Presentation v Raghuraman SessionV
Transcript of Presentation v Raghuraman SessionV
-
8/12/2019 Presentation v Raghuraman SessionV
1/23
IndiaIndias Nuclears Nuclear ProgrammeProgramme
V RaghuramanV Raghuraman
Confederation of Indian IndustryConfederation of Indian Industry
Confederation of Indian Industry
-
8/12/2019 Presentation v Raghuraman SessionV
2/23
ENERGY SCENARIOENERGY SCENARIO
-
8/12/2019 Presentation v Raghuraman SessionV
3/23
GENERATING CAPACITY 147458 MW
Power Infrastructure in India (end Jan.09)
Source: CEA
(As on 31-01-09 )
FUEL MIX
RES** (MNRE)
, 13242.41, 9%
Hydro(Renewable) ,
36762.76, 25%Nuclear , 4120,
3%
Total Thermal ,
93332.64, 63%
Total Thermal Nuclear Hydro (Renewable) RES** (MNRE)
-
8/12/2019 Presentation v Raghuraman SessionV
4/23
Electricity Requirement 2031Electricity Requirement 2031 -- 3232
8% 9%
Total Energy Requirement 3880 4806
Energy Requirement at Bus Bar 3628 4493
592 733
778 960
Billion kWh
Projected Peak Demand (GW)
Installed Capacity Requirement (GW)
GDP Growth Rate
-
8/12/2019 Presentation v Raghuraman SessionV
5/23
190
226
157
213
117
300
220
320
100
150
200
250
300
350
DESPITE THE ECONOMIC SLOWDOWN, DEMAND WILLDESPITE THE ECONOMIC SLOWDOWN, DEMAND WILL
BE HIGHER THAN CURRENT ESTIMATESBE HIGHER THAN CURRENT ESTIMATES
* Including captive demand** See appendix for details on demand estimation approaches
Source: Central Electricity Authority (CEA); Global Insight (World Industry Monitor); Planning Commission; McKinsey analysis
Revised Likely rangeRevised Likely range
Peak demand estimates*
GW, 2007-2017
Adjusted comparable
economy approach**
Sectoral intensity
approach**
Integrated Energy Policy
CEA estimates
158
2012 20172007
Additional capacity
of ~240-265 GWrequired
-
8/12/2019 Presentation v Raghuraman SessionV
6/23
6
Expected Fuel Mix in Country (2031-32)
Source : Report on Integrated Energy Policy
With limited hydro capacity, generation from fossil
fuel and nuclear is bound to increase significantly.
-
8/12/2019 Presentation v Raghuraman SessionV
7/23
Potential of Nuclear Power in India
Resource Potential (GWe-Yr)
Uranium (78,000 tonnes metal) In PHWRs 330
(about10,000 MWe PHWRs.)
&
In FBRs - 42,200
Thorium(518,000 tonnes metal)In Breeders150,000*
(*This is equivalent to Indias total electricity requirements for
Several Thousand Years considering current consumption levels.)
-
8/12/2019 Presentation v Raghuraman SessionV
8/23
Nuclear Power Installed capacityNuclear Power Installed capacityPotential (GW)Potential (GW)
Year Unit
Optim isti c* Pessimisti c
2010 Gwe 11 9
2020 Gwe 29 21
2030 Gwe 63 48
2040 Gwe 131 104
2050 Gwe 275 208
Source: DOAE
* It is assumed that India will be able to import 8000 MW of LWRswith fuel over the next ten years.
Scenario
-
8/12/2019 Presentation v Raghuraman SessionV
9/23
Nuclear Energy in IndiaNuclear Energy in India
7
NARORA
440 MWe ( 2x220)
17 NUCLEAR POWER PLANTS UNITS IN OPERATION
RAWATBHATA
740 MWe
(1x100+1x200+2x220)
KAIGA
660 MWe (3x220)
KALPAKKAM
440 MWe (2x220)
KAKRAPAR
440 MWe (2X220)TARAPUR1400 MWe
(2x160 + 2x540*)
-
8/12/2019 Presentation v Raghuraman SessionV
10/23
Nuclear Energy in IndiaNuclear Energy in IndiaConti..Conti..
15
6 NUCLEAR POWER UNITS UNDER CONSTRUCTION
RAWATBHATA
440MWe (2X220)
KUDANKULAM
2000 MWe (2x1000)
KAIGA
220 MWe(1x220)
KALPAKKAM
500 MWe (1x500)
-
8/12/2019 Presentation v Raghuraman SessionV
11/23
Nuclear Energy in IndiaNuclear Energy in IndiaConti..Conti..
28
Narora, UP2 (440 MWe) 2 (1400 MWe)
IN OPERATION
UNDER CONSTRUCTION
LIKELY ADDITIONS
NUCLEAR POWER PLANTS PLANNED
Rawatbhatajasthan3 (640 MWe)
2(440 MWe)
2(1400MWe)
Kudankulam, TN
2 (2000 MWe)
4 (4000 MWe)
Kaiga,Karnataka2 (440 MWe)2 (440 MWe)2 (1400 MWe)
Kalpakkam, TN2 (440 MWe)1 (500 MWe)2 (1000 MWe)
Kakrapar, Gujarat
2 (440 MWe)2 (1400 MWe)
Tarapur, Maharashtr a3 (860 MWe)1 (540 MWe)3 (2300 MWe)
Jaitapur, Maharashtra
6 (6000-8000 MWe)
SITES ALREADY APPROVED FOR PRE-PROJECT ACTIVITIES
RAWATBHATA
1400 MWe
KUDANKULAM
2000 MWe
KAKRAPAR
1400 MWeJAITAPUR
2000 MWe
-
8/12/2019 Presentation v Raghuraman SessionV
12/23
-
8/12/2019 Presentation v Raghuraman SessionV
13/23
Nuclear Energy in IndiaNuclear Energy in India
6
Three Stage Nuclear Power Program
-
8/12/2019 Presentation v Raghuraman SessionV
14/23
Ownership Models
All operating nuclear power plants owned operated by NPCIL
FBR under construction is owned will be operated by BHAVINI
Presently ownership is limited by law to Government of India or,A Government Company
NTPC as a Government Company proposes to participate in NuclearPower Generation
CurrentSituationinNuclearPowerGenerationinIndia
-
8/12/2019 Presentation v Raghuraman SessionV
15/23
15
Project Execution Models
Indigenous nuclear power plants executed on multi-package model
Plants supplied by overseas entities executed on E P or EPC basis
CurrentSituationinNuclearPowerGenerationinIndia
-
8/12/2019 Presentation v Raghuraman SessionV
16/23
16
Prospective Ownership Modelsrospective Ownership Models
Existing DAE Corporationsxisting DAE Corporationse.g., NPCIL, BHAVINI.g., NPCIL, BHAVINI
New Government ownedew Government owned SPVsPVs created under DAE auspicesreated under DAE auspices Nonon-DAE Government CorporationsAE Government Corporations
e.g., NTPC.g., NTPC Publicublic Private Partnerships (PPP)rivate Partnerships (PPP) Private Ownershiprivate OwnershipDomestic / Overseas / JVomestic / Overseas / JV
Emerging trends in Nuclear Power Generation in India
-
8/12/2019 Presentation v Raghuraman SessionV
17/23
-
8/12/2019 Presentation v Raghuraman SessionV
18/23
18
Issues requiring Discussion and Resolutionssues requiring Discussion and Resolution Amendment to Atomic Energy Actmendment to Atomic Energy Act Public Liabilityublic Liability Process for Promoter Selectionrocess for Promoter Selection
Prere-qualification Criteriaualification Criteria Eligibility Criteria for Overseas Investors Partnersligibility Criteria for Overseas Investors Partners Bidding and Bid Evaluation Processidding and Bid Evaluation Process Acceptable Technology Optionscceptable Technology Options
Nomination of Prospective Sitesomination of Prospective Sites Fuel Procurement Supply and Pricinguel Procurement Supply and Pricing
Emerging trends in Nuclear Power Generation in India
-
8/12/2019 Presentation v Raghuraman SessionV
19/23
19
Issues requiring Discussion and Resolution ( contdssues requiring Discussion and Resolution ( contd. Spent Fuel Managementpent Fuel Management Project Contracting Execution Strategiesroject Contracting Execution Strategies Fiscal Incentivesiscal Incentives AERB Approval Requirements and ProcessesERB Approval Requirements and Processes Uniform and Consistent Design Basis Criterianiform and Consistent Design Basis Criteria
Indigenous Content Maximizationndigenous Content Maximization Protection against Terrorist Attacksrotection against Terrorist Attacks
Emerging trends in Nuclear Power Generation in India
-
8/12/2019 Presentation v Raghuraman SessionV
20/23
20
Front End Work to be undertaken by Indian Governmentront End Work to be undertaken by Indian Government Appointment of a Nodal Agencyppointment of a Nodal Agency Nomination of Potential Sitesomination of Potential Sites
Site Evaluation Studiesite Evaluation Studies Land Availabilityand Availability Population Environmental Impactopulation Environmental Impact Geoeo-political Strategic Aspectsolitical Strategic Aspects Seismologyeismology Onn-shore and Offhore and Off-shore Geologyhore Geology Topographyopography Bathymetryathymetry Oceanographyceanography Meteorologyeteorology Flood Level Datalood Level Data Fresh Water Availabilityresh Water Availability Power Evacuationower Evacuation Transportation Logisticsransportation Logistics
AERB ApprovalERB Approval
Emerging trends in Nuclear Power Generation in India
-
8/12/2019 Presentation v Raghuraman SessionV
21/23
21
Formation of Shell Companiesormation of Shell Companies
Land Acquisition and Developmentand Acquisition and Development
Development of Plant Design Basesevelopment of Plant Design Bases
Enunciation of Principles of PPAnunciation of Principles of PPA
Development of Tendering Norms Conditions and Bidevelopment of Tendering Norms Conditions and Bid-qualificationualificationSelection processeselection processes
Front End Work to be undertaken by Indian GovernmentFront End Work to be undertaken by Indian Government
( contd. )( contd. )
Emerging trends in Nuclear Power Generation in India
-
8/12/2019 Presentation v Raghuraman SessionV
22/23
22
Adaptation of Standard Designs to Indian Conditionsdaptation of Standard Designs to Indian Conditions Evaluation of Indian Manufacturing and Construction Capabilitiesvaluation of Indian Manufacturing and Construction Capabilities
CapacitiesCapacities
Firming up Scope and Details of Procurement of Equipment andirming up Scope and Details of Procurement of Equipment andServices from Indiaervices from India
Basic Engineering for Site Dependentasic Engineering for Site Dependent BoPoP Facilities in respect ofacilities in respect ofIdentified Sitesdentified Sites
Suggested Initiatives for OverseasSuggested Initiatives for Overseas CorporatesCorporates
Emerging trends in Nuclear Power Generation in India
-
8/12/2019 Presentation v Raghuraman SessionV
23/23
THANK YOUTHANK YOU