PRESUPUESTO 20013

download PRESUPUESTO 20013

of 114

Transcript of PRESUPUESTO 20013

  • 7/29/2019 PRESUPUESTO 20013

    1/114

    EDIFICIO NOELIAEDIFICIO MULTIFAMILIAR RESIDENCIAL "Noelia II"FECHA SETIEMBRE 2,012UBICACI N

    DATOS:EDIFICIO DE DEPARTAMENTOS

    CONFIGURACION SEMISOTANO + 07 PISOS

    AREA TOTAL CONSTRUIDA 220.00 m2ESTACIONAMIENTOS 8.00

    ASCENSORES 1.00

    AREA DEL TERRENO 258.21 m2 PRECIO DEL TERRENO US$M2 1,363.23 $ / m2COSTO DEL TERRENO S/. 932,800.00 SolesCOSTO DEL TERRENO US$ 352,000.00 Dolares

    TIEMPO DE EJECUCION DEL PROYECTO 9.00 Meses

    TC DOLLAR 2.65

    INGRESOS POR VENTAS

    Descripcion Area Precio Venta sub IGV TOT( m2 ) U.S.D. TOTAL 0.09 U.S

    D001 0.00 1,120.00 0.00 0.00D101 0.00 1,120.00 0.00 0.00D102 0.00 1,120.00 0.00 0.00D201 0.00 1,120.00 0.00 0.00D202 0.00 1,120.00 0.00 0.00D301 0.00 1,120.00 0.00 0.00D302 0.00 1,120.00 0.00 0.00D401 0.00 1,120.00 0.00 0.00D402 0.00 1,120.00 0.00 0.00D501 0.00 1,120.00 0.00 0.00D502 0.00 1,120.00 0.00 0.00

    D601 0.00 1,120.00 0.00 0.00D602 0.00 1,120.00 0.00 0.00D701 0.00 1,120.00 0.00 0.00D702 0.00 1,120.00 0.00 0.00Estacionamiento Simple 01 7,500.00 675.00Estacionamiento Simple 02 7,500.00 675.00Estacionamiento Simple 03 7,500.00 675.00Estacionamiento Simple 04 7,500.00 675.00Estacionamiento Simple 05 7,500.00 675.00Estacionamiento Simple 06 7,500.00 675.00Estacionamiento Simple 07 7,500.00 675.00Estacionamiento Simple 08 7,500.00 675.00

    0.00 60,000.00 5,400.00 6

    EGRESOS sub - TOTAL I.G.V. TOT

    Terreno 75.52% 932,800.00 0.00 93Alcabala 3.02% 37,312.00 0.00 3Demolicion de Construccion Existente 3.44% 36,000.00 6,480.00 4Proyectos 2.87% 30,000.00 5,400.00 3Licencias 1.50% 18,500.00 0.00 1Monto de Obra 2.24% 24,122.60 3,497.78 2Costo Administrativo 6.56% 81,000.00 0.00 8Gastos de Ventas 2.43% 25,423.73 4,576.27 3Gasrtos Notariales 1.21% 15,000.00 0.00 1SERPAR / Conexin Domiciliaria de Servicios 1.21% 15,000.00 0.00 1

    100.00% 1,215,158.33 19,954.05 1,23

    UTILIDAD OPERACIONAL -1,056,158.33 -5,644.05 -1,06PAGO DE IGV

    GASTOS FINANCIEROSSUBTOTAL -1,05

  • 7/29/2019 PRESUPUESTO 20013

    2/114

    Area Techada Total : 3,192.07 m2

    tem

    1.00 ESTRUCTURAS2.00 ARQUITECTURA

    3.00 INSTALACIONES ELECTRIC4.00 INSTALACIONES ELECTRO5.00 INSTALACIONES SANITARI

    COSTO DIRECTOG.GENERALES +UTILIDAD

    SUB TOTAL (sin I.G.V.)IGVTOTAL (con I.G.V.)

    EDIFICIRESUMEN PRESUPU

    Decripci

  • 7/29/2019 PRESUPUESTO 20013

    3/114

    Plazo 8.00 8.00TC 2.65

    ProyectadaTotal Ratio Ratio

    S/. S/. / m2 US$ / m2

    10,052.42 3.15 1.1912,304.02 3.85 1.45

    S 0.00 0.00 0.00ECANICAS 0.00 0.00 0.00S 0.00 0.00 0.00

    S/. 22,356.44 7.00 2.647.90% 1,766.16 0.55 0.21

    S/. 24,122.60 7.56 2.8514.5% S/. 3,497.78 1.10 0.41

    S/. 27,620.38 8.65 3.27

    RESIDENCIAL "NOELIA II"ESTO CONSTRUCCION

    n

  • 7/29/2019 PRESUPUESTO 20013

    4/114

  • 7/29/2019 PRESUPUESTO 20013

    5/114

    LARGO ANCHO

    ESTRUCTURAS

    * Trazo y replanteo preliminar m

    1 19.95 26.95

    excavacion zapatas

    * ZAPATA-1 m

    1 2.30 2.15

    ZAPATA-2 m

    5 1.50 1.20

    ZAPATA-3 m

    2 3.00 1.20

    ZAPATA-4 m1 2.30 1.80

    ZAPATA-5 m

    1 2.20 2.00

    ZAPATA-6 m

    5 1.50 4.00

    ZAPATA-7 m

    2 1.20 2.20

    ZAPATA-8 m

    1 6.68 1.80

    ZAPATA-9 m

    1 3.20 1.80

    ZAPATA-10 m

    4 1.80 1.80

    ZAPATA-11 m

    1 4.68 1.50

    ZAPATA-12 m

    1 5.70 1.80

    ZAPATA-13 m

    1 1.20 4.00

    ZAPATA-14 m

    6 0.60 0.60

    ZAPATA-15 m

    1 2.05 1.80

    ASCENSOR m

    HOJA DE SUSTENTO DE METRADOS

    ITEM DESCRIPCION und CANTMEDIDAS

  • 7/29/2019 PRESUPUESTO 20013

    6/114

    1 3.00 3.00

    EJE-1 VIGA DE CIMENTACION m

    1 10.00 0.25

    EJE-2 VIGA DE CIMENTACION m

    1 10.70 0.25

    EJE-3 VIGA DE CIMENTACION m1 9.90 0.25

    EJE-4 VIGA DE CIMENTACION m

    1 5.00 0.25

    EJE-5 VIGA DE CIMENTACION m

    1 3.35 0.25

    EJE-6 VIGA DE CIMENTACION m

    1 3.35 0.25

    EJE-7 VIGA DE CIMENTACION m

    1 13.10 0.25

    EJE-8 VIGA DE CIMENTACION m

    1 17.20 0.25

    EJE-A VIGA DE CIMENTACION m

    1 13.00 0.25

    EJE-B VIGA DE CIMENTACION m

    1 13.00 0.25

    EJE-C VIGA DE CIMENTACION m

    1 13.50 0.25

    EJE-D VIGA DE CIMENTACION m1 1.80 0.25

    EJE-F VIGA DE CIMENTACION m

    1 10.10 0.25

    EJE-G VIGA DE CIMENTACION m

    1 7.10 0.25

    CISTERNA m

    1 5.00 3.50

    totates:

    * Relleno con material propio m

    Excavacion 1 245.00

    Z-1 -1 2.15 2.00

    Z-2 -5 1.50 0.95

    Z-3 -2 3.00 1.05

    Z-4 -1 2.15 1.68

    Z-5 -1 1.85 2.05

  • 7/29/2019 PRESUPUESTO 20013

    7/114

    Z-6 -5 1.50 3.50

    Z-7 -2 1.05 2.00

    Z-8 -1 6.68 1.55

    Z-9 -1 3.20 1.55

    Z-10 -4 1.80 1.55

    Z-11 -1 4.55 1.35

    Z-12 -1 5.55 1.65

    Z-13 -1 1.05 3.75

    Z-14 -6 0.60 0.45Z-15 -1 2.05 1.55

    * Acarreo de Material Proveniente de Excavaciones m

    Excavacion 1 245.00

    Relleno -1 87.56

    * Eliminacion de Material Acarreado m

    solado.- Concreto 1:10 hormigon m

    Z-1 1 2.30 2.15

    Z-2 5 1.50 1.20

    Z-3 2 3.00 1.20Z-4 1 2.30 1.80

    Z-5 1 1.20 1.50

    Z-6 5 1.50 4.00

    Z-7 2 1.20 2.00

    Z-8 1 6.68 1.80

    Z-9 1 3.20 1.80

    Z-10 4 1.80 1.80

    Z-11 1 4.68 1.50

    Z-12 1 5.70 1.80

    Z-13 1 1.20 4.00

    Z-14 6 0.60 0.60

    Z-15 1 2.05 1.80

    ASCENSOR 1 3.00 3.00CISTERNA 1 4.06 2.06

    * DADOS.- Encofrado y desencofrado m

    DADO-C-1 2 19 0.60 0.25

    DADO-C-2 2 2 0.75 0.25

    DADO-C-3 2 6 0.20 0.20

    DADO-PL-1 2 1 4.15 0.15

    DADO-PL-2 2 2 2.00 0.15

    DADO-PL-3 2 1 3.50 0.15

    DADO-PL-4 2 1 2.60 0.15

    DADO-PL-5 2 4 1.10 0.15

    DADO-PL-6 2 1 4.78 0.25

    DADO-PL-7 2 1 1.60 0.25

    DADO-PL-8 2 2 1.00 0.15

    DADO-PL-9 2 1 1.50 0.15

    DADO-PL-10 2 1 2.50 0.15

    DADO-PL-11 2 1 3.10 0.15

    EJE-1 VIGA DE CIMENTACION m2

    m2 2 10.00 1.00

    m2

  • 7/29/2019 PRESUPUESTO 20013

    8/114

    EJE-2 VIGA DE CIMENTACION m2

    m2 2 10.70 1.00

    m2

    EJE-3 VIGA DE CIMENTACION m2

    m2 2 9.90 1.00

    m2

    EJE-4 VIGA DE CIMENTACION m2

    m2 2 5.00 1.00

    m2EJE-5 VIGA DE CIMENTACION m2

    m2 2 3.35 1.00

    m2

    EJE-6 VIGA DE CIMENTACION m2

    m2 2 3.35 1.00

    m2

    EJE-7 VIGA DE CIMENTACION m2

    m2 2 13.10 1.00

    m2

    EJE-8 VIGA DE CIMENTACION m2

    m2 2 17.20 1.00

    m2

    EJE-A VIGA DE CIMENTACION m2

    m2 2 13.00 1.00

    m2

    EJE-B VIGA DE CIMENTACION m2

    m2 2 13.00 1.00

    m2

    EJE-C VIGA DE CIMENTACION m2

    m2 2 13.50 1.00

    m2

    EJE-D VIGA DE CIMENTACION m2

    m2 2 1.80 1.00

    m2

    EJE-F VIGA DE CIMENTACION m2

    m2 2 10.10 1.00

    m2EJE-G VIGA DE CIMENTACION m2

    2 7.10 1.00

    ASCENSOR 2 1 3.00 3.00

    CISTERNA 2 4 5.00 0.25

    2 4 3.60 0.25

    1 1 5.00 3.60

    * zapatas - Concreto 210kg/cm m LARGO ANCHOZ-1 1 2.30 2.15

    Z-2 5 1.50 1.20

    Z-3 2 3.00 1.20

    Z-4 1 2.30 1.80

    Z-5 1 1.20 1.50

  • 7/29/2019 PRESUPUESTO 20013

    9/114

    Z-6 5 1.50 4.00

    Z-7 2 1.20 2.00

    Z-8 1 6.68 1.80

    Z-9 1 3.20 1.80

    Z-10 4 1.80 1.80

    Z-11 1 4.68 1.50

    Z-12 1 5.70 1.80

    Z-13 1 1.20 4.00

    Z-14 6 0.60 0.60Z-15 1 2.05 1.80

    ASCENSOR 1 3.00 3.00

    CISTERNA 1 5.00 3.50

    DADO-C-1 19 0.60 0.25

    DADO-C-2 2 0.75 0.25

    DADO-C-3 6 0.20 0.20

    DADO-PL-1 1 4.15 0.20

    DADO-PL-2 2 2.00 0.20

    DADO-PL-3 1 3.50 0.20

    DADO-PL-4 1 2.60 0.20

    DADO-PL-5 4 1.10 0.20

    DADO-PL-6 1 4.78 0.25

    DADO-PL-7 1 1.60 0.25

    DADO-PL-8 2 1.00 0.20

    DADO-PL-9 1 1.50 0.20

    DADO-PL-10 1 2.50 0.20

    DADO-PL-11 1 3.10 0.20vigas de cimentacion

    VIGAS DE CIMENTACION 1 131.10 0.25

    Cisterna

    CISTERNA 2 5.00 0.25

    2 3.60 0.25

    2 5.00 3.60

    * zapatas .- Acero fy=4200kg/cm kg

    #veces cantidad longitud

    Z-1 longitudinales- 5/8" 1 18 2.25

    transeversales- 5/8" 1 18 2.25

    Z-2 longitudinales- 5/8" 5 12 1.45

    transeversales- 5/8" 5 10 1.15

    Z-3 longitudinales- 5/8" 2 24 2.95

    transeversales- 5/8" 2 10 1.15

    Z-4 longitudinales- 5/8" 2 18 2.10

    transeversales- 5/8" 2 14 1.75

    Z-5 longitudinales- 5/8" 1 16 1.95

    transeversales- 5/8" 1 18 2.15

    Z-6 longitudinales- 5/8" 5 12 1.45

    transeversales- 5/8" 5 32 3.95

  • 7/29/2019 PRESUPUESTO 20013

    10/114

    Z-7 longitudinales- 5/8" 2 8 1.00

    transeversales- 5/8" 2 18 2.15

    Z-8 longitudinales- 5/8" 1 54 6.65

    transeversales- 5/8" 1 14 1.75

    Z-9 longitudinales- 5/8" 1 26 3.15

    transeversales- 5/8" 1 14 1.75

    Z-10 longitudinales- 5/8" 4 14 1.75

    transeversales- 5/8" 4 14 1.75

    Z-11 longitudinales- 5/8" 1 38 4.50

    transeversales- 5/8" 1 12 1.45

    Z-12 longitudinales- 5/8" 1 46 5.65

    transeversales- 5/8" 1 14 1.75

    Z-13 longitudinales- 5/8" 1 10 1.15

    transeversales- 5/8" 1 32 3.95

    Z-14 longitudinales- 5/8" 6 4 0.55

    transeversales- 5/8" 6 4 0.55

    Z-15 longitudinales- 5/8" 1 16 2.00

    transeversales- 5/8" 1 14 1.75

    VIGA DE CIMENTACION longitudinales- 5/8" 7 4 18.90

    Estribos- 3/8" 7 100 1.40

    VIGA DE CIMENTACION longitudinales- 5/8" 5 4 26.95

    Estribos- 3/8" 5 140 1.40

    ASCENSOR longitudinales- 5/8" 1 12 2.95

    longitudinales- 5/8" 1 12 2.95

    CISTERNA longitudinales- 1/2" 4 21 3.10longitudinales- 1/2" 4 15 3.10longitudinales- 1/2" 2 21 3.80

    longitudinales- 1/2" 2 15 5.30

    * Columnas.- concreto 210kg/cm mC-1 19 0.60 0.25

    C-2 2 0.75 0.25

    C-3 6 0.20 0.20

  • 7/29/2019 PRESUPUESTO 20013

    11/114

    * Placas.- concreto 210kg/cm m

    PL-1 1 4.15 0.15

    PL-2 2 2.00 0.15

    PL-3 1 3.50 0.15

    PL-4 1 2.60 0.15

    PL-5 4 1.10 0.15

    PL-6 1 4.78 0.25PL-7 1 1.60 0.25

    PL-8 2 1.00 0.15

    PL-9 1 1.50 0.15

    PL-10 1 2.50 0.15

    PL-11 1 3.10 0.15

    * Columnas.- Encofrado y desencofrado mC-1 2 19 0.60 0.25

    C-2 2 2 0.75 0.25

    C-3 2 6 0.20 0.20

    * Placas.- Encofrado y desencofrado m

    PL-1 2 1 4.15 0.15

    PL-2 2 2 2.00 0.15

    PL-3 2 1 3.50 0.15

    PL-4 2 1 2.60 0.15

    PL-5 2 4 1.10 0.15

    PL-6 2 1 4.78 0.25

    PL-7 2 1 1.60 0.25

    PL-8 2 2 1.00 0.15

    PL-9 2 1 1.50 0.15

    PL-10 2 1 2.50 0.15

    PL-11 2 1 3.10 0.15

    * Columnas.- Acero Fy=4200 kg/cm kg# veces Cantidad Longitud

    C-1

    5/8" 19 8.00 4.70

    3/8" 19 20 2.30

    C-2

    5/8" 2 12.00 4.70

    3/8" 2 20 3.45

    C-3

    5/8" 6 4.00 4.70

    3/8" 6 20 0.80

    placas.- Acero Fy=4200 kg/cm kgPL-1

    1/2" 2 20 4.70

    3/8" 2 20 4.70

    3/8" 2 20 11.20

    PL-2

    1/2" 2 12 4.70

  • 7/29/2019 PRESUPUESTO 20013

    12/114

    3/8" 2 8 4.70

    3/8" 2 20 4.50

    PL-3

    1/2" 1 20 4.70

    3/8" 1 16 4.70

    3/8" 1 20 11.20

    PL-4

    1/2" 1 20 4.70

    3/8" 1 14 4.70 3/8" 1 20 11.20

    PL-5

    5/8" 4 12 4.70

    3/8" 4 20 2.40

    PL-6

    1/2" 1 24 4.70

    5/8" 1 12 4.70

    3/8" 1 20 6.80

    PL-7

    5/8" 1 12 4.70

    3/8" 1 20 2.50

    PL-8

    5/8" 2 12 4.70

    3/8" 2 20 2.50

    PL-9

    1/2" 1 12 4.70

    3/8" 1 8 4.70

    3/8" 1 20 4.20

    PL-10

    5/8" 1 12 4.70

    3/8" 1 16 4.70

    3/8" 1 20 6.40

    PL-11

    1/2" 1 36 4.70

    3/8" 1 20 6.80

    ESCALERA- Concreto 210kg/cm m8 7.92 0.25

    ESCALERA- Acero fy=4200 kg/cm kg # veces cantidad longitud

    1/2" 24 2.00 1.20

    1/2" 10 2.00 4.20

    ESCALERA-- Encofrado y desencofrado m

    CONTRAPASOS 15.00 0.18 1.20

    ABAJO 2.00 4.00 1.20

    LOSA Aligerada- Concreto 210kg/cm mpiso E=0.05 1 19.95 24.45

    viguetas PAO-1 11 9.00 0.11

    viguetas PAO-2 19 6.15 0.11

    viguetas PAO-3 8 9.00 0.11

    viguetas PAO-4 5 11.40 0.11

    viguetas PAO-5 8 14.00 0.11

    viguetas PAO-6 5 17.00 0.11

    viguetas PAO-7 20 20.00 0.11

  • 7/29/2019 PRESUPUESTO 20013

    13/114

    Losa Aligerada.- Encofrado y desencofrado m1 19.95 24.45

    losa Aligerada.- Acero fy=4200 kg/cm kg # veces cantidad longitudPAO-1 1/2" 11 1.00 17.00

    3/8" 11 1.00 3.70

    PAO-2 1/2" 19 1.00 9.20

    3/8" 19 1.00 2.20PAO-3 1/2" 8 1.00 14.60

    3/8" 8 1.00 2.20

    PAO-4 1/2" 5 1.00 30.00

    PAO-5 1/2" 8 1.00 30.00

    PAO-6 1/2" 5 1.00 36.00

    PAO-7 1/2" 20 1.00 60.00

    3/8" 20 1.00 10.00

    Vigas .- Concreto 210kg/cm m AREAV-4 1.00 19.95 0.250

    V-5 5.00 19.95 0.250

    V-3 2.00 27.00 0.250

    V-3 1.00 20.00 0.250V-1 3.00 24.00 0.250

    V-6 1.00 24.00 0.250

    V-2 1.00 18.00 0.250

    V-CHATA-1 1.00 6.00 0.200

    V-CHATA-2 1.00 18.00 0.200

    Vigas.- Encofrado y desencofrado mV-4 1.00 19.95

    V-5 5.00 19.95

    V-3 2.00 27.00

    V-3 1.00 20.00

    V-1 3.00 24.00

    V-6 1.00 24.00

    V-2 1.00 18.00V-CHATA-1 1.00 6.00

    V-CHATA-2 1.00 18.00

    Vigas--Acero fy=4200kg/cm kgVigas # veces cantidad longitud

    V-4

    5/8" 1 8.00 22.74

    3/8" 1 68.00 1.50

    V-5

    5/8" 1 8.00 29.45

    3/8" 1 88.00 1.50

    V-5

    5/8" 1 8.00 29.60 3/8" 1 90.00 1.50

    V-5

    5/8" 1 8.00 29.60

    3/8" 1 90.00 1.50V-5

    5/8" 1 8.00 29.00

    3/8" 1 88.00 1.50

    V-5

    5/8" 2 8.00 29.00

    3/8" 2 88.00 1.50

  • 7/29/2019 PRESUPUESTO 20013

    14/114

    V-CHATA-2

    5/8" 1 8.00 25.00

    3/8" 1 88.00 1.50

    V-1

    5/8" 3 7.00 33.00

    3/8" 3 110.00 1.50

    V-6

    5/8" 1 7.00 33.00

    3/8" 1 120.00 1.50V-3

    5/8" 1 7.00 35.00

    3/8" 1 125.00 1.50

    V-3

    5/8" 1 7.00 24.00

    3/8" 1 80.00 1.50

    V-CHATA-1

    5/8" 1 6.00 12.00

    3/8" 1 20.00 2.00

    V-2

    5/8" 1 7.00 28.00

    3/8" 1 80.00 1.50

    Asensor--Acero fy=4200kg/cm kg

    ASCENSOR longitudinales- 5/8" 1 42 32.00

    VERTICAL 3/8" 1 22.00 32.00

    HORIZONTAL 3/8" 1 107.67 14.44

    HORIZONTAL 3/8" 1 22.00 7.00

    ASENSOR.- Concreto 210kg/cm m AREAOCHO VISOS 1.00 1.07 28.000

    ASENSOR .- Encofrado y desencofrado m14.44 32.00

  • 7/29/2019 PRESUPUESTO 20013

    15/114

    ECHA : 12 de diciembre de 2012Rt = 1.18 kg/cm2.

    Df = 2.00m

    ALTO

    591.47 ok537.65

    6.40

    1.30 6.43

    11.70

    1.30 11.70

    9.40

    1.30 9.36

    5.401.30 5.38

    5.70

    1.30 5.72

    39.001.30 39.00

    6.90

    1.30 6.86

    15.60

    1.30 15.63

    7.50

    1.30 7.49

    16.80

    1.30 16.85

    9.10

    1.30 9.13

    13.30

    1.30 13.34

    6.20

    1.30 6.24

    2.80

    1.30 2.81

    4.80

    1.30 4.80

    18.00

    PARCIAL TOTAL

  • 7/29/2019 PRESUPUESTO 20013

    16/114

    2.00 18.00

    1.50

    0.60 1.50

    1.600.60 1.61

    1.500.60 1.49

    0.80

    0.60 0.75

    0.50

    0.60 0.50

    0.50

    0.60 0.50

    2.00

    0.60 1.97

    2.20

    0.50 2.15

    2.00

    0.60 1.95

    2.00

    0.60 1.95

    2.00

    0.60 2.03

    0.300.60 0.27

    1.50

    0.60 1.52

    1.10

    0.60 1.07 217.91 ok

    46.90

    2.68 46.90 51.59 ok

    245.00 269.50 ok

    0.80 -63.65 87.56 ok245.00

    0.60 -2.58

    0.60 -4.28

    0.60 -3.78

    0.60 -2.17

    0.60 -2.28

  • 7/29/2019 PRESUPUESTO 20013

    17/114

    0.60 -15.75

    0.60 -2.52

    0.60 -6.21

    0.60 -2.98

    0.60 -6.70

    0.60 -3.69

    0.60 -5.49

    0.60 -2.36

    0.60 -0.970.60 -1.91

    1.30 157.44 225.17 ok245.00

    -87.56

    247.69 ok

    15.18 ok0.10 0.49

    0.10 0.90

    0.10 0.720.10 0.41

    0.10 0.18

    0.10 3.00

    0.10 0.48

    0.10 1.20

    0.10 0.58

    0.10 1.30

    0.10 0.70

    0.10 1.03

    0.10 0.48

    0.10 0.22

    0.10 0.37

    0.10 0.900.10 0.84

    250.36 ok0.70 3.99

    0.70 0.53

    0.70 0.34

    0.70 0.87

    0.70 0.84

    0.70 0.74

    0.70 0.55

    0.70 0.92

    0.70 1.67

    0.70 0.56

    0.70 0.42

    0.70 0.32

    0.70 0.53

    0.70 0.65

    169.18 ok12.00

    0.60 12.00

  • 7/29/2019 PRESUPUESTO 20013

    18/114

    12.80

    0.60 12.84

    11.900.60 11.88

    6.000.60 6.00

    4.00

    0.60 4.02

    4.00

    0.60 4.02

    15.70

    0.60 15.72

    17.20

    0.50 17.20

    15.60

    0.60 15.60

    15.60

    0.60 15.60

    16.20

    0.60 16.20

    2.20

    0.60 2.16

    12.10

    0.60 12.12

    8.50

    0.60 8.52

    0.70 12.60

    66.16

    2.80 28.00

    2.80 20.16

    1.00 18.00

    ALTO 121.44 ok0.70 3.46

    0.70 6.30

    0.70 5.04

    0.70 2.90

    0.70 1.26

  • 7/29/2019 PRESUPUESTO 20013

    19/114

    0.70 21.00

    0.70 3.36

    0.70 8.42

    0.70 4.03

    0.70 9.07

    0.70 4.91

    0.70 7.18

    0.70 3.36

    0.70 1.510.70 2.58

    0.70 6.30

    0.70 12.25

    0.70 2.00

    0.70 0.26

    0.70 0.17

    0.70 0.58

    0.70 0.56

    0.70 0.49

    0.70 0.36

    0.70 0.62

    0.70 0.84

    0.70 0.28

    0.70 0.28

    0.70 0.21

    0.70 0.35

    0.70 0.43

    0.60 19.67 21.63 ok

    2.80 7.00 23.14 ok2.80 5.04

    0.25 9.00

    4,734.40 okdensidad

    1.55 62.78

    1.55 62.78

    1.55 134.85

    1.55 89.13

    1.55 219.48

    1.55 35.65

    1.55 117.18

    1.55 75.95

    1.55 48.36

    1.55 59.99

    1.55 134.85

    1.55 979.60

  • 7/29/2019 PRESUPUESTO 20013

    20/114

    1.55 24.80

    1.55 119.97

    1.55 556.61

    1.55 37.98

    1.55 126.95

    1.55 37.98

    1.55 151.90

    1.55 151.90

    1.55 265.05

    1.55 26.97

    1.55 402.85

    1.55 37.98

    1.55 17.83

    1.55 195.92

    1.55 20.46

    1.55 20.46

    1.55 49.60

    1.55 37.98

    3,025.00

    1.55 820.26

    0.56 546.06

    1.55 835.45

    0.56 547.82

    121.00

    1.55 54.87

    1.55 54.87

    832.70 ok0.99 257.80

    0.99 184.14

    0.99 158.00

    0.99 157.41

    8.25 8.30 58.1 66.35 72.985 ok2.00 5.70

    3.00 1.13

    3.00 0.72

  • 7/29/2019 PRESUPUESTO 20013

    21/114

    19.03 13.80 96.6 115.63 127.193 ok

    3.00 1.87

    3.00 1.80

    3.00 1.58

    3.00 1.17

    3.00 1.98

    3.00 3.593.00 1.20

    3.00 0.90

    3.00 0.68

    3.00 1.13

    3.00 1.40

    123.30 98.60 690.2 813.50 894.85 ok3.00 96.90

    3.00 12.00

    3.00 14.40

    220.40 176.30 1234.1 1,454.50 1599.95 ok

    3.00 25.80

    3.00 25.80

    3.00 21.90

    3.00 16.50

    3.00 30.00

    3.00 30.18

    3.00 11.10

    3.00 13.80

    3.00 9.90

    3.00 15.90

    3.00 19.50

    2,077.00 2,077.00 14539 16,616.00 18277.6 okDensidad

    1.55 1,107.32

    0.56 489.44

    1.55 174.84

    0.56 77.28

    1.55 174.84

    0.56 53.76

    2,960.00 2,960.00 20720 23,680.00 26048 ok

    0.99 186.12

    0.56 105.28

    0.56 250.88

    0.99 111.67

  • 7/29/2019 PRESUPUESTO 20013

    22/114

    0.56 42.11

    0.56 100.80

    0.99 93.06

    0.56 42.11

    0.56 125.44

    0.99 93.06

    0.56 36.850.56 125.44

    1.55 349.68

    0.56 107.52

    0.99 111.67

    1.55 87.42

    0.56 76.16

    1.55 87.42

    0.56 28.00

    1.55 174.84

    0.56 56.00

    0.99 55.84

    0.56 21.06

    0.56 47.04

    1.55 87.42

    0.56 42.11

    0.56 71.68

    0.99 167.51

    0.56 76.16

    17.38 17.38 TODOS LOS PISOS15.84

    densidad 1,232.00

    0.99 57.02

    0.99 83.16

    233.64

    16.38

    7.20

    39.90 39.90 319.2 351.120.05 24.39

    0.15 1.63

    0.15 1.93 53.6555250.15 1.19

    0.15 0.94

    0.15 1.85

    0.15 1.40

    0.15 6.60

  • 7/29/2019 PRESUPUESTO 20013

    23/114

    487.80 487.80 3902.4 4292.64487.78

    densidad 2,394.00 2,394.00 19152 21067.20.99 185.13

    0.56 22.79

    0.99 173.05

    0.56 23.410.99 115.63

    0.56 9.86

    0.99 148.50

    0.99 237.60

    0.99 178.20

    0.99 1,188.00

    0.56 112.00

    199.60 199.60 1596.8 1756.480.50 21.70

    0.50 25.70

    0.50 29.75

    0.50 21.750.50 27.75

    0.50 25.75

    0.20 19.45

    0.75 7.95

    0.60 19.80

    265.10 265.10 2120.8 2332.880.85 16.96

    0.85 84.79

    0.85 45.90 0.90.85 17.00

    0.85 61.20

    0.85 20.40

    0.20 3.600.75 4.50

    0.60 10.80

    6,476.00 6,476.00 51808 56988.8densidad

    1.55 281.98

    0.56 57.12

    1.55 365.18

    0.56 73.92

    1.55 367.040.56 75.60

    1.55 367.04

    0.56 75.60

    1.55 359.60

    0.56 73.92

    1.55 719.20

    0.56 147.84

  • 7/29/2019 PRESUPUESTO 20013

    24/114

    1.55 310.00

    0.56 73.92

    1.55 1,074.15

    0.56 277.20

    1.55 358.05

    0.56 100.80

    1.55 379.75

    0.56 105.00

    1.55 260.40

    0.56 67.20

    1.55 111.60

    0.56 22.40

    1.55 303.80

    0.56 67.20

    3,777.40 OK1.55 2,083.20

    0.56 394.24

    0.56 870.64

    0.56 86.24

    34.21 OK1.00 31.07

    508.31 OK1.00 462.08

  • 7/29/2019 PRESUPUESTO 20013

    25/114

    FECHA : 1

    LARGO ANCHO ALTOESTRUCTURAS

    * Trazo y replanteo preliminar m1 19.95 26.95

    * Columnas.- concreto 210kg/cm mC-1 19 0.60 0.25 2.40

    C-2 2 0.75 0.25 2.40

    C-3 6 0.20 0.20 2.40

    placas.- concreto 210kg/cm m

    PL-1 1 4.15 0.15 2.40PL-2 2 2.00 0.15 2.40

    PL-3 1 3.50 0.15 2.40

    PL-4 1 2.60 0.15 2.40

    PL-5 4 1.10 0.15 2.40

    PL-6 1 4.78 0.25 2.40

    PL-7 1 1.60 0.25 2.40

    PL-8 2 1.00 0.15 2.40

    PL-9 1 1.50 0.15 2.40

    PL-10 1 2.50 0.15 2.40

    PL-11 1 3.10 0.15 2.40

    * Columnas.- Encofrado y desencofrado mC-1 2 19 0.60 0.25 2.40

    C-2 2 2 0.75 0.25 2.40

    C-3 2 6 0.20 0.20 2.40

    placa.- Encofrado y desencofrado mPL-1 2 1 4.15 0.15 2.40

    PL-2 2 2 2.00 0.15 2.40

    PL-3 2 1 3.50 0.15 2.40

    PL-4 2 1 2.60 0.15 2.40

    PL-5 2 4 1.10 0.15 2.40

    PL-6 2 1 4.78 0.25 2.40PL-7 2 1 1.60 0.25 2.40

    PL-8 2 2 1.00 0.15 2.40

    PL-9 2 1 1.50 0.15 2.40

    PL-10 2 1 2.50 0.15 2.40

    PL-11 2 1 3.10 0.15 2.40

    * Columnas.- Acero Fy=4200 kg/cm kg# veces Cantidad Longitud Densidad

    HOJA DE SUSTENTO DE METRADOS

    ITEM DESCRIPCION und CANTMEDIDAS

  • 7/29/2019 PRESUPUESTO 20013

    26/114

    C-1

    5/8" 19 8.00 4.70 1.55

    3/8" 19 20 2.30 0.56

    C-2

    5/8" 2 12.00 4.70 1.55

    3/8" 2 20 3.45 0.56

    C-3

    5/8" 6 4.00 4.70 1.55

    3/8" 6 20 0.80 0.56

    placa.- Acero Fy=4200 kg/cm kg

    PL-1

    1/2" 2 20 4.70 0.99

    3/8" 2 20 4.70 0.56

    3/8" 2 20 11.20 0.56

    PL-2

    1/2" 2 12 4.70 0.99

    3/8" 2 8 4.70 0.56

    3/8" 2 20 4.50 0.56

    PL-3 1/2" 1 20 4.70 0.99

    3/8" 1 16 4.70 0.56

    3/8" 1 20 11.20 0.56

    PL-4

    1/2" 1 20 4.70 0.99

    3/8" 1 14 4.70 0.56

    3/8" 1 20 11.20 0.56

    PL-5

    5/8" 4 12 4.70 1.55

    3/8" 4 20 2.40 0.56

    PL-6

    1/2" 1 24 4.70 0.99 5/8" 1 12 4.70 1.55

    3/8" 1 20 6.80 0.56

    PL-7

    5/8" 1 12 4.70 1.55

    3/8" 1 20 2.50 0.56

    PL-8

    5/8" 2 12 4.70 1.55

    3/8" 2 20 2.50 0.56

    PL-9

    1/2" 1 12 4.70 0.99

    3/8" 1 8 4.70 0.56

    3/8" 1 20 4.20 0.56

    PL-10

    5/8" 1 12 4.70 1.55

    3/8" 1 16 4.70 0.56

    3/8" 1 20 6.40 0.56

    PL-11

    1/2" 1 36 4.70 0.99

    3/8" 1 20 6.80 0.56

  • 7/29/2019 PRESUPUESTO 20013

    27/114

    ESCALERA- Concreto 210kg/cm m2 1.20 1.20

    ESCALERA- Acero fy=4200 kg/cm kg # veces cantidad longitud densidad

    3/8" 24 2.00 1.20 0.56

    3/8" 10 2.00 4.20 0.56

    ESCALERA-- Encofrado y desencofrado mCONTRAPASOS 15.00 0.18 1.20

    ABAJO 2.00 4.00 1.20

    LOSA Aligerada- Concreto 210kg/cm mpiso E=0.05 1 19.95 24.45 0.05

    viguetas PAO-1 11 9.00 0.11 0.15

    viguetas PAO-2 19 6.15 0.11 0.15

    viguetas PAO-3 8 9.00 0.11 0.15

    viguetas PAO-4 5 11.40 0.11 0.15

    viguetas PAO-5 8 14.00 0.11 0.15

    viguetas PAO-6 5 17.00 0.11 0.15

    viguetas PAO-7 20 20.00 0.11 0.15

    Losa Aligerada.- Encofrado y desencofrado m

    1 19.95 24.45

    losa Aligerada.- Acero fy=4200 kg/cm kg # veces cantidad longitud densidadPAO-1 1/2" 11 1.00 17.00 0.99

    3/8" 11 1.00 3.70 0.56

    PAO-2 1/2" 19 1.00 9.20 0.99

    3/8" 19 1.00 2.20 0.56

    PAO-3 1/2" 8 1.00 14.60 0.99

    3/8" 8 1.00 2.20 0.56PAO-4 1/2" 5 1.00 30.00 0.99

    PAO-5 1/2" 8 1.00 30.00 0.99

    PAO-6 1/2" 5 1.00 36.00 0.99

    PAO-7 1/2" 20 1.00 60.00 0.99

    3/8" 20 1.00 10.00 0.56

    Vigas .- Concreto 210kg/cm m AREAV-4 1.00 19.95 0.250 0.50

    V-5 5.00 19.95 0.250 0.50

    V-3 2.00 27.00 0.250 0.50

    V-3 1.00 20.00 0.250 0.50

    V-1 3.00 24.00 0.250 0.50V-6 1.00 24.00 0.250 0.50

    V-2 1.00 18.00 0.250 0.20

    V-CHATA-1 1.00 6.00 0.200 0.75

    V-CHATA-2 1.00 18.00 0.200 0.60

    Vigas.- Encofrado y desencofrado mV-4 1.00 19.95 0.85

    V-5 5.00 19.95 0.85

    V-3 2.00 27.00 0.85

  • 7/29/2019 PRESUPUESTO 20013

    28/114

    V-3 1.00 20.00 0.85

    V-1 3.00 24.00 0.85

    V-6 1.00 24.00 0.85

    V-2 1.00 18.00 0.20

    V-CHATA-1 1.00 6.00 0.75

    V-CHATA-2 1.00 18.00 0.60

    Vigas--Acero fy=4200kg/cm kgVigas # veces cantidad longitud densidadV-4

    5/8" 1 8.00 22.74 1.55

    3/8" 1 68.00 1.50 0.56

    V-5

    5/8" 1 8.00 29.45 1.55

    3/8" 1 88.00 1.50 0.56

    V-5

    5/8" 1 8.00 29.60 1.55

    3/8" 1 90.00 1.50 0.56

    V-5

    5/8" 1 8.00 29.60 1.55

    3/8" 1 90.00 1.50 0.56V-5

    5/8" 1 8.00 29.00 1.55

    3/8" 1 88.00 1.50 0.56

    V-5

    5/8" 2 8.00 29.00 1.55

    3/8" 2 88.00 1.50 0.56

    V-CHATA-2

    5/8" 1 8.00 25.00 1.55

    3/8" 1 88.00 1.50 0.56

    V-1

    5/8" 3 7.00 33.00 1.55

    3/8" 3 110.00 1.50 0.56V-6

    5/8" 1 7.00 33.00 1.55

    3/8" 1 120.00 1.50 0.56

    V-3

    5/8" 1 7.00 35.00 1.55

    3/8" 1 125.00 1.50 0.56

    V-3

    5/8" 1 7.00 24.00 1.55

    3/8" 1 80.00 1.50 0.56

    V-CHATA-1

    5/8" 1 6.00 12.00 1.55

    3/8" 1 20.00 2.00 0.56

    V-2

    5/8" 1 7.00 28.00 1.55

    3/8" 1 80.00 1.50 0.56

  • 7/29/2019 PRESUPUESTO 20013

    29/114

    2 de diciembre de 2012Rt = 1.18 kg/cm2.

    Df = 2.00m

    537.70537.65

    8.306.84

    0.90

    0.58

    13.80

    1.491.44

    1.26

    0.94

    1.58

    2.87

    0.96

    0.72

    0.54

    0.90

    1.12

    98.6077.52

    9.60

    11.52

    176.3020.64

    20.64

    17.52

    13.20

    24.00

    24.148.88

    11.04

    7.92

    12.72

    15.60

    2,077.00

    PARCIAL TOTAL

  • 7/29/2019 PRESUPUESTO 20013

    30/114

    1,107.32

    489.44

    174.84

    77.28

    174.84

    53.76

    2,960.00

    186.12

    105.28

    250.88

    111.67

    42.11

    100.80

    93.06

    42.11

    125.44

    93.06

    36.85

    125.44

    349.68

    107.52

    111.6787.42

    76.16

    87.42

    28.00

    174.84

    56.00

    55.84

    21.06

    47.04

    87.42

    42.11

    71.68

    167.51

    76.16

  • 7/29/2019 PRESUPUESTO 20013

    31/114

    4.404.40

    45.00

    27.76

    16.76

    23.6016.38

    7.20

    39.9024.39

    1.63

    1.93

    1.19

    0.94

    1.85

    1.40

    6.60

    487.80487.78

    2,394.00185.13

    22.79

    173.05

    23.41

    115.63

    9.86148.50

    237.60

    178.20

    1,188.00

    112.00

    199.6021.70

    25.70

    29.75

    21.75

    27.7525.75

    19.45

    7.95

    19.80

    265.1016.96

    84.79

    45.90

  • 7/29/2019 PRESUPUESTO 20013

    32/114

    17.00

    61.20

    20.40

    3.60

    4.50

    10.80

    6,476.00

    281.98

    57.12

    365.18

    73.92

    367.04

    75.60

    367.04

    75.60

    359.60

    73.92

    719.20

    147.84

    310.00

    73.92

    1,074.15

    277.20

    358.05

    100.80

    379.75

    105.00

    260.40

    67.20

    111.60

    22.40

    303.80

    67.20

  • 7/29/2019 PRESUPUESTO 20013

    33/114

    DENOMINACION A B L / H No. Element

    AREA DE TERRENO 19.95 26.95solado zapata 1 2.30 2.15 0.10 1.00solado zapata 2 1.50 1.20 0.10 5.00

    solado zapata 3 3.00 1.20 0.10 2.00solado zapata 4 2.30 1.80 0.10 1.00solado zapata 5 2.20 2.00 0.10 1.00solado zapata 6 1.50 4.00 0.10 5.00solado zapata 7 1.20 2.20 0.10 2.00solado zapata 8 6.68 1.80 0.10 1.00solado zapata 9 3.20 1.80 0.10 1.00solado zapata 10 1.80 1.80 0.10 4.00solado zapata 11 4.68 1.50 0.10 1.00solado zapata 12 5.70 1.80 0.10 1.00solado zapata 13 1.20 4.00 0.10 1.00solado zapata 14 0.60 0.60 0.10 6.00solado zapata 15 1.80 1.80 0.10 1.00

    EXCAVACIONES

    Z1 2.30 2.15 1.30 1.00Z2 1.50 1.20 1.30 5.00Z3 3.00 1.20 1.30 2.00Z4 2.30 1.80 1.30 1.00Z5 2.20 2.00 1.30 1.00Z6 1.50 4.00 1.30 5.00Z7 1.20 2.20 1.30 2.00Z8 6.68 1.80 1.30 1.00Z9 3.20 1.80 1.30 1.00Z10 1.80 1.80 1.30 4.00Z11 4.68 1.50 1.30 1.00Z12 5.70 1.80 1.30 1.00Z13 1.20 4.00 1.30 1.00Z14 0.60 0.60 1.30 6.00Z15 1.80 1.80 1.30 1.00

    asensor 3.00 3.00 2.00 1.00

    EXCAVACION MASIVA

    EJE-1 VIGA DE CIMENTACION 0.25 0.60 10.00 1.00EJE-2 VIGA DE CIMENTACION 0.25 0.60 10.70 1.00EJE-3 VIGA DE CIMENTACION 0.25 0.60 9.90 1.00EJE-4 VIGA DE CIMENTACION 0.25 0.60 5.00 1.00EJE-5 VIGA DE CIMENTACION 0.25 0.60 3.35 1.00EJE-6 VIGA DE CIMENTACION 0.25 0.60 3.35 1.00EJE-7 VIGA DE CIMENTACION 0.25 0.60 13.10 1.00EJE-8 VIGA DE CIMENTACION 0.25 0.60 17.20 1.00EJE-A VIGA DE CIMENTACION 0.25 0.60 13.00 1.00EJE-B VIGA DE CIMENTACION 0.25 0.60 13.00 1.00EJE-C VIGA DE CIMENTACION 0.25 0.60 13.50 1.00EJE-D VIGA DE CIMENTACION 0.25 0.60 1.80 1.00

  • 7/29/2019 PRESUPUESTO 20013

    34/114

    EJE-E VIGA DE CIMENTACION 0.25 0.60 10.10 1.00EJE-F VIGA DE CIMENTACION 0.25 0.60 7.10 1.00EJE-G VIGA DE CIMENTACION 0.25 0.60 4.06 1.00

    Cisterna 5.00 3.50 2.68 1.00

    RELLENO

    Z1 2.00 2.15 0.58 1.00Z2 0.95 1.20 0.58 5.00Z3 1.05 1.20 0.58 2.00Z4 1.68 1.80 0.58 1.00Z5 2.05 2.00 0.58 1.00Z6 3.50 4.00 0.58 5.00Z7 2.00 2.20 0.58 2.00Z8 1.55 1.80 0.58 1.00Z9 1.55 1.80 0.58 1.00Z10 1.55 1.80 0.58 4.00Z11 1.35 1.50 0.58 1.00Z12 1.65 1.80 0.58 1.00Z13 3.75 4.00 0.58 1.00

    Z14 0.45 0.60 0.58 6.00Z15 1.55 1.80 0.58 1.00

    CONCRETO SIMPLE

    CONCRETO ARMADO

    Z-1 2.30 2.15 0.60 1.00Z-2 1.50 1.20 0.60 5.00Z-3 3.00 1.20 0.60 2.00Z-4 2.30 1.80 0.60 1.00Z-5 1.20 1.50 0.60 1.00Z-6 1.50 4.00 0.60 5.00Z-7 1.20 2.00 0.60 2.00Z-8 6.68 1.80 0.60 1.00Z-9 3.20 1.80 0.60 1.00

    Z-10 1.80 1.80 0.60 4.00

    Z-11 4.68 1.50 0.60 1.00Z-12 5.70 1.80 0.60 1.00Z-13 1.20 4.00 0.60 1.00Z-14 0.60 0.60 0.60 6.00Z-15 2.05 1.80 0.60 1.00

    ASCENSOR 3.00 3.00 0.50 1.00CISTERNA 4.06 2.06 0.60 1.00DADO-C-1 0.60 0.25 0.70 19.00DADO-C-2 0.75 0.25 0.70 2.00DADO-C-3 0.20 0.20 0.70 6.00

    DADO-PL-1 4.15 0.15 0.70 1.00

  • 7/29/2019 PRESUPUESTO 20013

    35/114

    DADO-PL-2 2.00 0.15 0.70 2.00DADO-PL-3 3.50 0.15 0.70 1.00DADO-PL-4 2.60 0.15 0.70 1.00DADO-PL-5 1.10 0.15 0.70 4.00DADO-PL-6 4.78 0.25 0.70 1.00DADO-PL-7 1.60 0.25 0.70 1.00DADO-PL-8 1.00 0.15 0.70 2.00DADO-PL-9 1.50 0.15 0.70 1.00

    DADO-PL-10 2.50 0.15 0.70 1.00DADO-PL-11 3.10 0.15 0.70 1.00

    VIGAS DE CIMENTACION 10.65 0.25 0.60 1.00CISTERNA 5.00 0.25 2.80 2.00

    3.50 0.25 2.80 2.00

    Z-1 longitudinales- 5/8" 2.25 1 9 1.00transeversales- 5/8" 2.25 1 9 1.00

    1.00Z-2 longitudinales- 5/8" 1.45 5 6 1.00

    transeversales- 5/8" 1.15 5 5 1.001.00

    Z-3 longitudinales- 5/8" 2.95 2 12 1.00transeversales- 5/8" 1.15 2 5 1.00

    1.00Z-4 longitudinales- 5/8" 2.10 2 9 1.00

    transeversales- 5/8" 1.75 2 7 1.001.00

    Z-5 longitudinales- 5/8" 1.95 1 8 1.00transeversales- 5/8" 2.15 1 9 1.00

    1.00Z-6 longitudinales- 5/8" 1.45 5 6 1.00

    transeversales- 5/8" 3.95 5 16 1.001.00

    Z-7 longitudinales- 5/8" 1.00 2 4 1.00transeversales- 5/8" 2.15 2 9 1.00

    1.00Z-8 longitudinales- 5/8" 6.65 1 27 1.00

    transeversales- 5/8" 1.75 1 7 1.001.00

    Z-9 longitudinales- 5/8" 3.15 1 13 1.00transeversales- 5/8" 1.75 1 7 1.00

    1.00Z-10 longitudinales- 5/8" 1.75 4 7 1.00

    transeversales- 5/8" 1.75 4 7 1.001.00

    Z-11 longitudinales- 5/8" 4.50 1 19 1.00

    transeversales- 5/8" 1.45 1 6 1.001.00Z-12 longitudinales- 5/8" 5.65 1 23 1.00

    transeversales- 5/8" 1.75 1 7 1.001.00

    Z-13 longitudinales- 5/8" 1.15 1 5 1.00transeversales- 5/8" 3.95 1 16 1.00

    1.00Z-14 longitudinales- 5/8" 0.55 6 2 1.00

    transeversales- 5/8" 0.55 6 2 1.001.00

  • 7/29/2019 PRESUPUESTO 20013

    36/114

    Z-15 longitudinales- 5/8" 2.00 1 8 1.00transeversales- 5/8" 1.75 1 7 1.00

    1.00CIMENTACION longitudinales- 5/8" 18.90 7 4 1.00

    Estribos- 3/8" 1.40 7 100 1.001.00

    CIMENTACION longitudinales- 5/8" 26.95 5 4 1.00Estribos- 3/8" 1.40 5 140 1.00

    1.00ASCENSOR longitudinales- 5/8" 2.95 1 12 1.00

    longitudinales- 5/8" 2.95 1 12 1.00

    VC - 2 eje 03 0.25 0.50 11.00 1.00VC - 2 eje 04 0.25 0.50 8.00 1.00VC - 2 eje 05 0.25 0.50 8.00 1.00

    VC - 2 eje 06 0.25 0.50 11.00 1.00VC - 2 eje B 0.25 0.50 15.00 1.00

    ascensor 1 3.00 3.00 2.00 1.00

    cisterna 1 0.20 2.40 5.30 2.00cisterna 2 0.20 2.40 2.40 3.00cisterna 3 0.20 2.40 5.30 2.00cisterna 4 0.25 0.50 2.40 2.00

    cimiento corrido 1-1 1.00 0.60 5.00 1.00cimiento corrido 1-1a 0.15 0.30 5.00 1.00

    cimiento corrido 2-2 1.00 0.50 4.00 1.00cimiento corrido 2-2a 0.15 0.30 4.00 1.00cimiento corrido 3-3 1.00 0.50 12.00 1.00cimiento corrido 3-3a 0.00 0.00 12.00 1.00cimiento corrido 4-4 1.10 0.60 24.00 1.00cimiento corrido 4-4a 0.70 0.15 24.00 1.00cimiento corrido 5-5 1.00 0.50 17.00 1.00cimiento corrido 5-5a 0.80 0.15 17.00 1.00

    C1 0.60 0.25 2.40 14.00

  • 7/29/2019 PRESUPUESTO 20013

    37/114

    C2 0.70 0.25 2.40 1.00C3 0.25 0.25 2.40 2.00C4 0.15 0.25 2.40 8.00

    P1 0.75 0.25 2.40 1.00P2 1.10 0.25 2.40 1.00

    losa 1 2.65 0.50 0.20 1.00losa 2 0.80 2.20 0.20 1.00losa 3 2.60 0.90 0.20 1.00losa 4 0.85 2.40 0.20 1.00losa 5 1.25 1.20 0.20 1.00losa 6 0.80 2.20 0.20 1.00losa 7 2.65 0.50 0.20 1.00

    aligerado 1 8.15 2.60 0.20 1.008.15 2.15 0.20 1.008.15 1.85 0.20 1.008.15 2.60 0.20 1.00

    aligerado 2 5.30 2.45 0.20 1.005.30 2.45 0.20 1.00

    VP-1 0.25 0.40 7.15 1.00VP-1 0.25 0.40 7.15 1.00VP-1 0.25 0.40 4.30 1.00VP-1 0.25 0.40 4.30 1.00VP-1 0.25 0.40 4.30 1.00

    VP-1 0.25 0.40 4.30 1.00VP-1 0.25 0.40 4.30 1.00VA-1 0.25 0.20 2.60 1.00VA-1 0.25 0.20 2.60 1.00VA-1 0.25 0.20 2.60 1.00VA-1 0.25 0.20 2.60 1.00VA-2 0.25 0.20 0.75 1.00VA-2 0.25 0.20 0.75 1.00VA-2 0.25 0.20 2.20 1.00VA-2 0.25 0.20 2.20 1.00VA-2 0.25 0.20 2.40 1.00VS 0.25 0.40 18.00 1.00VC 0.20 0.35 1.60 1.00

    V-100 0.25 0.40 14.10 1.00V-101 0.60 0.20 14.10 1.00VT 0.10 0.20 7.45 1.00VT 0.10 0.20 7.15 1.00VB 0.10 0.20 14.10 1.00

  • 7/29/2019 PRESUPUESTO 20013

    38/114

    sub TOTALDesperdicio 10%

    TOTAL

    x y LSemi SOTANO 49.00 30.00 79.001 PISO 53.00 45.00 98.002 PISO 53.00 45.00 98.003 PISO 53.00 45.00 98.004 PISO 53.00 45.00 98.005 PISO 53.00 45.00 98.006 PISO 53.00 45.00 98.007 PISO 53.00 45.00 98.00

  • 7/29/2019 PRESUPUESTO 20013

    39/114

    No. piso No. Estribo L Estribos L refuerzo N varillas 01 N varillas 02N varil las 03 N. viguetas

    1.001.00

    1.001.001.001.001.001.001.001.001.001.001.001.001.00

    1.001.001.001.001.001.001.001.001.001.001.001.001.001.001.00

    1.00

    1.001.001.001.001.001.001.001.001.001.001.001.00

  • 7/29/2019 PRESUPUESTO 20013

    40/114

    1.001.001.00

    1.00

    1.001.001.001.001.001.001.001.001.001.001.001.001.00

    1.001.00

    1.001.001.001.001.001.001.001.001.001.00

    1.001.001.001.001.001.001.001.001.001.001.00

  • 7/29/2019 PRESUPUESTO 20013

    41/114

    1.001.001.001.001.001.001.001.00

    1.001.001.002.002.00

    1.001.001.001.001.001.001.001.001.001.001.001.001.001.001.001.001.001.00

    1.001.001.001.001.001.001.001.001.001.001.001.001.00

    1.001.001.001.001.001.001.001.001.001.001.00

  • 7/29/2019 PRESUPUESTO 20013

    42/114

    1.001.001.001.001.001.001.001.00

    1.001.001.00

    1.00 73.33 1.70 12.00 5.001.00 53.33 1.70 9.00 5.001.00 53.33 1.70 9.00 5.00

    1.00 73.33 1.70 12.00 5.001.00 100.00 1.70 16.00 5.00

    8.00 128.00 24.20

    1.001.001.001.00

    1.001.00

    1.001.001.001.001.001.001.001.00

    8.00 16.00 1.90 3.00 0.00 8.00

  • 7/29/2019 PRESUPUESTO 20013

    43/114

    8.00 16.00 2.10 3.00 0.00 2.00 8.008.00 16.00 1.20 3.00 0.00 4.001.00 16.00 1.00 3.00 0.00 4.00 0.00

    8.00 16.00 2.20 3.40 0.00 8.00 0.00 4.008.00 16.00 2.90 3.40 0.00 8.00 0.00 6.00

    8.00 10.60 2.008.00 3.20 8.808.00 10.40 3.608.00 3.40 9.608.00 5.00 4.808.00 3.20 8.808.00 10.60 2.00

    8.00 6.508.00 5.388.00 4.638.00 6.50

    8.00 6.138.00 6.13

    8.00 47.67 1.50 7.95 4.008.00 47.67 1.50 7.95 4.008.00 28.67 1.50 5.10 4.008.00 28.67 1.50 5.10 4.008.00 28.67 1.50 5.10 4.00

    8.00 28.67 1.50 5.10 4.008.00 28.67 1.50 5.10 4.008.00 17.33 1.10 3.00 4.008.00 17.33 1.10 3.00 4.008.00 17.33 1.10 3.00 4.008.00 17.33 1.10 3.00 4.008.00 5.00 1.10 1.15 4.008.00 5.00 1.10 1.15 4.008.00 14.67 1.10 2.60 4.008.00 14.67 1.10 2.60 4.008.00 16.00 1.10 2.80 4.008.00 120.00 1.50 18.80 4.008.00 10.67 1.30 2.30 4.00

    8.00 94.00 1.50 14.90 6.008.00 94.00 1.80 14.50 11.008.00 49.67 0.40 7.85 20.008.00 47.67 0.40 7.55 21.008.00 94.00 0.40 14.50 22.00

  • 7/29/2019 PRESUPUESTO 20013

    44/114

    total ( ml. )

    peso x ml.

    peso ( Kg.)

    h muro tarrajeo int. tarrajeo ext. cielo raso pintura2.40 189.60 307.20 72.00 138.49 379.202.40 235.20 398.40 115.20 166.67 513.602.40 235.20 398.40 115.20 166.67 513.602.40 235.20 398.40 115.20 166.67 513.602.40 235.20 398.40 115.20 166.67 513.602.40 235.20 398.40 115.20 166.67 513.602.40 235.20 398.40 115.20 166.67 513.602.40 235.20 398.40 115.20 166.67 513.60

    1,836.00 3,096.00 878.40 1,305.18 3,974.40

  • 7/29/2019 PRESUPUESTO 20013

    45/114

    Area Encofrado solado Excavacion EX, MASIV Relleno concreto cimiento

    537.650.490.90

    0.720.410.443.000.531.200.581.300.701.030.480.220.32

    6.4311.70

    9.365.385.72

    39.006.86

    15.637.49

    16.859.13

    13.346.242.814.21

    18.00

    1.501.611.490.750.500.501.972.581.951.952.030.27

  • 7/29/2019 PRESUPUESTO 20013

    46/114

    1.521.070.61

    46.90

    2.493.311.461.752.38

    40.605.101.621.626.471.171.728.70

    0.941.62

    2.975.404.322.481.08

    18.002.887.213.467.78

    4.216.162.881.302.214.505.022.000.260.170.44

  • 7/29/2019 PRESUPUESTO 20013

    47/114

    0.420.370.270.460.840.280.210.16

    0.260.331.60

    14.009.80

  • 7/29/2019 PRESUPUESTO 20013

    48/114

    11.008.008.00

    11.0015.00

    3.003.00 0.23

    2.00 2.003.00 0.186.00 6.00

    0.00 0.0015.84 15.84

    1.50 2.528.50 8.50

    1.50 2.04

    456.96 40.32

  • 7/29/2019 PRESUPUESTO 20013

    49/114

    36.48 3.3638.40 2.4015.36 0.72

    38.40 3.6051.84 5.28

    20.68 2.1223.68 2.8229.92 3.7426.72 3.2619.84 2.4023.68 2.8220.68 2.12

    169.52 13.56140.18 11.21120.62 9.65169.52 13.56

    0.00103.88 8.31103.88 8.31

    60.06 5.7260.06 5.7236.12 3.4436.12 3.4436.12 3.44

    36.12 3.4436.12 3.4413.52 1.0413.52 1.0413.52 1.0413.52 1.04

    3.90 0.303.90 0.30

    11.44 0.8811.44 0.8812.48 0.96

    151.20 14.4011.52 0.90

    118.44 11.28112.80 13.5429.80 1.1928.60 1.1456.40 2.26

  • 7/29/2019 PRESUPUESTO 20013

    50/114

    1,771.36 12.32 178.15 67.17 80.96 371.40 35.34177.14 1.23 17.81 6.72 8.10 37.14 3.53

    1,345.25 1,948.50 13.55 195.96 73.89 89.06 408.54 38.87

    p. apan. p. cont. rpt. clt. inod.0.00 5.00 0.00 3.00 2.002.00 7.00 6.00 1.10 2.002.00 12.00 6.00 7.00 4.002.00 12.00 6.00 7.00 4.002.00 12.00 6.00 7.00 4.002.00 12.00 6.00 7.00 4.002.00 12.00 6.00 7.00 4.002.00 12.00 6.00 7.00 4.00

    14.00 84.00 42.00 46.10 28.00

  • 7/29/2019 PRESUPUESTO 20013

    51/114

    sobrecimiento falso piso contrapis ladrillos 1/4" 3/8" 1/2" 5/8"

  • 7/29/2019 PRESUPUESTO 20013

    52/114

  • 7/29/2019 PRESUPUESTO 20013

    53/114

    19.3520.70

    0.0043.5027.60

    0.0070.8011.04

    0.0036.1225.20

    0.0015.6018.92

    0.0043.50

    316.000.00

    8.4037.84

    0.00177.69

    12.600.00

    40.3212.60

    0.0050.4050.40

    0.0084.24

    8.700.00128.82

    12.600.005.52

    63.200.007.927.920.00

  • 7/29/2019 PRESUPUESTO 20013

    54/114

    16.4012.60

    0.00529.20975.10

    0.00539.00978.25

    0.0035.4035.40

    124.67 60.0090.67 45.0090.67 45.00

    124.67 60.00170.00 80.00

    3,161.60 96.00

    203.52138.24203.52

    19.20

    0.23 3.00

    0.18 2.40

    0.00 0.00

    2.52 7.20

    2.04 5.10

    17.703,404.80 2,688.00

  • 7/29/2019 PRESUPUESTO 20013

    55/114

    268.80 48.00 192.00307.20 192.00

    128.00 96.00 0.00

    35.20 108.80 217.6046.40 163.20 217.60

    84.80112.64149.76130.56

    96.00112.64

    84.80

    5,424.64 36.08 88.084,485.76 29.83 72.833,859.84 25.67 62.675,424.64 36.08 88.08

    3,324.16 19.91 60.703,324.16 19.91 60.70

    572.00 254.40572.00 254.40344.00 163.20344.00 163.20344.00 163.20

    344.00 163.20344.00 163.20152.53 96.00152.53 96.00152.53 96.00152.53 96.00

    44.00 36.8044.00 36.80

    129.07 83.20129.07 83.20140.80 89.60

    1,440.00 601.60110.93 73.60

    1,128.00 715.201,353.60 1,276.00158.93 1,256.00152.53 1,268.40300.80 2,552.00

  • 7/29/2019 PRESUPUESTO 20013

    56/114

    4.97 0.00 35.40 0.00 25,971.20 17,933.68 2,125.05 16,877.250.50 0.00 3.54 0.00 2,597.12 1,793.37 212.50 1,687.725.46 0.00 38.94 0.00 28,568.32 19,727.04 2,337.55 18,564.97

    0.22 0.56 0.99 1.55

    6,285.03 11,047.14 2,314.18 28,775.71

    Lvt. ducha Lvd. Grf. Coc. Grf. Dch. No.10 No.122.00 2.00 0.00 0.00 2.00 300.00 100.002.00 2.00 2.00 2.00 2.00 0.00 150.004.00 4.00 2.00 2.00 4.00 0.00 200.004.00 4.00 2.00 2.00 4.00 0.00 250.004.00 4.00 2.00 2.00 4.00 0.00 300.004.00 4.00 2.00 2.00 4.00 0.00 350.004.00 4.00 2.00 2.00 4.00 0.00 400.004.00 4.00 2.00 2.00 4.00 0.00 450.00

    28.00 28.00 14.00 14.00 28.00 300.00 2,200.00

  • 7/29/2019 PRESUPUESTO 20013

    57/114

  • 7/29/2019 PRESUPUESTO 20013

    58/114

  • 7/29/2019 PRESUPUESTO 20013

    59/114

  • 7/29/2019 PRESUPUESTO 20013

    60/114

    11.008.008.00

    11.0015.0053.00

  • 7/29/2019 PRESUPUESTO 20013

    61/114

  • 7/29/2019 PRESUPUESTO 20013

    62/114

    106.00 0.0010.60 0.00

    116.60 0.00

    48,422.06

    No.14 No.16 PVC 1/2" PVC 3/4" PVC 1" CPVC 1/2"300.00 100.00 30.00 30.00 20.00 20.00560.00 120.00 40.00 40.00 20.00 20.00620.00 140.00 50.00 50.00 20.00 20.00640.00 160.00 60.00 60.00 20.00 20.00680.00 180.00 70.00 70.00 20.00 20.00720.00 200.00 80.00 80.00 20.00 20.00760.00 220.00 90.00 90.00 20.00 20.00800.00 240.00 100.00 100.00 20.00 20.00

    5,080.00 1,360.00 520.00 520.00 160.00 160.00

    104.00 104.00 32.00 32.00

    agua

  • 7/29/2019 PRESUPUESTO 20013

    63/114

    EXCAVACION EXCAVACIONES

    6.43 0.00 6.4311.70 0.00 11.70

    9.36 0.00 9.365.38 0.00 5.385.72 0.00 5.72

    39.00 0.00 39.006.86 0.00 6.86

    15.63 0.00 15.637.49 0.00 7.49

    16.85 0.00 16.859.13 0.00 9.13

    13.34 0.00 13.346.24 0.00 6.242.81 0.00 2.814.21 0.00 4.21

  • 7/29/2019 PRESUPUESTO 20013

    64/114

  • 7/29/2019 PRESUPUESTO 20013

    65/114

    #REF!

  • 7/29/2019 PRESUPUESTO 20013

    66/114

    0.00 124.67 60.000.00 90.67 45.000.00 90.67 45.00

    0.00 124.67 60.000.00 170.00 80.00

    600.67 290.000.00 336.37 449.50 785.87

    0.000.000.00 203.520.00 138.240.00 203.520.00 19.20

    0.00 564.48 316.110.000.23

    2.000.186.000.00

    15.842.528.502.04

    37.31

    0.00 37.31 1,906.69 0.00 4,166.40

  • 7/29/2019 PRESUPUESTO 20013

    67/114

    150.53 47.52 297.60172.03 0.00 297.60

    0.00 95.04 0.002,229.25 142.56 4,761.60

    19.71 107.71 337.28 3.60 38.4025.98 161.57 337.28 5.28 51.8445.70 269.28 674.56 989.54 8.88 90.24

    47.49 2.12 20.6863.08 2.82 23.6883.87 3.74 29.9273.11 3.26 26.7253.76 2.40 19.8463.08 2.82 23.6847.49 2.12 20.68

    431.87 19.28 165.20

    1,193.42 20.20 87.19 13.56 169.52986.87 16.71 72.10 11.21 140.18849.16 14.37 62.04 9.65 120.62

    1,193.42 20.20 87.19 13.56 169.520.00 0.00 0.00 0.00 0.00

    731.32 11.15 60.09 8.31 103.88731.32 11.15 60.09 8.31 103.88

    5,685.50 93.78 428.72 6,208.00 64.61 807.60

    320.32 394.32 5.72 60.06320.32 394.32 5.72 60.06192.64 252.96 3.44 36.12192.64 252.96 3.44 36.12192.64 252.96 3.44 36.12

    192.64 252.96 3.44 36.12192.64 252.96 3.44 36.12

    85.42 148.80 1.04 13.5285.42 148.80 1.04 13.5285.42 148.80 1.04 13.5285.42 148.80 1.04 13.5224.64 57.04 0.30 3.9024.64 57.04 0.30 3.9072.28 128.96 0.88 11.4472.28 128.96 0.88 11.4478.85 138.88 0.96 12.48

    806.40 932.48 14.40 151.2062.12 114.08 0.90 11.52

    631.68 1,108.56 11.28 118.44758.02 0.00 13.54 112.8089.00 1,946.80 1.19 29.8085.42 1,966.02 1.14 28.60

    168.45 3,955.60 2.26 56.404,819.29 13,183.06 18,002.35 80.82 906.72

  • 7/29/2019 PRESUPUESTO 20013

    68/114

    PVC 2" PVC 3" PVC4 "20.00 0.00 30.0030.00 15.00 40.0040.00 15.00 50.0050.00 15.00 60.0060.00 15.00 70.0070.00 15.00 80.0080.00 15.00 90.0090.00 15.00 100.00

    440.00 105.00 520.00

    88.00 21.00 104.00

    desague

  • 7/29/2019 PRESUPUESTO 20013

    69/114

  • 7/29/2019 PRESUPUESTO 20013

    70/114

  • 7/29/2019 PRESUPUESTO 20013

    71/114

  • 7/29/2019 PRESUPUESTO 20013

    72/114

    0.000.000.00

    0.000.000.00

    40.32 456.96

  • 7/29/2019 PRESUPUESTO 20013

    73/114

    3.36 36.482.40 38.400.72 15.36

    7,133.41 46.80 547.20

    5,653.20

  • 7/29/2019 PRESUPUESTO 20013

    74/114

    CODIGO

    10-00000110-000027

    10-00004210-00001710-00003210-00004710-00002210-00005710-00005210-000054

    22-000047

    24-00000224-00004124-00009924-00014724-000146

    50-000091

    32-00004732-000023

    34-000023

    38-00010538-00007938-00011238-000107

    46-000027

    44-00001044-00001444-000094

    66-00003866-00001566-00001266-00000866-00003266-000019

    68-000016

    53-000049

  • 7/29/2019 PRESUPUESTO 20013

    75/114

    53-00021453-00013353-00009153-00001153-00001853-00022053-000022

    53-00002153-00001653-00001553-00016253-00000153-00019553-00004753-00004853-00001053-00023353-00002753-00020353-00009653-00002353-00007653-00001953-00005453-00005753-00005953-00006153-00006353-00006553-000066

    58-000025

    58-000043

    60-00001060-00001860-00002360-00021860-00019960-00007260-00004160-00004060-000128

    60-000102

    60-00010460-00010460-00006160-00006360-00000560-00000760-00021460-00021260-00013360-000135

  • 7/29/2019 PRESUPUESTO 20013

    76/114

    60-00021360-00003560-00001360-00003660-00011260-00011160-000110

    60-00010960-00010860-00010760-00010660-00010560-000104

  • 7/29/2019 PRESUPUESTO 20013

    77/114

    DESCRIPCION

    ESTRUCTURASAcero en columnas, habilitacin y colocacimConcreto columna f'c = 210 Kg/cm2

    Encofrado / desencofrado, columna con madera tornillo en brutoAcero en vigas, habilitacin y colocacinConcreto en vigas f'c = 210 Kg/cm2Encofrado / desencofrado de vigas con madera tornillo

    Acero en losa aligerada, habilitacin y colocacinConcreto losa aligerada f'c=210 kg/cm2Encofrado/desencofrado de losa aligerada, madera tornillo en brutoLadrillo para techo 15x30x30 cm. de arcilla

    ARQUITECTURAMUROS / TABIQUERIA Y ALBA ILERIAMuro de ladrillo k.k. de soga tipo iv mezcla c:c:a 1:2:9 para tarrajeo

    REVOQUES Y ENLUCIDO

    Tarrajeo frotachado, muros interiores ( C:A ) 1:5Tarrajeo frotachado, muros Exteriores ( C:A ) 1:5Tarrajeo de columnas, ( C:A ) 1:5 , espesor = 1.5cmTarrajeo de Cielo Raso, ( C:A ) 1:5 , espesor = 1.5cm ( en interior )Vestidura de derrames en puertas, ventanas y vanos

    PISOSPiso de cermica de 30x30cm tipo celima

    ZOCALOS Y REVESTIMIENTOSEnchape cermica de 30x30cm tipo celimaZcalo de maylica de color 15x15 de 1ra

    REVESTIMIENTO DE PASOS Y CONTRAPASOSPasos y contrapasos de cermico 20x20cm pasos=30cm, contrapasos=15cm

    CARPINTERIA DE MADERAPuerta apanelada madera caoba marco 2"x 4" Laqueada y barnizadaPuertas contraplacadas espesor=45mm, con triplay lupuna 6 mmRepostero c/puertas de melamine 19mm, tablero post-formado, fondo 0.60mCloset c/puertas de melamine 19mm c/cajones y accesorios cromados, fondo 0.60m

    VIDRIOSVidrio crudo bronce o gris de 6mm

    CERRAJERIABisagras capuchinas aluminizadas 3 1/2"Cerradura para puertas interiores, Tipo YALECerradura empotrada p/principal, 3 golpes Tipo YALE

    APARATOS SANITARIOS Y ACCESORIOSInodoro rapid jet, blanco trebolLavat.manantial top piece std esp.trebolDucha 1.20x0.80 hecha en obraLavatorio de cocina acero inoxidable 1 pozaLlav.bar pico girat. 5/8" Ipanema cromadaGriferia vainsa mezcladora de ducha

    PINTURAPintura ltex supermate vencedor con base de imprimante

    INSTALACIONES ELECTRICASCaja de pase 0.40x0.40x0.15

  • 7/29/2019 PRESUPUESTO 20013

    78/114

    Caja de pase de 100x100x50Caja de paso 150x150x100Caja de paso para telfono, f.c. 0.6 x 0.35 x 0.15 (externosCentros de luz y braquetes, suministro e instalacinConductor a tierra 1x10 mm2 desnudo, suministro e instalacinConductor a tierra 1x16 mm2 desnudo, suministro e instalacinInterruptor conmutacin doble, suministro y colocacin

    Interruptor conmutacin simple, suministro y colocacinInterruptor dobleInterruptor simple, suministro y colocacinInterruptor termomegnetico monofsica 2x40amp.Salida de techo c/tubo.sel. cable tw12 cajas livianasSalida para alumbrado en paredSalida para antena t.v.Salida para luz de conmutacinSalida para telfonoSalida para timbreSalida para tomacorrienteSalida para tomacorriente estabilizadoTomacorriente bipolar simple, (0.10x0.05) 10a.220vTomacorriente doble, suministro y colocacinTubera pvc-sap 100 mmTubera pvc-sap 19 mmTubera pvc-sap 35mmTubera pvc-sap 80mmTubera pvc-sel 25mmCable No. 10Cable No. 12Cable No. 14Cable No. 16

    INSTALACIONES ELECTROMECANICASAscensor con Capacidad para seis ( 06 ), personas - 07 Pisos

    Suministro e Instalacin de Equipo Contra IncendioINSTALACIONES SANITARIASCaja ciega de registro(10"x20")Caja de concreto 0.20x0.20 c/tap a mortero 1:4Caja de desag 10" x 20"Caja de registro 0.30 x 0.60 ciega con registro roscado de 4"Caja de registro 0.60 x 0.60 tapa concreCaja de registro 10" x 24"Codo 1 1/2" pvc salCodo 2 1/2 - 1 1/2"Codo 45 pvc desag sal de 3"

    Codo 90 pvc de agua de 3/4", clase 10 suminist e instalacin

    Codo de 90 pvc desag de 3", suministro e instalacinCodo de 90 pvc desag de 3", suministro e instalacinRegistro 0 2" bronce roscadoRegistro de bronce roscado 4"Salida de agua fra pvc de 1/2"Salida de desag pvc de 2"Salida de desag pvc de 3"Salida de desague pvc de 4"Sombrero de ventilacin de 3", suministro e instalacinSombrero de ventilacin pvc de 4, suministro e instalacin

  • 7/29/2019 PRESUPUESTO 20013

    79/114

    Sumidero 2" bronceVlvula de compuerta de 1/2", de bronce suministro e instalac.Vlvula de compuerta bronce 1", suministro y colocacinVlvula de compuerta de 1 1/4", de bronce suministro e instalac.Vlvula check de bronce de 1", suministro e instalacinVlvula check de bronce de 1/2", suministro e instalacinTuberia PVC 1/2", clase 10

    Tuberia PVC 3/4", clase 10Tuberia PVC 1", clase 10Tuberia CPVC 1/2", clase 10Tuberia PVC 2", desagueTuberia PVC 3", desagueTuberia PVC 4", desague

  • 7/29/2019 PRESUPUESTO 20013

    80/114

    Und. M.OBRA EQUIPO MATERIALES Precio Unitario Metrado sub-TOTAL

    10,052.42KG 0.86 0.08 2.84 3.78 175.00 661.50M3 193.360 48.120 204.780 446.26 1.70 758.64

    M2 24.93 1.25 18.32 44.50 25.30 1,125.85Kg 0.86 0.08 3.03 3.97 499.00 1,981.03M3 86.260 23.540 203.290 313.09 3.00 939.27M2 26.60 0.00 22.23 48.83 3.90 190.44KG 0.86 0.05 2.79 3.70 184.00 680.80M3 86.070 19.350 203.060 308.48 4.32 1,332.63M2 15.96 0.80 11.57 28.33 62.00 1,756.46UN 0.64 0.02 0.83 1.49 420.00 625.80

    12,304.02

    M2 21.89 1.09 29.70 52.68 90.00 4,741.20 45.79

    M2 12.15 0.68 4.29 17.12 125.00 2,140.00 17.12M2 15.19 0.83 4.99 21.01 0.00 21.01M2 19.19 0.65 2.99 22.83 7.59 173.28 15.64M2 27.78 1.56 2.21 31.55 62.00 1,956.10 21.77ML 22.78 0.46 0.60 23.84 0.00 16.06

    M2 27.71 0.28 25.13 53.12 62.00 3,293.44 42.28

    M2 23.75 0.24 25.35 49.34 0.00 42.99M2 27.71 1.39 23.66 52.76 0.00 52.76

    ML 41.57 0.42 13.82 55.81 0.00 55.81

    M2 187.37 1.87 190.42 379.66 0.00 379.66M2 87.58 9.02 116.00 212.60 0.00 212.60ML 279.00 23.94 259.00 561.94 0.00 561.94ML 487.82 23.97 313.73 825.52 0.00 672.93

    M2 18.00 3.38 45.00 66.38 0.00 63.38

    UN 9.02 0.45 3.61 13.08 0.00 7.06UN 18.23 0.91 28.00 47.14 0.00 46.91PZ 41.57 0.00 46.50 88.07 0.00 70.50

    UN 49.45 2.47 86.91 138.83 0.00 134.38UN 98.91 4.95 60.63 164.49 0.00 110.58UN 182.25 9.11 125.00 316.36 0.00 314.11UN 91.12 4.56 117.32 213.00 0.00 181.88UN 91.12 2.73 55.89 149.74 0.00 118.62UN 91.12 4.56 290.00 385.68 0.00 354.56

    M2 9.12 0.46 2.47 12.05 0.000.00

    PT 18.23 0.91 85.42 104.56 0.00

  • 7/29/2019 PRESUPUESTO 20013

    81/114

    UN 18.23 0.91 5.98 25.12 0.00UN 45.83 2.29 17.62 65.74 0.00PT 28.65 1.43 17.88 47.96 0.00PT 45.83 2.29 11.06 59.18 0.00ML 2.15 0.11 3.88 6.14 0.00ML 2.15 0.11 2.88 5.14 0.00PT 45.83 2.29 35.11 83.23 0.00

    UN 45.83 2.29 27.42 75.54 0.00UN 45.83 2.29 27.42 75.54 0.00UN 45.83 2.29 14.20 62.32 0.00PZ 15.19 0.76 43.50 59.45 0.00PT 45.83 2.29 28.86 76.98 0.00PT 45.83 2.29 40.21 88.33 0.00PT 25.72 1.29 37.42 64.43 0.00PT 57.29 2.86 53.61 113.76 0.00PT 34.28 1.71 25.90 61.89 0.00UN 29.93 1.50 43.42 74.85 0.00PT 57.29 2.86 32.10 92.25 0.00PT 51.00 2.55 24.49 78.04 0.00PT 22.92 1.15 6.80 30.87 0.00PT 23.95 1.20 42.19 67.34 0.00ML 7.64 0.38 43.77 51.79 0.00ML 7.64 0.38 3.47 11.49 0.00ML 9.16 0.46 3.79 13.41 0.00ML 11.46 0.57 18.61 30.64 0.00ML 9.16 0.46 2.54 12.16 0.00ML 1.80 0.60 2.00 4.40 0.00ML 1.80 0.60 1.25 3.65 0.00ML 1.80 0.60 0.90 3.30 0.00ML 1.80 0.60 0.70 3.10 0.00

    0.00Und. 9,345.00 79,432.00 4,673.00 93,450.00 0.00

    Und. 5,200.00 44,200.00 2,600.00 52,000.00 0.000.00

    UN 152.78 7.64 78.13 238.55 0.00UN 61.18 3.06 2.80 67.04 0.00 124.24UN 110.66 5.53 13.72 129.91 0.00 155.53UN 152.78 7.64 86.58 247.00 0.00 157.64UN 152.78 7.64 62.05 222.47 0.00 157.64UN 76.39 3.82 107.11 187.32 0.00 108.82PZ 16.92 0.85 2.26 20.03 0.00 12.11PZ 22.55 1.13 6.55 30.23 0.00 16.68PZ 22.55 1.13 2.46 26.14 0.00 12.59

    PZ 22.55 1.13 3.37 27.05 0.00 11.80

    PZ 16.92 0.85 4.12 21.89 0.00 13.97PZ 16.92 0.85 4.12 21.89 0.00 13.97UN 22.55 1.13 7.21 30.89 0.00 23.34UN 22.55 1.13 8.62 32.30 0.00 24.75PT 67.66 3.38 8.84 79.88 0.00 27.22PT 57.29 2.86 23.78 83.93 0.00 41.64PT 57.29 2.86 33.57 93.72 0.00 51.43PT 57.29 2.86 47.78 107.93 0.00 65.64PZ 9.57 0.48 8.71 18.76 0.00 18.76PZ 9.57 0.48 14.81 24.86 0.00 24.86

  • 7/29/2019 PRESUPUESTO 20013

    82/114

    UN 22.55 1.13 3.87 27.55 0.00 20.00PZ 31.22 1.56 26.07 58.85 0.00 51.63UN 31.22 1.56 40.19 72.97 0.00 65.75UN 37.47 1.87 50.96 90.30 0.00 76.83PZ 31.22 1.56 29.97 62.75 0.00 55.53PZ 31.12 1.56 21.42 54.10 0.00 46.98ML. 4.00 1.25 1.50 6.75 0.00 5.50

    ML. 4.00 1.25 2.00 7.25 0.00 6.00ML. 4.00 1.25 2.50 7.75 0.00 6.50ML. 4.00 1.25 5.00 10.25 0.00 9.00ML. 4.00 1.25 2.50 7.75 0.00 6.50ML. 4.00 1.25 4.00 9.25 0.00 8.00ML. 4.00 1.25 6.00 11.25 0.00 10.00

  • 7/29/2019 PRESUPUESTO 20013

    83/114

    LADRILLO 0.49 3,500.00 1,715.00

    ARENA 38.14 3.20 122.05CEMENTO 23.00 18.00 414.00

    2,251.05

    CEMENTO 18.00 19.00 342.00ARENA 38.14 1.00 38.14PIEDRA CHANCADA 55.00 1.22 67.10

    447.24

    80.00 14.0050.00 14.00

    4,518.29

    0.25

  • 7/29/2019 PRESUPUESTO 20013

    84/114

    |

    PRECIOS ACTUALES

    PRECIOS ACTUALES

  • 7/29/2019 PRESUPUESTO 20013

    85/114

  • 7/29/2019 PRESUPUESTO 20013

    86/114

    1,120.00700.00

    1,820.00

    2,000.001,500.00

    612.004,112.003,412.00

  • 7/29/2019 PRESUPUESTO 20013

    87/114

    AREA DEL TERRENO: 220.00

    E-01 E-02 E-03 E-04 E-05 E-06 E-07

    Semi- Sotano 0.00 0.00 0.00 0.00 0.00 0.00 0.00Primer Piso 0.00 0.00 0.00 0.00 0.00 0.00 0.00Segundo Piso 0.00 0.00 0.00 0.00 0.00 0.00 0.00Tercer Piso 0.00 0.00 0.00 0.00 0.00 0.00 0.00Cuarto Piso 0.00 0.00 0.00 0.00 0.00 0.00 0.00Quinto Piso 0.00 0.00 0.00 0.00 0.00 0.00 0.00Sexto Piso 0.00 0.00 0.00 0.00 0.00 0.00 0.00Setimo Piso 0.00 0.00 0.00 0.00 0.00 0.00 0.00octavo 0.00 0.00 0.00 0.00 0.00 0.00 0.00azotea

    Azotea 0.00 0.00 0.00 0.00 0.00 0.00 0.00

    Area Total

    AREA CONSTRUIDA: 3,192.07AREA VENDIBLE 3,192.07AREA

  • 7/29/2019 PRESUPUESTO 20013

    88/114

    E-08 Dpto. 001 Dpto.002 A. Comun Vendible A. Libre

    0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 406.610.00 0.00 0.00 0.00 397.190.00 0.00 0.00 0.00 397.190.00 0.00 0.00 0.00 397.190.00 0.00 0.00 0.00 397.190.00 0.00 0.00 0.00 397.190.00 0.00 0.00 0.00 397.190.00 0.00 0.00 0.00 397.19

    5.16

    0.00 0.00 0.00 0.00 0.00 220.00

    0.00 3,192.07

  • 7/29/2019 PRESUPUESTO 20013

    89/114

    435.00 0.00 220.00 0.00435.00 176,875.35 138.49 0.00435.00 172,775.48 166.67 0.00435.00 172,775.48 166.67 0.00435.00 172,775.48 166.67 0.00435.00 172,775.48 166.67 0.00435.00 172,775.48 166.67 0.00435.00 172,775.48 166.67 0.00

    435.00 0.00 27.65 0.00

    1,213,528.20 1,386.16

  • 7/29/2019 PRESUPUESTO 20013

    90/114

    220.00138.49166.67166.67166.67166.67166.67166.67

    27.65

  • 7/29/2019 PRESUPUESTO 20013

    91/114

    CODIGO

    02-000001

    02-00005602-00005702-00005102-00005302-000078

    04-000064

    06-00001306-00000206-00006906-000022

    06-000009

    09-00010609-00008909-00009109-00004009-00008309-000090

    11-00000311-00020711-00027311-00015811-00017811-00028711-00010211-00017511-00027211-00021210-00000110-00002710-00004210-00001710-00003210-00004710-00002210-000057

    10-00005210-00005410-00006010-00006310-00006610-00006910-00007210-000075

  • 7/29/2019 PRESUPUESTO 20013

    92/114

    22-000047

    24-00000224-00004124-00009924-000147

    24-000146

    50-000091

    32-00004732-000023

    34-000023

    38-00010538-00007938-00011238-000107

    46-000027

    44-00001044-00001444-000094

    66-00003866-00001566-00001266-00000866-000032

    66-000019

    68-000016

    53-00004953-00021453-00013353-00009153-00001153-00001853-00022053-00002253-000021

    53-00001653-00001553-00016253-00000153-00019553-00004753-00004853-00001053-00023353-000027

  • 7/29/2019 PRESUPUESTO 20013

    93/114

    53-00020353-00009653-00002353-00007653-00001953-00005453-00005753-00005953-00006153-00006353-00006553-000066

    58-00002558-000043

    60-00001060-00001860-00002360-000218

    60-00019960-00007260-00004160-00004060-00012860-00010260-00010460-00010460-00006160-00006360-00000560-00000760-000214

    60-00021260-00013360-00013560-00021360-00003560-00001360-00003660-00011260-00011160-00011060-00010960-00010860-000107

    60-00010660-00010560-000104

  • 7/29/2019 PRESUPUESTO 20013

    94/114

    DESCRIPCION

    ESTRUCTURASOBRAS PROVISIONALESGuardiana

    Agua para la construccinDesage para La construccin (Red)Caseta para oficina, almacn y guardianaCerco malla p/obra con postes de madera de 4x4Trazo y replanteo

    TRABAJOS PROVISIONALESEncofrado de calzaduras

    MOVIMIENTO DE TIERRASEliminacin de excedentes (equipo) d=10km.(zona urbana comercial)Excavacin de zanjas p/cimientos (manual hasta 1.00 m profundidad (a mano)Excavacin masiva e/p h=2.80m (equipo)Nivelacin riego y apisonado(manual)

    Perfilado y preparacin de zanja (equipo) agua / desageOBRAS DE CONCRETO SIMPLECimientos corrido, mezcla ( C:H) 1:12 + 30% piedra 8"Encofrado de sobrecimientos hasta 0.30m. de alturaContrapiso de 2 ", mezcla ( C:H ) 1:5Gradas de concreto f'c = 175 kg/cm2Sobrecimiento corrido, mezcla ( C:H) 1:18 + 25% piedra 3"Solado de concreto, e=3" para zapatas y vigas de cimentacion

    OBRAS DE CONCRETO ARMADOAcero en zapatasConcreto zapata, f'c 210 kg/cm2

    Acero en escalera habilitacin y colocacinConcreto escalera fc=210 kg/cm2, con equipoEncofrado de escaleras, (incluye desencofrado)

    Acero en cisterna, habilitacin y colocacinConcreto cisterna f'c = 210 kg/cm2Encofrado vigas de cimentacin

    Acero en vigas de cimentacin, habilitacin y colocacinConcreto viga de cimentacin, f'c 210 kg/cm2

    Acero en columnas, habilitacin y colocacimConcreto columna f'c = 210 Kg/cm2Encofrado / desencofrado, columna con madera tornillo en bruto

    Acero en vigas, habilitacin y colocacinConcreto en vigas f'c = 210 Kg/cm2Encofrado / desencofrado de vigas con madera tornillo

    Acero en losa aligerada, habilitacin y colocacinConcreto losa aligera f'c=210 kg/cm2

    Encofrado/desencofrado de losa aligerada, madera tornillo en brutoLadrillo para techo 15x30x30 cm. de arcilla

    Acero en placas, habilitacin y colocacinConcreto placas f'c=210 kg/cm2Encofrado/desencofrado de placas

    Acero en losa macisa, habilitacin y colocacinConcreto losa macisa f'c=210 kg/cm2Encofrado/desencofrado de losa macisa

    ARQUITECTURA

  • 7/29/2019 PRESUPUESTO 20013

    95/114

    MUROS / TABIQUERIA Y ALBA ILERIAMuro de ladrillo k.k. de soga tipo iv mezcla c:c:a 1:2:9 para tarrajeo

    REVOQUES Y ENLUCIDOTarrajeo frotachado, muros interiores ( C:A ) 1:5Tarrajeo frotachado, muros Exteriores ( C:A ) 1:5Tarrajeo de columnas, ( C:A ) 1:5 , espesor = 1.5cmTarrajeo de Cielo Raso, ( C:A ) 1:5 , espesor = 1.5cm ( en interior )

    Vestidura de derrames en puertas, ventanas y vanosPISOSPiso de cermica de 30x30cm tipo celima

    ZOCALOS Y REVESTIMIENTOSEnchape cermica de 30x30cm tipo celimaZcalo de maylica de color 15x15 de 1ra

    REVESTIMIENTO DE PASOS Y CONTRAPASOSPasos y contrapasos de cermico 20x20cm pasos=30cm, contrapasos=15cm

    CARPINTERIA DE MADERAPuerta apanelada madera caoba marco 2"x 4" Laqueada y barnizadaPuertas contraplacadas espesor=45mm, con triplay lupuna 6 mmRepostero c/puertas de melamine 19mm, tablero post-formado, fondo 0.60mCloset c/puertas de melamine 19mm c/cajones y accesorios cromados, fondo 0.60m

    VIDRIOSVidrio crudo bronce o gris de 6mm

    CERRAJERIABisagras capuchinas aluminizadas 3 1/2"Cerradura para puertas interiores, Tipo YALECerradura empotrada p/principal, 3 golpes Tipo YALE

    APARATOS SANITARIOS Y ACCESORIOSInodoro rapid jet, blanco trebolLavat.manantial top piece std esp.trebolDucha 1.20x0.80 hecha en obraLavatorio de cocina acero inoxidable 1 pozaLlav.bar pico girat. 5/8" Ipanema cromada

    Griferia vainsa mezcladora de duchaPINTURAPintura ltex supermate vencedor con base de imprimante

    INSTALACIONES ELECTRICASCaja de pase 0.40x0.40x0.15Caja de pase de 100x100x50Caja de paso 150x150x100Caja de paso para telfono, f.c. 0.6 x 0.35 x 0.15 (externosCentros de luz y braquetes, suministro e instalacinConductor a tierra 1x10 mm2 desnudo, suministro e instalacinConductor a tierra 1x16 mm2 desnudo, suministro e instalacinInterruptor conmutacin doble, suministro y colocacinInterruptor conmutacin simple, suministro y colocacin

    Interruptor dobleInterruptor simple, suministro y colocacinInterruptor termomegnetico monofsica 2x40amp.Salida de techo c/tubo.sel. cable tw12 cajas livianasSalida para alumbrado en paredSalida para antena t.v.Salida para luz de conmutacinSalida para telfonoSalida para timbreSalida para tomacorriente

  • 7/29/2019 PRESUPUESTO 20013

    96/114

    Salida para tomacorriente estabilizadoTomacorriente bipolar simple, (0.10x0.05) 10a.220vTomacorriente doble, suministro y colocacinTubera pvc-sap 100 mmTubera pvc-sap 19 mmTubera pvc-sap 35mmTubera pvc-sap 80mmTubera pvc-sel 25mmCable No. 10Cable No. 12Cable No. 14Cable No. 16

    INSTALACIONES ELECTROMECANICASAscensor con Capacidad para seis ( 06 ), personas - 07 PisosSuministro e Instalacin de Equipo Contra Incendio

    INSTALACIONES SANITARIASCaja ciega de registro(10"x20")Caja de concreto 0.20x0.20 c/tap a mortero 1:4Caja de desag 10" x 20"Caja de registro 0.30 x 0.60 ciega con registro roscado de 4"

    Caja de registro 0.60 x 0.60 tapa concreCaja de registro 10" x 24"Codo 1 1/2" pvc salCodo 2 1/2 - 1 1/2"Codo 45 pvc desag sal de 3"Codo 90 pvc de agua de 3/4", clase 10 suminist e instalacinCodo de 90 pvc desag de 3", suministro e instalacinCodo de 90 pvc desag de 3", suministro e instalacinRegistro 0 2" bronce roscadoRegistro de bronce roscado 4"Salida de agua fra pvc de 1/2"Salida de desag pvc de 2"Salida de desag pvc de 3"

    Salida de desague pvc de 4"Sombrero de ventilacin de 3", suministro e instalacinSombrero de ventilacin pvc de 4, suministro e instalacinSumidero 2" bronceVlvula de compuerta de 1/2", de bronce suministro e instalac.Vlvula de compuerta bronce 1", suministro y colocacinVlvula de compuerta de 1 1/4", de bronce suministro e instalac.Vlvula check de bronce de 1", suministro e instalacinVlvula check de bronce de 1/2", suministro e instalacinTuberia PVC 1/2", clase 10Tuberia PVC 3/4", clase 10Tuberia PVC 1", clase 10Tuberia CPVC 1/2", clase 10

    Tuberia PVC 2", desagueTuberia PVC 3", desagueTuberia PVC 4", desague

  • 7/29/2019 PRESUPUESTO 20013

    97/114

    Und. Metrado MES 001 MES 002 MES 003 MES 004 MES 005 MES 006

    Dia #REF! 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

    ML #REF! 15.00% 20.00% 15.00% 10.00% 10.00% 10.00%PT #REF! 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%M2 #REF! 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%ML #REF! 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%M2 #REF! 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

    M2 #REF! 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

    M3 #REF! 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%M3 #REF! 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%M3 #REF! 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%M2 #REF! 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

    ML #REF! 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

    M3 #REF! 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%M2 #REF! 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%m2 #REF! 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%M3 #REF! 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%M3 #REF! 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%M2 #REF! 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

    KG #REF! 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%M3 #REF! 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%KG #REF! 20.00% 20.00% 20.00% 20.00% 20.00% 0.00%M3 #REF! 20.00% 20.00% 20.00% 20.00% 20.00% 0.00%M2 #REF! 20.00% 20.00% 20.00% 20.00% 20.00% 0.00%KG #REF! 0.00% 100.00% 0.00% 0.00% 0.00% 0.00%M3 #REF! 0.00% 100.00% 0.00% 0.00% 0.00% 0.00%M2 #REF! 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%KG #REF! 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%M3 #REF! 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%KG 175.00 20.00% 20.00% 20.00% 20.00% 20.00% 0.00%M3 1.70 20.00% 20.00% 20.00% 20.00% 20.00% 0.00%M2 25.30 20.00% 20.00% 20.00% 20.00% 20.00% 0.00%Kg 499.00 0.00% 20.00% 20.00% 20.00% 20.00% 20.00%M3 3.00 0.00% 20.00% 20.00% 20.00% 20.00% 20.00%M2 3.90 0.00% 20.00% 20.00% 20.00% 20.00% 20.00%KG 184.00 0.00% 20.00% 20.00% 20.00% 20.00% 20.00%M3 4.32 0.00% 20.00% 20.00% 20.00% 20.00% 20.00%

    M2 62.00 0.00% 20.00% 20.00% 20.00% 20.00% 20.00%UN 420.00 0.00% 20.00% 20.00% 20.00% 20.00% 20.00%KG #REF! 20.00% 20.00% 20.00% 20.00% 20.00% 0.00%M3 #REF! 20.00% 20.00% 20.00% 20.00% 20.00% 0.00%M2 #REF! 20.00% 20.00% 20.00% 20.00% 20.00% 0.00%KG #REF! 0.00% 20.00% 20.00% 20.00% 20.00% 20.00%M3 #REF! 0.00% 20.00% 20.00% 20.00% 20.00% 20.00%M2 #REF! 0.00% 20.00% 20.00% 20.00% 20.00% 20.00%

  • 7/29/2019 PRESUPUESTO 20013

    98/114

    M2 90.00 0.00% 20.00% 20.00% 20.00% 20.00% 20.00%

    M2 125.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%M2 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%M2 7.59 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%M2 62.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

    ML 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

    M2 62.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

    M2 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%M2 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

    ML 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

    M2 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%M2 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%ML 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%ML 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

    M2 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

    UN 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%UN 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%PZ 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

    UN 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%UN 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%UN 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%UN 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%UN 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

    UN 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

    M2 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

    PT 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%UN 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%UN 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PT 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PT 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%ML 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%ML 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PT 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%UN 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%

    UN 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%UN 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PZ 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PT 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PT 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PT 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PT 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PT 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%UN 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PT 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%

  • 7/29/2019 PRESUPUESTO 20013

    99/114

    PT 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PT 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PT 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%ML 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%ML 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%ML 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%ML 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%ML 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%ML 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%ML 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%ML 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%ML 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%

    Und. 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%Und. 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

    UN 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%UN 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%UN 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%UN 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%

    UN 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%UN 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PZ 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PZ 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PZ 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PZ 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PZ 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PZ 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%UN 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%UN 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PT 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PT 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PT 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%

    PT 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PZ 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PZ 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%UN 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PZ 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%UN 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%UN 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PZ 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%PZ 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%ML. 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%ML. 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%ML. 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%ML. 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%

    ML. 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%ML. 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%ML. 0.00 10.00% 20.00% 20.00% 20.00% 20.00% 10.00%

  • 7/29/2019 PRESUPUESTO 20013

    100/114

    MES 007 MES 008 MES 009TOTAL POR

    PARTIDA

    0.00% 0.00% 0.00% 100.00%

    10.00% 5.00% 5.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%

    0.00% 0.00% 0.00% 100.00%

    0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%

    0.00% 0.00% 0.00% 100.00%

    0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%

    0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%

    0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%

  • 7/29/2019 PRESUPUESTO 20013

    101/114

    0.00% 0.00% 0.00% 100.00%

    100.00% 0.00% 0.00% 100.00%100.00% 0.00% 0.00% 100.00%100.00% 0.00% 0.00% 100.00%100.00% 0.00% 0.00% 100.00%

    100.00% 0.00% 0.00% 100.00%

    0.00% 100.00% 0.00% 100.00%

    0.00% 100.00% 0.00% 100.00%0.00% 100.00% 0.00% 100.00%

    0.00% 100.00% 0.00% 100.00%

    0.00% 0.00% 100.00% 100.00%0.00% 0.00% 100.00% 100.00%0.00% 0.00% 100.00% 100.00%0.00% 0.00% 100.00% 100.00%

    0.00% 0.00% 100.00% 100.00%

    0.00% 0.00% 100.00% 100.00%0.00% 0.00% 100.00% 100.00%0.00% 0.00% 100.00% 100.00%

    50.00% 50.00% 0.00% 100.00%50.00% 50.00% 0.00% 100.00%50.00% 50.00% 0.00% 100.00%50.00% 50.00% 0.00% 100.00%50.00% 50.00% 0.00% 100.00%

    50.00% 50.00% 0.00% 100.00%

    0.00% 0.00% 100.00% 100.00%

    0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%

    0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%

  • 7/29/2019 PRESUPUESTO 20013

    102/114

    0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%

    0.00% 50.00% 50.00% 100.00%0.00% 50.00% 50.00% 100.00%

    0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%

    0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%

    0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%

    0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%0.00% 0.00% 0.00% 100.00%

  • 7/29/2019 PRESUPUESTO 20013

    103/114

    CODIGO DESCRIPCION

    ESTRUCTURASOBRAS PROVISIONALES

    02-000001 Guardiana02-000056 Agua para la construccin02-000057 Desage para La construccin (Red)02-000051 Caseta para oficina, almacn y guardiana02-000053 Cerco malla p/obra con postes de madera de 4x402-000078 Trazo y replanteo

    TRABAJOS PROVISIONALES04-000064 Encofrado de calzaduras

    MOVIMIENTO DE TIERRAS06-000013 Eliminacin de excedentes (equipo) d=10km.(zona urbana comercial)06-000002 Excavacin de zanjas p/cimientos (manual hasta 1.00 m profundidad (a mano)06-000069 Excavacin masiva e/p h=2.80m (equipo)06-000022 Nivelacin riego y apisonado(manual)

    06-000009 Perfilado y preparacin de zanja (equipo) agua / desageOBRAS DE CONCRETO SIMPLE

    09-000106 Cimientos corrido, mezcla ( C:H) 1:12 + 30% piedra 8"09-000089 Encofrado de sobrecimientos hasta 0.30m. de altura09-000091 Contrapiso de 2 ", mezcla ( C:H ) 1:509-000040 Gradas de concreto f'c = 175 kg/cm209-000083 Sobrecimiento corrido, mezcla ( C:H) 1:18 + 25% piedra 3"09-000090 Solado de concreto, e=3" para zapatas y vigas de cimentacion

    OBRAS DE CONCRETO ARMADO11-000003 Acero en zapatas11-000207 Concreto zapata, f'c 210 kg/cm211-000273 Acero en escalera habilitacin y colocacin11-000158 Concreto escalera fc=210 kg/cm2, con equipo

    11-000178 Encofrado de escaleras, (incluye desencofrado)11-000287 Acero en cisterna, habilitacin y colocacin11-000102 Concreto cisterna f'c = 210 kg/cm211-000175 Encofrado vigas de cimentacin11-000272 Acero en vigas de cimentacin, habilitacin y colocacin11-000212 Concreto viga de cimentacin, f'c 210 kg/cm210-000001 Acero en columnas, habilitacin y colocacim10-000027 Concreto columna f'c = 210 Kg/cm210-000042 Encofrado / desencofrado, columna con madera tornillo en bruto10-000017 Acero en vigas, habilitacin y colocacin10-000032 Concreto en vigas f'c = 210 Kg/cm210-000047 Encofrado / desencofrado de vigas con madera tornillo10-000022 Acero en losa aligerada, habilitacin y colocacin

    10-000057 Concreto losa aligera f'c=210 kg/cm210-000052 Encofrado/desencofrado de losa aligerada, madera tornillo en bruto10-000054 Ladrillo para techo 15x30x30 cm. de arcilla10-000060 Acero en placas, habilitacin y colocacin10-000063 Concreto placas f'c=210 kg/cm210-000066 Encofrado/desencofrado de placas10-000069 Acero en losa macisa, habilitacin y colocacin10-000072 Concreto losa macisa f'c=210 kg/cm210-000075 Encofrado/desencofrado de losa macisa

    ARQUITECTURA

  • 7/29/2019 PRESUPUESTO 20013

    104/114

    MUROS / TABIQUERIA Y ALBAILERIA22-000047 Muro de ladrillo k.k. de soga tipo iv mezcla c:c:a 1:2:9 para tarrajeo

    REVOQUES Y ENLUCIDO24-000002 Tarrajeo frotachado, muros interiores ( C:A ) 1:524-000041 Tarrajeo frotachado, muros Exteriores ( C:A ) 1:524-000099 Tarrajeo de columnas, ( C:A ) 1:5 , espesor = 1.5cm24-000147 Tarrajeo de Cielo Raso, ( C:A ) 1:5 , espesor = 1.5cm ( en interior )24-000146 Vestidura de derrames en puertas, ventanas y vanos

    PISOS50-000091 Piso de cermica de 30x30cm tipo celima

    ZOCALOS Y REVESTIMIENTOS32-000047 Enchape cermica de 30x30cm tipo celima32-000023 Zcalo de maylica de color 15x15 de 1ra

    REVESTIMIENTO DE PASOS Y CONTRAPASOS34-000023 Pasos y contrapasos de cermico 20x20cm pasos=30cm, contrapasos=15cm

    CARPINTERIA DE MADERA38-000105 Puerta apanelada madera caoba marco 2"x 4" Laqueada y barnizada38-000079 Puertas contraplacadas espesor=45mm, con triplay lupuna 6 mm38-000112 Repostero c/puertas de melamine 19mm, tablero post-formado, fondo 0.60m38-000107 Closet c/puertas de melamine 19mm, fondo 0.60m

    VIDRIOS46-000027 Vidrio crudo bronce o gris de 6mmCERRAJERIA

    44-000010 Bisagras capuchinas aluminizadas 3 1/2"44-000014 Cerradura para puertas interiores, Tipo YALE44-000094 Cerradura empotrada p/principal, 3 golpes Tipo YALE

    APARATOS SANITARIOS Y ACCESORIOS66-000038 Inodoro rapid jet, blanco trebol66-000015 Lavat.manantial top piece std esp.trebol66-000012 Ducha 1.20x0.80 hecha en obra66-000008 Lavatorio de cocina acero inoxidable 1 poza66-000032 Llav.bar pico girat. 5/8" Ipanema cromada66-000019 Griferia vainsa mezcladora de ducha

    PINTURA68-000016 Pintura ltex supermate vencedor con base de imprimanteINSTALACIONES ELECTRICAS

    53-000049 Caja de pase 0.40x0.40x0.1553-000214 Caja de pase de 100x100x5053-000133 Caja de paso 150x150x10053-000091 Caja de paso para telfono, f.c. 0.6 x 0.35 x 0.15 (externos53-000011 Centros de luz y braquetes, suministro e instalacin53-000018 Conductor a tierra 1x10 mm2 desnudo, suministro e instalacin53-000220 Conductor a tierra 1x16 mm2 desnudo, suministro e instalacin53-000022 Interruptor conmutacin doble, suministro y colocacin53-000021 Interruptor conmutacin simple, suministro y colocacin53-000016 Interruptor doble

    53-000015 Interruptor simple, suministro y colocacin53-000162 Interruptor termomegnetico monofsica 2x40amp.53-000001 Salida de techo c/tubo.sel. cable tw12 cajas livianas53-000195 Salida para alumbrado en pared53-000047 Salida para antena t.v.53-000048 Salida para luz de conmutacin53-000010 Salida para telfono53-000233 Salida para timbre53-000027 Salida para tomacorriente53-000203 Salida para tomacorriente estabilizado53-000096 Tomacorriente bipolar simple, (0.10x0.05) 10a.220v

  • 7/29/2019 PRESUPUESTO 20013

    105/114

    53-000023 Tomacorriente doble, suministro y colocacin53-000076 Tubera pvc-sap 100 mm53-000019 Tubera pvc-sap 19 mm53-000054 Tubera pvc-sap 35mm53-000057 Tubera pvc-sap 80mm53-000059 Tubera pvc-sel 25mm53-000061 Cable No. 1053-000063 Cable No. 12

    53-000065 Cable No. 1453-000066 Cable No. 16

    INSTALACIONES ELECTROMECANICAS58-000025 Ascensor con Capacidad para seis ( 06 ), personas - 07 Pisos58-000043 Suministro e Instalacin de Equipo Contra Incendio

    INSTALACIONES SANITARIAS60-000010 Caja ciega de registro(10"x20")60-000018 Caja de concreto 0.20x0.20 c/tap a mortero 1:460-000023 Caja de desag 10" x 20"60-000218 Caja de registro 0.30 x 0.60 ciega con registro roscado de 4"60-000199 Caja de registro 0.60 x 0.60 tapa concre60-000072 Caja de registro 10" x 24"60-000041 Codo 1 1/2" pvc sal

    60-000040 Codo 2 1/2 - 1 1/2"60-000128 Codo 45 pvc desag sal de 3"60-000102 Codo 90 pvc de agua de 3/4", clase 10 suminist e instalacin60-000104 Codo de 90 pvc desag de 3", suministro e instalacin60-000104 Codo de 90 pvc desag de 3", suministro e instalacin60-000061 Registro 0 2" bronce roscado60-000063 Registro de bronce roscado 4"60-000005 Salida de agua fra pvc de 1/2"60-000007 Salida de desag pvc de 2"60-000214 Salida de desag pvc de 3"60-000212 Salida de desague pvc de 4"60-000133 Sombrero de ventilacin de 3", suministro e instalacin60-000135 Sombrero de ventilacin pvc de 4, suministro e instalacin60-000213 Sumidero 2" bronce60-000035 Vlvula de compuerta de 1/2", de bronce suministro e instalac.60-000013 Vlvula de compuerta bronce 1", suministro y colocacin60-000036 Vlvula de compuerta de 1 1/4", de bronce suministro e instalac.60-000112 Vlvula check de bronce de 1", suministro e instalacin60-000111 Vlvula check de bronce de 1/2", suministro e instalacin60-000110 Tuberia PVC 1/2", clase 1060-000109 Tuberia PVC 3/4", clase 1060-000108 Tuberia PVC 1", clase 1060-000107 Tuberia CPVC 1/2", clase 1060-000106 Tuberia PVC 2", desague60-000105 Tuberia PVC 3", desague60-000104 Tuberia PVC 4", desague

    COSTO DIRECTO

    G GENERALES + UTILIDAD

    SUBTOTAL

    IGV

    TOTAL

  • 7/29/2019 PRESUPUESTO 20013

    106/114

  • 7/29/2019 PRESUPUESTO 20013

    107/114

    MES 001 MES 002 MES 003 MES 004 MES 005 MES 006 MES 007

    #REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!

    0.00 0.00 0.00 0.00 0.00 0.00 0.00#REF! #REF! #REF! #REF! #REF! #REF! #REF!

    0.00 0.00 0.00 0.00 0.00 0.00 0.00#REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!

    #REF! #REF! #REF! #REF! #REF! #REF! #REF!0.00 0.00 0.00 0.00 0.00 0.00 0.00

    #REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!

    0.00 0.00 0.00 0.00 0.00 0.00 0.00#REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!

    #REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!

    132.30 132.30 132.30 132.30 132.30 0.00 0.00136.99 136.99 136.99 136.99 136.99 0.00 0.00219.96 219.96 219.96 219.96 219.96 0.00 0.00

    0.00 396.21 396.21 396.21 396.21 396.21 0.000.00 187.85 187.85 187.85 187.85 187.85 0.000.00 38.09 38.09 38.09 38.09 38.09 0.000.00 136.16 136.16 136.16 136.16 136.16 0.00

    0.00 266.53 266.53 266.53 266.53 266.53 0.000.00 351.29 351.29 351.29 351.29 351.29 0.000.00 223.44 223.44 223.44 223.44 223.44 0.00

    #REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!#REF! #REF! #REF! #REF! #REF! #REF! #REF!

    0.00 0.00 0.00 0.00 0.00 0.00 0.00

  • 7/29/2019 PRESUPUESTO 20013

    108/114

    0.00 0.00 0.00 0.00 0.00 0.00 0.000.00 845.64 845.64 845.64 845.64 845.64 0.00

    0.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 2,003.750.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 141.480.00 0.00 0.00 0.00 0.00 0.00 1,349.740.00 0.00 0.00 0.00 0.00 0.00 0.00

    0.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.00

    0.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.00

    0.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.00

    0.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.00

    0.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.00

    0.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.00

    0.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.00

    0.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.00

    0.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.00

    0.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.000.00 0.00 0.00