TABLA DE CANTIDADES Y PRECIOS RUBRO DESCRIPCION UNIDAD CANTIDAD P. UNITARIO P. TOTAL 1 1 LIMPIEZA MANUAL DEL TERRENO m2 269.42 1.86 501.12 2 2 REPLANTEO y NIVELACION con EQUIPO TOPOGRAFICO m2 62.29 5.03 313.32 3 3 EXCAVACION MANUAL EN CIMIENTOS Y PLINTOS m3 21.82 9.08 198.13 4 4 DESALOJO A MAQUINA. EQUIPO: CARGADORA FRONTAL y VOLQUETA m3 12.70 5.77 73.28 5 5 RELLENO COMPACTADO CON SUELO NATURAL m3 11.24 6.08 68.34 6 6 REPLANTILLO H.S. 140 KG/CM2. EQUIPO: CONCRETERA 1 SACO m3 1.30 128.10 166.53 7 7 PLINTOS DE HORMIGON .H.S 210KG/CM2. EQUIPO: CONCRETERA 1 SACO y VIBRADOR m3 4.37 159.37 696.45 8 8 HORMIGON COLUMNAS 0.20x0.30. F´C = 210KG/CM2. EQUIPO: CONCRETERA 1 SACO, VIBRA m3 3.78 258.44 976.90 9 9 HORMIGON EN VIGAS, 0.20x0.50. F´C = 210KG/CM2. EQUIPO: CONCRETERA 1 SACO, VIBR m3 9.66 269.69 2,605.21 10 10 m3 1.76 199.59 351.28 11 11 HORMIGON EN ESCALERAS, F´C = 210KG/CM2. EQUIPO: CONCRETERA 1 SACO, VIBRADOR, E m2 3.06 342.04 1,046.64 12 12 HORMIGON EN LOSA DE 20 CM, F´C = 210KG/CM2. EQUIPO: CONCRETERA 1 SACO, VIBRADO m3 12.40 230.20 2,854.48 13 13 BLOQUE DE ALIVIANAMIENTO 15*20*40 CM. TIMBRADO INCLUYE ESTIBAJE u 870.00 0.84 730.80 14 14 ACERO DE REFUERZO 8 -12 mm. ALAMBRE GALVANIZADO # 18 . EQUIPO: CIZALLA kg ### 2.03 6,841.89 15 15 BORDILLO DE TINA DE BAÑO H=40 CM, BLOQUE ENLUC.,CERAMICA GRAIMAN 20x20 m 2.90 133.90 388.31 16 16 MESA DE COCINA HORMIGON ARMADO. ENCOFRADO m 10.40 15.13 157.35 17 17 MAMPOSTERIA DE LADRILLO MAMBRON. MORTERO 1: 6, e = 2.5 cm. m2 271.05 40.18 10,890.79 18 18 LAVANDERIA DE JABONCILLO TUBO HG 1PLG-ASMT 120 u 1.00 209.96 209.96 19 19 CAJA DE REVISION (0.60X0.60X0.60) u 3.00 36.37 109.11 20 20 TAPA SANITARIA u 3.00 35.37 106.11 21 21 ENLUCIDO DE FAJAS m 146.17 5.02 733.77 22 22 ENLUCIDO VERTICAL INCLUYE ANDAMIOS m2 305.94 8.78 2,686.15 23 23 ENLUCIDO LISO EXTERIOR INCLUYE ANDAMIOS m2 239.01 8.99 2,148.70 24 24 ENLUCIDO HORIZONTAL LISO INCLUYE ANDAMIOS. MORTERO 1:6, e=1.5 cm m2 144.26 8.99 1,296.90 25 25 m2 62.00 9.40 582.80 26 26 CERAMICA PARA PARED m2 55.02 26.19 1,440.97 27 27 ALISADO DE PISOS(MORTERO 1:3, E = 1.5 CM) m2 136.70 8.69 1,187.92 28 28 CONTRAPISO H.S 180KG/CM2. E = 6 CM. PIEDRA BOLA. EQUIPO: CONCRETERA 1 SACO m2 56.91 55.01 3,130.62 29 29 MEDIA DUELA DE CHANDUL m2 66.69 52.04 3,470.55 30 30 CERAMICA PARA PISOS (GRAIMAN 30X30, MORTERO 1:3; e=1cm m2 13.00 27.09 352.17 31 31 PORCELANATO EN PISOS TIPO GRAIMAN m2 52.96 48.23 2,554.26 32 32 BARREDERA DE LAUREL m 91.00 4.40 400.40 33 33 VENTANA COREDIZA DE ALUMINIO m2 38.91 119.65 4,655.58 34 34 SALIDA MEDIDORES HG. LLAVE DE PASO Y ACCESORIOS H.G pto. 1.00 32.77 32.77 35 35 SALIDA DE AGUA FRIA HG. LLAVE DE CONTROL Y ACCESORIOS H.G pto. 12.00 17.58 210.96 36 36 SALIDA DE AGUA CALIENTE HG. LLAVE DE CONTROL Y ACCESORIOS H.G pto. 7.00 17.58 123.06 37 37 SALIDA PARA LAVADORAS. LLAVE DE CONTROL Y ACCESORIOS pto. 2.00 18.78 37.56 38 38 LLAVE DE PASO 3/4" u 4.00 14.09 56.36 39 39 TUBERIA PVC 1/2" m 27.90 5.64 157.36 40 40 LLAVE DE PICO FV DE LAVANDERIA u 3.00 16.10 48.30 41 41 CANALIZACION PVC 50 MM pto. 16.00 20.89 334.24 42 42 CANALIZACION PVC 110 MM pto. 3.00 33.28 99.84 43 43 BAJANTES AGUAS SERVIDAS PVC 110 MM. UNION CODO m 3.20 9.46 30.27 44 44 BAJANTES DE AGUAS LLUVIAS 110MM. UNION CODO m 5.20 9.46 49.19 45 45 TUBERIA PVC 110MM DESAGUE (MAT/TRAN/INST) m 20.60 9.46 194.88 46 46 REJILLA INTERIOR DE PISO 50MM u 10.00 10.54 105.40 47 47 TABLERO CONTROL GE4-8 PTO.S BREAKER 1 POLO 15-50 A u 1.00 148.29 148.29 48 48 ILUMINACION. CONDUCTOR N° 12 pto. 18.00 38.64 695.52 49 49 SALIDA PARA TELEFONOS. ALAMBRE TELEFONICO, ALUG 2 x20 pto. 4.00 18.45 73.80 50 50 SALIDAS ANTENAS TV u 4.00 20.61 82.44 51 51 TOMACORRIENTE DOBLE 2#10 T.CONDUIT EMT. 1/2" pto 20.00 34.12 682.40 52 52 PUERTAS PRICIPALES LACADAS u 1.00 270.91 270.91 53 53 MUEBLE BAJO COCINA (TABLERO TRIPLEX) m 5.30 163.95 868.94 54 54 MUEBLES ALTOS DE COCINA (TABLERO TRIPLEX) m 10.00 167.71 1,677.10 55 55 CLOSET (TABLERO TRIPLEX) m2 16.32 167.71 2,737.03 56 56 CERRADURA PRINCIPAL (CESA), TIPO NOVA CROMADA u 1.00 121.40 121.40 57 57 CERRADURA DORMITORIO (CESA)TIPO, NOVA CROMADA u 3.00 27.23 81.69 HORMIGON EN CADENAS 0.20x0.20. F´C = 210KG/CM2. EQUIPO: CONCRETE180RA 1 SACO, MASILLADO EN LOSA + IMPERMEABILIZANTE, SIKA 1 , e=3cm, MORTERO 1:3

Transcript of Precios Unitarios

Page 1: Precios Unitarios

TABLA DE CANTIDADES Y PRECIOS

RUBRO DESCRIPCION UNIDAD CANTIDAD P. UNITARIO P. TOTAL

1 1 LIMPIEZA MANUAL DEL TERRENO m2 269.42 1.86 501.12 62

2 2 REPLANTEO y NIVELACION con EQUIPO TOPOGRAFICO m2 62.29 5.03 313.32 125

3 3 EXCAVACION MANUAL EN CIMIENTOS Y PLINTOS m3 21.82 9.08 198.13 188

4 4 DESALOJO A MAQUINA. EQUIPO: CARGADORA FRONTAL y VOLQUETA m3 12.70 5.77 73.28 251

5 5 RELLENO COMPACTADO CON SUELO NATURAL m3 11.24 6.08 68.34 314

6 6 REPLANTILLO H.S. 140 KG/CM2. EQUIPO: CONCRETERA 1 SACO m3 1.30 128.10 166.53 377

7 7 PLINTOS DE HORMIGON .H.S 210KG/CM2. EQUIPO: CONCRETERA 1 SACO y VIBRADOR m3 4.37 159.37 696.45 440

8 8 HORMIGON COLUMNAS 0.20x0.30. F´C = 210KG/CM2. EQUIPO: CONCRETERA 1 SACO, m3 3.78 258.44 976.90 503

9 9 HORMIGON EN VIGAS, 0.20x0.50. F´C = 210KG/CM2. EQUIPO: CONCRETERA 1 SACO, VI m3 9.66 269.69 2,605.21 566

10 10 m3 1.76 199.59 351.28 629

11 11 HORMIGON EN ESCALERAS, F´C = 210KG/CM2. EQUIPO: CONCRETERA 1 SACO, VIBRA m2 3.06 342.04 1,046.64 692

12 12 HORMIGON EN LOSA DE 20 CM, F´C = 210KG/CM2. EQUIPO: CONCRETERA 1 SACO, VIB m3 12.40 230.20 2,854.48 755

13 13 BLOQUE DE ALIVIANAMIENTO 15*20*40 CM. TIMBRADO INCLUYE ESTIBAJE u 870.00 0.84 730.80 818

14 14 ACERO DE REFUERZO 8 -12 mm. ALAMBRE GALVANIZADO # 18 . EQUIPO: CIZALLA kg 3,370.39 2.03 6,841.89 881

15 15 BORDILLO DE TINA DE BAÑO H=40 CM, BLOQUE ENLUC.,CERAMICA GRAIMAN 20x20 m 2.90 133.90 388.31 944

16 16 MESA DE COCINA HORMIGON ARMADO. ENCOFRADO m 10.40 15.13 157.35 1007

17 17 MAMPOSTERIA DE LADRILLO MAMBRON. MORTERO 1: 6, e = 2.5 cm. m2 271.05 40.18 10,890.79 1070

18 18 LAVANDERIA DE JABONCILLO TUBO HG 1PLG-ASMT 120 u 1.00 209.96 209.96 1133

19 19 CAJA DE REVISION (0.60X0.60X0.60) u 3.00 36.37 109.11 1196

20 20 TAPA SANITARIA u 3.00 35.37 106.11 1259

21 21 ENLUCIDO DE FAJAS m 146.17 5.02 733.77 1322

22 22 ENLUCIDO VERTICAL INCLUYE ANDAMIOS m2 305.94 8.78 2,686.15 1385

23 23 ENLUCIDO LISO EXTERIOR INCLUYE ANDAMIOS m2 239.01 8.99 2,148.70 1448

24 24 ENLUCIDO HORIZONTAL LISO INCLUYE ANDAMIOS. MORTERO 1:6, e=1.5 cm m2 144.26 8.99 1,296.90 1511

25 25 m2 62.00 9.40 582.80 1574

26 26 CERAMICA PARA PARED m2 55.02 26.19 1,440.97 1637

27 27 ALISADO DE PISOS(MORTERO 1:3, E = 1.5 CM) m2 136.70 8.69 1,187.92 1700

28 28 CONTRAPISO H.S 180KG/CM2. E = 6 CM. PIEDRA BOLA. EQUIPO: CONCRETERA 1 SACO m2 56.91 55.01 3,130.62 1763

29 29 MEDIA DUELA DE CHANDUL m2 66.69 52.04 3,470.55 1826

30 30 CERAMICA PARA PISOS (GRAIMAN 30X30, MORTERO 1:3; e=1cm m2 13.00 27.09 352.17 1889

31 31 PORCELANATO EN PISOS TIPO GRAIMAN m2 52.96 48.23 2,554.26 1952

32 32 BARREDERA DE LAUREL m 91.00 4.40 400.40 2015

33 33 VENTANA COREDIZA DE ALUMINIO m2 38.91 119.65 4,655.58 2078

34 34 SALIDA MEDIDORES HG. LLAVE DE PASO Y ACCESORIOS H.G pto. 1.00 32.77 32.77 2141

35 35 SALIDA DE AGUA FRIA HG. LLAVE DE CONTROL Y ACCESORIOS H.G pto. 12.00 17.58 210.96 2204

36 36 SALIDA DE AGUA CALIENTE HG. LLAVE DE CONTROL Y ACCESORIOS H.G pto. 7.00 17.58 123.06 2267

37 37 SALIDA PARA LAVADORAS. LLAVE DE CONTROL Y ACCESORIOS pto. 2.00 18.78 37.56 2330

38 38 LLAVE DE PASO 3/4" u 4.00 14.09 56.36 2393

39 39 TUBERIA PVC 1/2" m 27.90 5.64 157.36 2456

40 40 LLAVE DE PICO FV DE LAVANDERIA u 3.00 16.10 48.30 2519

41 41 CANALIZACION PVC 50 MM pto. 16.00 20.89 334.24 2582

42 42 CANALIZACION PVC 110 MM pto. 3.00 33.28 99.84 2645

43 43 BAJANTES AGUAS SERVIDAS PVC 110 MM. UNION CODO m 3.20 9.46 30.27 2708

44 44 BAJANTES DE AGUAS LLUVIAS 110MM. UNION CODO m 5.20 9.46 49.19 2771

45 45 TUBERIA PVC 110MM DESAGUE (MAT/TRAN/INST) m 20.60 9.46 194.88 2834

46 46 REJILLA INTERIOR DE PISO 50MM u 10.00 10.54 105.40 2897

47 47 TABLERO CONTROL GE4-8 PTO.S BREAKER 1 POLO 15-50 A u 1.00 148.29 148.29 2960

48 48 ILUMINACION. CONDUCTOR N° 12 pto. 18.00 38.64 695.52 3023

49 49 SALIDA PARA TELEFONOS. ALAMBRE TELEFONICO, ALUG 2 x20 pto. 4.00 18.45 73.80 3086

50 50 SALIDAS ANTENAS TV u 4.00 20.61 82.44 3149

51 51 TOMACORRIENTE DOBLE 2#10 T.CONDUIT EMT. 1/2" pto 20.00 34.12 682.40 3212

52 52 PUERTAS PRICIPALES LACADAS u 1.00 270.91 270.91 3275

53 53 MUEBLE BAJO COCINA (TABLERO TRIPLEX) m 5.30 163.95 868.94 3338

54 54 MUEBLES ALTOS DE COCINA (TABLERO TRIPLEX) m 10.00 167.71 1,677.10 3401

55 55 CLOSET (TABLERO TRIPLEX) m2 16.32 167.71 2,737.03 3464

56 56 CERRADURA PRINCIPAL (CESA), TIPO NOVA CROMADA u 1.00 121.40 121.40 3527

57 57 CERRADURA DORMITORIO (CESA)TIPO, NOVA CROMADA u 3.00 27.23 81.69 3590

HORMIGON EN CADENAS 0.20 x0.20. F´C = 210KG/CM2. EQUIPO: CONCRETE180RA 1 SACO, VIBRADOR, ENCOFRADO CADENA

MASILLADO EN LOSA + IMPERMEABILIZANTE, SIKA 1 , e=3cm, MORTERO 1:3

Page 2: Precios Unitarios

58 58 CERRADURA BAÑO (CESA), TIPO NOVA CROMADA u 3.00 24.65 73.95 3653

59 59 CERRADURA PASILLO (CESA), TIPO NOVA CROMADA u 1.00 27.23 27.23 3716

60 60 PASAMANO DE HIERRO C/MANGON MADERA m 6.60 86.55 571.23 3779

61 61 PUERTA DE PLYWOOD TAMBOR 0.70 LACADA, INCLUYE MARCOS Y TAPAMARCOS u 4.00 167.71 670.84 3842

62 62 PUERTA DE PLYWOOD TAMBOR 0.80 LACADA, INCLUYE MARCOS Y TAPAMARCOS u 2.00 187.06 374.12 3905

63 63 PUERTA DE PLYWOOD TAMBOR 0.90 LACADA, INCLUYE MARCOS Y TAPAMARCOS u 4.00 187.06 748.24 3968

64 64 TANQUE CALENTADOR 30 GL. u 1.00 358.17 358.17 4031

65 65 PINTURA DE CAUCHO INTERIOR 2 MANOS, LATEX VINYL ACRILICO, CEMENTO BLANCO. m2 305.94 3.77 1,153.37 4094

66 66 PINTURA DE CAUCHO EXTERIOR 2 MANOS, LATEX VINYL ACRILICO, CEMENTO BLANCO. m2 192.24 4.14 795.85 4157

67 67 PINTURA CAUCHO CIELO RAZO. LATEX VINYL ACRILICO, CEMENTO BLANCO. EQUIPO: A m2 144.26 4.14 597.24 4220

68 68 TEJA COMUN INC. TIRAS EUCALIP.MORTERO 1:3 m2 4.80 25.55 122.64 4283

69 69 LAVAMANOS POMPANO BLANCO u 3.00 115.00 345.00 4346

70 70 INODORO TANQUE BAJO TIPO SAVEX u 3.00 264.50 793.50 4409

71 71 LAVAPLATOS COMPLETO, GRIFERIA u 1.00 385.83 385.83 4472

72 72 ACCESORIOS DE BAÑO jg 3.00 54.21 162.63 4535

73 73 DUCHA SENCILLA CROMADA COMPLETA - INCL. MEZCLADORA Y GRIFERIA u 2.00 121.53 243.06 4598

Page 3: Precios Unitarios

63

Page 4: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:LIMPIEZA MANUAL DEL TERRENO m2

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.069 0.07 4.79%

SUBTOTAL M 0.07 4.79%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

D= C*R

PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.32 0.89 61.78%

MAESTRO MAY. (Est. Ocup. C1) 0.50 346.62 2.09 3.02 0.16 0.48 33.56%

-

SUBTOTAL N 1.37 95.33%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

SUBTOTAL O - 0.00%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

SUBTOTAL P - 0.00%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 1.44 100%

INDIRECTOS Y UTILIDAD 29.00% 0.42 29.0%

COSTO TOTAL DEL RUBRO 1.86 129.00%

Page 5: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:REPLANTEO y NIVELACION con EQUIPO TOPOGRAFICO m2

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.169 0.17 4.33%

ESTACION TOTAL 1.000 2.50 0.140 0.35 8.97%

SUBTOTAL M 0.52 13.31%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

D= C*R

TOPOGRAFO 2 (Est. Ocup. C1) 1.00 346.62 2.09 3.02 0.14 0.42 10.84%

CADENERO (Est. Ocup. D2) 7.00 322.33 2.10 3.02 0.98 2.96 75.89%

-

SUBTOTAL N 3.38 86.73%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

SUBTOTAL O - 0.00%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

SUBTOTAL P - 0.00%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 3.90 100%

INDIRECTOS Y UTILIDAD 29.0% 1.13 29.0%

COSTO TOTAL DEL RUBRO 5.03 129.00%

Page 6: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:EXCAVACION MANUAL EN CIMIENTOS Y PLINTOS m3

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.335 0.34 4.76%

SUBTOTAL M 0.34 4.76%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

D= C*R

PEON (Est. Ocup. E2) 2.00 318.00 2.10 2.78 1.60 4.45 63.18%

ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.80 2.26 32.05%

SUBTOTAL N 6.70 95.23%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

SUBTOTAL O - 0.00%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

SUBTOTAL P - 0.00%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 7.04 100%

INDIRECTOS Y UTILIDAD 29.0% 2.04 29.0%

COSTO TOTAL DEL RUBRO 9.08 129.00%

Page 7: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:DESALOJO A MAQUINA. EQUIPO: CARGADORA FRONTAL y VOLQUETA m3

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.023 0.02 0.51%

CARGADORA FRONTAL 1.000 40.00 0.040 1.60 35.79%

VOLQUETE 10 M3 2.000 30.00 0.040 2.40 53.69%

SUBTOTAL M 4.02 90.00%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

D= C*R

OPERADOR EQUIPO PESADO GRUPO 1 (Est. Ocu 1.00 346.62 2.09 3.02 0.04 0.12 2.70%

CHOFER TIPO E VOLQUETAS(Est. Op. C1) 2.00 485.64 2.06 4.16 0.08 0.33 7.45%

SUBTOTAL N 0.45 10.15%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

SUBTOTAL O - 0.00%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

SUBTOTAL P - 0.00%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 4.47 100%

INDIRECTOS Y UTILIDAD 29.0% 1.30 29.0%

COSTO TOTAL DEL RUBRO 5.77 129.00%

Page 8: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:RELLENO COMPACTADO CON SUELO NATURAL m3

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.148 0.15 3.14%

PLANCHA VIBROCOMPAC. 1.000 3.00 0.533 1.60 33.97%

SUBTOTAL M 1.75 37.11%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

D= C*R

PEON (Est. Ocup. E2) 2.00 318.00 2.10 2.78 1.07 2.96 62.92%

SUBTOTAL N 2.96 62.92%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

SUBTOTAL O - 0.00%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

SUBTOTAL P - 0.00%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 4.71 100%

INDIRECTOS Y UTILIDAD 29.0% 1.37 29.0%

COSTO TOTAL DEL RUBRO 6.08 129.00%

Page 9: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:REPLANTILLO H.S. 140 KG/CM2. EQUIPO: CONCRETERA 1 SACO m3

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 1.331 1.33 1.34%

CONCRETERA 1.000 6.50 1.000 6.50 6.55%

SUBTOTAL M 7.83 7.89%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

D= C*R

PEON (Est. Ocup. E2) 7.00 318.00 2.10 2.78 7.00 19.46 19.60%

ALBANIL (Est. Ocup. D2) 2.00 322.33 2.10 2.82 2.00 5.64 5.68%

MAESTRO MAY. (Est. Ocup. C1) 0.50 346.62 2.09 3.02 0.50 1.51 1.52%

SUBTOTAL N 26.61 26.80%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CEMENTO SACO 6.180 6.723 41.55 41.84%

ARENA M3 0.650 #N/A #N/A 2.29%

RIPIO M3 0.950 #N/A #N/A 4.31%

AGUA M3 0.240 #N/A #N/A 0.05%

SUBTOTAL O 48.15 48.49%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CEMENTO SACO 6.180 0.50 3.09 3.11%

ARENA M3 0.650 8.50 5.53 5.56%

RIPIO M3 0.950 8.50 8.08 8.13%

AGUA LT 0.240 0.10 0.02 0.02%

SUBTOTAL P 16.71 16.83%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 99.30 100%

INDIRECTOS Y UTILIDAD 29.0% 28.80 29.0%

COSTO TOTAL DEL RUBRO 128.10 129.00%

Page 10: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:PLINTOS DE HORMIGON .H.S 210KG/CM2. EQUIPO: CONCRETERA 1 SACO y VIBRADOR m3

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 1.774 1.77 1.44%

CONCRETERA 1.000 6.50 1.333 8.67 7.02%

VIBRADOR 1.000 4.00 1.333 5.33 4.32%

SUBTOTAL M 15.77 12.77%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

D= C*R

PEON (Est. Ocup. E2) 7.00 318.00 2.10 2.78 9.33 25.94 21.00%

ALBANIL (Est. Ocup. D2) 2.00 322.33 2.10 2.82 2.67 7.52 6.09%

MAESTRO MAY. (Est. Ocup. C1) 0.50 346.62 2.09 3.02 0.67 2.01 1.63%

SUBTOTAL N 35.47 28.71%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CEMENTO SACO 7.210 6.723 48.47 39.24%

ARENA M3 0.650 #N/A #N/A 1.84%

RIPIO M3 0.950 #N/A #N/A 3.46%

AGUA M3 0.220 #N/A #N/A 0.04%

SUBTOTAL O 55.07 44.58%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CEMENTO SACO 7.210 0.50 3.61 2.92%

ARENA M3 0.650 8.50 5.53 4.47%

RIPIO M3 0.950 8.50 8.08 6.54%

AGUA LT 0.220 0.10 0.02 0.02%

SUBTOTAL P 17.23 13.94%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 123.54 100%

INDIRECTOS Y UTILIDAD 29.0% 35.83 29.0%

COSTO TOTAL DEL RUBRO 159.37 129.00%

Page 11: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:HORMIGON COLUMNAS 0.20x0.30. F´C = 210KG/CM2. EQUIPO: CONCRETERA 1 SACO, VIBRADOR, ENCOFRADO COLUMNA m3

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 3.549 3.55 1.77%

CONCRETERA 1.000 6.50 2.667 17.33 8.65%

VIBRADOR 1.000 4.00 2.667 10.67 5.32%

SUBTOTAL M 31.55 15.75%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

D= C*R

PEON (Est. Ocup. E2) 7.00 318.00 2.10 2.78 18.67 51.90 25.91%

ALBANIL (Est. Ocup. D2) 2.00 322.33 2.10 2.82 5.33 15.04 7.51%

MAESTRO MAY. (Est. Ocup. C1) 0.50 346.62 2.09 3.02 1.33 4.03 2.01%

SUBTOTAL N 70.97 35.42%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CEMENTO SACO 7.210 6.723 48.47 24.20%

ARENA M3 0.650 3.500 2.28 1.14%

RIPIO M3 0.950 4.500 4.27 2.13%

AGUA M3 0.220 #N/A #N/A 0.02%

ADITIVO KG 0.300 2.230 0.67 0.33%

ENCOFRADO M2 3.760 5.960 22.41 11.19%

CLAVOS,ALAMBRE, VARIOS GLB 1.000 2.000 2.00 1.00%

SUBTOTAL O 80.15 40.01%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CEMENTO SACO 7.210 0.50 3.61 1.80%

ARENA M3 0.650 8.50 5.53 2.76%

RIPIO M3 0.950 8.50 8.08 4.03%

AGUA LT 0.220 0.10 0.02 0.01%

ADITIVO KG 0.300 0.05 0.02 0.01%

ENCOFRADO M2 3.760 0.10 0.38 0.19%

CLAVOS,ALAMBRE, VARIOS GLB 1.000 0.05 0.05 0.02%

SUBTOTAL P 17.67 8.82%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 200.34 100%

INDIRECTOS Y UTILIDAD 29.0% 58.10 29.0%

COSTO TOTAL DEL RUBRO 258.44 129.00%

Page 12: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:HORMIGON EN VIGAS, 0.20x0.50. F´C = 210KG/CM2. EQUIPO: CONCRETERA 1 SACO, VIBRADOR. ENCOFRADO VIGA m3

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 3.549 3.55 1.70%

CONCRETERA 1.000 6.50 2.667 17.33 8.29%

VIBRADOR 1.000 4.00 2.667 10.67 5.10%

ELEVADOR 1.000 5.00 2.667 13.33 6.38%

SUBTOTAL M 44.88 21.47%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

D= C*R

PEON (Est. Ocup. E2) 7.00 318.00 2.10 2.78 18.67 51.90 24.83%

ALBANIL (Est. Ocup. D2) 2.00 322.33 2.10 2.82 5.33 15.04 7.20%

MAESTRO MAY. (Est. Ocup. C1) 0.50 346.62 2.09 3.02 1.33 4.03 1.93%

SUBTOTAL N 70.97 33.95%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CEMENTO SACO 7.210 6.723 48.47 23.19%

ARENA M3 0.650 3.500 2.28 1.09%

RIPIO M3 0.950 4.500 4.27 2.04%

AGUA M3 0.220 #N/A #N/A 0.02%

ADITIVO KG 0.300 2.230 0.67 0.32%

ENCOFRADO M2 3.000 5.960 17.88 8.55%

CLAVOS,ALAMBRE, VARIOS GLB 1.000 2.000 2.00 0.96%

SUBTOTAL O 75.62 36.17%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CEMENTO SACO 7.210 0.50 3.61 1.72%

ARENA M3 0.650 8.50 5.53 2.64%

RIPIO M3 0.950 8.50 8.08 3.86%

AGUA LT 0.220 0.10 0.02 0.01%

ADITIVO KG 0.300 0.05 0.02 0.01%

ENCOFRADO M2 3.000 0.10 0.30 0.14%

CLAVOS,ALAMBRE, VARIOS GLB 1.000 0.05 0.05 0.02%

SUBTOTAL P 17.59 8.41%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 209.06 100%

INDIRECTOS Y UTILIDAD 29.0% 60.63 29.0%

COSTO TOTAL DEL RUBRO 269.69 129.00%

Page 13: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

m3

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 2.129 2.13 1.38%

CONCRETERA 1.000 6.50 1.600 10.40 6.72%

VIBRADOR 1.000 4.00 1.600 6.40 4.14%

SUBTOTAL M 18.93 12.23%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

D= C*R

PEON (Est. Ocup. E2) 7.00 318.00 2.10 2.78 11.20 31.14 20.12%

ALBANIL (Est. Ocup. D2) 2.00 322.33 2.10 2.82 3.20 9.02 5.83%

MAESTRO MAY. (Est. Ocup. C1) 0.50 346.62 2.09 3.02 0.80 2.42 1.56%

SUBTOTAL N 42.58 27.52%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CEMENTO SACO 7.210 6.723 48.47 31.33%

ARENA M3 0.650 3.500 2.28 1.47%

RIPIO M3 0.950 4.500 4.27 2.76%

AGUA M3 0.220 #N/A #N/A 0.03%

ADITIVO KG 0.300 2.230 0.67 0.43%

ENCOFRADO M2 3.000 5.960 17.88 11.56%

CLAVOS,ALAMBRE, VARIOS GLB 1.000 2.000 2.00 1.29%

SUBTOTAL O 75.62 48.88%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CEMENTO SACO 7.210 0.50 3.61 2.33%

ARENA M3 0.650 8.50 5.53 3.57%

RIPIO M3 0.950 8.50 8.08 5.22%

AGUA LT 0.220 0.10 0.02 0.01%

ADITIVO KG 0.300 0.05 0.02 0.01%

ENCOFRADO M2 3.000 0.10 0.30 0.19%

CLAVOS,ALAMBRE, VARIOS GLB 1.000 0.05 0.05 0.03%

SUBTOTAL P 17.59 11.37%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 154.72 100%

INDIRECTOS Y UTILIDAD 29.0% 44.87 29.0%

COSTO TOTAL DEL RUBRO 199.59 129.00%

RUBRO:HORMIGON EN CADENAS 0.20 x0.20. F´C = 210KG/CM2. EQUIPO: CONCRETE180RA 1 SACO, VIBRADOR, ENCOFRADO CADENA

Page 14: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:HORMIGON EN ESCALERAS, F´C = 210KG/CM2. EQUIPO: CONCRETERA 1 SACO, VIBRADOR, ENCOFRADO ESCALERA m2

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 5.322 5.32 2.01%

CONCRETERA 1.000 6.50 4.000 26.00 9.81%

VIBRADOR 1.000 4.00 4.000 16.00 6.03%

SUBTOTAL M 47.32 17.85%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

D= C*R

PEON (Est. Ocup. E2) 7.00 318.00 2.10 2.78 28.00 77.84 29.36%

ALBANIL (Est. Ocup. D2) 2.00 322.33 2.10 2.82 8.00 22.56 8.51%

MAESTRO MAY. (Est. Ocup. C1) 0.50 346.62 2.09 3.02 2.00 6.04 2.28%

SUBTOTAL N 106.44 40.14%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CEMENTO SACO 7.210 6.723 48.47 18.28%

ARENA M3 0.650 3.500 2.28 0.86%

RIPIO M3 0.950 4.500 4.27 1.61%

AGUA M3 0.220 #N/A #N/A 0.02%

ADITIVO KG 0.300 2.230 0.67 0.25%

ENCOFRADO M2 6.000 5.960 35.76 13.49%

CLAVOS,ALAMBRE, VARIOS GLB 1.000 2.000 2.00 0.75%

SUBTOTAL O 93.50 35.26%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CEMENTO SACO 7.210 0.50 3.61 1.36%

ARENA M3 0.650 8.50 5.53 2.08%

RIPIO M3 0.950 8.50 8.08 3.05%

AGUA LT 0.220 0.10 0.02 0.01%

ADITIVO KG 0.300 0.05 0.02 0.01%

ENCOFRADO M2 6.000 0.10 0.60 0.23%

CLAVOS,ALAMBRE, VARIOS GLB 1.000 0.05 0.05 0.02%

SUBTOTAL P 17.89 6.75%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 265.15 100%

INDIRECTOS Y UTILIDAD 29.0% 76.89 29.0%

COSTO TOTAL DEL RUBRO 342.04 129.00%

Page 15: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:HORMIGON EN LOSA DE 20 CM, F´C = 210KG/CM2. EQUIPO: CONCRETERA 1 SACO, VIBRADOR, ENCOFRADO LOSA m3

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 2.920 2.92 1.64%

CONCRETERA 1.000 6.50 1.600 10.40 5.83%

VIBRADOR 1.000 4.00 1.600 6.40 3.59%

ELEVADOR 1.000 5.00 1.600 8.00 4.48%

SUBTOTAL M 27.72 15.53%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

D= C*R

PEON (Est. Ocup. E2) 9.00 318.00 2.10 2.78 14.40 40.03 22.43%

ALBANIL (Est. Ocup. D2) 3.00 322.33 2.10 2.82 4.80 13.54 7.59%

MAESTRO MAY. (Est. Ocup. C1) 1.00 346.62 2.09 3.02 1.60 4.83 2.71%

SUBTOTAL N 58.40 32.73%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CEMENTO SACO 7.210 6.723 48.47 27.16%

ARENA M3 0.650 3.500 2.28 1.27%

RIPIO M3 0.950 4.500 4.27 2.40%

AGUA M3 0.220 #N/A #N/A 0.03%

ADITIVO KG 0.300 2.230 0.67 0.37%

ENCOFRADO DE LOSA M2 9.610 1.600 15.38 8.62%

CLAVOS,ALAMBRE, VARIOS GLB 1.000 2.000 2.00 1.12%

SUBTOTAL O 73.12 40.97%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CEMENTO SACO 7.210 0.50 3.61 2.02%

ARENA M3 0.650 8.50 5.53 3.10%

RIPIO M3 0.950 8.50 8.08 4.53%

AGUA LT 0.220 0.10 0.02 0.01%

ADITIVO KG 0.300 0.05 0.02 0.01%

ENCOFRADO DE LOSA M2 9.610 0.20 1.92 1.08%

CLAVOS,ALAMBRE, VARIOS GLB 1.000 0.05 0.05 0.03%

SUBTOTAL P 19.21 10.77%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 178.45 100%

INDIRECTOS Y UTILIDAD 29.0% 51.75 29.0%

COSTO TOTAL DEL RUBRO 230.20 129.00%

Page 16: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:BLOQUE DE ALIVIANAMIENTO 15*20*40 CM. TIMBRADO INCLUYE ESTIBAJE u

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.014 0.01 2.15%

SUBTOTAL M 0.01 2.15%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PEON (Est. Ocup. E2) 5.00 318.00 2.10 2.78 0.10 0.28 42.77%

SUBTOTAL N 0.28 42.77%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

BLOQUE ALIVIANADO PARA LOSA E=15 CM. U 1.000 0.350 0.35 53.85%

SUBTOTAL O 0.35 53.85%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

BLOQUE ALIVIANADO PARA LOSA E=15 CM. U 1.000 0.01 0.01 1.54%

SUBTOTAL P 0.01 1.54%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 0.65 100%

INDIRECTOS Y UTILIDAD 29.0% 0.19 29.0%

COSTO TOTAL DEL RUBRO 0.84 129.00%

Page 17: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:ACERO DE REFUERZO 8 -12 mm. ALAMBRE GALVANIZADO # 18 . EQUIPO: CIZALLA kg

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.013 0.01 0.83%

SUBTOTAL M 0.01 0.83%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

D= C*R

PEON (Est. Ocup. E2) 2.00 318.00 2.10 2.78 0.06 0.17 10.62%

FIERRERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.03 0.08 5.39%

SUBTOTAL N 0.25 16.01%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

ACERO DE REFUERZO KG 1.050 1.080 1.13 72.25%

ALAMBRE DE AMARRE # 18 KG 0.050 2.223 0.11 7.08%

SUBTOTAL O 1.25 79.33%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

ACERO DE REFUERZO KG 1.050 0.05 0.05 3.34%

ALAMBRE DE AMARRE # 18 KG 0.050 0.05 0.00 0.16%

SUBTOTAL P 0.06 3.50%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 1.57 100%

INDIRECTOS Y UTILIDAD 29.0% 0.46 29.0%

COSTO TOTAL DEL RUBRO 2.03 129.00%

Page 18: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:BORDILLO DE TINA DE BAÑO H=40 CM, BLOQUE ENLUC.,CERAMICA GRAIMAN 20x20 m

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.159 0.16 0.15%

SUBTOTAL M 0.16 0.15%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

D= C*R

PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.50 1.39 1.34%

ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.50 1.41 1.36%

MAESTRO MAY. (Est. Ocup. C1) 0.25 346.62 2.09 3.02 0.13 0.38 0.36%

SUBTOTAL N 3.18 3.06%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

LADRILLO TIPO CHAMBO U 10.000 0.120 1.20 1.16%

CEMENTO SACO 10.300 6.723 69.25 66.71%

ARENA M3 1.040 3.500 3.64 3.51%

AGUA M3 0.320 #N/A #N/A 0.07%

CERAMICA EN PARED M2 1.000 #N/A #N/A 11.64%

SUBTOTAL O 86.24 83.08%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

LADRILLO TIPO CHAMBO U 10.000 0.01 0.10 0.10%

CEMENTO SACO 10.300 0.50 5.15 4.96%

ARENA M3 1.040 8.50 8.84 8.52%

AGUA LT 0.320 0.10 0.03 0.03%

CERAMICA EN PARED M2 1.000 0.10 0.10 0.10%

SUBTOTAL P 14.22 13.70%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 103.80 100%

INDIRECTOS Y UTILIDAD 29.0% 30.10 29.0%

COSTO TOTAL DEL RUBRO 133.90 129.00%

Page 19: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:MAMPOSTERIA DE LADRILLO MAMBRON. MORTERO 1: 6, e = 2.5 cm. m2

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.304 0.30 2.59%

SUBTOTAL M 0.30 2.59%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

D= C*R

PEON (Est. Ocup. E2) 4.00 318.00 2.10 2.78 1.33 3.70 31.57%

ALBANIL (Est. Ocup. D2) 2.00 322.33 2.10 2.82 0.67 1.88 16.01%

MAESTRO MAY. (Est. Ocup. C1) 0.50 346.62 2.09 3.02 0.17 0.50 4.29%

SUBTOTAL N 6.08 51.87%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

LADRILLO TIPO CHAMBO U 33.000 0.120 3.96 33.76%

CEMENTO SACO 0.100 6.723 0.67 5.73%

ARENA M3 0.020 3.500 0.07 0.60%

AGUA M3 0.308 #N/A #N/A 0.58%

SUBTOTAL O 4.77 40.67%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

LADRILLO TIPO CHAMBO U 33.000 0.01 0.33 2.81%

CEMENTO SACO 0.100 0.50 0.05 0.43%

ARENA M3 0.020 8.50 0.17 1.45%

AGUA LT 0.308 0.10 0.03 0.26%

SUBTOTAL P 0.58 4.95%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 11.73 100%

INDIRECTOS Y UTILIDAD 29.0% 3.40 29.0%

COSTO TOTAL DEL RUBRO 15.13 129.00%

Page 20: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:MESA DE COCINA HORMIGON ARMADO. ENCOFRADO m

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.636 0.64 2.04%

SUBTOTAL M 0.64 2.04%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PEON (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 17.85%

ALBANIL (Est. Ocup. D2) 2.00 322.33 2.10 2.82 2.00 5.64 18.11%

MAESTRO MAY. (Est. Ocup. C1) 0.50 346.62 2.09 3.02 0.50 1.51 4.85%

SUBTOTAL N 12.71 40.80%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CEMENTO SACO 0.500 6.723 3.36 10.79%

ARENA M3 0.060 3.500 0.21 0.67%

RIPIO M3 0.090 4.500 0.40 1.30%

AGUA M3 0.002 #N/A #N/A 0.00%

ACERO DE REFUERZO KG 4.800 #N/A #N/A 16.65%

TABLA DURA DE ENCOFRADO U 1.500 #N/A #N/A 7.70%

TIRAS DE MADERA U 0.250 1.200 0.30 1.20%

CLAVOS,ALAMBRE, VARIOS GLB 1.000 2.500 2.50 8.03%

PINGOS 2.5 U 1.000 #N/A #N/A 4.59%

SUBTOTAL O 15.86 50.93%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CEMENTO SACO 0.500 0.50 0.25 0.80%

ARENA M3 0.060 8.50 0.51 1.64%

RIPIO M3 0.090 8.50 0.77 2.46%

AGUA LT 0.003 0.10 0.00 0.00%

ACERO DE REFUERZO KG 4.800 0.05 0.24 0.77%

TABLA DURA DE ENCOFRADO U 1.500 0.05 0.08 0.24%

TIRAS DE MADERA U 0.250 0.01 0.00 0.01%

CLAVOS,ALAMBRE, VARIOS GLB 1.000 0.05 0.05 0.16%

PINGOS 2.5 U 1.000 0.05 0.05 0.16%

SUBTOTAL P 1.94 6.24%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 31.15 100%

INDIRECTOS Y UTILIDAD 29.0% 9.03 29.0%

COSTO TOTAL DEL RUBRO 40.18 129.00%

Page 21: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:LAVANDERIA DE JABONCILLO TUBO HG 1PLG-ASMT 120 u

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 4.245 4.25 2.61%

SUBTOTAL M 4.25 2.61%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 11.94 33.19 20.39%

ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 11.94 33.67 20.69%

MAESTRO MAY. (Est. Ocup. C1) 0.50 346.62 2.09 3.02 5.97 18.03 11.08%

SUBTOTAL N 84.89 52.16%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CEMENTO SACO 2.030 6.723 13.65 8.39%

ARENA M3 0.270 3.500 0.95 0.58%

AGUA M3 0.070 0.220 0.02 0.01%

ACERO DE REFUERZO KG 5.000 #N/A #N/A 3.32%

LADRILLO TIPO CHAMBO U 176.000 #N/A #N/A 12.98%

PIEDRA BOLA M3 0.150 #N/A #N/A 0.41%

LLAVE DE MANGUERA DE PICO U 1.000 9.000 9.00 5.53%

LLAVE DE PASO FV U 1.000 8.500 8.50 5.22%

CODOS PVC 1/2" U 2.000 2.500 5.00 3.07%

TUBO ROSCABLE 1/2" AGUA FRIA U 0.320 8.000 2.56 1.57%

SUBTOTAL O 66.87 41.08%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CEMENTO SACO 2.030 0.50 1.02 0.62%

ARENA M3 0.270 8.50 2.30 1.41%

AGUA LT 0.070 0.10 0.01 0.00%

ACERO DE REFUERZO KG 5.000 0.05 0.25 0.15%

LADRILLO TIPO CHAMBO U 176.000 0.01 1.76 1.08%

PIEDRA BOLA M3 0.150 8.50 1.28 0.78%

LLAVE DE MANGUERA DE PICO U 1.000 0.05 0.05 0.03%

LLAVE DE PASO FV U 1.000 0.05 0.05 0.03%

CODOS PVC 1/2" U 2.000 0.01 0.02 0.01%

TUBO ROSCABLE 1/2" AGUA FRIA U 0.320 0.10 0.03 0.02%

SUBTOTAL P 6.75 4.15%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 162.76 100%

INDIRECTOS Y UTILIDAD 29.0% 47.20 29.0%

COSTO TOTAL DEL RUBRO 209.96 129.00%

Page 22: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:CAJA DE REVISION (0.60X0.60X0.60) u

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.889 0.89 3.15%

SUBTOTAL M 0.89 3.15%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 2.50 6.95 24.65%

ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 2.50 7.05 25.01%

MAESTRO MAY. (Est. Ocup. C1) 0.50 346.62 2.09 3.02 1.25 3.78 13.39%

SUBTOTAL N 17.78 63.05%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CEMENTO SACO 0.270 6.723 1.82 6.44%

ARENA M3 0.030 3.500 0.11 0.37%

AGUA M3 0.010 0.220 0.00 0.01%

ACERO DE REFUERZO KG 1.200 #N/A #N/A 4.60%

LADRILLO TIPO CHAMBO U 40.000 #N/A #N/A 17.03%

PIEDRA BOLA M3 0.050 #N/A #N/A 0.80%

SUBTOTAL O 8.24 29.24%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CEMENTO SACO 0.270 0.50 0.14 0.48%

ARENA M3 0.030 8.50 0.26 0.90%

AGUA LT 0.010 0.10 0.00 0.00%

ACERO DE REFUERZO KG 1.200 0.05 0.06 0.21%

LADRILLO TIPO CHAMBO U 40.000 0.01 0.40 1.42%

PIEDRA BOLA M3 0.050 8.50 0.43 1.51%

SUBTOTAL P 1.28 4.53%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 28.19 100%

INDIRECTOS Y UTILIDAD 29.0% 8.18 29.0%

COSTO TOTAL DEL RUBRO 36.37 129.00%

Page 23: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:TAPA SANITARIA u

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.562 0.56 2.05%

SUBTOTAL M 0.56 2.05%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 1.00 2.78 10.14%

ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 1.00 2.82 10.28%

FIERRERO (Est. Ocup. D2) 2.00 322.33 2.10 2.82 2.00 5.64 20.57%

SUBTOTAL N 11.24 40.99%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CEMENTO SACO 0.241 6.723 1.62 5.91%

ARENA M3 0.023 3.500 0.08 0.29%

RIPIO M3 0.034 4.500 0.15 0.56%

AGUA M3 0.008 #N/A #N/A 0.01%

ACERO DE REFUERZO KG 8.000 #N/A #N/A 31.52%

TABLA DURA DE ENCOFRADO U 2.500 #N/A #N/A 14.57%

SUBTOTAL O 14.49 52.86%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CEMENTO SACO 0.241 0.50 0.12 0.44%

ARENA M3 0.023 8.50 0.20 0.71%

RIPIO M3 0.034 8.50 0.29 1.05%

AGUA LT 0.008 0.10 0.00 0.00%

ACERO DE REFUERZO KG 8.000 0.05 0.40 1.46%

TABLA DURA DE ENCOFRADO U 2.500 0.05 0.13 0.46%

SUBTOTAL P 1.13 4.12%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 27.42 100%

INDIRECTOS Y UTILIDAD 29.0% 7.95 29.0%

COSTO TOTAL DEL RUBRO 35.37 129.00%

Page 24: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:ENLUCIDO DE FAJAS m

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.172 0.17 4.42%

SUBTOTAL M 0.17 4.42%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.62 1.71 43.95%

ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.62 1.73 44.58%

SUBTOTAL N 3.44 88.53%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CEMENTO SACO 0.025 6.723 0.17 4.32%

ARENA M3 0.008 3.500 0.03 0.72%

SUBTOTAL O 0.20 5.04%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CEMENTO SACO 0.025 0.50 0.01 0.32%

ARENA M3 0.008 8.50 0.07 1.75%

SUBTOTAL P 0.08 2.07%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 3.89 100%

INDIRECTOS Y UTILIDAD 29.0% 1.13 29.0%

COSTO TOTAL DEL RUBRO 5.02 129.00%

Page 25: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:ENLUCIDO VERTICAL INCLUYE ANDAMIOS m2

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.271 0.27 3.98%

ANDAMIOS 1.000 0.19 0.889 0.17 2.45%

SUBTOTAL M 0.44 6.43%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.89 2.47 36.29%

ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.89 2.51 36.81%

MAESTRO MAY. (Est. Ocup. C1) 0.16 346.62 2.09 3.02 0.14 0.43 6.31%

SUBTOTAL N 5.41 79.41%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CEMENTO SACO 0.099 6.723 0.66 9.76%

ARENA M3 0.020 3.500 0.07 1.03%

AGUA M3 0.005 0.220 0.00 0.02%

SUBTOTAL O 0.74 10.81%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CEMENTO SACO 0.099 0.50 0.05 0.73%

ARENA M3 0.020 8.50 0.17 2.50%

AGUA LT 0.005 0.10 0.00 0.01%

SUBTOTAL P 0.22 3.23%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 6.81 100%

INDIRECTOS Y UTILIDAD 29.0% 1.97 29.0%

COSTO TOTAL DEL RUBRO 8.78 129.00%

Page 26: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:ENLUCIDO LISO EXTERIOR INCLUYE ANDAMIOS m2

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.271 0.27 3.89%

ANDAMIOS 2.000 0.19 0.889 0.33 4.78%

SUBTOTAL M 0.60 8.67%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.89 2.47 35.46%

ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.89 2.51 35.97%

MAESTRO MAY. (Est. Ocup. C1) 0.16 346.62 2.09 3.02 0.14 0.43 6.16%

SUBTOTAL N 5.41 77.59%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CEMENTO SACO 0.099 6.723 0.66 9.54%

ARENA M3 0.020 3.500 0.07 1.00%

AGUA M3 0.005 0.220 0.00 0.02%

SUBTOTAL O 0.74 10.56%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CEMENTO SACO 0.099 0.50 0.05 0.71%

ARENA M3 0.020 8.50 0.17 2.44%

AGUA LT 0.005 0.10 0.00 0.01%

SUBTOTAL P 0.22 3.16%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 6.97 100%

INDIRECTOS Y UTILIDAD 29.0% 2.02 29.0%

COSTO TOTAL DEL RUBRO 8.99 129.00%

Page 27: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:ENLUCIDO HORIZONTAL LISO INCLUYE ANDAMIOS. MORTERO 1:6, e=1.5 cm m2

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.271 0.27 3.89%

ANDAMIOS 2.000 0.19 0.889 0.33 4.78%

SUBTOTAL M 0.60 8.67%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.89 2.47 35.46%

ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.89 2.51 35.97%

MAESTRO MAY. (Est. Ocup. C1) 0.16 346.62 2.09 3.02 0.14 0.43 6.16%

SUBTOTAL N 5.41 77.59%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CEMENTO SACO 0.099 6.723 0.66 9.54%

ARENA M3 0.020 3.500 0.07 1.00%

AGUA M3 0.005 0.220 0.00 0.02%

SUBTOTAL O 0.74 10.56%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CEMENTO SACO 0.099 0.50 0.05 0.71%

ARENA M3 0.020 8.50 0.17 2.44%

AGUA LT 0.005 0.10 0.00 0.01%

SUBTOTAL P 0.22 3.16%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 6.97 100%

INDIRECTOS Y UTILIDAD 29.0% 2.02 29.0%

COSTO TOTAL DEL RUBRO 8.99 129.00%

Page 28: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

m2

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.204 0.20 2.80%

SUBTOTAL M 0.20 2.80%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.73 2.02 27.72%

ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.73 2.05 28.12%

SUBTOTAL N 4.07 55.85%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CEMENTO SACO 0.309 6.723 2.08 28.50%

ARENA M3 0.031 3.500 0.11 1.49%

AGUA M3 0.009 0.220 0.00 0.03%

IMPERMEABILIZANTE SIKA 1 KG 0.330 1.250 0.41 5.66%

SUBTOTAL O 2.60 35.67%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CEMENTO SACO 0.309 0.50 0.15 2.12%

ARENA M3 0.031 8.50 0.26 3.61%

AGUA LT 0.009 0.10 0.00 0.01%

IMPERMEABILIZANTE SIKA 1 KG 0.330 0.01 0.00 0.16%

SUBTOTAL P 0.42 5.90%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 7.29 100%

INDIRECTOS Y UTILIDAD 29.0% 2.11 29.0%

COSTO TOTAL DEL RUBRO 9.40 129.00%

RUBRO:MASILLADO EN LOSA + IMPERMEABILIZANTE, SIKA 1 , e=3cm, MORTERO 1:3

Page 29: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:CERAMICA PARA PARED m2

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.259 0.26 1.28%

SUBTOTAL M 0.26 1.28%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.73 2.02 9.96%

ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.73 2.05 10.10%

MAESTRO MAY. (Est. Ocup. C1) 1.00 346.62 2.09 3.02 0.36 1.10 5.41%

SUBTOTAL N 5.17 25.46%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CERAMICA EN PARED M2 1.050 12.080 12.68 62.48%

BONDEX SACO 0.330 5.600 1.85 9.10%

EMPORADOR KG 0.150 1.445 0.22 1.07%

SUBTOTAL O 14.75 72.66%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CERAMICA EN PARED M2 1.050 0.10 0.11 0.52%

BONDEX SACO 0.330 0.05 0.02 0.08%

EMPORADOR KG 0.330 0.01 0.00 0.02%

SUBTOTAL P 0.12 0.61%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 20.30 100%

INDIRECTOS Y UTILIDAD 29.0% 5.89 29.0%

COSTO TOTAL DEL RUBRO 26.19 129.00%

Page 30: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:ALISADO DE PISOS(MORTERO 1:3, E = 1.5 CM) m2

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.259 0.26 3.84%

SUBTOTAL M 0.26 3.84%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.73 2.02 29.99%

ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.73 2.05 30.42%

MAESTRO MAY. (Est. Ocup. C1) 1.00 346.62 2.09 3.02 0.36 1.10 16.29%

SUBTOTAL N 5.17 76.69%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CEMENTO SACO 0.155 6.723 1.04 15.46%

ARENA M3 0.016 3.500 0.06 0.83%

AGUA M3 0.005 0.220 0.00 0.02%

SUBTOTAL O 1.10 16.31%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CEMENTO SACO 0.155 0.50 0.08 1.15%

ARENA M3 0.016 8.50 0.14 2.02%

AGUA LT 0.005 0.10 0.00 0.01%

SUBTOTAL P 0.21 3.18%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 6.74 100%

INDIRECTOS Y UTILIDAD 29.0% 1.95 29.0%

COSTO TOTAL DEL RUBRO 8.69 129.00%

Page 31: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:CONTRAPISO H.S 180KG/CM2. E = 6 CM. PIEDRA BOLA. EQUIPO: CONCRETERA 1 SACO m2

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.334 0.33 0.78%

CONCRETERA 1.000 6.50 0.250 1.63 3.81%

SUBTOTAL M 1.96 4.59%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PEON (Est. Ocup. E2) 5.00 318.00 2.10 2.78 1.25 3.47 8.15%

ALBANIL (Est. Ocup. D2) 4.00 322.33 2.10 2.82 1.00 2.82 6.61%

MAESTRO MAY. (Est. Ocup. C1) 1.00 346.62 2.09 3.02 0.13 0.38 0.89%

SUBTOTAL N 6.67 15.65%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CEMENTO SACO 0.402 6.723 2.70 6.34%

ARENA M3 0.039 #N/A #N/A 0.32%

RIPIO M3 0.057 #N/A #N/A 0.60%

AGUA M3 0.014 #N/A #N/A 0.01%

PIEDRA BOLA M3 0.150 #N/A #N/A 1.58%

RIPIO M3 0.090 #N/A #N/A 0.95%

PORCELANATO M2 1.050 25.000 26.25 61.56%

SUBTOTAL O 30.43 71.36%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CEMENTO SACO 0.402 0.50 0.20 0.47%

ARENA M3 0.039 8.50 0.33 0.78%

RIPIO M3 0.057 8.50 0.48 1.14%

AGUA LT 0.014 0.10 0.00 0.00%

PIEDRA BOLA M3 0.150 8.50 1.28 2.99%

RIPIO M3 0.090 8.50 0.77 1.79%

PORCELANATO M2 1.050 0.50 0.53 1.23%

SUBTOTAL P 3.58 8.40%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 42.64 100%

INDIRECTOS Y UTILIDAD 29.0% 12.37 29.0%

COSTO TOTAL DEL RUBRO 55.01 129.00%

Page 32: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:MEDIA DUELA DE CHANDUL m2

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.232 0.23 0.58%

PULIDORA 1.000 4.00 0.800 3.20 7.93%

SUBTOTAL M 3.43 8.51%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.80 2.22 5.51%

CARPINTERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 0.80 2.42 5.99%

SUBTOTAL N 4.64 11.50%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CLAVOS 2 - 2.5, 3 " KG 0.150 1.571 0.24 0.58%

MEDIA DUELA DE CHANDUL MACHIMBRADA M2 1.050 30.000 31.50 78.09%

SUBTOTAL O 31.74 78.67%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CLAVOS 2 - 2.5, 3 " KG 0.150 0.01 0.00 0.00%

MEDIA DUELA DE CHANDUL MACHIMBRADA M2 1.050 0.50 0.53 1.30%

SUBTOTAL P 0.53 1.31%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 40.34 100%

INDIRECTOS Y UTILIDAD 29.0% 11.70 29.0%

COSTO TOTAL DEL RUBRO 52.04 129.00%

Page 33: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:CERAMICA PARA PISOS (GRAIMAN 30X30, MORTERO 1:3; e=1cm m2

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.259 0.26 1.23%

SUBTOTAL M 0.26 1.23%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.73 2.02 9.62%

ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.73 2.05 9.76%

MAESTRO MAY. (Est. Ocup. C1) 1.00 346.62 2.09 3.02 0.36 1.10 5.23%

SUBTOTAL N 5.17 24.61%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CERAMICA EN PISO M2 1.050 12.536 13.16 62.68%

BONDEX SACO 0.330 5.600 1.85 8.80%

EMPORADOR KG 0.150 1.445 0.22 1.03%

SUBTOTAL O 15.23 72.51%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CERAMICA EN PISO M2 1.050 0.10 0.11 0.50%

BONDEX SACO 0.330 0.05 0.02 0.08%

EMPORADOR KG 0.150 1.445 0.22 1.03%

SUBTOTAL P 0.34 1.61%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 21.00 100%

INDIRECTOS Y UTILIDAD 29.0% 6.09 29.0%

COSTO TOTAL DEL RUBRO 27.09 129.00%

Page 34: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:PORCELANATO EN PISOS TIPO GRAIMAN m2

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.316 0.32 0.85%

SUBTOTAL M 0.32 0.85%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.89 2.47 6.61%

ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.89 2.51 6.70%

MAESTRO MAY. (Est. Ocup. C1) 1.00 346.62 2.09 3.02 0.44 1.34 3.59%

SUBTOTAL N 6.32 16.91%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

PORCELANATO M2 1.050 25.000 26.25 70.21%

BONDEX PREMIUM SACO 0.330 10.500 3.47 9.27%

EMPORADOR KG 0.150 1.445 0.22 0.58%

SUBTOTAL O 29.93 80.05%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

PORCELANATO M2 1.050 0.50 0.53 1.40%

BONDEX PREMIUM SACO 0.330 0.25 0.08 0.22%

EMPORADOR KG 0.150 1.445 0.22 0.58%

SUBTOTAL P 0.82 2.20%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 37.39 100%

INDIRECTOS Y UTILIDAD 29.0% 10.84 29.0%

COSTO TOTAL DEL RUBRO 48.23 129.00%

Page 35: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:BARREDERA DE LAUREL m

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.044 0.04 1.29%

SUBTOTAL M 0.04 1.29%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.15 0.42 12.31%

CADENERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 0.15 0.46 13.37%

SUBTOTAL N 0.88 25.68%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

BARREDERAS INSTALADAS a=9 CM ML 0.402 6.000 2.41 70.73%

CLAVOS 2 - 2.5, 3 " KG 0.039 1.571 0.06 1.80%

SUBTOTAL O 2.47 72.53%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

BARREDERAS INSTALADAS a=9 CM ML 0.402 0.05 0.02 0.59%

CLAVOS 2 - 2.5, 3 " KG 0.039 0.01 0.00 0.01%

SUBTOTAL P 0.02 0.60%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 3.41 100%

INDIRECTOS Y UTILIDAD 29.0% 0.99 29.0%

COSTO TOTAL DEL RUBRO 4.40 129.00%

Page 36: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:VENTANA COREDIZA DE ALUMINIO m2

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 2.226 2.23 2.40%

SUBTOTAL M 2.23 2.40%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 3.00 8.33 8.98%

INSTALADOR (Est. Ocup. D2) 4.00 322.33 2.10 3.02 11.98 36.19 39.02%

SUBTOTAL N 44.52 48.00%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

VENTANAS DE AL. Y VIDRIO CORREDIZA M2 1.000 45.000 45.00 48.52%

SUBTOTAL O 45.00 48.52%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

VENTANAS DE AL. Y VIDRIO CORREDIZA M2 1.000 1.00 1.00 1.08%

SUBTOTAL P 1.00 1.08%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 92.75 100%

INDIRECTOS Y UTILIDAD 29.0% 26.90 29.0%

COSTO TOTAL DEL RUBRO 119.65 129.00%

Page 37: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:SALIDA MEDIDORES HG. LLAVE DE PASO Y ACCESORIOS H.G pto.

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.630 0.63 2.48%

SUBTOTAL M 0.63 2.48%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.50 1.39 5.47%

AYUDANTE (Est. Ocup. E2) 4.00 318.00 2.10 2.78 2.00 5.56 21.89%

ALBANIL (Est. Ocup. D2) 2.00 322.33 2.10 2.82 1.00 2.82 11.10%

PLOMERO (Est. Ocup. D2) 2.00 322.33 2.10 2.82 1.00 2.82 11.10%

SUBTOTAL N 12.59 49.57%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

TUBO ROSCABLE 1/2" AGUA FRIA U 1.000 8.000 8.00 31.50%

LLAVE DE PASO FV U 0.300 8.500 2.55 10.04%

CODOS PVC 3/4 U 2.000 0.220 0.44 1.73%

PERMATEX 3 ONZ. U 0.150 1.950 0.29 1.15%

TEE PVC 1/2" U 2.000 0.180 0.36 1.42%

UNION PVC 1/2" U 2.000 0.180 0.36 1.42%

SUBTOTAL O 12.00 47.25%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

TUBO ROSCABLE 1/2" AGUA FRIA U 1.000 0.10 0.10 0.39%

LLAVE DE PASO FV U 0.300 0.05 0.02 0.06%

CODOS PVC 3/4 U 2.000 0.01 0.02 0.08%

PERMATEX 3 ONZ. U 0.150 0.01 0.00 0.01%

TEE PVC 1/2" U 2.000 0.01 0.02 0.08%

UNION PVC 1/2" U 2.000 0.01 0.02 0.08%

SUBTOTAL P 0.18 0.69%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 25.40 100%

INDIRECTOS Y UTILIDAD 29.0% 7.37 29.0%

COSTO TOTAL DEL RUBRO 32.77 129.00%

Page 38: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:SALIDA DE AGUA FRIA HG. LLAVE DE CONTROL Y ACCESORIOS H.G pto.

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.359 0.36 2.63%

SUBTOTAL M 0.36 2.63%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.32 0.89 6.53%

AYUDANTE (Est. Ocup. E2) 3.00 318.00 2.10 2.78 0.96 2.67 19.58%

ALBANIL (Est. Ocup. D2) 2.00 322.33 2.10 2.82 0.64 1.80 13.24%

PLOMERO (Est. Ocup. D2) 2.00 322.33 2.10 2.82 0.64 1.80 13.24%

SUBTOTAL N 7.17 52.59%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

TUBO ROSCABLE 1/2" AGUA FRIA U 0.250 8.000 2.00 14.67%

LLAVE DE PASO FV U 0.300 8.500 2.55 18.71%

CODOS PVC 3/4 U 2.000 0.220 0.44 3.23%

PERMATEX 3 ONZ. U 0.150 1.950 0.29 2.15%

TEE PVC 1/2" U 2.000 0.180 0.36 2.64%

UNION PVC 1/2" U 2.000 0.180 0.36 2.64%

SUBTOTAL O 6.00 44.04%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

TUBO ROSCABLE 1/2" AGUA FRIA U 0.250 0.10 0.03 0.18%

LLAVE DE PASO FV U 0.300 0.05 0.02 0.11%

CODOS PVC 3/4 U 2.000 0.01 0.02 0.15%

PERMATEX 3 ONZ. U 0.150 0.01 0.00 0.01%

TEE PVC 1/2" U 2.000 0.01 0.02 0.15%

UNION PVC 1/2" U 2.000 0.01 0.02 0.15%

SUBTOTAL P 0.10 0.74%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 13.63 100%

INDIRECTOS Y UTILIDAD 29.0% 3.95 29.0%

COSTO TOTAL DEL RUBRO 17.58 129.00%

Page 39: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:SALIDA DE AGUA CALIENTE HG. LLAVE DE CONTROL Y ACCESORIOS H.G pto.

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.359 0.36 2.63%

SUBTOTAL M 0.36 2.63%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.32 0.89 6.53%

AYUDANTE (Est. Ocup. E2) 3.00 318.00 2.10 2.78 0.96 2.67 19.58%

ALBANIL (Est. Ocup. D2) 2.00 322.33 2.10 2.82 0.64 1.80 13.24%

PLOMERO (Est. Ocup. D2) 2.00 322.33 2.10 2.82 0.64 1.80 13.24%

SUBTOTAL N 7.17 52.59%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

TUBO HIDRO 3 1/2" AGUA CALIENTE U 0.250 8.000 2.00 14.67%

LLAVE DE PASO FV U 0.300 8.500 2.55 18.71%

CODOS PVC 3/4 U 2.000 0.220 0.44 3.23%

PERMATEX 3 ONZ. U 0.150 1.950 0.29 2.15%

TEE PVC 1/2" U 2.000 0.180 0.36 2.64%

UNION PVC 1/2" U 2.000 0.180 0.36 2.64%

SUBTOTAL O 6.00 44.04%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

TUBO HIDRO 3 1/2" AGUA CALIENTE U 0.250 0.10 0.03 0.18%

LLAVE DE PASO FV U 0.300 0.05 0.02 0.11%

CODOS PVC 3/4 U 2.000 0.01 0.02 0.15%

PERMATEX 3 ONZ. U 0.150 0.01 0.00 0.01%

TEE PVC 1/2" U 2.000 0.01 0.02 0.15%

UNION PVC 1/2" U 2.000 0.01 0.02 0.15%

SUBTOTAL P 0.10 0.74%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 13.63 100%

INDIRECTOS Y UTILIDAD 29.0% 3.95 29.0%

COSTO TOTAL DEL RUBRO 17.58 129.00%

Page 40: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:SALIDA PARA LAVADORAS. LLAVE DE CONTROL Y ACCESORIOS pto.

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.403 0.40 2.77%

SUBTOTAL M 0.40 2.77%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.32 0.89 6.11%

AYUDANTE (Est. Ocup. E2) 4.00 318.00 2.10 2.78 1.28 3.56 24.44%

ALBANIL (Est. Ocup. D2) 2.00 322.33 2.10 2.82 0.64 1.80 12.40%

PLOMERO (Est. Ocup. D2) 2.00 322.33 2.10 2.82 0.64 1.80 12.40%

SUBTOTAL N 8.06 55.34%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

TUBO HIDRO 3 1/2" AGUA CALIENTE U 0.250 8.000 2.00 13.74%

LLAVE DE PASO FV U 0.300 8.500 2.55 17.51%

CODOS PVC 3/4 U 2.000 0.220 0.44 3.02%

PERMATEX 3 ONZ. U 0.150 1.950 0.29 2.01%

TEE PVC 1/2" U 2.000 0.180 0.36 2.47%

UNION PVC 1/2" U 2.000 0.180 0.36 2.47%

SUBTOTAL O 6.00 41.23%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

TUBO HIDRO 3 1/2" AGUA CALIENTE U 0.250 0.10 0.03 0.17%

LLAVE DE PASO FV U 0.300 0.05 0.02 0.10%

CODOS PVC 3/4 U 2.000 0.01 0.02 0.14%

PERMATEX 3 ONZ. U 0.150 0.01 0.00 0.01%

TEE PVC 1/2" U 2.000 0.01 0.02 0.14%

UNION PVC 1/2" U 2.000 0.01 0.02 0.14%

SUBTOTAL P 0.10 0.70%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 14.56 100%

INDIRECTOS Y UTILIDAD 29.0% 4.22 29.0%

COSTO TOTAL DEL RUBRO 18.78 129.00%

Page 41: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:LLAVE DE PASO 3/4" u

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.090 0.09 0.82%

SUBTOTAL M 0.09 0.82%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.32 0.90 8.26%

AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.32 0.89 8.15%

SUBTOTAL N 1.79 16.41%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

LLAVE DE PASO FV U 1.000 8.500 8.50 77.84%

PERMATEX 3 ONZ. U 0.250 1.950 0.49 4.46%

SUBTOTAL O 8.99 82.30%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

LLAVE DE PASO FV U 1.000 0.05 0.05 0.46%

PERMATEX 3 ONZ. U 0.250 0.01 0.00 0.02%

SUBTOTAL P 0.05 0.48%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 10.92 100%

INDIRECTOS Y UTILIDAD 29.0% 3.17 29.0%

COSTO TOTAL DEL RUBRO 14.09 129.00%

Page 42: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:TUBERIA PVC 1/2" m

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.140 0.14 3.20%

SUBTOTAL M 0.14 3.20%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.50 1.41 32.27%

AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.50 1.39 31.81%

SUBTOTAL N 2.80 64.07%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

TUBO ROSCABLE 1/2" AGUA FRIA U 0.167 8.000 1.33 30.52%

PERMATEX 3 ONZ. U 0.001 1.950 0.00 0.04%

UNION PVC 1/2" U 0.330 0.180 0.06 1.36%

CODOS PVC 1/2" U 0.040 0.180 0.01 0.16%

TEE PVC 1/2" U 0.040 0.180 0.01 0.16%

SUBTOTAL O 1.41 32.25%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

TUBO ROSCABLE 1/2" AGUA FRIA U 0.167 0.10 0.02 0.38%

PERMATEX 3 ONZ. U 0.001 0.01 0.00 0.00%

UNION PVC 1/2" U 0.330 0.01 0.00 0.08%

CODOS PVC 1/2" U 0.040 0.01 0.00 0.01%

TEE PVC 1/2" U 0.040 0.01 0.00 0.01%

SUBTOTAL P 0.02 0.48%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 4.37 100%

INDIRECTOS Y UTILIDAD 29.0% 1.27 29.0%

COSTO TOTAL DEL RUBRO 5.64 129.00%

Page 43: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:LLAVE DE PICO FV DE LAVANDERIA u

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.140 0.14 1.12%

SUBTOTAL M 0.14 1.12%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.50 1.41 11.30%

AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.50 1.39 11.14%

SUBTOTAL N 2.80 22.44%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

LLAVE DE MANGUERA DE PICO U 1.000 9.000 9.00 72.12%

PERMATEX 3 ONZ. U 0.250 1.950 0.49 3.91%

SUBTOTAL O 9.49 76.02%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

LLAVE DE MANGUERA DE PICO U 1.000 0.05 0.05 0.40%

PERMATEX 3 ONZ. U 0.250 0.01 0.00 0.02%

SUBTOTAL P 0.05 0.42%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 12.48 100%

INDIRECTOS Y UTILIDAD 29.0% 3.62 29.0%

COSTO TOTAL DEL RUBRO 16.10 129.00%

Page 44: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:CANALIZACION PVC 50 MM pto.

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.448 0.45 2.77%

SUBTOTAL M 0.45 2.77%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 1.60 4.51 27.87%

AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 1.60 4.45 27.47%

SUBTOTAL N 8.96 55.34%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

POLILIMPIA LT 0.010 8.550 0.09 0.53%

POLIPEGA LT 0.010 10.550 0.11 0.65%

TUBO PVC 50 MM DESAGUE U 1.000 5.330 5.33 32.92%

ACCESORIOS PVC 50 MM U 1.000 1.200 1.20 7.41%

SUBTOTAL O 6.72 41.51%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

POLILIMPIA LT 0.010 0.01 0.00 0.00%

POLIPEGA LT 0.010 0.01 0.00 0.00%

TUBO PVC 50 MM DESAGUE U 1.000 0.05 0.05 0.31%

ACCESORIOS PVC 50 MM U 1.000 0.01 0.01 0.06%

SUBTOTAL P 0.06 0.37%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 16.19 100%

INDIRECTOS Y UTILIDAD 29.0% 4.70 29.0%

COSTO TOTAL DEL RUBRO 20.89 129.00%

Page 45: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:CANALIZACION PVC 110 MM pto.

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.448 0.45 1.74%

SUBTOTAL M 0.45 1.74%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 1.60 4.51 17.49%

AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 1.60 4.45 17.24%

SUBTOTAL N 8.96 34.73%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

POLILIMPIA LT 0.020 8.550 0.17 0.66%

POLIPEGA LT 0.020 10.550 0.21 0.82%

TUBO PVC 110 MM DESAGUE U 1.000 13.350 13.35 51.74%

ACCESORIOS DE PVC 110 MM U 1.000 2.600 2.60 10.08%

SUBTOTAL O 16.33 63.30%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

POLILIMPIA LT 0.020 0.01 0.00 0.00%

POLIPEGA LT 0.020 0.01 0.00 0.00%

TUBO PVC 110 MM DESAGUE U 1.000 0.05 0.05 0.19%

ACCESORIOS DE PVC 110 MM U 1.000 0.01 0.01 0.04%

SUBTOTAL P 0.06 0.23%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 25.80 100%

INDIRECTOS Y UTILIDAD 29.0% 7.48 29.0%

COSTO TOTAL DEL RUBRO 33.28 129.00%

Page 46: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:BAJANTES AGUAS SERVIDAS PVC 110 MM. UNION CODO m

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.056 0.06 0.76%

SUBTOTAL M 0.06 0.76%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.20 0.56 7.69%

AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.20 0.56 7.59%

SUBTOTAL N 1.12 15.28%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

POLILIMPIA LT 0.020 8.550 0.17 2.33%

POLIPEGA LT 0.020 10.550 0.21 2.88%

TUBO PVC 110 MM DESAGUE U 0.333 13.350 4.45 60.65%

ACCESORIOS DE PVC 110 MM U 0.500 2.600 1.30 17.74%

SUBTOTAL O 6.13 83.60%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

POLILIMPIA LT 0.020 0.01 0.00 0.00%

POLIPEGA LT 0.020 0.01 0.00 0.00%

TUBO PVC 110 MM DESAGUE U 0.333 0.05 0.02 0.23%

ACCESORIOS DE PVC 110 MM U 0.500 0.01 0.01 0.07%

SUBTOTAL P 0.02 0.30%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 7.33 100%

INDIRECTOS Y UTILIDAD 29.0% 2.13 29.0%

COSTO TOTAL DEL RUBRO 9.46 129.00%

Page 47: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:BAJANTES DE AGUAS LLUVIAS 110MM. UNION CODO m

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.056 0.06 0.76%

SUBTOTAL M 0.06 0.76%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.20 0.56 7.69%

AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.20 0.56 7.59%

SUBTOTAL N 1.12 15.28%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

POLILIMPIA LT 0.020 8.550 0.17 2.33%

POLIPEGA LT 0.020 10.550 0.21 2.88%

TUBO PVC 110 MM DESAGUE U 0.333 13.350 4.45 60.65%

ACCESORIOS DE PVC 110 MM U 0.500 2.600 1.30 17.74%

SUBTOTAL O 6.13 83.60%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

POLILIMPIA LT 0.020 0.01 0.00 0.00%

POLIPEGA LT 0.020 0.01 0.00 0.00%

TUBO PVC 110 MM DESAGUE U 0.333 0.05 0.02 0.23%

ACCESORIOS DE PVC 110 MM U 0.500 0.01 0.01 0.07%

SUBTOTAL P 0.02 0.30%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 7.33 100%

INDIRECTOS Y UTILIDAD 29.0% 2.13 29.0%

COSTO TOTAL DEL RUBRO 9.46 129.00%

Page 48: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:TUBERIA PVC 110MM DESAGUE (MAT/TRAN/INST) m

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.056 0.06 0.76%

SUBTOTAL M 0.06 0.76%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.20 0.56 7.69%

AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.20 0.56 7.59%

SUBTOTAL N 1.12 15.28%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

POLILIMPIA LT 0.020 8.550 0.17 2.33%

POLIPEGA LT 0.020 10.550 0.21 2.88%

TUBO PVC 110 MM DESAGUE U 0.333 13.350 4.45 60.65%

ACCESORIOS DE PVC 110 MM U 0.500 2.600 1.30 17.74%

SUBTOTAL O 6.13 83.60%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

POLILIMPIA LT 0.020 0.01 0.00 0.00%

POLIPEGA LT 0.020 0.01 0.00 0.00%

TUBO PVC 110 MM DESAGUE U 0.333 0.05 0.02 0.23%

ACCESORIOS DE PVC 110 MM U 0.500 0.01 0.01 0.07%

SUBTOTAL P 0.02 0.30%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 7.33 100%

INDIRECTOS Y UTILIDAD 29.0% 2.13 29.0%

COSTO TOTAL DEL RUBRO 9.46 129.00%

Page 49: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:REJILLA INTERIOR DE PISO 50MM u

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.112 0.11 1.37%

SUBTOTAL M 0.11 1.37%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.40 1.13 13.81%

PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.40 1.11 13.61%

SUBTOTAL N 2.24 27.42%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

REJILLA DE PISO CROMADA FV U 1.000 5.690 5.69 69.65%

ARENA M3 0.001 3.500 0.00 0.04%

CEMENTO SACO 0.010 6.723 0.07 0.82%

SUBTOTAL O 5.76 70.51%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

REJILLA DE PISO CROMADA FV U 1.000 0.05 0.05 0.61%

ARENA M3 0.001 8.50 0.01 0.10%

CEMENTO SACO 0.010 0.50 0.01 0.06%

SUBTOTAL P 0.06 0.78%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 8.17 100%

INDIRECTOS Y UTILIDAD 29.0% 2.37 29.0%

COSTO TOTAL DEL RUBRO 10.54 129.00%

Page 50: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:TABLERO CONTROL GE4-8 PTO.S BREAKER 1 POLO 15-50 A u

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 1.065 1.07 0.93%

SUBTOTAL M 1.07 0.93%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 3.00 8.33 7.25%

ELECTRICISTA (Est. Ocup. D2) 1.00 322.33 2.10 2.82 3.00 8.45 7.35%

MAESTRO MAY. (Est. Ocup. C1) 1.00 346.62 2.09 3.02 1.50 4.52 3.94%

SUBTOTAL N 21.30 18.53%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

TABLERO DE DISTRIBUCION 4 CIRCUITOS U 1.000 50.000 50.00 43.50%

BREAKERS 20 A U 8.000 5.250 42.00 36.54%

SUBTOTAL O 92.00 80.03%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

TABLERO DE DISTRIBUCION 4 CIRCUITOS U 1.000 0.50 0.50 0.43%

BREAKERS 20 A U 8.000 0.01 0.08 0.07%

SUBTOTAL P 0.58 0.50%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 114.95 100%

INDIRECTOS Y UTILIDAD 29.0% 33.34 29.0%

COSTO TOTAL DEL RUBRO 148.29 129.00%

Page 51: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:ILUMINACION. CONDUCTOR N° 12 pto.

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.775 0.78 2.59%

SUBTOTAL M 0.78 2.59%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 1.00 2.78 9.28%

AYUDANTE (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 18.56%

ELECTRICISTA (Est. Ocup. D2) 2.00 322.33 2.10 2.82 2.00 5.64 18.83%

MAESTRO MAY. (Est. Ocup. C1) 1.00 346.62 2.09 3.02 0.50 1.51 5.04%

SUBTOTAL N 15.49 51.72%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

TUBO PVC PESADO DE 1/2" * 3 M U 1.500 1.330 2.00 6.66%

CABLE # 12 SOLIDO ML 10.000 0.480 4.80 16.03%

INTERRUPTOR SIMPLE LUMINEX U 1.000 4.911 4.91 16.40%

BOQUILLA PLAFON U 1.000 0.900 0.90 3.01%

CAJETIN RECTANGULAR PROFUNDO U 1.000 0.480 0.48 1.60%

CAJETIN OCTOGONAL U 1.000 0.350 0.35 1.17%

SUBTOTAL O 13.44 44.86%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

TUBO PVC PESADO DE 1/2" * 3 M U 1.500 0.05 0.08 0.25%

CABLE # 12 SOLIDO ML 10.000 0.01 0.10 0.33%

INTERRUPTOR SIMPLE LUMINEX U 1.000 0.02 0.02 0.07%

BOQUILLA PLAFON U 1.000 0.02 0.02 0.07%

CAJETIN RECTANGULAR PROFUNDO U 1.000 0.01 0.01 0.03%

CAJETIN OCTOGONAL U 1.000 0.01 0.01 0.03%

SUBTOTAL P 0.24 0.78%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 29.95 100%

INDIRECTOS Y UTILIDAD 29.0% 8.69 29.0%

COSTO TOTAL DEL RUBRO 38.64 129.00%

Page 52: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:SALIDA PARA TELEFONOS. ALAMBRE TELEFONICO, ALUG 2 x20 pto.

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.527 0.53 3.69%

SUBTOTAL M 0.53 3.69%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

PEON (Est. Ocup. E2) 2.00 318.00 2.10 2.78 1.00 2.78 19.44%

AYUDANTE (Est. Ocup. E2) 3.00 318.00 2.10 2.78 1.50 4.17 29.16%

ELECTRICISTA (Est. Ocup. D2) 2.00 322.33 2.10 2.82 1.00 2.82 19.72%

MAESTRO MAY. (Est. Ocup. C1) 1.00 346.62 2.09 3.02 0.25 0.76 5.28%

SUBTOTAL N 10.53 73.60%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

TUBO PVC PESADO DE 1/2" * 3 M U 1.000 1.330 1.33 9.30%

ALAMBRE # 20 DE TELEFONO ML 6.500 0.200 1.30 9.09%

CAJETIN RECTANGULAR PROFUNDO U 1.000 0.480 0.48 3.36%

SUBTOTAL O 3.11 21.75%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

TUBO PVC PESADO DE 1/2" * 3 M U 1.000 0.05 0.05 0.35%

ALAMBRE # 20 DE TELEFONO ML 6.500 0.01 0.07 0.45%

CAJETIN RECTANGULAR PROFUNDO U 1.000 0.01 0.01 0.07%

SUBTOTAL P 0.13 0.87%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 14.30 100%

INDIRECTOS Y UTILIDAD 29.0% 4.15 29.0%

COSTO TOTAL DEL RUBRO 18.45 129.00%

Page 53: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:SALIDAS ANTENAS TV u

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.560 0.56 3.50%

SUBTOTAL M 0.56 3.50%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 2.00 5.56 34.79%

ELECTRICISTA (Est. Ocup. D2) 1.00 322.33 2.10 2.82 2.00 5.64 35.29%

SUBTOTAL N 11.20 70.09%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

TUBO PVC PESADO DE 1/2" * 3 M U 1.000 1.330 1.33 8.32%

CABLE COAXIAL TV CABLE ML 6.500 0.350 2.28 14.24%

CAJETIN RECTANGULAR PROFUNDO U 1.000 0.480 0.48 3.00%

SUBTOTAL O 4.09 25.56%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

TUBO PVC PESADO DE 1/2" * 3 M U 1.000 0.05 0.05 0.31%

CABLE COAXIAL TV CABLE ML 6.500 0.01 0.07 0.41%

CAJETIN RECTANGULAR PROFUNDO U 1.000 0.01 0.01 0.06%

SUBTOTAL P 0.13 0.78%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 15.98 100%

INDIRECTOS Y UTILIDAD 29.0% 4.63 29.0%

COSTO TOTAL DEL RUBRO 20.61 129.00%

Page 54: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:TOMACORRIENTE DOBLE 2#10 T.CONDUIT EMT. 1/2" pto

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.775 0.78 2.93%

SUBTOTAL M 0.78 2.93%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

ELECTRICISTA (Est. Ocup. D2) 2.00 322.33 2.10 2.82 2.00 5.64 21.32%

AYUDANTE (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 21.02%

PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 1.00 2.78 10.51%

MAESTRO MAY. (Est. Ocup. C1) 1.00 346.62 2.09 3.02 0.50 1.51 5.71%

SUBTOTAL N 15.49 58.56%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

TUBO PVC PESADO DE 1/2" * 3 M U 1.000 1.330 1.33 5.03%

CABLE # 12 SOLIDO ML 9.000 0.480 4.32 16.33%

TOMACORRIENTE DOBLE POLARIZADO LUMINEX U 1.000 3.880 3.88 14.67%

CAJETIN RECTANGULAR PROFUNDO U 1.000 0.480 0.48 1.81%

SUBTOTAL O 10.01 37.84%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

TUBO PVC PESADO DE 1/2" * 3 M U 1.000 0.05 0.05 0.19%

CABLE # 12 SOLIDO ML 9.000 0.01 0.09 0.34%

TOMACORRIENTE DOBLE POLARIZADO LUMINEX U 1.000 0.02 0.02 0.08%

CAJETIN RECTANGULAR PROFUNDO U 1.000 0.01 0.01 0.04%

SUBTOTAL P 0.17 0.64%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 26.45 100%

INDIRECTOS Y UTILIDAD 29.0% 7.67 29.0%

COSTO TOTAL DEL RUBRO 34.12 129.00%

Page 55: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:PUERTAS PRICIPALES LACADAS u

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.429 0.43 0.20%

SUBTOTAL M 0.43 0.20%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 2.65%

CARPINTERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 1.00 3.02 1.44%

SUBTOTAL N 8.58 4.09%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

PUERTAS DE MADERA PRINCIPAL U 1.000 200.000 200.00 95.23%

SUBTOTAL O 200.00 95.23%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

PUERTAS DE MADERA PRINCIPAL U 1.000 1.00 1.00 0.48%

SUBTOTAL P 1.00 0.48%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 210.01 100%

INDIRECTOS Y UTILIDAD 29.0% 60.90 29.0%

COSTO TOTAL DEL RUBRO 270.91 129.00%

Page 56: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:MUEBLE BAJO COCINA (TABLERO TRIPLEX) m

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.290 0.29 0.23%

SUBTOTAL M 0.29 0.23%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 1.00 2.78 2.19%

CARPINTERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 1.00 3.02 2.38%

SUBTOTAL N 5.80 4.56%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

MUEBLES BAJOS DE COCINA ML 1.000 120.000 120.00 94.42%

SUBTOTAL O 120.00 94.42%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

MUEBLES BAJOS DE COCINA ML 1.000 1.00 1.00 0.79%

SUBTOTAL P 1.00 0.79%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 127.09 100%

INDIRECTOS Y UTILIDAD 29.0% 36.86 29.0%

COSTO TOTAL DEL RUBRO 163.95 129.00%

Page 57: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:MUEBLES ALTOS DE COCINA (TABLERO TRIPLEX) m

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.429 0.43 0.33%

SUBTOTAL M 0.43 0.33%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 4.28%

CARPINTERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 1.00 3.02 2.32%

SUBTOTAL N 8.58 6.60%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

MUEBLES ALTOS DE COCINA ML 1.000 120.000 120.00 92.30%

SUBTOTAL O 120.00 92.30%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

MUEBLES ALTOS DE COCINA ML 1.000 1.00 1.00 0.77%

SUBTOTAL P 1.00 0.77%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 130.01 100%

INDIRECTOS Y UTILIDAD 29.0% 37.70 29.0%

COSTO TOTAL DEL RUBRO 167.71 129.00%

Page 58: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:CLOSET (TABLERO TRIPLEX) m2

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.429 0.43 0.33%

SUBTOTAL M 0.43 0.33%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 4.28%

CARPINTERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 1.00 3.02 2.32%

SUBTOTAL N 8.58 6.60%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CLOSETS M2 1.000 120.000 120.00 92.30%

SUBTOTAL O 120.00 92.30%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CLOSETS M2 1.000 1.00 1.00 0.77%

SUBTOTAL P 1.00 0.77%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 130.01 100%

INDIRECTOS Y UTILIDAD 29.0% 37.70 29.0%

COSTO TOTAL DEL RUBRO 167.71 129.00%

Page 59: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:CERRADURA PRINCIPAL (CESA), TIPO NOVA CROMADA u

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.429 0.43 0.46%

SUBTOTAL M 0.43 0.46%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 5.91%

CARPINTERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 1.00 3.02 3.21%

SUBTOTAL N 8.58 9.12%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CERRADURA PRINCIPAL U 1.000 85.000 85.00 90.32%

SUBTOTAL O 85.00 90.32%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CERRADURA PRINCIPAL U 1.000 0.10 0.10 0.11%

SUBTOTAL P 0.10 0.11%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 94.11 100%

INDIRECTOS Y UTILIDAD 29.0% 27.29 29.0%

COSTO TOTAL DEL RUBRO 121.40 129.00%

Page 60: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:CERRADURA DORMITORIO (CESA)TIPO, NOVA CROMADA u

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.429 0.43 2.03%

SUBTOTAL M 0.43 2.03%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 26.34%

CARPINTERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 1.00 3.02 14.31%

SUBTOTAL N 8.58 40.64%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CERRADURA LLAVE SEGURO GEO O YALE ITAL. U 1.000 12.000 12.00 56.85%

SUBTOTAL O 12.00 56.85%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CERRADURA LLAVE SEGURO GEO O YALE ITAL. U 1.000 0.10 0.10 0.47%

SUBTOTAL P 0.10 0.47%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 21.11 100%

INDIRECTOS Y UTILIDAD 29.0% 6.12 29.0%

COSTO TOTAL DEL RUBRO 27.23 129.00%

Page 61: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:CERRADURA BAÑO (CESA), TIPO NOVA CROMADA u

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.429 0.43 2.24%

SUBTOTAL M 0.43 2.24%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 29.09%

CARPINTERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 1.00 3.02 15.80%

SUBTOTAL N 8.58 44.90%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CERRADURA DE BAÑO U 1.000 10.000 10.00 52.33%

SUBTOTAL O 10.00 52.33%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CERRADURA DE BAÑO U 1.000 0.10 0.10 0.52%

SUBTOTAL P 0.10 0.52%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 19.11 100%

INDIRECTOS Y UTILIDAD 29.0% 5.54 29.0%

COSTO TOTAL DEL RUBRO 24.65 129.00%

Page 62: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:CERRADURA PASILLO (CESA), TIPO NOVA CROMADA u

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.429 0.43 2.03%

SUBTOTAL M 0.43 2.03%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 26.34%

CARPINTERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 1.00 3.02 14.31%

SUBTOTAL N 8.58 40.64%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

CERRADURA LLAVE SEGURO GEO O YALE ITAL. U 1.000 12.000 12.00 56.85%

SUBTOTAL O 12.00 56.85%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

CERRADURA LLAVE SEGURO GEO O YALE ITAL. U 1.000 0.10 0.10 0.47%

SUBTOTAL P 0.10 0.47%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 21.11 100%

INDIRECTOS Y UTILIDAD 29.0% 6.12 29.0%

COSTO TOTAL DEL RUBRO 27.23 129.00%

Page 63: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:PASAMANO DE HIERRO C/MANGON MADERA m

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.290 0.29 0.43%

SUBTOTAL M 0.29 0.43%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 1.00 2.78 4.14%

INSTALADOR (Est. Ocup. D2) 1.00 322.33 2.10 3.02 1.00 3.02 4.50%

SUBTOTAL N 5.80 8.65%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

MANGON DE MADERA ML 1.000 20.000 20.00 29.81%

PASAMANO DE HIERRO M 1.000 40.000 40.00 205.55%

SUBTOTAL O 60.00 235.36%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

MANGON DE MADERA ML 1.000 0.50 0.50 0.75%

PASAMANO DE HIERRO M 1.000 0.50 0.50 2.57%

SUBTOTAL P 1.00 3.31%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 67.09 250%

INDIRECTOS Y UTILIDAD 29.0% 19.46 29.0%

COSTO TOTAL DEL RUBRO 86.55 279.00%

Page 64: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:PUERTA DE PLYWOOD TAMBOR 0.70 LACADA, INCLUYE MARCOS Y TAPAMARCOS u

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.429 0.43 0.33%

SUBTOTAL M 0.43 0.33%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 4.28%

CARPINTERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 1.00 3.02 2.32%

SUBTOTAL N 8.58 6.60%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

PUERTAS TAMBORADAS DE 0,70 U 1.000 120.000 120.00 92.30%

SUBTOTAL O 120.00 92.30%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

PUERTAS TAMBORADAS DE 0,70 U 1.000 1.00 1.00 0.77%

SUBTOTAL P 1.00 0.77%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 130.01 100%

INDIRECTOS Y UTILIDAD 29.0% 37.70 29.0%

COSTO TOTAL DEL RUBRO 167.71 129.00%

Page 65: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:PUERTA DE PLYWOOD TAMBOR 0.80 LACADA, INCLUYE MARCOS Y TAPAMARCOS u

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.429 0.43 0.30%

SUBTOTAL M 0.43 0.30%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 3.83%

CARPINTERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 1.00 3.02 2.08%

SUBTOTAL N 8.58 5.92%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

PUERTAS TAMBORADAS DE 0,90 U 1.000 135.000 135.00 93.10%

SUBTOTAL O 135.00 93.10%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

PUERTAS TAMBORADAS DE 0,90 U 1.000 1.00 1.00 0.69%

SUBTOTAL P 1.00 0.69%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 145.01 100%

INDIRECTOS Y UTILIDAD 29.0% 42.05 29.0%

COSTO TOTAL DEL RUBRO 187.06 129.00%

Page 66: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:PUERTA DE PLYWOOD TAMBOR 0.90 LACADA, INCLUYE MARCOS Y TAPAMARCOS u

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.429 0.43 0.30%

SUBTOTAL M 0.43 0.30%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 3.83%

CARPINTERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 1.00 3.02 2.08%

SUBTOTAL N 8.58 5.92%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

PUERTAS TAMBORADAS DE 0,90 U 1.000 135.000 135.00 93.10%

SUBTOTAL O 135.00 93.10%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

PUERTAS TAMBORADAS DE 0,90 U 1.000 1.00 1.00 0.69%

SUBTOTAL P 1.00 0.69%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 145.01 100%

INDIRECTOS Y UTILIDAD 29.0% 42.05 29.0%

COSTO TOTAL DEL RUBRO 187.06 129.00%

Page 67: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:TANQUE CALENTADOR 30 GL. u

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.280 0.28 0.10%

SUBTOTAL M 0.28 0.10%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 1.00 2.78 1.00%

PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 1.00 2.82 1.02%

SUBTOTAL N 5.60 2.02%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

TANQUE CALENTOR 30 GL U 1.000 263.393 263.39 94.87%

VALVULA CHECKE FV U 1.000 5.500 5.50 1.98%

ACCESORIOS IPS U 4.000 0.300 1.20 0.43%

PERMATEX 3 ONZ. U 0.300 1.950 0.59 0.21%

SUBTOTAL O 270.68 97.49%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

TANQUE CALENTOR 30 GL U 1.000 1.00 1.00 0.36%

VALVULA CHECKE FV U 1.000 0.05 0.05 0.02%

ACCESORIOS IPS U 4.000 0.01 0.04 0.01%

PERMATEX 3 ONZ. U 0.300 0.01 0.00 0.00%

SUBTOTAL P 1.09 0.39%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 277.65 100%

INDIRECTOS Y UTILIDAD 29.0% 80.52 29.0%

COSTO TOTAL DEL RUBRO 358.17 129.00%

Page 68: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:PINTURA DE CAUCHO INTERIOR 2 MANOS, LATEX VINYL ACRILICO, CEMENTO BLANCO. EQUIPO: ANDAMIOS m2

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.056 0.06 1.92%

ANDAMIOS 0.040 0.19 0.200 0.00 0.05%

SUBTOTAL M 0.06 1.97%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.20 0.56 19.04%

PINTOR (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.20 0.56 19.32%

SUBTOTAL N 1.12 38.36%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

PINTURA DE CAUCHO PERMALATEX GL 0.080 16.518 1.32 45.25%

LIJA # 60 PLG. 0.200 0.446 0.09 3.06%

CARBONATO DE CALCIO TIPO A KG 0.020 0.230 0.00 0.16%

RESAFLEX GL 0.020 13.393 0.27 9.17%

YESO KG 0.100 0.500 0.05 5.88%

SUBTOTAL O 1.73 63.53%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

PINTURA DE CAUCHO PERMALATEX GL 0.080 0.05 0.00 0.14%

LIJA # 60 PLG. 0.200 0.01 0.00 0.07%

CARBONATO DE CALCIO TIPO A KG 0.020 0.01 0.00 0.01%

RESAFLEX GL 0.020 0.05 0.00 0.03%

YESO KG 0.100 0.01 0.00 0.12%

SUBTOTAL P 0.01 0.36%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 2.92 100%

INDIRECTOS Y UTILIDAD 29.0% 0.85 29.0%

COSTO TOTAL DEL RUBRO 3.77 129.00%

Page 69: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:PINTURA DE CAUCHO EXTERIOR 2 MANOS, LATEX VINYL ACRILICO, CEMENTO BLANCO. EQUIPO: ANDAMIOS m2

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.070 0.07 2.18%

ANDAMIOS 0.040 0.19 0.250 0.00 0.06%

SUBTOTAL M 0.07 2.24%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.25 0.70 21.65%

PINTOR (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.25 0.71 21.96%

SUBTOTAL N 1.40 43.61%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

PINTURA DE CAUCHO PERMALATEX GL 0.080 16.518 1.32 41.17%

LIJA # 60 PLG. 0.200 0.446 0.09 2.78%

CARBONATO DE CALCIO TIPO A KG 0.020 0.230 0.00 0.14%

RESAFLEX GL 0.020 13.393 0.27 8.34%

YESO KG 0.100 0.500 0.05 5.38%

SUBTOTAL O 1.73 57.81%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

PINTURA DE CAUCHO PERMALATEX GL 0.080 0.05 0.00 0.12%

LIJA # 60 PLG. 0.200 0.01 0.00 0.06%

CARBONATO DE CALCIO TIPO A KG 0.020 0.01 0.00 0.01%

RESAFLEX GL 0.020 0.05 0.00 0.03%

YESO KG 0.100 0.01 0.00 0.11%

SUBTOTAL P 0.01 0.33%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 3.21 100%

INDIRECTOS Y UTILIDAD 29.0% 0.93 29.0%

COSTO TOTAL DEL RUBRO 4.14 129.00%

Page 70: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:PINTURA CAUCHO CIELO RAZO. LATEX VINYL ACRILICO, CEMENTO BLANCO. EQUIPO: ANDAMIOS m2

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.070 0.07 2.18%

ANDAMIOS 0.040 0.19 0.250 0.00 0.06%

SUBTOTAL M 0.07 2.24%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.25 0.70 21.65%

PINTOR (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.25 0.71 21.96%

SUBTOTAL N 1.40 43.61%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

PINTURA DE CAUCHO PERMALATEX GL 0.080 16.518 1.32 41.17%

LIJA # 60 PLG. 0.200 0.446 0.09 2.78%

CARBONATO DE CALCIO TIPO A KG 0.020 0.230 0.00 0.14%

RESAFLEX GL 0.020 13.393 0.27 8.34%

YESO KG 0.100 0.500 0.05 5.38%

SUBTOTAL O 1.73 57.81%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

PINTURA DE CAUCHO PERMALATEX GL 0.080 0.05 0.00 0.12%

LIJA # 60 PLG. 0.200 0.01 0.00 0.06%

CARBONATO DE CALCIO TIPO A KG 0.020 0.01 0.00 0.01%

RESAFLEX GL 0.020 0.05 0.00 0.03%

YESO KG 0.100 0.01 0.00 0.11%

SUBTOTAL P 0.01 0.33%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 3.21 100%

INDIRECTOS Y UTILIDAD 29.0% 0.93 29.0%

COSTO TOTAL DEL RUBRO 4.14 129.00%

Page 71: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:TEJA COMUN INC. TIRAS EUCALIP.MORTERO 1:3 m2

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.211 0.21 1.07%

SUBTOTAL M 0.21 1.07%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.73 2.02 10.20%

INSTALADOR (Est. Ocup. D2) 1.00 322.33 2.10 3.02 0.73 2.20 11.08%

SUBTOTAL N 4.22 21.29%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

ECUATEJA CLASICA M2 1.050 9.821 10.31 52.06%

TIRAS DE MADERA U 3.000 1.500 4.50 22.72%

CLAVOS DE ACERO 1.5 " NEGRO U 0.250 0.030 0.01 0.04%

SUBTOTAL O 14.82 74.81%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

ECUATEJA CLASICA M2 1.050 0.50 0.53 2.65%

TIRAS DE MADERA U 3.000 0.01 0.03 0.15%

CLAVOS DE ACERO 1.5 " NEGRO U 0.250 0.01 0.00 0.01%

SUBTOTAL P 0.56 2.81%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 19.81 100%

INDIRECTOS Y UTILIDAD 29.0% 5.74 29.0%

COSTO TOTAL DEL RUBRO 25.55 129.00%

Page 72: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:LAVAMANOS POMPANO BLANCO u

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.448 0.45 0.50%

SUBTOTAL M 0.45 0.50%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 1.60 4.45 4.99%

PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 1.60 4.51 5.06%

SUBTOTAL N 8.96 10.05%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

LAVAMANOS CHELSEA AZUL COBALTO O SIMILAR U 1.000 40.000 40.00 44.87%

LLAVE FV 221/78 CROMADA VERSALLES U 1.000 25.000 25.00 28.04%

TUBO DE ABASTO 1/2" DE NYLON U 2.000 4.550 9.10 10.21%

SIFON DESAGUE - LAVAVO U 1.000 4.800 4.80 5.38%

SUBTOTAL O 78.90 88.50%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

LAVAMANOS CHELSEA AZUL COBALTO O SIMILAR U 1.000 0.50 0.50 0.56%

LLAVE FV 221/78 CROMADA VERSALLES U 1.000 0.25 0.25 0.28%

TUBO DE ABASTO 1/2" DE NYLON U 2.000 0.02 0.04 0.04%

SIFON DESAGUE - LAVAVO U 1.000 0.05 0.05 0.06%

SUBTOTAL P 0.84 0.94%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 89.15 100%

INDIRECTOS Y UTILIDAD 29.0% 25.85 29.0%

COSTO TOTAL DEL RUBRO 115.00 129.00%

Page 73: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:INODORO TANQUE BAJO TIPO SAVEX u

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.448 0.45 0.22%

SUBTOTAL M 0.45 0.22%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 1.60 4.45 2.17%

PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 1.60 4.51 2.20%

SUBTOTAL N 8.96 4.37%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

INODORO TANQUE BAJO LINEA INTERM. COLOR SUAVE U 1.000 140.000 140.00 68.28%

TUBO DE ABASTO 1/2" DE NYLON U 1.000 4.550 4.55 2.22%

CEMENTO SACO 0.010 6.723 0.07 0.03%

ARENA M3 0.030 3.500 0.11 0.05%

ANILLO DE CERA U 3.000 8.000 24.00 11.71%

TACOS FISHER Y TORNILLO U 3.000 0.700 2.10 1.02%

SUBTOTAL O 170.82 83.31%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

INODORO TANQUE BAJO LINEA INTERM. COLOR SUAVE U 1.000 0.50 0.50 0.24%

TUBO DE ABASTO 1/2" DE NYLON U 1.000 0.02 0.02 0.01%

CEMENTO SACO 0.010 0.50 0.01 0.00%

ARENA M3 0.030 8.50 0.26 0.12%

ANILLO DE CERA U 3.000 8.00 24.00 11.71%

TACOS FISHER Y TORNILLO U 3.000 0.01 0.03 0.01%

SUBTOTAL P 24.81 12.10%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 205.04 100%

INDIRECTOS Y UTILIDAD 29.0% 59.46 29.0%

COSTO TOTAL DEL RUBRO 264.50 129.00%

Page 74: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:LAVAPLATOS COMPLETO, GRIFERIA u

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.839 0.84 0.28%

SUBTOTAL M 0.84 0.28%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 3.00 8.33 2.78%

PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 3.00 8.45 2.82%

SUBTOTAL N 16.78 5.61%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

FREGADERO TEKA O SIMILAR 1* .50 M U 1.000 98.500 98.50 32.93%

MEZCLADORA DE COCINA CROMO-ORO U 1.000 166.786 166.79 55.76%

PERMATEX 3 ONZ. U 0.100 1.950 0.20 0.07%

TUBO DE ABASTO 1/2" DE NYLON U 2.000 4.550 9.10 3.04%

SIFON DESAGUE - FREGADERO U 1.000 5.800 5.80 1.94%

SUBTOTAL O 280.38 93.74%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

FREGADERO TEKA O SIMILAR 1* .50 M U 1.000 0.50 0.50 0.17%

MEZCLADORA DE COCINA CROMO-ORO U 1.000 0.50 0.50 0.17%

PERMATEX 3 ONZ. U 0.100 0.01 0.00 0.00%

TUBO DE ABASTO 1/2" DE NYLON U 2.000 0.02 0.04 0.01%

SIFON DESAGUE - FREGADERO U 1.000 0.05 0.05 0.02%

SUBTOTAL P 1.09 0.36%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 299.09 100%

INDIRECTOS Y UTILIDAD 29.0% 86.74 29.0%

COSTO TOTAL DEL RUBRO 385.83 129.00%

Page 75: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:ACCESORIOS DE BAÑO jg

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.302 0.30 0.72%

SUBTOTAL M 0.30 0.72%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

INSTALADOR (Est. Ocup. D2) 1.00 322.33 2.10 3.02 2.00 6.04 14.37%

SUBTOTAL N 6.04 14.37%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

JUEGO DE ACCESORIOS SPAZZIO U 1.000 28.384 28.38 67.55%

TACOS FISHER Y TORNILLO U 10.000 0.700 7.00 16.66%

SUBTOTAL O 35.38 84.21%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

JUEGO DE ACCESORIOS SPAZZIO U 1.000 0.20 0.20 0.48%

TACOS FISHER Y TORNILLO U 10.000 0.01 0.10 0.24%

SUBTOTAL P 0.30 0.71%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 42.02 100%

INDIRECTOS Y UTILIDAD 29.0% 12.19 29.0%

COSTO TOTAL DEL RUBRO 54.21 129.00%

Page 76: Precios Unitarios

ANALISIS DE PRECIOS UNITARIOS

UNIDAD:

RUBRO:DUCHA SENCILLA CROMADA COMPLETA - INCL. MEZCLADORA Y GRIFERIA u

DETALLE: 0

EQUIPOS

DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %

HERRAMIENTA MANUAL 5 % M.O. 0.560 0.56 0.59%

SUBTOTAL M 0.56 0.59%

MANO DE OBRA

DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %

AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 2.00 5.56 5.90%

PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 2.00 5.64 5.99%

SUBTOTAL N 11.20 11.89%

MATERIALES

DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %

MEZCLADORA DE DUCHA MALENA U 1.000 82.000 82.00 87.04%

PERMATEX 3 ONZ. U 0.100 1.950 0.20 0.21%

SUBTOTAL O 82.20 87.25%

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %

MEZCLADORA DE DUCHA MALENA U 1.000 0.25 0.25 0.27%

PERMATEX 3 ONZ. U 0.100 0.01 0.00 0.00%

SUBTOTAL P 0.25 0.27%

TOTAL COSTOS DIRECTOS X=(M+N+O+P) 94.21 100%

INDIRECTOS Y UTILIDAD 29.0% 27.32 29.0%

COSTO TOTAL DEL RUBRO 121.53 129.00%

Page 77: Precios Unitarios

(hora/und) EQUIPO MANO DE OBRA COSTO HO

0.320 1 HERRAMIENTA MANUAL 5 % M.O. 1 PEON (Est. Ocup. E2) 2.78

2 CARGADORA FRONTAL 40.00 2 AYUDANTE (Est. Ocup. E2) 2.78

25 1 3 VOLQUETE 10 M3 30.00 3 ALBANIL (Est. Ocup. D2) 2.82

4 MOTONIVELADORA 35.00 4 ADOQUINADOR (Est. Ocup. D 2.82

5 RODILLO VIBRATORIO LISO 25.00 5 FIERRERO (Est. Ocup. D2) 2.82

6 PLANCHA VIBROCOMPAC. 3.00 6 MAESTRO MAY. (Est. Ocup. C 3.02

7 TANQUERO 15.00 7 CHOFER TIPO E VOLQUETAS( 4.16

8 ENCOFRADO METALICO 0.05 8 OPERADOR EQUIPO PESADO G 3.02

9 CONCRETERA 6.50 9 OPERADOR EQUIPO PESADO G 2.94

10 VIBRADOR 4.00 10 PLOMERO (Est. Ocup. D2) 2.82

11 EXCAVADORA 30.00 11 PINTOR (Est. Ocup. D2) 2.82

12 ACABADORA DE ASFALTO 35.00 12 AY. MAQUINARIA (Est. Ocup. 2.82

13 DISTRIBUIDOR DE ASFALTO 25.00 13 ENLUCIDOR (Est. Ocup. D2) 2.82

14 RODILLO NEUMATICO 18.00 14 ELECTRICISTA (Est. Ocup. D2 2.82

15 PLANTA ASFALTICA + GENERADOR 100.00 15 MAESTRO SOL. ESP. (Est. Ocu 3.02

16 ESCOBA MECANICA 10.00 16 INSTALADOR (Est. Ocup. D2) 2.82

17 COMPRESOR 12.00 17 CARPINTERO (Est. Ocup. D2) 2.82

18 ESTACION TOTAL 2.50 18 TOPOGRAFO 2 (Est. Ocup. C1 3.02

19 PULIDORA 4.00 19 CADENERO (Est. Ocup. D2) 2.82

20 ELEVADOR 5.00

21 EQUIPO DE SUELDA Y PINTURA 1.20

22 ENCOFRADO DE MADERA 5.000

23 ANDAMIOS 0.188

MATERIALES

1 CEMENTO 6.72 SACO 1

2 ARENA 3.50 M3 2

3 RIPIO 4.50 M3 3

4 AGUA 0.220 M3 4

5 PIEDRA BOLA 4.50 M3 5

6 ALAMBRE DE AMARRE # 18 2.22 KG 6

7 ACERO DE REFUERZO 1.08 KG 7

8 ACERO ESTRUCTURAL 1.06 KG 8

9 TABLA DURA DE ENCOFRADO 1.60 U 9

10 RIELES DE EUCALIPTO 2.23 U 10

11 CLAVOS 2 - 2.5, 3 " 1.57 KG 11

12 PINGOS 2.5 1.43 U 12

13 LADRILLO TIPO CHAMBO 0.12 U 13

14 IMPERMEABILIZANTE SIKA 1 1.25 KG 14

15 MARMOL PULIDO Y ABRILLANTADO IMPORTADO 150.00 ML 15

16 CERAMICA EN PARED 12.08 M2 16

17 CERAMICA EN PISO 12.54 M2 17

18 EMPORADOR 1.44 KG 18

19 CENEFA DE CERAMICA 10.72 ML 19

20 ECUATEJA CLASICA 9.82 M2 20

21 TIRAS DE MADERA 1.50 U 21

22 CLAVOS DE ACERO 1.5 " NEGRO 0.03 U 22

23 PARQUET CHANUL O COLORADO PULIDO Y LACADO 3 MANOS 45.00 M2 23

24 PINTURA DE CAUCHO PERMALATEX 16.52 GL 24

25 BROCHA 5.36 U 25

26 LIJA # 60 0.45 PLG. 26

27 CARBONATO DE CALCIO TIPO A 0.23 KG 27

28 RESAFLEX 13.39 GL 28

29 PINTURA ANTICORROSIVA 18.58 GL 29

30 VENTANAS DE AL. Y VIDRIO CORREDIZA 45.00 M2 30

31 MUEBLES BAJOS DE COCINA 120.00 ML 31

32 MUEBLES ALTOS DE COCINA 120.00 ML 32

33 CLOSETS 120.00 M2 33

34 CERRADURA DE BAÑO 10.00 U 34

35 CERRADURA PRINCIPAL 85.00 U 35

36 CERRADURA LLAVE SEGURO GEO O YALE ITAL. 12.00 U 36

Page 78: Precios Unitarios

37 MANGON DE MADERA 20.00 ML 37

(hora/und) 38 PASAMANO DE HIERRO 40.00 M 38

0.140 39 PLATINA DE 1/2 * 1/8 * 6 M 2.80 U 39

REND 40 SUELDA 60 11 2.40 KG 40

57 2 41 TUBO RECTANGULAR 20 * 40 * 6 M 16.12 U 41

42 VARILLA CUADRADA DE 1/2 " * 6 M 5.60 U 42

43 TOL LAMINADO AL FRIO 1/32 29.00 PL. 43

44 PUERTAS TAMBORADAS DE 0,90 135.00 U 44

45 PUERTAS DE MADERA PRINCIPAL 200.00 U 45

46 PUERTAS TAMBORADAS DE 0,70 120.00 U 46

47 CHAPA ELECTRICA VIRO 80.00 U 47

48 LLAVE DE PASO FV 8.50 U 48

49 LLAVE DE MANGUERA DE PICO 9.00 U 49

50 LLAVE VALVULA ITAL. DE 1/2" 4.50 U 50

51 TUBO ROSCABLE 1/2" AGUA FRIA 8.00 U 51

52 TUBO HIDRO 3 1/2" AGUA CALIENTE 8.00 U 11.52 52

53 TEFLON 0.45 U 16.13 53

54 PERMATEX 3 ONZ. 1.95 U 27.66 54

55 ACCESORIOS IPS 0.30 U 55

56 MEDIDOR DE AGUA 90.00 U 56

57 ACCESORIOS DE PVC 110 MM 2.60 U 57

58 ACCESORIOS DE PVC 75 MM 2.25 U 58

59 ACCESORIOS PVC 50 MM 1.20 U 59

60 POLIPEGA 10.55 LT 60

61 POLILIMPIA 8.55 LT 61

62 TUBERIA DE H.S. 150 MM M.C. 2.50 U 62

63 REJILLA DE PISO CROMADA FV 5.69 U 63

64 CAJETIN RECTANGULAR PROFUNDO 0.48 U 64

65 CAJETIN OCTOGONAL 0.35 U 65

66 TUBO PVC PESADO DE 1/2" * 3 M 1.33 U 66

67 TUBO PVC LIVIANO DE 1/2" * 3 M 1.21 U 67

68 TUBO PVC PESADO DE 3/4" * 3 M 1.79 U 68

69 CABLE # 12 SOLIDO 0.48 ML 69

70 CABLE # 14 SOLIDO 0.35 ML 70

71 CABLE # 8 VARIOS HILOS 1.36 ML 71

72 ALAMBRE # 20 DE TELEFONO 0.20 ML 72

73 CABLE COAXIAL TV CABLE 0.35 ML 73

74 CABLE 8 HILOS PORTERO ELECTRICO 1.65 ML 74

75 BOQUILLA PLAFON 0.90 U 75

76 TOMACORRIENTE DOBLE POLARIZADO LUMINEX 3.88 U 76

77 INTERRUPTOR SIMPLE LUMINEX 4.91 U 77

78 CONMUTADOR LUMINEX 5.46 U 78

79 TOMA ESPECIAL ELECTRICA TV CABLE - TELEF. 5.80 U 79

80 PORTERO ELECTRICO 1 DPTO. + 1 EXTENSION 133.93 U 80

81 CODOS PVC 1/2" 0.18 U 81

82 CODOS PVC 3/4 0.22 U 82

83 TABLERO DE DISTRIBUCION 4 CIRCUITOS 50.00 U 83

84 BREAKERS 20 A 5.25 U 84

85 MEDIDOR DE LUZ 120.00 U 85

86 FREGADERO TEKA O SIMILAR 1* .50 M 98.50 U 86

87 MEZCLADORA DE COCINA CROMO-ORO 166.79 U 87

88 TUBO DE ABASTO 1/2" DE NYLON 4.55 U 88

89 SIFON DESAGUE - FREGADERO 5.80 U 89

90 INODORO TANQUE BAJO LINEA INTERM. COLOR SUAVE 140.00 U 90

91 INODORO TANQUE BAJO LINEA INTERM. COLOR FUERTE 150.00 U 91

92 LAVAMANOS EMPOTRABLE OACKBROOK COL. SUAVE 30.00 U 92

93 LAVAMANOS CHELSEA AZUL COBALTO O SIMILAR 40.00 U 93

94 MEZCLADORA DE LAVAVO FV FUTURA 67/102 4" 130.36 U 94

95 LLAVE FV 221/78 CROMADA VERSALLES 25.00 U 95

96 SIFON DESAGUE - LAVAVO 4.80 U 96

97 JUEGO DE ACCESORIOS SPAZZIO 28.38 U 97

98 TANQUE CALENTOR 30 GL 263.39 U 98

99 VALVULA CHECKE FV 5.50 U 99

Page 79: Precios Unitarios

100 MANGUERA - SALIDA DE GAS 1.60 ML 100

(hora/und) 101 DERIVACION DE COBRE PARA COCINA - CALEFON 4.50 U 101

0.800 102 ABRAZADERAS 0.16 U 102

REND 103 EXTRACTOR DE OLORES JET AIR 125.00 U 103

10 3 104 CHAMPEADORA MANUAL 1.60 U 104

105 YESO 0.50 KG 105

106 BLOQUE ALIVIANADO PARA LOSA E=15 CM. 0.35 U 106

107 SUBBASE CLASE 3 2.50 M3 107

108 BARREDERAS INSTALADAS a=9 CM 6.00 ML 108

109 MEDIA DUELA DE CHANDUL MACHIMBRADA 30.00 M2 109

110 PLATINA DE 1" * 3/16 * 6M. 7.07 U 110

111 BISAGRAS 5/8 * 3" PUERTA DE HIERRO 1.00 U 111

112 PICAPORTE HIERRO 5.50 U 112

113 VIDRIO CATEDRAL 4 MM. INSTALADO 9.82 M2 113

114 MEZCLADORA DE DUCHA MALENA 82.00 U 114

115 TUBO PVC 110 MM DESAGUE 13.35 U 115

116 TUBO PVC 75 MM DESAGUE 11.96 U 116

117 TUBO PVC 50 MM DESAGUE 5.33 U 117

118 SILICON DE PISTOLA 4.25 U 118

119 PINTURA ESMALTE COLOR 17.56 GL 119

120 CHAPA PHILIPS SENCILLA O TRAVEX 25.00 U 120

121 ENCOFRADO DE LOSA 1.60 M2 121

122 ADITIVO 2.230 KG 122

123 ENCOFRADO 5.960 M2 123

124 CLAVOS,ALAMBRE, VARIOS 2.000 GLB 124

125 BONDEX 5.600 SACO 125

126 POLIETILENO 1.000 M2 126

127 PORCELANATO 25.000 M2 127

128 BONDEX PREMIUM 10.500 SACO 128

129 TEE PVC 1/2" 0.180 U 129

130 UNION PVC 1/2" 0.180 U 130

131 TACOS FISHER Y TORNILLO 0.700 U 131

132 ANILLO DE CERA 8.000 U 132

Page 80: Precios Unitarios

(hora/und)

0.040

REND

200 4

Page 81: Precios Unitarios

(hora/und)

0.533

REND

15 5

Page 82: Precios Unitarios

(hora/und)

1.000

REND

8 6

Page 83: Precios Unitarios

(hora/und)

1.333

REND

6 7

Page 84: Precios Unitarios

(hora/und)

2.667

REND

3 8

Page 85: Precios Unitarios

(hora/und)

2.667

REND

3 9

Page 86: Precios Unitarios

(hora/und)

1.600

REND

5 10

Page 87: Precios Unitarios

(hora/und)

4.000

REND

2 11

0.050.0540.104

0.7488

Page 88: Precios Unitarios

(hora/und)

1.600

REND

5 12

Page 89: Precios Unitarios

(hora/und)

0.020

REND

400 13

Page 90: Precios Unitarios

(hora/und)

0.030

REND

267 14

10.02

Page 91: Precios Unitarios

(hora/und)

0.500

REND

16 15

Page 92: Precios Unitarios

(hora/und)

0.333

REND

24 17

Page 93: Precios Unitarios

(hora/und)

1.000

REND

8 16

Page 94: Precios Unitarios

(hora/und)

11.940

REND

0.67 18

Page 95: Precios Unitarios

(hora/und)

2.500

REND

3.2 19

Page 96: Precios Unitarios

(hora/und)

1.000

REND

8 20

Page 97: Precios Unitarios

(hora/und)

0.615

REND

13 21

Page 98: Precios Unitarios

(hora/und)

0.889

REND

9 22

Page 99: Precios Unitarios

(hora/und)

0.889

REND

9 23

Page 100: Precios Unitarios

(hora/und)

0.889

REND

9 24

Page 101: Precios Unitarios

(hora/und)

0.727

REND

11 25

Page 102: Precios Unitarios

(hora/und)

0.727

REND

11 26

Page 103: Precios Unitarios

(hora/und)

0.727

REND

11 27

Page 104: Precios Unitarios

(hora/und)

0.250

REND

32 28

Page 105: Precios Unitarios

(hora/und)

0.800

REND

10 29

Page 106: Precios Unitarios

(hora/und)

0.727

REND

11 30

Page 107: Precios Unitarios

(hora/und)

0.889

REND

9 31

Page 108: Precios Unitarios

(hora/und)

0.151

REND

53 32

Page 109: Precios Unitarios

(hora/und)

2.996

REND

2.67 33

Page 110: Precios Unitarios

(hora/und)

0.500

REND

16 34

Page 111: Precios Unitarios

(hora/und)

0.320

REND

25 35

Page 112: Precios Unitarios

(hora/und)

0.320

REND

25 36

Page 113: Precios Unitarios

(hora/und)

0.320

REND

25 37

Page 114: Precios Unitarios

(hora/und)

0.320

REND

25 38

Page 115: Precios Unitarios

(hora/und)

0.500

REND

16 39

Page 116: Precios Unitarios

(hora/und)

0.500

REND

16 40

Page 117: Precios Unitarios

(hora/und)

1.600

REND

5 41

Page 118: Precios Unitarios

(hora/und)

1.600

REND

5 42

Page 119: Precios Unitarios

(hora/und)

0.200

REND

40 43

Page 120: Precios Unitarios

(hora/und)

0.200

REND

40 44

Page 121: Precios Unitarios

(hora/und)

0.200

REND

40 45

Page 122: Precios Unitarios

(hora/und)

0.400

REND

20 46

Page 123: Precios Unitarios

(hora/und)

2.996

REND

2.67 47

Page 124: Precios Unitarios

(hora/und)

1.000

REND

8 48

Page 125: Precios Unitarios

(hora/und)

0.500

REND

16 49

Page 126: Precios Unitarios

(hora/und)

2.000

REND

4 50

Page 127: Precios Unitarios

(hora/und)

1.000

REND

8 51

Page 128: Precios Unitarios

(hora/und)

1.000

REND

8 52

Page 129: Precios Unitarios

(hora/und)

1.000

REND

8 53

Page 130: Precios Unitarios

(hora/und)

1.000

REND

8 54

Page 131: Precios Unitarios

(hora/und)

1.000

REND

8 55

Page 132: Precios Unitarios

(hora/und)

1.000

REND

8 56

1.12 4250011000

Page 133: Precios Unitarios

(hora/und)

1.000

REND

8 57

Page 134: Precios Unitarios

(hora/und)

1.000

REND

8 58

Page 135: Precios Unitarios

(hora/und)

1.000

REND

8 59

Page 136: Precios Unitarios

(hora/und)

1.000

REND

8 60

Page 137: Precios Unitarios

(hora/und)

1.000

REND

8 61

Page 138: Precios Unitarios

(hora/und)

1.000

REND

8 62

Page 139: Precios Unitarios

(hora/und)

1.000

REND

8 63

Page 140: Precios Unitarios

(hora/und)

1.000

REND

8 64

Page 141: Precios Unitarios

(hora/und)

0.200

REND

40 65

Page 142: Precios Unitarios

(hora/und)

0.250

REND

32 66

Page 143: Precios Unitarios

(hora/und)

0.250

REND

32 67

Page 144: Precios Unitarios

(hora/und)

0.727

REND

11 68

Page 145: Precios Unitarios

(hora/und)

1.600

REND

5 69

Page 146: Precios Unitarios

(hora/und)

1.600

REND

5 70

Page 147: Precios Unitarios

(hora/und)

2.996

REND

2.67 71

Page 148: Precios Unitarios

(hora/und)

2.000

REND

4 72

Page 149: Precios Unitarios

(hora/und)

2.000

REND

4 73

Page 150: Precios Unitarios

JORNAL NOMI. FSR318.00 2.10 COSTOS INDIRECTOS = 29.00%

318.00 2.10

322.33 2.10

322.33 2.10

322.33 2.10

346.62 2.09

485.64 2.06

346.62 2.09

337.08 2.09

322.33 2.10

322.33 2.10

322.33 2.10

322.33 2.10

322.33 2.10

346.62 2.09

322.33 2.10

322.33 2.10

346.62 2.09

322.33 2.10

TRANSPORTE

CEMENTO 0.50 SACO

ARENA 8.50 M3

RIPIO 8.50 M3

AGUA 0.100 LT

PIEDRA BOLA 8.50 M3

ALAMBRE DE AMARRE # 18 0.05 KG

ACERO DE REFUERZO 0.05 KG

ACERO ESTRUCTURAL 0.05 KG

TABLA DURA DE ENCOFRADO 0.05 U

RIELES DE EUCALIPTO 0.05 U

CLAVOS 2 - 2.5, 3 " 0.01 KG

PINGOS 2.5 0.05 U

LADRILLO TIPO CHAMBO 0.01 U

IMPERMEABILIZANTE SIKA 1 0.01 KG

MARMOL PULIDO Y ABRILLANTADO IMPORTADO 1.00 ML

CERAMICA EN PARED 0.10 M2

CERAMICA EN PISO 0.10 M2

EMPORADOR 0.01 KG

CENEFA DE CERAMICA 0.10 ML

ECUATEJA CLASICA 0.50 M2

TIRAS DE MADERA 0.01 U

CLAVOS DE ACERO 1.5 " NEGRO 0.01 U

PARQUET CHANUL O COLORADO PULIDO Y LACADO 3 MANOS 1.00 M2

PINTURA DE CAUCHO PERMALATEX 0.05 GL

BROCHA 0.01 U

LIJA # 60 0.01 PLG.

CARBONATO DE CALCIO TIPO A 0.01 KG

RESAFLEX 0.05 GL

PINTURA ANTICORROSIVA 0.10 GL

VENTANAS DE AL. Y VIDRIO CORREDIZA 1.00 M2

MUEBLES BAJOS DE COCINA 1.00 ML

MUEBLES ALTOS DE COCINA 1.00 ML

CLOSETS 1.00 M2

CERRADURA DE BAÑO 0.10 U

CERRADURA PRINCIPAL 0.10 U

CERRADURA LLAVE SEGURO GEO O YALE ITAL. 0.10 U

Page 151: Precios Unitarios

MANGON DE MADERA 0.50 ML

PASAMANO DE HIERRO 0.50 M

PLATINA DE 1/2 * 1/8 * 6 M 0.05 U

SUELDA 60 11 0.05 KG

TUBO RECTANGULAR 20 * 40 * 6 M 0.05 U

VARILLA CUADRADA DE 1/2 " * 6 M 0.05 U

TOL LAMINADO AL FRIO 1/32 0.05 PL.

PUERTAS TAMBORADAS DE 0,90 1.00 U

PUERTAS DE MADERA PRINCIPAL 1.00 U

PUERTAS TAMBORADAS DE 0,70 1.00 U

CHAPA ELECTRICA VIRO 0.05 U

LLAVE DE PASO FV 0.05 U

LLAVE DE MANGUERA DE PICO 0.05 U

LLAVE VALVULA ITAL. DE 1/2" 0.05 U

TUBO ROSCABLE 1/2" AGUA FRIA 0.10 U

TUBO HIDRO 3 1/2" AGUA CALIENTE 0.10 U

TEFLON 0.01 U

PERMATEX 3 ONZ. 0.01 U

ACCESORIOS IPS 0.01 U

MEDIDOR DE AGUA 1.00 U

ACCESORIOS DE PVC 110 MM 0.01 U

ACCESORIOS DE PVC 75 MM 0.01 U

ACCESORIOS PVC 50 MM 0.01 U

POLIPEGA 0.01 LT

POLILIMPIA 0.01 LT

TUBERIA DE H.S. 150 MM M.C. 0.20 U

REJILLA DE PISO CROMADA FV 0.05 U

CAJETIN RECTANGULAR PROFUNDO 0.01 U

CAJETIN OCTOGONAL 0.01 U

TUBO PVC PESADO DE 1/2" * 3 M 0.05 U

TUBO PVC LIVIANO DE 1/2" * 3 M 0.05 U

TUBO PVC PESADO DE 3/4" * 3 M 0.05 U

CABLE # 12 SOLIDO 0.01 ML

CABLE # 14 SOLIDO 0.01 ML

CABLE # 8 VARIOS HILOS 0.01 ML

ALAMBRE # 20 DE TELEFONO 0.01 ML

CABLE COAXIAL TV CABLE 0.01 ML

CABLE 8 HILOS PORTERO ELECTRICO 0.01 ML

BOQUILLA PLAFON 0.02 U

TOMACORRIENTE DOBLE POLARIZADO LUMINEX 0.02 U

INTERRUPTOR SIMPLE LUMINEX 0.02 U

CONMUTADOR LUMINEX 0.02 U

TOMA ESPECIAL ELECTRICA TV CABLE - TELEF. 0.02 U

PORTERO ELECTRICO 1 DPTO. + 1 EXTENSION 0.25 U

CODOS PVC 1/2" 0.01 U

CODOS PVC 3/4 0.01 U

TABLERO DE DISTRIBUCION 4 CIRCUITOS 0.50 U

BREAKERS 20 A 0.01 U

MEDIDOR DE LUZ U

FREGADERO TEKA O SIMILAR 1* .50 M 0.50 U

MEZCLADORA DE COCINA CROMO-ORO 0.50 U

TUBO DE ABASTO 1/2" DE NYLON 0.02 U

SIFON DESAGUE - FREGADERO 0.05 U

INODORO TANQUE BAJO LINEA INTERM. COLOR SUAVE 0.50 U

INODORO TANQUE BAJO LINEA INTERM. COLOR FUERTE 0.50 U

LAVAMANOS EMPOTRABLE OACKBROOK COL. SUAVE 0.50 U

LAVAMANOS CHELSEA AZUL COBALTO O SIMILAR 0.50 U

MEZCLADORA DE LAVAVO FV FUTURA 67/102 4" 0.25 U

LLAVE FV 221/78 CROMADA VERSALLES 0.25 U

SIFON DESAGUE - LAVAVO 0.05 U

JUEGO DE ACCESORIOS SPAZZIO 0.20 U

TANQUE CALENTOR 30 GL 1.00 U

VALVULA CHECKE FV 0.05 U

Page 152: Precios Unitarios

MANGUERA - SALIDA DE GAS 0.05 ML

DERIVACION DE COBRE PARA COCINA - CALEFON 0.05 U

ABRAZADERAS 0.01 U

EXTRACTOR DE OLORES JET AIR 1.00 U

CHAMPEADORA MANUAL 0.05 U

YESO 0.01 KG

BLOQUE ALIVIANADO PARA LOSA E=15 CM. 0.01 U

SUBBASE CLASE 3 6.00 M3

BARREDERAS INSTALADAS a=9 CM 0.05 ML

MEDIA DUELA DE CHANDUL MACHIMBRADA 0.50 M2

PLATINA DE 1" * 3/16 * 6M. 0.05 U

BISAGRAS 5/8 * 3" PUERTA DE HIERRO 0.05 U

PICAPORTE HIERRO 0.05 U

VIDRIO CATEDRAL 4 MM. INSTALADO 0.50 M2

MEZCLADORA DE DUCHA MALENA 0.25 U

TUBO PVC 110 MM DESAGUE 0.05 U

TUBO PVC 75 MM DESAGUE 0.05 U

TUBO PVC 50 MM DESAGUE 0.05 U

SILICON DE PISTOLA 0.05 U

PINTURA ESMALTE COLOR 0.10 GL

CHAPA PHILIPS SENCILLA O TRAVEX 0.05 U

ENCOFRADO DE LOSA 0.20 M2

ADITIVO 0.05 KG

ENCOFRADO 0.10 M2

CLAVOS,ALAMBRE, VARIOS 0.05 GLB

BONDEX 0.05 SACO

POLIETILENO 0.05 M2

PORCELANATO 0.50 M2

BONDEX PREMIUM 0.25 SACO

TEE PVC 1/2" 0.01 U

UNION PVC 1/2" 0.01 U

TACOS FISHER Y TORNILLO 0.01 U

ANILLO DE CERA 8.00 U