 510,925.38

Page 12: Presupuesto Dm

RECURSOS MANO DE OBRA

PROYECTO : RECONSTRUCCION DE LA I.E.I. Nº 427 JESUS DIVINA MISERICORDIA DEL DISTRITO DE CIUDAD NUEVA - TACNA

FECHA - MAYO DE 2010

LUGAR : TACNA-TACNA-TACNA

ITEM CATEGORIA UND

PROGRAMADO PROGRAMADO POR MES

P.U. METRADO COSTO MES 01 MES 02 MES 03

METRADO COSTO METRADO COSTO METRADO COSTO

1.00 TOPOGRAFO HH 11.04 21.94 242.16 21.94 242.16 2.00 CAPATAZ HH 11.15 885.70 10,109.36 295.23 3,369.79 295.23 3,369.79 295.23 3,369.79 3.00 OPERARIO HH 11.04 5,696.70 64,310.23 1,898.90 21,436.74 1,898.90 21,436.74 1,898.90 21,436.74 4.00 OFICIAL HH 9.84 2,288.86 22,990.99 762.95 7,663.66 762.95 7,663.66 762.95 7,663.66 5.00 PEON HH 8.88 7,122.89 64,480.79 2,374.30 21,493.60 2,374.30 21,493.60 2,374.30 21,493.60

(*)Costo Directo 162,133.53 54,205.95 53,963.79 53,963.79

TACNAREGIONALGOBIERNO

Desarrollo para todos

Page 13: Presupuesto Dm

RECURSOS MATERIALES

PROYECTO : RECONSTRUCCION DE LA I.E.I. Nº 427 JESUS DIVINA MISERICORDIA DEL DISTRITO DE CIUDAD NUEVA - TACNA FECHA - MAYO DE 2010 LUGAR : TACNA-TACNA-TACNA

ITEM DETALLE UND P.U. PROGRAMADO PROGRAMADO POR MES

MES 01 MES 02 MES 03 METRADO COSTO METRADO COSTO METRADO COSTO METRADO COSTO

2.6.22.24 COSTO DE CONSTRUCCION POR ADM. DIRECTA - BIENES 316,042.02

1.00 ALAMBRE NEGRO RECOCIDO # 16 KG 4.50 549.88 2,456.30 183.29 818.77 183.29 818.77 183.29 818.77 2.00 ALAMBRE NEGRO RECOCIDO # 8 KG 4.50 119.31 536.96 39.77 178.99 39.77 178.99 39.77 178.99 3.00 CLAVOS PARA MADERA C/C 2" KG 4.30 53.76 231.95 17.92 77.32 17.92 77.32 17.92 77.32 4.00 CLAVOS PARA MADERA C/C 3" KG 4.30 258.63 1,117.46 86.21 372.49 86.21 372.49 86.21 372.49 5.00 PERNO DE 1/2"x12" CON TUERCA UND 3.20 18.30 58.32 18.30 58.32 6.00 PERNOS HEXAGONALES DE 3/4" x 3 1/2" PZA 4.20 9.00 37.80 9.00 37.80 7.00 FIERRO LISO DE 1/4" KG 3.50 15.87 55.55 15.87 55.55 8.00 FIERRO LISO 1/2" M 3.50 109.89 384.62 109.89 384.62 9.00 POLEA METALICA DE DIAMETRO 3" X 1/2" UND 12.50 2.00 25.00 2.00 25.00 10.00 CLAVOS CON CABEZA PROMEDIO KG 3.60 1.31 4.90 1.31 4.90 11.00 TUBO ACERO NEGRO REDONDO 2 1/2" x 2mm x 6 PZA 300.00 10.55 3,164.25 10.55 3,164.25 12.00 ACERO FY=4,200 KG/CM2 KG 3.00 12,622.31 37,866.94 4,207.44 12,622.31 4,207.44 12,622.31 4,207.44 12,622.31 13.00 ARENA FINA M3 35.00 130.64 4,576.11 43.55 1,525.37 43.55 1,525.37 43.55 1,525.37 14.00 THOR GEL(CAJA DE 5 KG) KG 95.00 12.00 1,140.00 12.00 1,140.00 15.00 ARENILLA M3 35.00 31.83 1,113.74 10.61 371.25 10.61 371.25 10.61 371.25 16.00 TIERRA DE CHACRA M3 25.00 29.67 743.08 9.89 247.69 9.89 247.69 9.89 247.69 17.00 PIEDRA CHANCADA DE 1/2" M3 50.00 118.78 5,939.03 39.59 1,979.68 39.59 1,979.68 39.59 1,979.68 18.00 PIEDRA GRANDE DE 8" M3 40.00 27.31 1,091.79 9.10 363.93 9.10 363.93 9.10 363.93 19.00 AFIRMADO M3 30.00 107.28 3,218.27 35.76 1,072.76 35.76 1,072.76 35.76 1,072.76 20.00 ARENA GRUESA M3 25.00 103.95 2,600.95 34.65 866.98 34.65 866.98 34.65 866.98 21.00 CONFITILLO M3 30.00 0.40 12.10 0.13 4.03 0.13 4.03 0.13 4.03 22.00 PIEDRA MEDIANA M3 25.00 7.85 196.49 2.62 65.50 2.62 65.50 2.62 65.50 23.00 PIEDRA LAJA M2 55.00 9.92 545.16 3.31 181.72 3.31 181.72 3.31 181.72 24.00 CONDUCTOR DE COBRE DESNUDO 16 MM2 M 8.70 4.00 34.80 4.00 34.80 - - 25.00 CONECTOR UND 8.00 4.00 32.00 4.00 32.00 - - 26.00 CONDUCTOR TW SOLIDO 2.5mm2 M 1.85 550.91 1,021.59 550.91 1,021.59 - - 27.00 CONDUCTOR TW SOLIDO 4 mm2 M 2.35 246.16 578.36 246.16 578.36 - - 28.00 CONDUCTOR CABLEADO 2.5 mm2 THW M 2.10 123.09 258.12 123.09 258.12 - - 29.00 CONDUCTOR CABLEADO 4.0 mm2 THW M 2.50 33.48 83.85 33.48 83.85 - - 30.00 CONDUCTOR CABLEADO 6 mm2 THW M 3.20 66.95 214.50 66.95 214.50 - - 31.00 GANCHO GALVANIZADO 100mm UND 4.40 54.22 238.57 54.22 238.57 - - 32.00 INODORO BABY DE LOSA DE PRIMERA PARA NIÑOS PZA 270.00 2.00 540.00 2.00 540.00 - - 33.00 LAVATORIO DE LOSA BLANCA 1ra (incl. accesorios) UND 150.00 2.00 300.00 2.00 300.00 - - 34.00 INODORO DE LOZA BLANCO TQUE. BAJO inc. accesorios UND 180.00 2.00 360.00 2.00 360.00 - - 35.00 LLAVE DUCHA CROMADA UND 45.00 1.00 45.00 1.00 45.00 - - 36.00 PRUEBA HIDRAULICA PARA RED DE DESAGUE GLB 750.00 1.00 750.00 1.00 750.00 37.00 REGISTRO DE BRONCE DE 4" UND 15.00 5.00 75.00 5.00 75.00 - - 38.00 SUMIDERO CROMADO DE 2" UND 6.00 8.00 48.00 8.00 48.00 - - 39.00 GRIFO DE BRONCE 1/2" UND 15.00 11.00 165.00 11.00 165.00 - - 40.00 PRUEBA HIDRAULICA GENERAL GLB 750.00 1.00 750.00 0.33 250.00 0.33 250.00 0.33 250.00 41.00 FAROLA CONICAS TRANSPARENTES UND 100.00 13.00 1,300.00 13.00 1,300.00 - - 42.00 TABLERO DE DISTRIBUCION METALICO P/4 LLAVES PZA 350.00 2.00 700.00 2.00 700.00 - - 43.00 INTERRUPTOR TERMOMAGNETIC DE 3x175Ax380V UND 630.00 1.00 630.00 1.00 630.00 - - 44.00 INTERRUPTOR TERMOMAGNETICO 2x20 A. UND 40.00 1.00 40.00 1.00 40.00 - - 45.00 INTERRUPTOR TERMOMAGNETICO 2x30 A. UND 45.00 1.00 45.00 1.00 45.00 - - 46.00 INTERRUPTOR TERMOMAGNETICO 3x40 A. UND 150.00 1.00 150.00 1.00 150.00 - - 47.00 CAJA DE PASE GALVANIZADA DE 4" X 4"X 2" PZA 8.50 8.00 68.00 8.00 68.00 - - 48.00 CAJA OCTOGONAL GALV. 4" X 2 1/8 " UND 2.00 35.00 70.00 17.50 35.00 17.50 35.00 49.00 CAJA RECTANGULAR GALV. LIV. 2"x4" UND 2.00 38.00 76.00 19.00 38.00 19.00 38.00 50.00 ROSETA RJ45 PZA 3.00 2.00 6.00 1.00 3.00 1.00 3.00 51.00 PLACA DE SALIDA DE TELEVISION Y TELEFONO UND 6.00 2.00 12.00 1.00 6.00 1.00 6.00 52.00 INTERRUPTOR SIMPLE UND 10.00 8.00 80.00 4.00 40.00 4.00 40.00 53.00 TOMACORRIENTE DOBLE C/PTA A TIERRA UND 12.00 23.00 276.00 23.00 276.00 - - 54.00 INTERRUPTOR DOBLE UND 12.00 5.00 60.00 5.00 60.00 - - 55.00 ARTEFACTO FLUORESCENTE RECTO TPR 3 X 36 W UND 150.00 8.00 1,200.00 8.00 1,200.00 - - 56.00 ARTEFACTO FLUORESCENTE TIPO BE 1X36W UND 105.00 1.00 105.00 1.00 105.00 - - 57.00 ARTEFACTO FLUORESCENTE RECTO TPR 2 x 36 W UND 120.00 11.00 1,320.00 11.00 1,320.00 - - 58.00 ARTEFACTO FLUORESCENTE CIRCULAR TPC 1 X 32 W UND 85.00 9.00 765.00 9.00 765.00 - - 59.00 BRAQUETE 32 W UND 75.00 1.00 75.00 1.00 75.00 - - 60.00 ASFALTO RC-250 GLN 8.00 35.61 284.94 17.81 142.47 17.81 142.47 61.00 LADRILLO K.K. DE ARCILLA 14X24X10 CM. UND 1.05 12,248.18 12,860.61 4,082.73 4,286.87 4,082.73 4,286.87 4,082.73 4,286.87 62.00 LADRILLO PASTELERO 20X20X3 CM UND 1.22 6,409.00 7,818.98 2,136.33 2,606.33 2,136.33 2,606.33 2,136.33 2,606.33 63.00 LADRILLO DE TECHO 30x30x15 cm UND 2.03 1,790.25 3,631.65 596.75 1,210.55 596.75 1,210.55 596.75 1,210.55 64.00 CONDUCTOR 2x1x10 MM2 NYY M 15.70 46.35 727.65 23.18 363.83 23.18 363.83 65.00 CONDUCTOR 2x1x6 MM2 NYY M 8.80 90.64 797.28 45.32 398.64 45.32 398.64 66.00 CEMENTO PORTLAND TIPO I (42.5KG) BOL 23.00 1,883.43 43,320.63 627.81 14,440.21 627.81 14,440.21 627.81 14,440.21 67.00 PLANCHA DE FIBROCEMENTO 1.83 x 1.10 m x 5 mm PLN 35.90 30.63 1,099.58 30.63 1,099.58 - - 68.00 TAPA DE CONCRETO 12'' X 24'' UND 38.00 4.00 152.00 4.00 152.00 - - 69.00 CAJA PREFABRICADA DE CONCRETO C/TAPA UND 35.00 4.00 140.00 4.00 140.00 - - 70.00 CAJA CONCRETO SIMPLE PARA VALVULAS UND 35.00 2.00 70.00 2.00 70.00 - - 71.00 CERAMICO DE 20 x 30 cm. M2 32.00 136.77 4,376.41 136.77 4,376.41 - - 72.00 CERAMICO DE 30 x 30 cm. M2 32.00 233.35 7,467.02 233.35 7,467.02 - - 73.00 CERAMICO BLANCO DE 20 x 30 cm M2 32.00 58.88 1,883.95 58.88 1,883.95 - - 74.00 CERRADURA DE TRES GOLPES UND 65.00 10.00 650.00 10.00 650.00 - - 75.00 CERRADURA "SAPITO" DE BRONCE UND 5.50 55.00 302.50 55.00 302.50 - - 76.00 BISAGRA ALUMINIZADA 2 1/2"x2 1/2" UND 3.50 110.00 385.00 110.00 385.00 - - 77.00 BISAGRA ALUMINIZADA 4"x4" UND 5.00 68.00 340.00 68.00 340.00 - - 78.00 CERRADURA DE PERILLA UND 30.00 2.00 60.00 2.00 60.00 - - 79.00 TAPIZ DE GOMA M2 12.50 44.30 553.95 44.30 553.95 - - 80.00 CAL ( BOLSA X 20 KG) BOL 38.00 16.98 645.06 16.98 645.06 - - 81.00 CINTA AISLANTE RLL 3.00 5.00 15.00 5.00 15.00 - - 82.00 CINTA AISLANTE UND 3.00 28.77 86.22 28.77 86.22 - - 83.00 CINTA TEFLON RLL 1.50 43.19 65.61 43.19 65.61 - - 84.00 CESPED M2 6.50 441.34 2,870.88 441.34 2,870.88 - - 85.00 SOLDADURA CELLOCORD KG 14.50 874.61 12,681.85 874.61 12,681.85 - - 86.00 ACCESORIOS DIVERSOS GLB 160.00 54.22 8,675.20 54.22 8,675.20 - - 87.00 ESPUMA PLASTICA DURA A/DENSIDAD 2X1M e=2" UND 90.00 3.10 279.44 3.10 279.44 - - 88.00 JEBE MICROPOROSO M 180.00 1.21 217.40 1.21 217.40 - - 89.00 CINTA BANDIT 1/2" PZA 3.00 0.50 1.50 0.50 1.50 - - 90.00 PRESILLO PARA CINTA BANDIT CJA 1.50 8.00 12.00 8.00 12.00 - - 91.00 TEROKAL GLN 45.00 0.29 13.08 0.29 13.08 - - 92.00 YESO EN BOLSA DE 20 Kg BLS 11.60 33.90 393.50 33.90 393.50 - - 93.00 PORCELANA KG 5.00 90.53 452.17 90.53 452.17 - -

TACNAREGIONALGOBIERNO

Desarrollo para todos

Page 14: Presupuesto Dm

RECURSOS MATERIALES

PROYECTO : RECONSTRUCCION DE LA I.E.I. Nº 427 JESUS DIVINA MISERICORDIA DEL DISTRITO DE CIUDAD NUEVA - TACNA FECHA - MAYO DE 2010 LUGAR : TACNA-TACNA-TACNA

ITEM DETALLE UND P.U. PROGRAMADO PROGRAMADO POR MES

MES 01 MES 02 MES 03 METRADO COSTO METRADO COSTO METRADO COSTO METRADO COSTO

TACNAREGIONALGOBIERNO

Desarrollo para todos

94.00 ADITIVO PLASTIFICANTE Y REDUCTOR DE AGUA GLN 75.00 14.80 1,110.70 14.80 1,110.70 - - 95.00 SOLVENTE SC-55 PARA LACA PROTECTORA GLN 78.00 23.24 1,812.11 23.24 1,812.11 - - 96.00 PINTURA BARNIZ GLN 45.00 4.05 182.26 4.05 182.26 - - 97.00 RODOPLAST PARA BORDE DE MAYOLICAS M 3.00 32.01 96.00 32.01 96.00 - - 98.00 LAVADERO A.INOX.19"x37"C/ESC. P. SAT.C/A UND 185.00 2.00 370.00 2.00 370.00 - - 99.00 PEGAMENTO PARA CERAMICO ( Bolsa 25 Kg.) BOL 23.00 77.05 1,772.41 77.05 1,772.41 - - 100.00 PEGAMENTO PARA PVC GLN 85.00 5.57 475.49 5.57 475.49 - - 101.00 TEROKAL GLN 65.00 1.23 80.15 1.23 80.15 - - 102.00 SOLDADURA CELLOCORD P 3/16" KG 16.00 49.95 798.95 49.95 798.95 - - 103.00 PLASTICA ESPESOR 0.1 mm M2 1.80 42.58 76.64 42.58 76.64 - - 104.00 GABINETE METALICO UND 60.00 1.00 60.00 1.00 60.00 - - 105.00 GRIFO DE RIEGO 3/4" UND 25.00 2.00 50.00 2.00 50.00 - - 106.00 MEDIDOR TRIFASICO DE ENERGIA ELECTRICA UND 330.00 1.00 330.00 1.00 330.00 - - 107.00 LIJA UND 1.50 1.50 2.25 1.50 2.25 - - 108.00 TRANSPORTE DE EQUIPO GLB 800.00 1.00 800.00 0.33 266.67 0.33 266.67 0.33 266.67 109.00 TRANSPORTE DE MATERIALES GLB 4,200.00 1.00 4,200.00 0.33 1,400.00 0.33 1,400.00 0.33 1,400.00 110.00 GASOLINA 84 OCTANOS GLN 9.50 37.39 356.56 37.39 356.56 - - 111.00 HORMIGON M3 33.00 64.95 2,142.33 21.65 714.11 21.65 714.11 21.65 714.11 112.00 LIJA PARA FIERRO PLG 1.80 87.27 156.72 87.27 156.72 - - 113.00 HOJA DE SIERRA PZA 5.50 168.76 928.18 168.76 928.18 - - 114.00 LIJA PARA CONCRETO HJA 1.80 144.54 258.35 144.54 258.35 - - 115.00 COLA SINTETICA GLN 26.20 3.97 103.86 3.97 103.86 - - 116.00 LIJA PARA MADERA UND 1.50 46.88 70.38 46.88 70.38 - - 117.00 AGUA M3 5.00 118.76 600.26 118.76 600.26 - - 118.00 ESTERA DE 2.00 X 3.00 M. UND 28.00 17.25 483.04 17.25 483.04 - - 119.00 PRUEBAS ELECTRICAS UND 750.00 1.00 750.00 1.00 750.00 - - 120.00 ESTIMADO EST 35.00 6.00 210.00 6.00 210.00 - - 121.00 REPOSTERO DE MADERA UND 2,000.00 1.00 2,000.00 1.00 2,000.00 - - 122.00 MOSTRADOR DE MADERA SEGUN MEDIDA UND 1,500.00 1.00 1,500.00 1.00 1,500.00 - - 123.00 ROPERO DE MADERA SEGUN MEDIDA GLB 3,200.00 1.00 3,200.00 1.00 3,200.00 - - 124.00 MADERA TORNILLO P2 5.50 4,966.24 27,315.63 1,655.41 9,105.21 1,655.41 9,105.21 1,655.41 9,105.21 125.00 MADERA CEDRO P2 9.50 1,169.40 11,108.49 389.80 3,702.83 389.80 3,702.83 389.80 3,702.83 126.00 REGLA DE MADERA P2 10.50 12.45 129.51 4.15 43.17 4.15 43.17 4.15 43.17 127.00 PALOS DE EUCALIPTO 2.5 M PZA 8.50 17.25 146.88 17.25 146.88 - - 128.00 PERGOLA DE MADERA SEGUN DISEÑO UND 1,850.00 1.00 1,850.00 1.00 1,850.00 - - 129.00 TRIPLAY DE 4'x8'x 19 mm PLN 135.00 4.25 573.99 1.42 191.33 1.42 191.33 1.42 191.33 130.00 TRIPLAY DE 4'x8'x 4 mm PLN 32.00 73.81 2,361.95 24.60 787.32 24.60 787.32 24.60 787.32 131.00 MALLA RASCHELL M2 3.50 440.60 1,544.25 440.60 1,544.25 132.00 MALLA ELECTROSOLDADA DE 2" X 2" No.12 M2 15.00 177.20 2,657.97 88.60 1,328.99 88.60 1,328.99 133.00 ANGULO 1"x1"x3/16" x 6m PZA 40.00 78.25 3,130.28 39.13 1,565.14 39.13 1,565.14 134.00 ANGULO ACERO 1 1/2" x 1 1/2" x 1/8" x 6m PZA 72.00 59.07 4,252.75 29.54 2,126.38 29.54 2,126.38 135.00 PUERTA METALICA EN INGRESO, INC PINTADO Y COLOCADO M2 3,200.00 2.00 6,400.00 1.00 3,200.00 1.00 3,200.00 136.00 AGUARRAZ GLN 16.50 0.37 6.32 0.19 3.16 0.19 3.16 137.00 PINTURA LATEX GLN 35.00 48.63 1,703.18 24.32 851.59 24.32 851.59 138.00 PINTURA ESMALTE SINTETICO GLN 45.00 0.86 38.88 0.43 19.44 0.43 19.44 139.00 PINTURA ANTICORROSIVA GLN 45.00 6.67 300.73 3.34 150.37 3.34 150.37 140.00 PINTURA ESMALTE GLN 45.00 9.15 411.43 4.58 205.72 4.58 205.72 141.00 LACA PROTECTORA ENCOFRADO P/CONCRETO CARAVISTA GLN 148.00 25.24 3,737.32 12.62 1,868.66 12.62 1,868.66 142.00 SELLADOR BLANCO PARA MUROS GLN 28.00 0.60 17.09 0.30 8.55 0.30 8.55 143.00 PINTURA IMPRIMANTE GLN 30.00 142.66 4,282.51 71.33 2,141.26 71.33 2,141.26 144.00 ARANDELA PLASTICA UND 0.95 135.55 129.04 67.78 64.52 67.78 64.52 145.00 CALAMINA PLN 25.00 23.52 588.00 11.76 294.00 11.76 294.00 146.00 TUBO GALVANIZADO DE 2" x 6 m. UND 160.00 20.33 3,252.80 10.17 1,626.40 10.17 1,626.40 147.00 TUBO GALVANIZADO DE 3" x 6 m. UND 235.00 0.33 77.55 0.17 38.78 0.17 38.78 148.00 TUBO GALVANIZADO DE 4" x 6 m. UND 315.00 0.33 103.95 0.17 51.98 0.17 51.98 149.00 TUBERIA F°G° 1/2" M 9.60 1.28 12.31 0.64 6.16 0.64 6.16 150.00 POSTES ORNAMENTALES UND 300.00 13.00 3,900.00 6.50 1,950.00 6.50 1,950.00 151.00 PLANCHA ACERO LAF 1.20 x 1200 x 2400 mm. (1/8") PZA 825.00 0.08 69.19 0.04 34.60 0.04 34.60 152.00 ESTRUCTURA DE FIBRA DE VIDRIO UND 1,500.00 6.00 9,000.00 3.00 4,500.00 3.00 4,500.00 153.00 VARILLA DE COBRE d=1/2" DE 2.5m UND 210.00 4.00 840.00 2.00 420.00 2.00 420.00 154.00 TUBERIA PVC SAP CLASE 10 3/4'' M 4.60 6.40 29.44 3.20 14.72 3.20 14.72 155.00 REDUCCION R PVC SAP P/AGUA 3/4" A 1/2" UND 2.50 3.00 7.50 1.50 3.75 1.50 3.75 156.00 UNION UNIVERSAL PVC SAP DE 1/2" UND 3.50 8.00 28.00 4.00 14.00 4.00 14.00 157.00 CODO DE 90°C/R PVC SAP P/AGUA DE 1/2" UND 1.30 66.00 85.80 33.00 42.90 33.00 42.90 158.00 TEE PVC SAP DE 1/2" C/R PARA AGUA UND 1.60 60.00 96.00 30.00 48.00 30.00 48.00 159.00 TEE PVC SAP P/AGUA DE 3/4" UND 2.20 4.00 8.80 2.00 4.40 2.00 4.40 160.00 CODO DE 90 PVC SAL DE 2" UND 4.50 21.00 94.50 10.50 47.25 10.50 47.25 161.00 CODO DE 90 PVC SAL DE 4" UND 6.00 5.00 30.00 2.50 15.00 2.50 15.00 162.00 TEE SANITARIA SIMPLE PVC SAL DE 4" UND 8.00 5.00 40.00 2.50 20.00 2.50 20.00 163.00 UNION UNIVERSAL PVC SAP 3/4" PZA 8.00 4.00 32.00 2.00 16.00 2.00 16.00 164.00 TRAMPA "P" PVC SAL DE 2" UND 11.50 11.00 126.50 5.50 63.25 5.50 63.25 165.00 CODO DE 90° PVC SAP P/AGUA DE 3/4" UND 2.10 14.00 29.40 7.00 14.70 7.00 14.70 166.00 CODO PVC SAP 3/4" X 90° PZA 2.10 6.92 14.54 3.46 7.27 3.46 7.27 167.00 CODO PVC AGUA,ROSCADO, DE 90 X 1/2 UND 1.50 4.00 6.00 2.00 3.00 2.00 3.00 168.00 CODO PVC SAP 1/2" X 90° UND 1.20 38.06 45.65 19.03 22.83 19.03 22.83 169.00 TUBO PVC SAL 2" X 3M PZA 9.00 20.48 184.22 10.24 92.11 10.24 92.11 170.00 TUBO PVC SAL 4" X 3M PZA 20.00 28.85 577.01 14.43 288.51 14.43 288.51 171.00 TEE PVC SAL 2" X 2" PZA 5.00 2.00 10.00 1.00 5.00 1.00 5.00 172.00 TEE PVC SAL 4" X 4" PZA 8.50 7.00 59.50 3.50 29.75 3.50 29.75 173.00 YEE PVC SAL DE 4" X 2" PZA 7.00 7.00 49.00 3.50 24.50 3.50 24.50 174.00 TUBO PVC SAP (ELECTRICA) D=20 mm x 3 m UND 9.40 110.47 1,038.36 55.24 519.18 55.24 519.18 175.00 TUBO PVC SAP (ELECTRICA) D=35 mm x 3 m UND 21.50 52.85 1,137.03 26.43 568.52 26.43 568.52 176.00 TUBO PVC SAP (ELECTRICA) SAP 50 mm PZA 30.50 1.10 33.55 0.55 16.78 0.55 16.78 177.00 TUBERIA PVC-CLASE 10 SP 3/4" x 5m. M 4.60 245.87 1,130.70 122.94 565.35 122.94 565.35 178.00 TUBERIA PVC-CLASE 10 SP 1/2" x 5m. M 2.80 96.53 270.25 48.27 135.13 48.27 135.13 179.00 TUBO PVC SAP (ELECTRICA) D=25 mm x 3 m UND 9.50 1.40 13.32 0.70 6.66 0.70 6.66 180.00 CURVA PVC SEL 3/4" PZA 0.80 64.40 51.52 32.20 25.76 32.20 25.76 181.00 UNION SIMPLE PVC-SEL 3/4" UND 0.50 46.00 23.00 23.00 11.50 23.00 11.50 182.00 UNION SIMPLE PVC-SAP CLASE 10 SP-1/2" UND 0.80 18.47 14.58 9.24 7.29 9.24 7.29 183.00 UNION SIMPLE PVC-SAP CLASE 10 SP-3/4" UND 1.00 22.99 22.99 11.50 11.50 11.50 11.50 184.00 CONEXION A TUBERIA EXTERNA EXISTENTE GLB 550.00 1.00 550.00 0.50 275.00 0.50 275.00 185.00 VALVULA COMPUERTA DE BRONCE DE 1/2" UND 30.00 4.00 120.00 2.00 60.00 2.00 60.00 186.00 VALVULA COMPUERTA DE BRONCE DE 3/4" UND 38.00 2.00 76.00 1.00 38.00 1.00 38.00 187.00 REGISTRO DE BRONCE DE 2" PZA 6.00 2.00 12.00 1.00 6.00 1.00 6.00 188.00 VIDRIO SEMIDOBLE P2 4.20 513.24 2,155.60 171.08 718.53 171.08 718.53 171.08 718.53

Page 15: Presupuesto Dm

RECURSOS MATERIALES

PROYECTO : RECONSTRUCCION DE LA I.E.I. Nº 427 JESUS DIVINA MISERICORDIA DEL DISTRITO DE CIUDAD NUEVA - TACNA FECHA - MAYO DE 2010 LUGAR : TACNA-TACNA-TACNA

ITEM DETALLE UND P.U. PROGRAMADO PROGRAMADO POR MES

MES 01 MES 02 MES 03 METRADO COSTO METRADO COSTO METRADO COSTO METRADO COSTO

TACNAREGIONALGOBIERNO

Desarrollo para todos

- - - - - - COSTO DIRECTO (INCLUYE IGV 19%) 316,042.02 91,086.04 161,427.37 63,528.62

Page 16: Presupuesto Dm

RECURSOS MAQUINARIA Y EQUIPOS

PROYECTO : RECONSTRUCCION DE LA I.E.I. Nº 427 JESUS DIVINA MISERICORDIA DEL DISTRITO DE CIUDAD NUEVA - TACNA

FECHA - MAYO DE 2010

LUGAR : TACNA-TACNA-TACNA

ITEM EQUIPO UND P.U.PROGRAMADO PROGRAMADO POR MES

METRADO COSTO MES 01 MES 02 MES 03METRADO COSTO METRADO COSTO METRADO COSTO

### 2.6.22.24 COSTO DE CONSTRUCCION POR ADM. DIRECTA - BIENES

32,750.32

1.00 MIRA TOPOGRAFICA HE 2.15 47.17 45.40 47.17 45.40 2.00 CIZALLA P/FIERRO CONST. HASTA 1" UND 4.00 199.76 226.91 66.59 75.64 66.59 75.64 66.59 75.64 3.00 WINCHA DE 30 MTS. PZA 50.00 38.50 45.40 38.50 45.40 4.00 JALON HE 2.15 94.71 90.81 94.71 90.81 5.00 WINCHE ELECTRICO HM 10.00 95.50 95.46 31.83 31.82 31.83 31.82 31.83 31.82 6.00 VOLQUETE DE 10 M3 HM 125.00 7,203.75 7,206.04 2,401.25 2,402.01 2,401.25 2,402.01 2,401.25 2,402.01 7.00 CAMION CISTERNA 4X2 (AGUA) 2,000 GAL. HM 68.00 35.36 35.16 11.79 11.72 11.79 11.72 11.79 11.72 8.00 ESMERIL ELECTRICO R. HM 4.50 216.95 217.70 72.32 72.57 72.32 72.57 72.32 72.57 9.00 ANDAMIO METALICO HM 4.40 1,234.20 1,234.20 411.40 411.40 411.40 411.40 411.40 411.40 10.00 COMPRESORA NEUMATICA 150 HP 380-590 PCM HM 90.00 3,507.30 3,507.24 90.00 3,507.24 11.00 COMPACTADOR VIBR. TIPO PLANCHA 4 HP HM 20.00 2,869.00 2,868.74 956.33 956.25 956.33 956.25 956.33 956.25 12.00 CARGADOR S/LLANTAS 100-125 HP 2.25 YD3 HM 155.00 2,097.15 2,095.75 1,048.58 1,047.88 1,048.58 1,047.88 13.00 MARTILLO NEUMATICO DE 25 Kg. HM 18.00 1,250.82 1,250.81 18.00 1,250.81 14.00 VIBRADOR DE CONCRETO 4 HP 2.40" HM 15.00 978.45 978.45 326.15 326.15 326.15 326.15 326.15 326.15 15.00 MOTOSOLDADORA DE 250 AMP. HM 18.00 1,721.88 1,721.85 860.94 860.93 860.94 860.93 16.00 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 HM 25.00 4,525.50 4,526.40 1,508.50 1,508.80 1,508.50 1,508.80 1,508.50 1,508.80 17.00 TEODOLITO HM 15.00 329.10 332.97 15.00 332.97 18.00 HERRAMIENTAS MANUALES %MO 0.00 0.00 6,271.03 - 2,090.34 - 2,090.34 - 2,090.34

COSTO DIRECTO ( INCLUYE IGV 19%) 32,750.32 15,068.13 9,795.50 7,886.70

TACNAREGIONALGOBIERNO

Desarrollo para todos

Page 17: Presupuesto Dm

EQUIPAMIENTO

PROYECTO RECONSTRUCCION DE LA I.E.I. Nº 427 JESUS DIVINA MISERICORDIA DEL DISTRITO DE CIUDAD NUEVA - TACNAENTIDAD GOBIERNO REGIONAL DE TACNA

GERENCIA REGIONAL DE INFRAESTRUCTURA DEPARTAMENT TACNAUNIDAD FORMULADORA DE ESTUDIOS PROVINCIA TACNA

SUB PRES EQUIPAMIENTO DISTRITO CIUDAD NUEVAFECHA MAYO DE 2010

Item Concepto Cantidad Costo Unitario Costo Total S/. mes 1 mes 2 mes 3 Total1 Mobiliario Pedagogico

Modulos Nivel Inicial (01 Mesa y 4 sillas) 7.00 420.00 2,940.00 2,940.00 2,940.00Modulos Docente (01 Escritorio y 01 Silla) 4.00 420.00 1,680.00 1,680.00 1,680.00Pizarra Acrilica 4.00 350.00 1,400.00 1,400.00 1,400.00Colchoneta 25.00 18.00 450.00 450.00 450.00Estantes Docentes 4.00 350.00 1,400.00 1,400.00 1,400.00

2 Mobiliario y Equipamiento para Administrativo y ComplementarioEscritorio de Madera (Oficina) 2.00 550.00 1,100.00 1,100.00 1,100.00Sillas de Madera (Oficina) 2.00 105.00 210.00 210.00 210.00Sillas de Madera (Visita) 6.00 105.00 630.00 630.00 630.00Estantes de Madera (Administracion) 2.00 300.00 600.00 600.00 600.00Computadoras Pentium IV (Administracion) 1.00 3,000.00 3,000.00 3,000.00 3,000.00Muebles para equipos de computo (Administracion) 1.00 450.00 450.00 450.00 450.00Impresora de inyeccion a tinta (Administracion) 1.00 350.00 350.00 350.00 350.00Cocina a gas semi industrial 02 Hornillas (Cocina) 1.00 850.00 850.00 850.00 850.00Refrigeradora 02 puertas mediana (Cocina) 1.00 2,000.00 2,000.00 2,000.00 2,000.00Televisor 21" + DVD 1.00 1,000.00 1,000.00 1,000.00 1,000.00Mesa de madera / sillas 0.80 x 2.5 Niños Comedor) 2.00 350.00 700.00 700.00 700.00Sillas de madera (niños Comedor) 20.00 90.00 1,800.00 1,800.00 1,800.00Cama de 1 plaza y media 1.00 450.00 450.00 450.00 450.00Colchon de 1 plaza y media 1.00 300.00 300.00 300.00 300.00Juegos Lúdicos para menores de 5 años (block) 10.00 150.00 1,500.00 1,500.00 1,500.00Modulo de Juegos Infantiles de sube y baja de tubo galvanizado 1.00 1,800.00 1,800.00 1,800.00 1,800.00Modulo de Juegos Infantiles de columpios de tubo galvanizado 1.00 1,150.00 1,150.00 1,150.00 1,150.00Modulo de Juegos Infantiles consistentes en 3 escaleras, tubos metali 1.00 15,000.00 15,000.00 15,000.00 15,000.00

Page 18: Presupuesto Dm

TOTAL EQUIPAMIENTO 40,760.00 40,760.00 40,760.00

Page 19: Presupuesto Dm

CRONOGRAMA DE MANO DE OBRA

PROYECTO : RECONSTRUCCION DE LA I.E.I. Nº 427 JESUS DIVINA MISERICORDIA DEL DISTRITO DE CIUDAD NUEVA - TACNA

FECHA - MAYO DE 2010

LUGAR : TACNA-TACNA-TACNA

ITEM CATEGORIA UNDPROGRAMADO MESES

P.U. METRADO COSTO MES 1 MES 2 MES 3

1 TOPOGRAFO HH 11.04 21.94 242.16 242.16

2 CAPATAZ HH 11.15 885.70 10,109.36 3,369.79 3,369.79 3,369.79

3 OPERARIO HH 11.04 5,696.70 64,310.23 21,436.74 21,436.74 21,436.74

4 OFICIAL HH 9.84 2,288.86 22,990.99 7,663.66 7,663.66 7,663.66

5 PEON HH 8.88 7,122.89 64,480.79 21,493.60 21,493.60 21,493.60

(*)Costo Directo 162,133.53 54,205.95 53,963.79 53,963.79

TACNAREGIONALGOBIERNO

Desarrollo para todos

Page 20: Presupuesto Dm

CRONOGRAMA DE ADQUISICION DE MATERIALES

PROYECTO : RECONSTRUCCION DE LA I.E.I. Nº 427 JESUS DIVINA MISERICORDIA DEL DISTRITO DE CIUDAD NUEVA - TACNA

FECHA - MAYO DE 2010

LUGAR : TACNA-TACNA-TACNA

ITEM CATEGORIA TOTAL MESES

MES 1 MES 2 MES 3

1 CEMENTO 43,318.89 43,318.89

2 ACERO DE REFUERZO 42,654.68 14,218.23 14,218.23 14,218.23

3 AGREGADOS 22,166.95 7,388.98 7,388.98 7,388.98

4 LADRILLOS 24,311.24 8,103.75 8,103.75 8,103.75

5 MADERA 38,553.63 12,851.21 12,851.21 12,851.21

6 CERAMICO 13,727.38 4,575.79 4,575.79 4,575.79

7 PINTURAS 6,753.82 2,251.27 2,251.27 2,251.27

8 VIDRIOS 2,155.60 718.53 718.53 718.53

9 OTROS 122,399.83 40,799.94 40,799.94 40,799.94

(*)Costo Directo 316,042.02 134,226.60 90,907.71 90,907.71

TACNAREGIONALGOBIERNO

Desarrollo para todos

Page 21: Presupuesto Dm

CRONOGRAMA DE ALQUILER DE EQUIPOS Y MAQUINARIAS

PROYECTO : RECONSTRUCCION DE LA I.E.I. Nº 427 JESUS DIVINA MISERICORDIA DEL DISTRITO DE CIUDAD NUEVA - TACNA

FECHA - MAYO DE 2010

LUGAR : TACNA-TACNA-TACNA

ITEM EQUIPO UND P.U.PROGRAMADO MESES

METRADO COSTO MES 1 MES 2 MES 3

1.00 MIRA TOPOGRAFICA HE 2.15 47.17 45.40 45.40 2.00 CIZALLA P/FIERRO CONST. HASTA 1" UND 4.00 199.76 226.91 75.64 75.64 75.64 3.00 WINCHA DE 30 MTS. PZA 50.00 38.50 45.40 45.40 4.00 JALON HE 2.15 94.71 90.81 90.81 5.00 WINCHE ELECTRICO HM 10.00 95.50 95.46 31.82 31.82 31.82 6.00 VOLQUETE DE 10 M3 HM 125.00 7,203.75 7,206.04 2,402.01 2,402.01 2,402.01 7.00 CAMION CISTERNA 4X2 (AGUA) 2,000 GAL. HM 68.00 35.36 35.16 11.72 11.72 11.72 8.00 ESMERIL ELECTRICO R. HM 4.50 216.95 217.70 72.57 72.57 72.57 9.00 ANDAMIO METALICO HM 4.40 1,234.20 1,234.20 411.40 411.40 411.40 10.00 COMPRESORA NEUMATICA 150 HP 380-590 PCM HM 90.00 3,507.30 3,507.24 3,507.24 11.00 COMPACTADOR VIBR. TIPO PLANCHA 4 HP HM 20.00 2,869.00 2,868.74 956.25 956.25 956.25 12.00 CARGADOR S/LLANTAS 100-125 HP 2.25 YD3 HM 155.00 2,097.15 2,095.75 1,047.88 1,047.88 13.00 MARTILLO NEUMATICO DE 25 Kg. HM 18.00 1,250.82 1,250.81 1,250.81 14.00 VIBRADOR DE CONCRETO 4 HP 2.40" HM 15.00 978.45 978.45 326.15 326.15 326.15 15.00 MOTOSOLDADORA DE 250 AMP. HM 18.00 1,721.88 1,721.85 860.93 860.93 16.00 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 HM 25.00 4,525.50 4,526.40 1,508.80 1,508.80 1,508.80 17.00 TEODOLITO HM 15.00 329.10 332.97 332.97 18.00 HERRAMIENTAS MANUALES %MO 0.00 0.00 6,271.03 2,090.34 2,090.34 2,090.34

COSTO DIRECTO ( INCLUYE IGV 19%) 32,750.32 15,068.13 9,795.50 7,886.70

TACNAREGIONALGOBIERNO