S10 Página 1 ING. CARLOS OLIVOS LARA CIP:56310 PRESUPUESTO OBRA : CONSTRUCCION Y EQUIPAMIENTO LABORATORIOS DE QUIMICA, METODOS, AUTOMATIZACION Y FISICA CLIENTE : UNIVERSIDAD NACIONAL DE INGENIERIA - FIIS DEPARTAMENTO :LIMA PROVINCIA : LIMA DISTRITO : SAN MARTIN DE PORRAS COSTOS AL : 30/11/2010 INSTALACIONES SANITARIAS 004 Subpresupuesto Precio S/. Parcial S/. Item Descripción Und. Metrado SISTEMA DE AGUA FRIA 25 31,468.45 3,177.72 63.00 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP - MANO DE OBRA pto 25.01 50.44 196.86 34.00 CODO DE F.G. DE 1/2" und 25.02 5.79 87.84 8.00 CODO DE F.G. DE 1" und 25.03 10.98 280.98 21.00 CODO DE F.G. DE 1 1/4" und 25.04 13.38 144.60 10.00 CODO DE F.G. DE 2" und 25.05 14.46 35.44 2.00 CODO DE F.G. DE 2 1/2" und 25.06 17.72 4.22 1.00 REDUCCION DE F.G. DE 1.1/2" A 1" und 25.07 4.22 96.84 3.00 NIPLE DE 2" CON PLANCHA ROMPE AGUA DE F.G. und 25.08 32.28 114.56 2.00 NIPLE DE 2 1/2" CON PLANCHA ROMPE AGUA DE F.G. und 25.09 57.28 1,067.54 108.60 RED DE DISTRIBUCION TUBERIA DE 1/2" PVC-SAP m 25.10 9.83 1,043.52 96.00 RED DE DISTRIBUCION TUBERIA DE 3/4" PVC-SAP m 25.11 10.87 71.70 6.00 RED DE DISTRIBUCION TUBERIA DE 1" PVC-SAP m 25.12 11.95 814.66 52.90 RED DE DISTRIBUCION TUBERIA DE 1 1/4" PVC-SAP m 25.13 15.40 2,688.42 153.80 RED DE DISTRIBUCION TUBERIA DE 1 1/2" PVC-SAP m 25.14 17.48 1,242.54 54.00 RED DE DISTRIBUCION TUBERIA DE 2" PVC-SAP m 25.15 23.01 104.80 5.00 RED DE DISTRIBUCION TUBERIA F.G. DE 2" m 25.16 20.96 47.26 2.00 RED DE DISTRIBUCION TUBERIA F.G. DE 2 1/2" m 25.17 23.63 120.96 96.00 CODO PVC-SAP SP AGUA DE 1/2" und 25.18 1.26 5.37 3.00 CODO PVC-SAP SP AGUA DE 3/4" und 25.19 1.79 18.90 6.00 CODO PVC-SAP SP AGUA DE 1" und 25.20 3.15 576.84 57.00 CODO PVC-SAP SP AGUA DE 1 1/4" und 25.21 10.12 567.32 52.00 CODO PVC-SAP SP AGUA DE 1 1/2" und 25.22 10.91 59.04 4.00 CODO PVC-SAP SP AGUA DE 2" und 25.23 14.76 3.92 2.00 TEE PVC SAP SP PARA AGUA DE 1/2" und 25.24 1.96 18.69 7.00 TEE PVC SAP SP PARA AGUA DE 3/4" und 25.25 2.67 16.72 4.00 TEE PVC SAP SP PARA AGUA DE 1" und 25.26 4.18 155.19 21.00 TEE PVC SAP SP PARA AGUA DE 1 1/4" und 25.27 7.39 231.00 30.00 TEE PVC SAP SP PARA AGUA DE 1 1/2" und 25.28 7.70 108.99 9.00 TEE PVC SAP SP PARA AGUA DE 2" und 25.29 12.11 14.83 1.00 TEE PVC SAP SP PARA AGUA DE 2.1/2" und 25.30 14.83 6.96 6.00 UNION SIMPLE PVC-P SP P/AGUA DE 1/2" und 25.31 1.16 18.48 14.00 UNION SIMPLE PVC-P SP P/AGUA DE 3/4" und 25.32 1.32 9.78 6.00 UNION SIMPLE PVC-P SP P/AGUA DE 1" und 25.33 1.63 61.50 10.00 UNION SIMPLE PVC-P SP P/AGUA DE 1 1/4" und 25.34 6.15 32.85 5.00 UNION SIMPLE PVC-P SP P/AGUA DE 1 1/2" und 25.35 6.57 68.55 15.00 UNION SIMPLE PVC-P SP P/AGUA DE 2" und 25.36 4.57 14.40 2.00 UNION UNIVERSAL DE F.G. DE 1" und 25.37 7.20 25.60 2.00 UNION UNIVERSAL DE F.G. DE 2" und 25.38 12.80 531.63 9.00 VALVULA ESFERICA DE BRONCE C/ACC. DE 1/2" und 25.39 59.07 387.85 5.00 VALVULA ESFERICA DE BRONCE C/ACC. DE 3/4" und 25.40 77.57 106.51 1.00 VALVULA ESFERICA DE BRONCE C/ACC. DE 1" und 25.41 106.51 867.20 5.00 VALVULA ESFERICA DE BRONCE C/ACC. DE 1 1/4" und 25.42 173.44 3,612.85 19.00 VALVULA ESFERICA DE BRONCE C/ACC. DE 1 1/2" und 25.43 190.15 1,089.00 5.00 VALVULA ESFERICA DE BRONCE C/ACC. DE 2" und 25.44 217.80 1,389.48 6.00 VALVULA CHECK DE 2" und 25.45 231.58

description

PRES-IISS

Transcript of PRES-IISS

  • S10 Pgina 1ING. CARLOS OLIVOS LARA CIP:56310

    PRESUPUESTOOBRA : CONSTRUCCION Y EQUIPAMIENTO LABORATORIOS DE QUIMICA, METODOS, AUTOMATIZACION Y FISICACLIENTE : UNIVERSIDAD NACIONAL DE INGENIERIA - FIISDEPARTAMENTO :LIMA PROVINCIA : LIMA DISTRITO : SAN MARTIN DE PORRASCOSTOS AL : 30/11/2010

    INSTALACIONES SANITARIAS004Subpresupuesto

    Precio S/. Parcial S/.Item Descripcin Und. Metrado

    SISTEMA DE AGUA FRIA25 31,468.45

    3,177.7263.00 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP - MANO DE OBRA pto25.01 50.44

    196.8634.00 CODO DE F.G. DE 1/2" und25.02 5.79

    87.848.00 CODO DE F.G. DE 1" und25.03 10.98

    280.9821.00 CODO DE F.G. DE 1 1/4" und25.04 13.38

    144.6010.00 CODO DE F.G. DE 2" und25.05 14.46

    35.442.00 CODO DE F.G. DE 2 1/2" und25.06 17.72

    4.221.00 REDUCCION DE F.G. DE 1.1/2" A 1" und25.07 4.22

    96.843.00 NIPLE DE 2" CON PLANCHA ROMPE AGUA DE F.G. und25.08 32.28

    114.562.00 NIPLE DE 2 1/2" CON PLANCHA ROMPE AGUA DE F.G. und25.09 57.28

    1,067.54108.60 RED DE DISTRIBUCION TUBERIA DE 1/2" PVC-SAP m25.10 9.83

    1,043.5296.00 RED DE DISTRIBUCION TUBERIA DE 3/4" PVC-SAP m25.11 10.87

    71.706.00 RED DE DISTRIBUCION TUBERIA DE 1" PVC-SAP m25.12 11.95

    814.6652.90 RED DE DISTRIBUCION TUBERIA DE 1 1/4" PVC-SAP m25.13 15.40

    2,688.42153.80 RED DE DISTRIBUCION TUBERIA DE 1 1/2" PVC-SAP m25.14 17.48

    1,242.5454.00 RED DE DISTRIBUCION TUBERIA DE 2" PVC-SAP m25.15 23.01

    104.805.00 RED DE DISTRIBUCION TUBERIA F.G. DE 2" m25.16 20.96

    47.262.00 RED DE DISTRIBUCION TUBERIA F.G. DE 2 1/2" m25.17 23.63

    120.9696.00 CODO PVC-SAP SP AGUA DE 1/2" und25.18 1.26

    5.373.00 CODO PVC-SAP SP AGUA DE 3/4" und25.19 1.79

    18.906.00 CODO PVC-SAP SP AGUA DE 1" und25.20 3.15

    576.8457.00 CODO PVC-SAP SP AGUA DE 1 1/4" und25.21 10.12

    567.3252.00 CODO PVC-SAP SP AGUA DE 1 1/2" und25.22 10.91

    59.044.00 CODO PVC-SAP SP AGUA DE 2" und25.23 14.76

    3.922.00 TEE PVC SAP SP PARA AGUA DE 1/2" und25.24 1.96

    18.697.00 TEE PVC SAP SP PARA AGUA DE 3/4" und25.25 2.67

    16.724.00 TEE PVC SAP SP PARA AGUA DE 1" und25.26 4.18

    155.1921.00 TEE PVC SAP SP PARA AGUA DE 1 1/4" und25.27 7.39

    231.0030.00 TEE PVC SAP SP PARA AGUA DE 1 1/2" und25.28 7.70

    108.999.00 TEE PVC SAP SP PARA AGUA DE 2" und25.29 12.11

    14.831.00 TEE PVC SAP SP PARA AGUA DE 2.1/2" und25.30 14.83

    6.966.00 UNION SIMPLE PVC-P SP P/AGUA DE 1/2" und25.31 1.16

    18.4814.00 UNION SIMPLE PVC-P SP P/AGUA DE 3/4" und25.32 1.32

    9.786.00 UNION SIMPLE PVC-P SP P/AGUA DE 1" und25.33 1.63

    61.5010.00 UNION SIMPLE PVC-P SP P/AGUA DE 1 1/4" und25.34 6.15

    32.855.00 UNION SIMPLE PVC-P SP P/AGUA DE 1 1/2" und25.35 6.57

    68.5515.00 UNION SIMPLE PVC-P SP P/AGUA DE 2" und25.36 4.57

    14.402.00 UNION UNIVERSAL DE F.G. DE 1" und25.37 7.20

    25.602.00 UNION UNIVERSAL DE F.G. DE 2" und25.38 12.80

    531.639.00 VALVULA ESFERICA DE BRONCE C/ACC. DE 1/2" und25.39 59.07

    387.855.00 VALVULA ESFERICA DE BRONCE C/ACC. DE 3/4" und25.40 77.57

    106.511.00 VALVULA ESFERICA DE BRONCE C/ACC. DE 1" und25.41 106.51

    867.205.00 VALVULA ESFERICA DE BRONCE C/ACC. DE 1 1/4" und25.42 173.44

    3,612.8519.00 VALVULA ESFERICA DE BRONCE C/ACC. DE 1 1/2" und25.43 190.15

    1,089.005.00 VALVULA ESFERICA DE BRONCE C/ACC. DE 2" und25.44 217.80

    1,389.486.00 VALVULA CHECK DE 2" und25.45 231.58

  • S10 Pgina 2ING. CARLOS OLIVOS LARA CIP:56310

    PRESUPUESTOOBRA : CONSTRUCCION Y EQUIPAMIENTO LABORATORIOS DE QUIMICA, METODOS, AUTOMATIZACION Y FISICACLIENTE : UNIVERSIDAD NACIONAL DE INGENIERIA - FIISDEPARTAMENTO :LIMA PROVINCIA : LIMA DISTRITO : SAN MARTIN DE PORRASCOSTOS AL : 30/11/2010

    INSTALACIONES SANITARIAS004Subpresupuesto

    Precio S/. Parcial S/.Item Descripcin Und. Metrado

    139.181.00 VALVULA FLOTADOR DE 2" und25.46 139.18

    421.782.00 VALVULA PIE CON CANASTILLA DE 2 1/2" und25.47 210.89

    192.202.00 UNION EXTENSIBLE DE 2" und25.48 96.10

    12.248.00 REDUCCION PVC SP P/AGUA DE 3/4"-1/2" und25.49 1.53

    9.484.00 REDUCCION PVC SP P/AGUA DE 1"-3/4" und25.50 2.37

    7.113.00 REDUCCION PVC SP P/AGUA DE 1"-1/2" und25.51 2.37

    56.439.00 REDUCCION PVC SP P/AGUA DE 1 1/2"-1/2" und25.52 6.27

    38.244.00 REDUCCION PVC SP P/AGUA DE 2" -1 1/2" und25.53 9.56

    4.271.00 REDUCCION PVC SP P/AGUA DE 1 1/2"-1" und25.54 4.27

    21.355.00 REDUCCION PVC SP P/AGUA DE 1 1/2"-3/4" und25.55 4.27

    67.0515.00 REDUCCION PVC SP P/AGUA DE 1 1/2"-11/4" und25.56 4.47

    28.683.00 REDUCCION PVC SP P/AGUA DE 2" -1" und25.57 9.56

    116.444.00 LLAVE DE RIEGO CON GRIFO DE 1/2" pza25.58 29.11

    2,264.7525.00 NICHO PARA VALULAS und25.59 90.59

    10.831.00 EXCAVACION DE ZANJAS HASTA 1.00 MT TERRENO NORMAL PARA REDES SANITARIAS Y/O ACI

    m25.60 10.83

    2,791.761.00 TANQUE HIDRONEUMATICO DE 140 GAL, C/ACC. PARA EQ. HIDRONEUMATICO und25.61 2,791.76

    3,925.842.00 BOMBA CENTRIFUGA DE 1.8HP, HDT 28M. Y 2.4Lit/seg und25.62 1,962.92

    2.801.00 NIVELACION Y APISONADO DE ZANJAS m25.63 2.80

    10.671.00 RELLENO DE ZANJAS m25.64 10.67

    7.441.00 ELIMINACION DE DESMONTE m25.65 7.44

    SISTEMA DE DESAGUE26 23,020.53

    2,789.6055.00 SALIDAS DE DESAGUE PVC SAL - MANO DE OBRA pto26.01 50.72

    2,465.68238.00 TUBERIA DE PVC SAL 2" m26.02 10.36

    204.5216.75 TUBERIA DE PVC SAL 3" m26.03 12.21

    2,708.01182.85 TUBERIA DE PVC SAL 4" m26.04 14.81

    476.2797.00 CODO PVC SAL 2"X90 pza26.05 4.91

    17.962.00 CODO PVC SAL 3"X90 pza26.06 8.98

    46.605.00 CODO PVC SAL 4"X90 pza26.07 9.32

    161.3711.00 CODO PVC-SAL C/VENT. 4"X2" und26.08 14.67

    166.9434.00 CODO PVC SAL 2"X45 pza26.09 4.91

    93.2010.00 CODO PVC SAL 4"X45 pza26.10 9.32

    339.7257.00 TEE SANITARIA PVC-SAL 2" und26.11 5.96

    307.2020.00 TEE SANITARIA PVC-SAL 4" und26.12 15.36

    17.451.00 TEE SANITARIA PVC-SAL 2"X4" und26.13 17.45

    295.8051.00 YEE SIMPLE PVC-SAL 2" und26.14 5.80

    47.005.00 YEE SIMPLE PVC-SAL 3" und26.15 9.40

    199.6813.00 YEE SIMPLE PVC-SAL 4" und26.16 15.36

    197.5212.00 YEE SIMPLE PVC-SAL 2"X4" und26.17 16.46

    65.807.00 YEE SIMPLE PVC-SAL 3"X2" und26.18 9.40

    6.211.00 YEE DOBLE PVC-SAL 2" und26.19 6.21

    25.411.00 YEE DOBLE PVC-SAL 2"X4" und26.20 25.41

    142.2020.00 TRAMPA P PVC-SAL DE 2" und26.21 7.11

    15.442.00 REDUCCION PVC-SAL DE 3" A 2" und26.22 7.72

    95.4012.00 REDUCCION PVC-SAL DE 4" A 2" und26.23 7.95

    172.3216.00 SOMBRERO VENTILACION PVC DE 2" pza26.24 10.77

  • S10 Pgina 3ING. CARLOS OLIVOS LARA CIP:56310

    PRESUPUESTOOBRA : CONSTRUCCION Y EQUIPAMIENTO LABORATORIOS DE QUIMICA, METODOS, AUTOMATIZACION Y FISICACLIENTE : UNIVERSIDAD NACIONAL DE INGENIERIA - FIISDEPARTAMENTO :LIMA PROVINCIA : LIMA DISTRITO : SAN MARTIN DE PORRASCOSTOS AL : 30/11/2010

    INSTALACIONES SANITARIAS004Subpresupuesto

    Precio S/. Parcial S/.Item Descripcin Und. Metrado

    56.253.00 SOMBRERO VENTILACION PVC DE 4" pza26.25 18.75

    563.0121.00 REGISTROS DE BRONCE CROMADO 2" pza26.26 26.81

    58.502.00 REGISTROS DE BRONCE CROMADO 3" pza26.27 29.25

    71.662.00 REGISTROS DE BRONCE CROMADO 4" pza26.28 35.83

    670.6020.00 SUMIDEROS DE 2" pza26.29 33.53

    108.693.00 SUMIDEROS DE 3" pza26.30 36.23

    613.222.00 VENTILACION C/TUBERIA DE ACERO S/DISEO DE 4" und26.31 306.61

    271.551.00 REBOSE C/TUBERIA DE ACERO S/DISEO DE 4" und26.32 271.55

    2,951.6412.00 CAJA DE REGISTRO DE DESAGUE 12" X 24" pza26.33 245.97

    918.513.00 CAJA DE REGISTRO DE DESAGUE 24" X 24" pza26.34 306.17

    1,649.95152.35 EXCAVACION DE ZANJAS HASTA 1.00 MT TERRENO NORMAL PARA REDES ELECTRICAS

    m26.35 10.83

    426.58152.35 NIVELACION Y APISONADO DE ZANJAS m26.36 2.80

    844.02152.35 CAMA DE ARENA m26.37 5.54

    1,625.57152.35 RELLENO DE ZANJAS m26.38 10.67

    1,133.48152.35 ELIMINACION DE DESMONTE m26.39 7.44

    COSTO DIRECTO 54,488.98

    GASTOS GENERALES 5,448.90

    SUB TOTAL 59,937.88

    IGV 19% 11,388.20

    PRESPUPUESTO TOTAL 71,326.08

    SON : SETENTIUN MIL TRESCIENTOS VEINTISEIS Y 08/100 NUEVOS SOLES