TABLA DE CANTIDADES Y PRECIOS
RUBRO DESCRIPCION UNIDAD CANTIDAD P. UNITARIO P. TOTAL
1 1 LIMPIEZA MANUAL DEL TERRENO m2 269.42 1.86 501.12 62
2 2 REPLANTEO y NIVELACION con EQUIPO TOPOGRAFICO m2 62.29 5.03 313.32 125
3 3 EXCAVACION MANUAL EN CIMIENTOS Y PLINTOS m3 21.82 9.08 198.13 188
4 4 DESALOJO A MAQUINA. EQUIPO: CARGADORA FRONTAL y VOLQUETA m3 12.70 5.77 73.28 251
5 5 RELLENO COMPACTADO CON SUELO NATURAL m3 11.24 6.08 68.34 314
6 6 REPLANTILLO H.S. 140 KG/CM2. EQUIPO: CONCRETERA 1 SACO m3 1.30 128.10 166.53 377
7 7 PLINTOS DE HORMIGON .H.S 210KG/CM2. EQUIPO: CONCRETERA 1 SACO y VIBRADOR m3 4.37 159.37 696.45 440
8 8 HORMIGON COLUMNAS 0.20x0.30. F´C = 210KG/CM2. EQUIPO: CONCRETERA 1 SACO, m3 3.78 258.44 976.90 503
9 9 HORMIGON EN VIGAS, 0.20x0.50. F´C = 210KG/CM2. EQUIPO: CONCRETERA 1 SACO, VI m3 9.66 269.69 2,605.21 566
10 10 m3 1.76 199.59 351.28 629
11 11 HORMIGON EN ESCALERAS, F´C = 210KG/CM2. EQUIPO: CONCRETERA 1 SACO, VIBRA m2 3.06 342.04 1,046.64 692
12 12 HORMIGON EN LOSA DE 20 CM, F´C = 210KG/CM2. EQUIPO: CONCRETERA 1 SACO, VIB m3 12.40 230.20 2,854.48 755
13 13 BLOQUE DE ALIVIANAMIENTO 15*20*40 CM. TIMBRADO INCLUYE ESTIBAJE u 870.00 0.84 730.80 818
14 14 ACERO DE REFUERZO 8 -12 mm. ALAMBRE GALVANIZADO # 18 . EQUIPO: CIZALLA kg 3,370.39 2.03 6,841.89 881
15 15 BORDILLO DE TINA DE BAÑO H=40 CM, BLOQUE ENLUC.,CERAMICA GRAIMAN 20x20 m 2.90 133.90 388.31 944
16 16 MESA DE COCINA HORMIGON ARMADO. ENCOFRADO m 10.40 15.13 157.35 1007
17 17 MAMPOSTERIA DE LADRILLO MAMBRON. MORTERO 1: 6, e = 2.5 cm. m2 271.05 40.18 10,890.79 1070
18 18 LAVANDERIA DE JABONCILLO TUBO HG 1PLG-ASMT 120 u 1.00 209.96 209.96 1133
19 19 CAJA DE REVISION (0.60X0.60X0.60) u 3.00 36.37 109.11 1196
20 20 TAPA SANITARIA u 3.00 35.37 106.11 1259
21 21 ENLUCIDO DE FAJAS m 146.17 5.02 733.77 1322
22 22 ENLUCIDO VERTICAL INCLUYE ANDAMIOS m2 305.94 8.78 2,686.15 1385
23 23 ENLUCIDO LISO EXTERIOR INCLUYE ANDAMIOS m2 239.01 8.99 2,148.70 1448
24 24 ENLUCIDO HORIZONTAL LISO INCLUYE ANDAMIOS. MORTERO 1:6, e=1.5 cm m2 144.26 8.99 1,296.90 1511
25 25 m2 62.00 9.40 582.80 1574
26 26 CERAMICA PARA PARED m2 55.02 26.19 1,440.97 1637
27 27 ALISADO DE PISOS(MORTERO 1:3, E = 1.5 CM) m2 136.70 8.69 1,187.92 1700
28 28 CONTRAPISO H.S 180KG/CM2. E = 6 CM. PIEDRA BOLA. EQUIPO: CONCRETERA 1 SACO m2 56.91 55.01 3,130.62 1763
29 29 MEDIA DUELA DE CHANDUL m2 66.69 52.04 3,470.55 1826
30 30 CERAMICA PARA PISOS (GRAIMAN 30X30, MORTERO 1:3; e=1cm m2 13.00 27.09 352.17 1889
31 31 PORCELANATO EN PISOS TIPO GRAIMAN m2 52.96 48.23 2,554.26 1952
32 32 BARREDERA DE LAUREL m 91.00 4.40 400.40 2015
33 33 VENTANA COREDIZA DE ALUMINIO m2 38.91 119.65 4,655.58 2078
34 34 SALIDA MEDIDORES HG. LLAVE DE PASO Y ACCESORIOS H.G pto. 1.00 32.77 32.77 2141
35 35 SALIDA DE AGUA FRIA HG. LLAVE DE CONTROL Y ACCESORIOS H.G pto. 12.00 17.58 210.96 2204
36 36 SALIDA DE AGUA CALIENTE HG. LLAVE DE CONTROL Y ACCESORIOS H.G pto. 7.00 17.58 123.06 2267
37 37 SALIDA PARA LAVADORAS. LLAVE DE CONTROL Y ACCESORIOS pto. 2.00 18.78 37.56 2330
38 38 LLAVE DE PASO 3/4" u 4.00 14.09 56.36 2393
39 39 TUBERIA PVC 1/2" m 27.90 5.64 157.36 2456
40 40 LLAVE DE PICO FV DE LAVANDERIA u 3.00 16.10 48.30 2519
41 41 CANALIZACION PVC 50 MM pto. 16.00 20.89 334.24 2582
42 42 CANALIZACION PVC 110 MM pto. 3.00 33.28 99.84 2645
43 43 BAJANTES AGUAS SERVIDAS PVC 110 MM. UNION CODO m 3.20 9.46 30.27 2708
44 44 BAJANTES DE AGUAS LLUVIAS 110MM. UNION CODO m 5.20 9.46 49.19 2771
45 45 TUBERIA PVC 110MM DESAGUE (MAT/TRAN/INST) m 20.60 9.46 194.88 2834
46 46 REJILLA INTERIOR DE PISO 50MM u 10.00 10.54 105.40 2897
47 47 TABLERO CONTROL GE4-8 PTO.S BREAKER 1 POLO 15-50 A u 1.00 148.29 148.29 2960
48 48 ILUMINACION. CONDUCTOR N° 12 pto. 18.00 38.64 695.52 3023
49 49 SALIDA PARA TELEFONOS. ALAMBRE TELEFONICO, ALUG 2 x20 pto. 4.00 18.45 73.80 3086
50 50 SALIDAS ANTENAS TV u 4.00 20.61 82.44 3149
51 51 TOMACORRIENTE DOBLE 2#10 T.CONDUIT EMT. 1/2" pto 20.00 34.12 682.40 3212
52 52 PUERTAS PRICIPALES LACADAS u 1.00 270.91 270.91 3275
53 53 MUEBLE BAJO COCINA (TABLERO TRIPLEX) m 5.30 163.95 868.94 3338
54 54 MUEBLES ALTOS DE COCINA (TABLERO TRIPLEX) m 10.00 167.71 1,677.10 3401
55 55 CLOSET (TABLERO TRIPLEX) m2 16.32 167.71 2,737.03 3464
56 56 CERRADURA PRINCIPAL (CESA), TIPO NOVA CROMADA u 1.00 121.40 121.40 3527
57 57 CERRADURA DORMITORIO (CESA)TIPO, NOVA CROMADA u 3.00 27.23 81.69 3590
HORMIGON EN CADENAS 0.20 x0.20. F´C = 210KG/CM2. EQUIPO: CONCRETE180RA 1 SACO, VIBRADOR, ENCOFRADO CADENA
MASILLADO EN LOSA + IMPERMEABILIZANTE, SIKA 1 , e=3cm, MORTERO 1:3
58 58 CERRADURA BAÑO (CESA), TIPO NOVA CROMADA u 3.00 24.65 73.95 3653
59 59 CERRADURA PASILLO (CESA), TIPO NOVA CROMADA u 1.00 27.23 27.23 3716
60 60 PASAMANO DE HIERRO C/MANGON MADERA m 6.60 86.55 571.23 3779
61 61 PUERTA DE PLYWOOD TAMBOR 0.70 LACADA, INCLUYE MARCOS Y TAPAMARCOS u 4.00 167.71 670.84 3842
62 62 PUERTA DE PLYWOOD TAMBOR 0.80 LACADA, INCLUYE MARCOS Y TAPAMARCOS u 2.00 187.06 374.12 3905
63 63 PUERTA DE PLYWOOD TAMBOR 0.90 LACADA, INCLUYE MARCOS Y TAPAMARCOS u 4.00 187.06 748.24 3968
64 64 TANQUE CALENTADOR 30 GL. u 1.00 358.17 358.17 4031
65 65 PINTURA DE CAUCHO INTERIOR 2 MANOS, LATEX VINYL ACRILICO, CEMENTO BLANCO. m2 305.94 3.77 1,153.37 4094
66 66 PINTURA DE CAUCHO EXTERIOR 2 MANOS, LATEX VINYL ACRILICO, CEMENTO BLANCO. m2 192.24 4.14 795.85 4157
67 67 PINTURA CAUCHO CIELO RAZO. LATEX VINYL ACRILICO, CEMENTO BLANCO. EQUIPO: A m2 144.26 4.14 597.24 4220
68 68 TEJA COMUN INC. TIRAS EUCALIP.MORTERO 1:3 m2 4.80 25.55 122.64 4283
69 69 LAVAMANOS POMPANO BLANCO u 3.00 115.00 345.00 4346
70 70 INODORO TANQUE BAJO TIPO SAVEX u 3.00 264.50 793.50 4409
71 71 LAVAPLATOS COMPLETO, GRIFERIA u 1.00 385.83 385.83 4472
72 72 ACCESORIOS DE BAÑO jg 3.00 54.21 162.63 4535
73 73 DUCHA SENCILLA CROMADA COMPLETA - INCL. MEZCLADORA Y GRIFERIA u 2.00 121.53 243.06 4598
63
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:LIMPIEZA MANUAL DEL TERRENO m2
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.069 0.07 4.79%
SUBTOTAL M 0.07 4.79%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
D= C*R
PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.32 0.89 61.78%
MAESTRO MAY. (Est. Ocup. C1) 0.50 346.62 2.09 3.02 0.16 0.48 33.56%
-
SUBTOTAL N 1.37 95.33%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
SUBTOTAL O - 0.00%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
SUBTOTAL P - 0.00%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 1.44 100%
INDIRECTOS Y UTILIDAD 29.00% 0.42 29.0%
COSTO TOTAL DEL RUBRO 1.86 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:REPLANTEO y NIVELACION con EQUIPO TOPOGRAFICO m2
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.169 0.17 4.33%
ESTACION TOTAL 1.000 2.50 0.140 0.35 8.97%
SUBTOTAL M 0.52 13.31%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
D= C*R
TOPOGRAFO 2 (Est. Ocup. C1) 1.00 346.62 2.09 3.02 0.14 0.42 10.84%
CADENERO (Est. Ocup. D2) 7.00 322.33 2.10 3.02 0.98 2.96 75.89%
-
SUBTOTAL N 3.38 86.73%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
SUBTOTAL O - 0.00%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
SUBTOTAL P - 0.00%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 3.90 100%
INDIRECTOS Y UTILIDAD 29.0% 1.13 29.0%
COSTO TOTAL DEL RUBRO 5.03 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:EXCAVACION MANUAL EN CIMIENTOS Y PLINTOS m3
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.335 0.34 4.76%
SUBTOTAL M 0.34 4.76%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
D= C*R
PEON (Est. Ocup. E2) 2.00 318.00 2.10 2.78 1.60 4.45 63.18%
ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.80 2.26 32.05%
SUBTOTAL N 6.70 95.23%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
SUBTOTAL O - 0.00%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
SUBTOTAL P - 0.00%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 7.04 100%
INDIRECTOS Y UTILIDAD 29.0% 2.04 29.0%
COSTO TOTAL DEL RUBRO 9.08 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:DESALOJO A MAQUINA. EQUIPO: CARGADORA FRONTAL y VOLQUETA m3
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.023 0.02 0.51%
CARGADORA FRONTAL 1.000 40.00 0.040 1.60 35.79%
VOLQUETE 10 M3 2.000 30.00 0.040 2.40 53.69%
SUBTOTAL M 4.02 90.00%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
D= C*R
OPERADOR EQUIPO PESADO GRUPO 1 (Est. Ocu 1.00 346.62 2.09 3.02 0.04 0.12 2.70%
CHOFER TIPO E VOLQUETAS(Est. Op. C1) 2.00 485.64 2.06 4.16 0.08 0.33 7.45%
SUBTOTAL N 0.45 10.15%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
SUBTOTAL O - 0.00%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
SUBTOTAL P - 0.00%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 4.47 100%
INDIRECTOS Y UTILIDAD 29.0% 1.30 29.0%
COSTO TOTAL DEL RUBRO 5.77 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:RELLENO COMPACTADO CON SUELO NATURAL m3
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.148 0.15 3.14%
PLANCHA VIBROCOMPAC. 1.000 3.00 0.533 1.60 33.97%
SUBTOTAL M 1.75 37.11%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
D= C*R
PEON (Est. Ocup. E2) 2.00 318.00 2.10 2.78 1.07 2.96 62.92%
SUBTOTAL N 2.96 62.92%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
SUBTOTAL O - 0.00%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
SUBTOTAL P - 0.00%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 4.71 100%
INDIRECTOS Y UTILIDAD 29.0% 1.37 29.0%
COSTO TOTAL DEL RUBRO 6.08 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:REPLANTILLO H.S. 140 KG/CM2. EQUIPO: CONCRETERA 1 SACO m3
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 1.331 1.33 1.34%
CONCRETERA 1.000 6.50 1.000 6.50 6.55%
SUBTOTAL M 7.83 7.89%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
D= C*R
PEON (Est. Ocup. E2) 7.00 318.00 2.10 2.78 7.00 19.46 19.60%
ALBANIL (Est. Ocup. D2) 2.00 322.33 2.10 2.82 2.00 5.64 5.68%
MAESTRO MAY. (Est. Ocup. C1) 0.50 346.62 2.09 3.02 0.50 1.51 1.52%
SUBTOTAL N 26.61 26.80%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CEMENTO SACO 6.180 6.723 41.55 41.84%
ARENA M3 0.650 #N/A #N/A 2.29%
RIPIO M3 0.950 #N/A #N/A 4.31%
AGUA M3 0.240 #N/A #N/A 0.05%
SUBTOTAL O 48.15 48.49%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CEMENTO SACO 6.180 0.50 3.09 3.11%
ARENA M3 0.650 8.50 5.53 5.56%
RIPIO M3 0.950 8.50 8.08 8.13%
AGUA LT 0.240 0.10 0.02 0.02%
SUBTOTAL P 16.71 16.83%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 99.30 100%
INDIRECTOS Y UTILIDAD 29.0% 28.80 29.0%
COSTO TOTAL DEL RUBRO 128.10 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:PLINTOS DE HORMIGON .H.S 210KG/CM2. EQUIPO: CONCRETERA 1 SACO y VIBRADOR m3
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 1.774 1.77 1.44%
CONCRETERA 1.000 6.50 1.333 8.67 7.02%
VIBRADOR 1.000 4.00 1.333 5.33 4.32%
SUBTOTAL M 15.77 12.77%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
D= C*R
PEON (Est. Ocup. E2) 7.00 318.00 2.10 2.78 9.33 25.94 21.00%
ALBANIL (Est. Ocup. D2) 2.00 322.33 2.10 2.82 2.67 7.52 6.09%
MAESTRO MAY. (Est. Ocup. C1) 0.50 346.62 2.09 3.02 0.67 2.01 1.63%
SUBTOTAL N 35.47 28.71%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CEMENTO SACO 7.210 6.723 48.47 39.24%
ARENA M3 0.650 #N/A #N/A 1.84%
RIPIO M3 0.950 #N/A #N/A 3.46%
AGUA M3 0.220 #N/A #N/A 0.04%
SUBTOTAL O 55.07 44.58%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CEMENTO SACO 7.210 0.50 3.61 2.92%
ARENA M3 0.650 8.50 5.53 4.47%
RIPIO M3 0.950 8.50 8.08 6.54%
AGUA LT 0.220 0.10 0.02 0.02%
SUBTOTAL P 17.23 13.94%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 123.54 100%
INDIRECTOS Y UTILIDAD 29.0% 35.83 29.0%
COSTO TOTAL DEL RUBRO 159.37 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:HORMIGON COLUMNAS 0.20x0.30. F´C = 210KG/CM2. EQUIPO: CONCRETERA 1 SACO, VIBRADOR, ENCOFRADO COLUMNA m3
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 3.549 3.55 1.77%
CONCRETERA 1.000 6.50 2.667 17.33 8.65%
VIBRADOR 1.000 4.00 2.667 10.67 5.32%
SUBTOTAL M 31.55 15.75%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
D= C*R
PEON (Est. Ocup. E2) 7.00 318.00 2.10 2.78 18.67 51.90 25.91%
ALBANIL (Est. Ocup. D2) 2.00 322.33 2.10 2.82 5.33 15.04 7.51%
MAESTRO MAY. (Est. Ocup. C1) 0.50 346.62 2.09 3.02 1.33 4.03 2.01%
SUBTOTAL N 70.97 35.42%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CEMENTO SACO 7.210 6.723 48.47 24.20%
ARENA M3 0.650 3.500 2.28 1.14%
RIPIO M3 0.950 4.500 4.27 2.13%
AGUA M3 0.220 #N/A #N/A 0.02%
ADITIVO KG 0.300 2.230 0.67 0.33%
ENCOFRADO M2 3.760 5.960 22.41 11.19%
CLAVOS,ALAMBRE, VARIOS GLB 1.000 2.000 2.00 1.00%
SUBTOTAL O 80.15 40.01%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CEMENTO SACO 7.210 0.50 3.61 1.80%
ARENA M3 0.650 8.50 5.53 2.76%
RIPIO M3 0.950 8.50 8.08 4.03%
AGUA LT 0.220 0.10 0.02 0.01%
ADITIVO KG 0.300 0.05 0.02 0.01%
ENCOFRADO M2 3.760 0.10 0.38 0.19%
CLAVOS,ALAMBRE, VARIOS GLB 1.000 0.05 0.05 0.02%
SUBTOTAL P 17.67 8.82%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 200.34 100%
INDIRECTOS Y UTILIDAD 29.0% 58.10 29.0%
COSTO TOTAL DEL RUBRO 258.44 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:HORMIGON EN VIGAS, 0.20x0.50. F´C = 210KG/CM2. EQUIPO: CONCRETERA 1 SACO, VIBRADOR. ENCOFRADO VIGA m3
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 3.549 3.55 1.70%
CONCRETERA 1.000 6.50 2.667 17.33 8.29%
VIBRADOR 1.000 4.00 2.667 10.67 5.10%
ELEVADOR 1.000 5.00 2.667 13.33 6.38%
SUBTOTAL M 44.88 21.47%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
D= C*R
PEON (Est. Ocup. E2) 7.00 318.00 2.10 2.78 18.67 51.90 24.83%
ALBANIL (Est. Ocup. D2) 2.00 322.33 2.10 2.82 5.33 15.04 7.20%
MAESTRO MAY. (Est. Ocup. C1) 0.50 346.62 2.09 3.02 1.33 4.03 1.93%
SUBTOTAL N 70.97 33.95%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CEMENTO SACO 7.210 6.723 48.47 23.19%
ARENA M3 0.650 3.500 2.28 1.09%
RIPIO M3 0.950 4.500 4.27 2.04%
AGUA M3 0.220 #N/A #N/A 0.02%
ADITIVO KG 0.300 2.230 0.67 0.32%
ENCOFRADO M2 3.000 5.960 17.88 8.55%
CLAVOS,ALAMBRE, VARIOS GLB 1.000 2.000 2.00 0.96%
SUBTOTAL O 75.62 36.17%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CEMENTO SACO 7.210 0.50 3.61 1.72%
ARENA M3 0.650 8.50 5.53 2.64%
RIPIO M3 0.950 8.50 8.08 3.86%
AGUA LT 0.220 0.10 0.02 0.01%
ADITIVO KG 0.300 0.05 0.02 0.01%
ENCOFRADO M2 3.000 0.10 0.30 0.14%
CLAVOS,ALAMBRE, VARIOS GLB 1.000 0.05 0.05 0.02%
SUBTOTAL P 17.59 8.41%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 209.06 100%
INDIRECTOS Y UTILIDAD 29.0% 60.63 29.0%
COSTO TOTAL DEL RUBRO 269.69 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
m3
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 2.129 2.13 1.38%
CONCRETERA 1.000 6.50 1.600 10.40 6.72%
VIBRADOR 1.000 4.00 1.600 6.40 4.14%
SUBTOTAL M 18.93 12.23%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
D= C*R
PEON (Est. Ocup. E2) 7.00 318.00 2.10 2.78 11.20 31.14 20.12%
ALBANIL (Est. Ocup. D2) 2.00 322.33 2.10 2.82 3.20 9.02 5.83%
MAESTRO MAY. (Est. Ocup. C1) 0.50 346.62 2.09 3.02 0.80 2.42 1.56%
SUBTOTAL N 42.58 27.52%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CEMENTO SACO 7.210 6.723 48.47 31.33%
ARENA M3 0.650 3.500 2.28 1.47%
RIPIO M3 0.950 4.500 4.27 2.76%
AGUA M3 0.220 #N/A #N/A 0.03%
ADITIVO KG 0.300 2.230 0.67 0.43%
ENCOFRADO M2 3.000 5.960 17.88 11.56%
CLAVOS,ALAMBRE, VARIOS GLB 1.000 2.000 2.00 1.29%
SUBTOTAL O 75.62 48.88%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CEMENTO SACO 7.210 0.50 3.61 2.33%
ARENA M3 0.650 8.50 5.53 3.57%
RIPIO M3 0.950 8.50 8.08 5.22%
AGUA LT 0.220 0.10 0.02 0.01%
ADITIVO KG 0.300 0.05 0.02 0.01%
ENCOFRADO M2 3.000 0.10 0.30 0.19%
CLAVOS,ALAMBRE, VARIOS GLB 1.000 0.05 0.05 0.03%
SUBTOTAL P 17.59 11.37%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 154.72 100%
INDIRECTOS Y UTILIDAD 29.0% 44.87 29.0%
COSTO TOTAL DEL RUBRO 199.59 129.00%
RUBRO:HORMIGON EN CADENAS 0.20 x0.20. F´C = 210KG/CM2. EQUIPO: CONCRETE180RA 1 SACO, VIBRADOR, ENCOFRADO CADENA
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:HORMIGON EN ESCALERAS, F´C = 210KG/CM2. EQUIPO: CONCRETERA 1 SACO, VIBRADOR, ENCOFRADO ESCALERA m2
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 5.322 5.32 2.01%
CONCRETERA 1.000 6.50 4.000 26.00 9.81%
VIBRADOR 1.000 4.00 4.000 16.00 6.03%
SUBTOTAL M 47.32 17.85%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
D= C*R
PEON (Est. Ocup. E2) 7.00 318.00 2.10 2.78 28.00 77.84 29.36%
ALBANIL (Est. Ocup. D2) 2.00 322.33 2.10 2.82 8.00 22.56 8.51%
MAESTRO MAY. (Est. Ocup. C1) 0.50 346.62 2.09 3.02 2.00 6.04 2.28%
SUBTOTAL N 106.44 40.14%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CEMENTO SACO 7.210 6.723 48.47 18.28%
ARENA M3 0.650 3.500 2.28 0.86%
RIPIO M3 0.950 4.500 4.27 1.61%
AGUA M3 0.220 #N/A #N/A 0.02%
ADITIVO KG 0.300 2.230 0.67 0.25%
ENCOFRADO M2 6.000 5.960 35.76 13.49%
CLAVOS,ALAMBRE, VARIOS GLB 1.000 2.000 2.00 0.75%
SUBTOTAL O 93.50 35.26%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CEMENTO SACO 7.210 0.50 3.61 1.36%
ARENA M3 0.650 8.50 5.53 2.08%
RIPIO M3 0.950 8.50 8.08 3.05%
AGUA LT 0.220 0.10 0.02 0.01%
ADITIVO KG 0.300 0.05 0.02 0.01%
ENCOFRADO M2 6.000 0.10 0.60 0.23%
CLAVOS,ALAMBRE, VARIOS GLB 1.000 0.05 0.05 0.02%
SUBTOTAL P 17.89 6.75%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 265.15 100%
INDIRECTOS Y UTILIDAD 29.0% 76.89 29.0%
COSTO TOTAL DEL RUBRO 342.04 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:HORMIGON EN LOSA DE 20 CM, F´C = 210KG/CM2. EQUIPO: CONCRETERA 1 SACO, VIBRADOR, ENCOFRADO LOSA m3
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 2.920 2.92 1.64%
CONCRETERA 1.000 6.50 1.600 10.40 5.83%
VIBRADOR 1.000 4.00 1.600 6.40 3.59%
ELEVADOR 1.000 5.00 1.600 8.00 4.48%
SUBTOTAL M 27.72 15.53%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
D= C*R
PEON (Est. Ocup. E2) 9.00 318.00 2.10 2.78 14.40 40.03 22.43%
ALBANIL (Est. Ocup. D2) 3.00 322.33 2.10 2.82 4.80 13.54 7.59%
MAESTRO MAY. (Est. Ocup. C1) 1.00 346.62 2.09 3.02 1.60 4.83 2.71%
SUBTOTAL N 58.40 32.73%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CEMENTO SACO 7.210 6.723 48.47 27.16%
ARENA M3 0.650 3.500 2.28 1.27%
RIPIO M3 0.950 4.500 4.27 2.40%
AGUA M3 0.220 #N/A #N/A 0.03%
ADITIVO KG 0.300 2.230 0.67 0.37%
ENCOFRADO DE LOSA M2 9.610 1.600 15.38 8.62%
CLAVOS,ALAMBRE, VARIOS GLB 1.000 2.000 2.00 1.12%
SUBTOTAL O 73.12 40.97%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CEMENTO SACO 7.210 0.50 3.61 2.02%
ARENA M3 0.650 8.50 5.53 3.10%
RIPIO M3 0.950 8.50 8.08 4.53%
AGUA LT 0.220 0.10 0.02 0.01%
ADITIVO KG 0.300 0.05 0.02 0.01%
ENCOFRADO DE LOSA M2 9.610 0.20 1.92 1.08%
CLAVOS,ALAMBRE, VARIOS GLB 1.000 0.05 0.05 0.03%
SUBTOTAL P 19.21 10.77%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 178.45 100%
INDIRECTOS Y UTILIDAD 29.0% 51.75 29.0%
COSTO TOTAL DEL RUBRO 230.20 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:BLOQUE DE ALIVIANAMIENTO 15*20*40 CM. TIMBRADO INCLUYE ESTIBAJE u
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.014 0.01 2.15%
SUBTOTAL M 0.01 2.15%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PEON (Est. Ocup. E2) 5.00 318.00 2.10 2.78 0.10 0.28 42.77%
SUBTOTAL N 0.28 42.77%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
BLOQUE ALIVIANADO PARA LOSA E=15 CM. U 1.000 0.350 0.35 53.85%
SUBTOTAL O 0.35 53.85%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
BLOQUE ALIVIANADO PARA LOSA E=15 CM. U 1.000 0.01 0.01 1.54%
SUBTOTAL P 0.01 1.54%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 0.65 100%
INDIRECTOS Y UTILIDAD 29.0% 0.19 29.0%
COSTO TOTAL DEL RUBRO 0.84 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:ACERO DE REFUERZO 8 -12 mm. ALAMBRE GALVANIZADO # 18 . EQUIPO: CIZALLA kg
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.013 0.01 0.83%
SUBTOTAL M 0.01 0.83%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
D= C*R
PEON (Est. Ocup. E2) 2.00 318.00 2.10 2.78 0.06 0.17 10.62%
FIERRERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.03 0.08 5.39%
SUBTOTAL N 0.25 16.01%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
ACERO DE REFUERZO KG 1.050 1.080 1.13 72.25%
ALAMBRE DE AMARRE # 18 KG 0.050 2.223 0.11 7.08%
SUBTOTAL O 1.25 79.33%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
ACERO DE REFUERZO KG 1.050 0.05 0.05 3.34%
ALAMBRE DE AMARRE # 18 KG 0.050 0.05 0.00 0.16%
SUBTOTAL P 0.06 3.50%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 1.57 100%
INDIRECTOS Y UTILIDAD 29.0% 0.46 29.0%
COSTO TOTAL DEL RUBRO 2.03 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:BORDILLO DE TINA DE BAÑO H=40 CM, BLOQUE ENLUC.,CERAMICA GRAIMAN 20x20 m
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.159 0.16 0.15%
SUBTOTAL M 0.16 0.15%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
D= C*R
PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.50 1.39 1.34%
ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.50 1.41 1.36%
MAESTRO MAY. (Est. Ocup. C1) 0.25 346.62 2.09 3.02 0.13 0.38 0.36%
SUBTOTAL N 3.18 3.06%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
LADRILLO TIPO CHAMBO U 10.000 0.120 1.20 1.16%
CEMENTO SACO 10.300 6.723 69.25 66.71%
ARENA M3 1.040 3.500 3.64 3.51%
AGUA M3 0.320 #N/A #N/A 0.07%
CERAMICA EN PARED M2 1.000 #N/A #N/A 11.64%
SUBTOTAL O 86.24 83.08%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
LADRILLO TIPO CHAMBO U 10.000 0.01 0.10 0.10%
CEMENTO SACO 10.300 0.50 5.15 4.96%
ARENA M3 1.040 8.50 8.84 8.52%
AGUA LT 0.320 0.10 0.03 0.03%
CERAMICA EN PARED M2 1.000 0.10 0.10 0.10%
SUBTOTAL P 14.22 13.70%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 103.80 100%
INDIRECTOS Y UTILIDAD 29.0% 30.10 29.0%
COSTO TOTAL DEL RUBRO 133.90 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:MAMPOSTERIA DE LADRILLO MAMBRON. MORTERO 1: 6, e = 2.5 cm. m2
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.304 0.30 2.59%
SUBTOTAL M 0.30 2.59%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
D= C*R
PEON (Est. Ocup. E2) 4.00 318.00 2.10 2.78 1.33 3.70 31.57%
ALBANIL (Est. Ocup. D2) 2.00 322.33 2.10 2.82 0.67 1.88 16.01%
MAESTRO MAY. (Est. Ocup. C1) 0.50 346.62 2.09 3.02 0.17 0.50 4.29%
SUBTOTAL N 6.08 51.87%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
LADRILLO TIPO CHAMBO U 33.000 0.120 3.96 33.76%
CEMENTO SACO 0.100 6.723 0.67 5.73%
ARENA M3 0.020 3.500 0.07 0.60%
AGUA M3 0.308 #N/A #N/A 0.58%
SUBTOTAL O 4.77 40.67%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
LADRILLO TIPO CHAMBO U 33.000 0.01 0.33 2.81%
CEMENTO SACO 0.100 0.50 0.05 0.43%
ARENA M3 0.020 8.50 0.17 1.45%
AGUA LT 0.308 0.10 0.03 0.26%
SUBTOTAL P 0.58 4.95%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 11.73 100%
INDIRECTOS Y UTILIDAD 29.0% 3.40 29.0%
COSTO TOTAL DEL RUBRO 15.13 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:MESA DE COCINA HORMIGON ARMADO. ENCOFRADO m
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.636 0.64 2.04%
SUBTOTAL M 0.64 2.04%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PEON (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 17.85%
ALBANIL (Est. Ocup. D2) 2.00 322.33 2.10 2.82 2.00 5.64 18.11%
MAESTRO MAY. (Est. Ocup. C1) 0.50 346.62 2.09 3.02 0.50 1.51 4.85%
SUBTOTAL N 12.71 40.80%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CEMENTO SACO 0.500 6.723 3.36 10.79%
ARENA M3 0.060 3.500 0.21 0.67%
RIPIO M3 0.090 4.500 0.40 1.30%
AGUA M3 0.002 #N/A #N/A 0.00%
ACERO DE REFUERZO KG 4.800 #N/A #N/A 16.65%
TABLA DURA DE ENCOFRADO U 1.500 #N/A #N/A 7.70%
TIRAS DE MADERA U 0.250 1.200 0.30 1.20%
CLAVOS,ALAMBRE, VARIOS GLB 1.000 2.500 2.50 8.03%
PINGOS 2.5 U 1.000 #N/A #N/A 4.59%
SUBTOTAL O 15.86 50.93%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CEMENTO SACO 0.500 0.50 0.25 0.80%
ARENA M3 0.060 8.50 0.51 1.64%
RIPIO M3 0.090 8.50 0.77 2.46%
AGUA LT 0.003 0.10 0.00 0.00%
ACERO DE REFUERZO KG 4.800 0.05 0.24 0.77%
TABLA DURA DE ENCOFRADO U 1.500 0.05 0.08 0.24%
TIRAS DE MADERA U 0.250 0.01 0.00 0.01%
CLAVOS,ALAMBRE, VARIOS GLB 1.000 0.05 0.05 0.16%
PINGOS 2.5 U 1.000 0.05 0.05 0.16%
SUBTOTAL P 1.94 6.24%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 31.15 100%
INDIRECTOS Y UTILIDAD 29.0% 9.03 29.0%
COSTO TOTAL DEL RUBRO 40.18 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:LAVANDERIA DE JABONCILLO TUBO HG 1PLG-ASMT 120 u
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 4.245 4.25 2.61%
SUBTOTAL M 4.25 2.61%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 11.94 33.19 20.39%
ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 11.94 33.67 20.69%
MAESTRO MAY. (Est. Ocup. C1) 0.50 346.62 2.09 3.02 5.97 18.03 11.08%
SUBTOTAL N 84.89 52.16%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CEMENTO SACO 2.030 6.723 13.65 8.39%
ARENA M3 0.270 3.500 0.95 0.58%
AGUA M3 0.070 0.220 0.02 0.01%
ACERO DE REFUERZO KG 5.000 #N/A #N/A 3.32%
LADRILLO TIPO CHAMBO U 176.000 #N/A #N/A 12.98%
PIEDRA BOLA M3 0.150 #N/A #N/A 0.41%
LLAVE DE MANGUERA DE PICO U 1.000 9.000 9.00 5.53%
LLAVE DE PASO FV U 1.000 8.500 8.50 5.22%
CODOS PVC 1/2" U 2.000 2.500 5.00 3.07%
TUBO ROSCABLE 1/2" AGUA FRIA U 0.320 8.000 2.56 1.57%
SUBTOTAL O 66.87 41.08%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CEMENTO SACO 2.030 0.50 1.02 0.62%
ARENA M3 0.270 8.50 2.30 1.41%
AGUA LT 0.070 0.10 0.01 0.00%
ACERO DE REFUERZO KG 5.000 0.05 0.25 0.15%
LADRILLO TIPO CHAMBO U 176.000 0.01 1.76 1.08%
PIEDRA BOLA M3 0.150 8.50 1.28 0.78%
LLAVE DE MANGUERA DE PICO U 1.000 0.05 0.05 0.03%
LLAVE DE PASO FV U 1.000 0.05 0.05 0.03%
CODOS PVC 1/2" U 2.000 0.01 0.02 0.01%
TUBO ROSCABLE 1/2" AGUA FRIA U 0.320 0.10 0.03 0.02%
SUBTOTAL P 6.75 4.15%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 162.76 100%
INDIRECTOS Y UTILIDAD 29.0% 47.20 29.0%
COSTO TOTAL DEL RUBRO 209.96 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:CAJA DE REVISION (0.60X0.60X0.60) u
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.889 0.89 3.15%
SUBTOTAL M 0.89 3.15%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 2.50 6.95 24.65%
ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 2.50 7.05 25.01%
MAESTRO MAY. (Est. Ocup. C1) 0.50 346.62 2.09 3.02 1.25 3.78 13.39%
SUBTOTAL N 17.78 63.05%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CEMENTO SACO 0.270 6.723 1.82 6.44%
ARENA M3 0.030 3.500 0.11 0.37%
AGUA M3 0.010 0.220 0.00 0.01%
ACERO DE REFUERZO KG 1.200 #N/A #N/A 4.60%
LADRILLO TIPO CHAMBO U 40.000 #N/A #N/A 17.03%
PIEDRA BOLA M3 0.050 #N/A #N/A 0.80%
SUBTOTAL O 8.24 29.24%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CEMENTO SACO 0.270 0.50 0.14 0.48%
ARENA M3 0.030 8.50 0.26 0.90%
AGUA LT 0.010 0.10 0.00 0.00%
ACERO DE REFUERZO KG 1.200 0.05 0.06 0.21%
LADRILLO TIPO CHAMBO U 40.000 0.01 0.40 1.42%
PIEDRA BOLA M3 0.050 8.50 0.43 1.51%
SUBTOTAL P 1.28 4.53%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 28.19 100%
INDIRECTOS Y UTILIDAD 29.0% 8.18 29.0%
COSTO TOTAL DEL RUBRO 36.37 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:TAPA SANITARIA u
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.562 0.56 2.05%
SUBTOTAL M 0.56 2.05%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 1.00 2.78 10.14%
ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 1.00 2.82 10.28%
FIERRERO (Est. Ocup. D2) 2.00 322.33 2.10 2.82 2.00 5.64 20.57%
SUBTOTAL N 11.24 40.99%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CEMENTO SACO 0.241 6.723 1.62 5.91%
ARENA M3 0.023 3.500 0.08 0.29%
RIPIO M3 0.034 4.500 0.15 0.56%
AGUA M3 0.008 #N/A #N/A 0.01%
ACERO DE REFUERZO KG 8.000 #N/A #N/A 31.52%
TABLA DURA DE ENCOFRADO U 2.500 #N/A #N/A 14.57%
SUBTOTAL O 14.49 52.86%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CEMENTO SACO 0.241 0.50 0.12 0.44%
ARENA M3 0.023 8.50 0.20 0.71%
RIPIO M3 0.034 8.50 0.29 1.05%
AGUA LT 0.008 0.10 0.00 0.00%
ACERO DE REFUERZO KG 8.000 0.05 0.40 1.46%
TABLA DURA DE ENCOFRADO U 2.500 0.05 0.13 0.46%
SUBTOTAL P 1.13 4.12%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 27.42 100%
INDIRECTOS Y UTILIDAD 29.0% 7.95 29.0%
COSTO TOTAL DEL RUBRO 35.37 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:ENLUCIDO DE FAJAS m
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.172 0.17 4.42%
SUBTOTAL M 0.17 4.42%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.62 1.71 43.95%
ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.62 1.73 44.58%
SUBTOTAL N 3.44 88.53%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CEMENTO SACO 0.025 6.723 0.17 4.32%
ARENA M3 0.008 3.500 0.03 0.72%
SUBTOTAL O 0.20 5.04%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CEMENTO SACO 0.025 0.50 0.01 0.32%
ARENA M3 0.008 8.50 0.07 1.75%
SUBTOTAL P 0.08 2.07%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 3.89 100%
INDIRECTOS Y UTILIDAD 29.0% 1.13 29.0%
COSTO TOTAL DEL RUBRO 5.02 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:ENLUCIDO VERTICAL INCLUYE ANDAMIOS m2
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.271 0.27 3.98%
ANDAMIOS 1.000 0.19 0.889 0.17 2.45%
SUBTOTAL M 0.44 6.43%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.89 2.47 36.29%
ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.89 2.51 36.81%
MAESTRO MAY. (Est. Ocup. C1) 0.16 346.62 2.09 3.02 0.14 0.43 6.31%
SUBTOTAL N 5.41 79.41%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CEMENTO SACO 0.099 6.723 0.66 9.76%
ARENA M3 0.020 3.500 0.07 1.03%
AGUA M3 0.005 0.220 0.00 0.02%
SUBTOTAL O 0.74 10.81%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CEMENTO SACO 0.099 0.50 0.05 0.73%
ARENA M3 0.020 8.50 0.17 2.50%
AGUA LT 0.005 0.10 0.00 0.01%
SUBTOTAL P 0.22 3.23%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 6.81 100%
INDIRECTOS Y UTILIDAD 29.0% 1.97 29.0%
COSTO TOTAL DEL RUBRO 8.78 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:ENLUCIDO LISO EXTERIOR INCLUYE ANDAMIOS m2
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.271 0.27 3.89%
ANDAMIOS 2.000 0.19 0.889 0.33 4.78%
SUBTOTAL M 0.60 8.67%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.89 2.47 35.46%
ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.89 2.51 35.97%
MAESTRO MAY. (Est. Ocup. C1) 0.16 346.62 2.09 3.02 0.14 0.43 6.16%
SUBTOTAL N 5.41 77.59%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CEMENTO SACO 0.099 6.723 0.66 9.54%
ARENA M3 0.020 3.500 0.07 1.00%
AGUA M3 0.005 0.220 0.00 0.02%
SUBTOTAL O 0.74 10.56%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CEMENTO SACO 0.099 0.50 0.05 0.71%
ARENA M3 0.020 8.50 0.17 2.44%
AGUA LT 0.005 0.10 0.00 0.01%
SUBTOTAL P 0.22 3.16%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 6.97 100%
INDIRECTOS Y UTILIDAD 29.0% 2.02 29.0%
COSTO TOTAL DEL RUBRO 8.99 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:ENLUCIDO HORIZONTAL LISO INCLUYE ANDAMIOS. MORTERO 1:6, e=1.5 cm m2
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.271 0.27 3.89%
ANDAMIOS 2.000 0.19 0.889 0.33 4.78%
SUBTOTAL M 0.60 8.67%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.89 2.47 35.46%
ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.89 2.51 35.97%
MAESTRO MAY. (Est. Ocup. C1) 0.16 346.62 2.09 3.02 0.14 0.43 6.16%
SUBTOTAL N 5.41 77.59%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CEMENTO SACO 0.099 6.723 0.66 9.54%
ARENA M3 0.020 3.500 0.07 1.00%
AGUA M3 0.005 0.220 0.00 0.02%
SUBTOTAL O 0.74 10.56%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CEMENTO SACO 0.099 0.50 0.05 0.71%
ARENA M3 0.020 8.50 0.17 2.44%
AGUA LT 0.005 0.10 0.00 0.01%
SUBTOTAL P 0.22 3.16%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 6.97 100%
INDIRECTOS Y UTILIDAD 29.0% 2.02 29.0%
COSTO TOTAL DEL RUBRO 8.99 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
m2
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.204 0.20 2.80%
SUBTOTAL M 0.20 2.80%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.73 2.02 27.72%
ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.73 2.05 28.12%
SUBTOTAL N 4.07 55.85%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CEMENTO SACO 0.309 6.723 2.08 28.50%
ARENA M3 0.031 3.500 0.11 1.49%
AGUA M3 0.009 0.220 0.00 0.03%
IMPERMEABILIZANTE SIKA 1 KG 0.330 1.250 0.41 5.66%
SUBTOTAL O 2.60 35.67%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CEMENTO SACO 0.309 0.50 0.15 2.12%
ARENA M3 0.031 8.50 0.26 3.61%
AGUA LT 0.009 0.10 0.00 0.01%
IMPERMEABILIZANTE SIKA 1 KG 0.330 0.01 0.00 0.16%
SUBTOTAL P 0.42 5.90%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 7.29 100%
INDIRECTOS Y UTILIDAD 29.0% 2.11 29.0%
COSTO TOTAL DEL RUBRO 9.40 129.00%
RUBRO:MASILLADO EN LOSA + IMPERMEABILIZANTE, SIKA 1 , e=3cm, MORTERO 1:3
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:CERAMICA PARA PARED m2
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.259 0.26 1.28%
SUBTOTAL M 0.26 1.28%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.73 2.02 9.96%
ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.73 2.05 10.10%
MAESTRO MAY. (Est. Ocup. C1) 1.00 346.62 2.09 3.02 0.36 1.10 5.41%
SUBTOTAL N 5.17 25.46%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CERAMICA EN PARED M2 1.050 12.080 12.68 62.48%
BONDEX SACO 0.330 5.600 1.85 9.10%
EMPORADOR KG 0.150 1.445 0.22 1.07%
SUBTOTAL O 14.75 72.66%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CERAMICA EN PARED M2 1.050 0.10 0.11 0.52%
BONDEX SACO 0.330 0.05 0.02 0.08%
EMPORADOR KG 0.330 0.01 0.00 0.02%
SUBTOTAL P 0.12 0.61%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 20.30 100%
INDIRECTOS Y UTILIDAD 29.0% 5.89 29.0%
COSTO TOTAL DEL RUBRO 26.19 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:ALISADO DE PISOS(MORTERO 1:3, E = 1.5 CM) m2
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.259 0.26 3.84%
SUBTOTAL M 0.26 3.84%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.73 2.02 29.99%
ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.73 2.05 30.42%
MAESTRO MAY. (Est. Ocup. C1) 1.00 346.62 2.09 3.02 0.36 1.10 16.29%
SUBTOTAL N 5.17 76.69%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CEMENTO SACO 0.155 6.723 1.04 15.46%
ARENA M3 0.016 3.500 0.06 0.83%
AGUA M3 0.005 0.220 0.00 0.02%
SUBTOTAL O 1.10 16.31%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CEMENTO SACO 0.155 0.50 0.08 1.15%
ARENA M3 0.016 8.50 0.14 2.02%
AGUA LT 0.005 0.10 0.00 0.01%
SUBTOTAL P 0.21 3.18%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 6.74 100%
INDIRECTOS Y UTILIDAD 29.0% 1.95 29.0%
COSTO TOTAL DEL RUBRO 8.69 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:CONTRAPISO H.S 180KG/CM2. E = 6 CM. PIEDRA BOLA. EQUIPO: CONCRETERA 1 SACO m2
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.334 0.33 0.78%
CONCRETERA 1.000 6.50 0.250 1.63 3.81%
SUBTOTAL M 1.96 4.59%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PEON (Est. Ocup. E2) 5.00 318.00 2.10 2.78 1.25 3.47 8.15%
ALBANIL (Est. Ocup. D2) 4.00 322.33 2.10 2.82 1.00 2.82 6.61%
MAESTRO MAY. (Est. Ocup. C1) 1.00 346.62 2.09 3.02 0.13 0.38 0.89%
SUBTOTAL N 6.67 15.65%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CEMENTO SACO 0.402 6.723 2.70 6.34%
ARENA M3 0.039 #N/A #N/A 0.32%
RIPIO M3 0.057 #N/A #N/A 0.60%
AGUA M3 0.014 #N/A #N/A 0.01%
PIEDRA BOLA M3 0.150 #N/A #N/A 1.58%
RIPIO M3 0.090 #N/A #N/A 0.95%
PORCELANATO M2 1.050 25.000 26.25 61.56%
SUBTOTAL O 30.43 71.36%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CEMENTO SACO 0.402 0.50 0.20 0.47%
ARENA M3 0.039 8.50 0.33 0.78%
RIPIO M3 0.057 8.50 0.48 1.14%
AGUA LT 0.014 0.10 0.00 0.00%
PIEDRA BOLA M3 0.150 8.50 1.28 2.99%
RIPIO M3 0.090 8.50 0.77 1.79%
PORCELANATO M2 1.050 0.50 0.53 1.23%
SUBTOTAL P 3.58 8.40%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 42.64 100%
INDIRECTOS Y UTILIDAD 29.0% 12.37 29.0%
COSTO TOTAL DEL RUBRO 55.01 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:MEDIA DUELA DE CHANDUL m2
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.232 0.23 0.58%
PULIDORA 1.000 4.00 0.800 3.20 7.93%
SUBTOTAL M 3.43 8.51%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.80 2.22 5.51%
CARPINTERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 0.80 2.42 5.99%
SUBTOTAL N 4.64 11.50%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CLAVOS 2 - 2.5, 3 " KG 0.150 1.571 0.24 0.58%
MEDIA DUELA DE CHANDUL MACHIMBRADA M2 1.050 30.000 31.50 78.09%
SUBTOTAL O 31.74 78.67%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CLAVOS 2 - 2.5, 3 " KG 0.150 0.01 0.00 0.00%
MEDIA DUELA DE CHANDUL MACHIMBRADA M2 1.050 0.50 0.53 1.30%
SUBTOTAL P 0.53 1.31%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 40.34 100%
INDIRECTOS Y UTILIDAD 29.0% 11.70 29.0%
COSTO TOTAL DEL RUBRO 52.04 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:CERAMICA PARA PISOS (GRAIMAN 30X30, MORTERO 1:3; e=1cm m2
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.259 0.26 1.23%
SUBTOTAL M 0.26 1.23%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.73 2.02 9.62%
ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.73 2.05 9.76%
MAESTRO MAY. (Est. Ocup. C1) 1.00 346.62 2.09 3.02 0.36 1.10 5.23%
SUBTOTAL N 5.17 24.61%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CERAMICA EN PISO M2 1.050 12.536 13.16 62.68%
BONDEX SACO 0.330 5.600 1.85 8.80%
EMPORADOR KG 0.150 1.445 0.22 1.03%
SUBTOTAL O 15.23 72.51%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CERAMICA EN PISO M2 1.050 0.10 0.11 0.50%
BONDEX SACO 0.330 0.05 0.02 0.08%
EMPORADOR KG 0.150 1.445 0.22 1.03%
SUBTOTAL P 0.34 1.61%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 21.00 100%
INDIRECTOS Y UTILIDAD 29.0% 6.09 29.0%
COSTO TOTAL DEL RUBRO 27.09 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:PORCELANATO EN PISOS TIPO GRAIMAN m2
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.316 0.32 0.85%
SUBTOTAL M 0.32 0.85%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.89 2.47 6.61%
ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.89 2.51 6.70%
MAESTRO MAY. (Est. Ocup. C1) 1.00 346.62 2.09 3.02 0.44 1.34 3.59%
SUBTOTAL N 6.32 16.91%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
PORCELANATO M2 1.050 25.000 26.25 70.21%
BONDEX PREMIUM SACO 0.330 10.500 3.47 9.27%
EMPORADOR KG 0.150 1.445 0.22 0.58%
SUBTOTAL O 29.93 80.05%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
PORCELANATO M2 1.050 0.50 0.53 1.40%
BONDEX PREMIUM SACO 0.330 0.25 0.08 0.22%
EMPORADOR KG 0.150 1.445 0.22 0.58%
SUBTOTAL P 0.82 2.20%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 37.39 100%
INDIRECTOS Y UTILIDAD 29.0% 10.84 29.0%
COSTO TOTAL DEL RUBRO 48.23 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:BARREDERA DE LAUREL m
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.044 0.04 1.29%
SUBTOTAL M 0.04 1.29%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.15 0.42 12.31%
CADENERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 0.15 0.46 13.37%
SUBTOTAL N 0.88 25.68%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
BARREDERAS INSTALADAS a=9 CM ML 0.402 6.000 2.41 70.73%
CLAVOS 2 - 2.5, 3 " KG 0.039 1.571 0.06 1.80%
SUBTOTAL O 2.47 72.53%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
BARREDERAS INSTALADAS a=9 CM ML 0.402 0.05 0.02 0.59%
CLAVOS 2 - 2.5, 3 " KG 0.039 0.01 0.00 0.01%
SUBTOTAL P 0.02 0.60%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 3.41 100%
INDIRECTOS Y UTILIDAD 29.0% 0.99 29.0%
COSTO TOTAL DEL RUBRO 4.40 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:VENTANA COREDIZA DE ALUMINIO m2
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 2.226 2.23 2.40%
SUBTOTAL M 2.23 2.40%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 3.00 8.33 8.98%
INSTALADOR (Est. Ocup. D2) 4.00 322.33 2.10 3.02 11.98 36.19 39.02%
SUBTOTAL N 44.52 48.00%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
VENTANAS DE AL. Y VIDRIO CORREDIZA M2 1.000 45.000 45.00 48.52%
SUBTOTAL O 45.00 48.52%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
VENTANAS DE AL. Y VIDRIO CORREDIZA M2 1.000 1.00 1.00 1.08%
SUBTOTAL P 1.00 1.08%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 92.75 100%
INDIRECTOS Y UTILIDAD 29.0% 26.90 29.0%
COSTO TOTAL DEL RUBRO 119.65 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:SALIDA MEDIDORES HG. LLAVE DE PASO Y ACCESORIOS H.G pto.
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.630 0.63 2.48%
SUBTOTAL M 0.63 2.48%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.50 1.39 5.47%
AYUDANTE (Est. Ocup. E2) 4.00 318.00 2.10 2.78 2.00 5.56 21.89%
ALBANIL (Est. Ocup. D2) 2.00 322.33 2.10 2.82 1.00 2.82 11.10%
PLOMERO (Est. Ocup. D2) 2.00 322.33 2.10 2.82 1.00 2.82 11.10%
SUBTOTAL N 12.59 49.57%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
TUBO ROSCABLE 1/2" AGUA FRIA U 1.000 8.000 8.00 31.50%
LLAVE DE PASO FV U 0.300 8.500 2.55 10.04%
CODOS PVC 3/4 U 2.000 0.220 0.44 1.73%
PERMATEX 3 ONZ. U 0.150 1.950 0.29 1.15%
TEE PVC 1/2" U 2.000 0.180 0.36 1.42%
UNION PVC 1/2" U 2.000 0.180 0.36 1.42%
SUBTOTAL O 12.00 47.25%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
TUBO ROSCABLE 1/2" AGUA FRIA U 1.000 0.10 0.10 0.39%
LLAVE DE PASO FV U 0.300 0.05 0.02 0.06%
CODOS PVC 3/4 U 2.000 0.01 0.02 0.08%
PERMATEX 3 ONZ. U 0.150 0.01 0.00 0.01%
TEE PVC 1/2" U 2.000 0.01 0.02 0.08%
UNION PVC 1/2" U 2.000 0.01 0.02 0.08%
SUBTOTAL P 0.18 0.69%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 25.40 100%
INDIRECTOS Y UTILIDAD 29.0% 7.37 29.0%
COSTO TOTAL DEL RUBRO 32.77 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:SALIDA DE AGUA FRIA HG. LLAVE DE CONTROL Y ACCESORIOS H.G pto.
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.359 0.36 2.63%
SUBTOTAL M 0.36 2.63%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.32 0.89 6.53%
AYUDANTE (Est. Ocup. E2) 3.00 318.00 2.10 2.78 0.96 2.67 19.58%
ALBANIL (Est. Ocup. D2) 2.00 322.33 2.10 2.82 0.64 1.80 13.24%
PLOMERO (Est. Ocup. D2) 2.00 322.33 2.10 2.82 0.64 1.80 13.24%
SUBTOTAL N 7.17 52.59%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
TUBO ROSCABLE 1/2" AGUA FRIA U 0.250 8.000 2.00 14.67%
LLAVE DE PASO FV U 0.300 8.500 2.55 18.71%
CODOS PVC 3/4 U 2.000 0.220 0.44 3.23%
PERMATEX 3 ONZ. U 0.150 1.950 0.29 2.15%
TEE PVC 1/2" U 2.000 0.180 0.36 2.64%
UNION PVC 1/2" U 2.000 0.180 0.36 2.64%
SUBTOTAL O 6.00 44.04%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
TUBO ROSCABLE 1/2" AGUA FRIA U 0.250 0.10 0.03 0.18%
LLAVE DE PASO FV U 0.300 0.05 0.02 0.11%
CODOS PVC 3/4 U 2.000 0.01 0.02 0.15%
PERMATEX 3 ONZ. U 0.150 0.01 0.00 0.01%
TEE PVC 1/2" U 2.000 0.01 0.02 0.15%
UNION PVC 1/2" U 2.000 0.01 0.02 0.15%
SUBTOTAL P 0.10 0.74%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 13.63 100%
INDIRECTOS Y UTILIDAD 29.0% 3.95 29.0%
COSTO TOTAL DEL RUBRO 17.58 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:SALIDA DE AGUA CALIENTE HG. LLAVE DE CONTROL Y ACCESORIOS H.G pto.
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.359 0.36 2.63%
SUBTOTAL M 0.36 2.63%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.32 0.89 6.53%
AYUDANTE (Est. Ocup. E2) 3.00 318.00 2.10 2.78 0.96 2.67 19.58%
ALBANIL (Est. Ocup. D2) 2.00 322.33 2.10 2.82 0.64 1.80 13.24%
PLOMERO (Est. Ocup. D2) 2.00 322.33 2.10 2.82 0.64 1.80 13.24%
SUBTOTAL N 7.17 52.59%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
TUBO HIDRO 3 1/2" AGUA CALIENTE U 0.250 8.000 2.00 14.67%
LLAVE DE PASO FV U 0.300 8.500 2.55 18.71%
CODOS PVC 3/4 U 2.000 0.220 0.44 3.23%
PERMATEX 3 ONZ. U 0.150 1.950 0.29 2.15%
TEE PVC 1/2" U 2.000 0.180 0.36 2.64%
UNION PVC 1/2" U 2.000 0.180 0.36 2.64%
SUBTOTAL O 6.00 44.04%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
TUBO HIDRO 3 1/2" AGUA CALIENTE U 0.250 0.10 0.03 0.18%
LLAVE DE PASO FV U 0.300 0.05 0.02 0.11%
CODOS PVC 3/4 U 2.000 0.01 0.02 0.15%
PERMATEX 3 ONZ. U 0.150 0.01 0.00 0.01%
TEE PVC 1/2" U 2.000 0.01 0.02 0.15%
UNION PVC 1/2" U 2.000 0.01 0.02 0.15%
SUBTOTAL P 0.10 0.74%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 13.63 100%
INDIRECTOS Y UTILIDAD 29.0% 3.95 29.0%
COSTO TOTAL DEL RUBRO 17.58 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:SALIDA PARA LAVADORAS. LLAVE DE CONTROL Y ACCESORIOS pto.
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.403 0.40 2.77%
SUBTOTAL M 0.40 2.77%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.32 0.89 6.11%
AYUDANTE (Est. Ocup. E2) 4.00 318.00 2.10 2.78 1.28 3.56 24.44%
ALBANIL (Est. Ocup. D2) 2.00 322.33 2.10 2.82 0.64 1.80 12.40%
PLOMERO (Est. Ocup. D2) 2.00 322.33 2.10 2.82 0.64 1.80 12.40%
SUBTOTAL N 8.06 55.34%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
TUBO HIDRO 3 1/2" AGUA CALIENTE U 0.250 8.000 2.00 13.74%
LLAVE DE PASO FV U 0.300 8.500 2.55 17.51%
CODOS PVC 3/4 U 2.000 0.220 0.44 3.02%
PERMATEX 3 ONZ. U 0.150 1.950 0.29 2.01%
TEE PVC 1/2" U 2.000 0.180 0.36 2.47%
UNION PVC 1/2" U 2.000 0.180 0.36 2.47%
SUBTOTAL O 6.00 41.23%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
TUBO HIDRO 3 1/2" AGUA CALIENTE U 0.250 0.10 0.03 0.17%
LLAVE DE PASO FV U 0.300 0.05 0.02 0.10%
CODOS PVC 3/4 U 2.000 0.01 0.02 0.14%
PERMATEX 3 ONZ. U 0.150 0.01 0.00 0.01%
TEE PVC 1/2" U 2.000 0.01 0.02 0.14%
UNION PVC 1/2" U 2.000 0.01 0.02 0.14%
SUBTOTAL P 0.10 0.70%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 14.56 100%
INDIRECTOS Y UTILIDAD 29.0% 4.22 29.0%
COSTO TOTAL DEL RUBRO 18.78 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:LLAVE DE PASO 3/4" u
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.090 0.09 0.82%
SUBTOTAL M 0.09 0.82%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.32 0.90 8.26%
AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.32 0.89 8.15%
SUBTOTAL N 1.79 16.41%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
LLAVE DE PASO FV U 1.000 8.500 8.50 77.84%
PERMATEX 3 ONZ. U 0.250 1.950 0.49 4.46%
SUBTOTAL O 8.99 82.30%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
LLAVE DE PASO FV U 1.000 0.05 0.05 0.46%
PERMATEX 3 ONZ. U 0.250 0.01 0.00 0.02%
SUBTOTAL P 0.05 0.48%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 10.92 100%
INDIRECTOS Y UTILIDAD 29.0% 3.17 29.0%
COSTO TOTAL DEL RUBRO 14.09 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:TUBERIA PVC 1/2" m
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.140 0.14 3.20%
SUBTOTAL M 0.14 3.20%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.50 1.41 32.27%
AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.50 1.39 31.81%
SUBTOTAL N 2.80 64.07%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
TUBO ROSCABLE 1/2" AGUA FRIA U 0.167 8.000 1.33 30.52%
PERMATEX 3 ONZ. U 0.001 1.950 0.00 0.04%
UNION PVC 1/2" U 0.330 0.180 0.06 1.36%
CODOS PVC 1/2" U 0.040 0.180 0.01 0.16%
TEE PVC 1/2" U 0.040 0.180 0.01 0.16%
SUBTOTAL O 1.41 32.25%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
TUBO ROSCABLE 1/2" AGUA FRIA U 0.167 0.10 0.02 0.38%
PERMATEX 3 ONZ. U 0.001 0.01 0.00 0.00%
UNION PVC 1/2" U 0.330 0.01 0.00 0.08%
CODOS PVC 1/2" U 0.040 0.01 0.00 0.01%
TEE PVC 1/2" U 0.040 0.01 0.00 0.01%
SUBTOTAL P 0.02 0.48%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 4.37 100%
INDIRECTOS Y UTILIDAD 29.0% 1.27 29.0%
COSTO TOTAL DEL RUBRO 5.64 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:LLAVE DE PICO FV DE LAVANDERIA u
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.140 0.14 1.12%
SUBTOTAL M 0.14 1.12%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.50 1.41 11.30%
AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.50 1.39 11.14%
SUBTOTAL N 2.80 22.44%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
LLAVE DE MANGUERA DE PICO U 1.000 9.000 9.00 72.12%
PERMATEX 3 ONZ. U 0.250 1.950 0.49 3.91%
SUBTOTAL O 9.49 76.02%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
LLAVE DE MANGUERA DE PICO U 1.000 0.05 0.05 0.40%
PERMATEX 3 ONZ. U 0.250 0.01 0.00 0.02%
SUBTOTAL P 0.05 0.42%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 12.48 100%
INDIRECTOS Y UTILIDAD 29.0% 3.62 29.0%
COSTO TOTAL DEL RUBRO 16.10 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:CANALIZACION PVC 50 MM pto.
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.448 0.45 2.77%
SUBTOTAL M 0.45 2.77%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 1.60 4.51 27.87%
AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 1.60 4.45 27.47%
SUBTOTAL N 8.96 55.34%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
POLILIMPIA LT 0.010 8.550 0.09 0.53%
POLIPEGA LT 0.010 10.550 0.11 0.65%
TUBO PVC 50 MM DESAGUE U 1.000 5.330 5.33 32.92%
ACCESORIOS PVC 50 MM U 1.000 1.200 1.20 7.41%
SUBTOTAL O 6.72 41.51%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
POLILIMPIA LT 0.010 0.01 0.00 0.00%
POLIPEGA LT 0.010 0.01 0.00 0.00%
TUBO PVC 50 MM DESAGUE U 1.000 0.05 0.05 0.31%
ACCESORIOS PVC 50 MM U 1.000 0.01 0.01 0.06%
SUBTOTAL P 0.06 0.37%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 16.19 100%
INDIRECTOS Y UTILIDAD 29.0% 4.70 29.0%
COSTO TOTAL DEL RUBRO 20.89 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:CANALIZACION PVC 110 MM pto.
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.448 0.45 1.74%
SUBTOTAL M 0.45 1.74%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 1.60 4.51 17.49%
AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 1.60 4.45 17.24%
SUBTOTAL N 8.96 34.73%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
POLILIMPIA LT 0.020 8.550 0.17 0.66%
POLIPEGA LT 0.020 10.550 0.21 0.82%
TUBO PVC 110 MM DESAGUE U 1.000 13.350 13.35 51.74%
ACCESORIOS DE PVC 110 MM U 1.000 2.600 2.60 10.08%
SUBTOTAL O 16.33 63.30%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
POLILIMPIA LT 0.020 0.01 0.00 0.00%
POLIPEGA LT 0.020 0.01 0.00 0.00%
TUBO PVC 110 MM DESAGUE U 1.000 0.05 0.05 0.19%
ACCESORIOS DE PVC 110 MM U 1.000 0.01 0.01 0.04%
SUBTOTAL P 0.06 0.23%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 25.80 100%
INDIRECTOS Y UTILIDAD 29.0% 7.48 29.0%
COSTO TOTAL DEL RUBRO 33.28 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:BAJANTES AGUAS SERVIDAS PVC 110 MM. UNION CODO m
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.056 0.06 0.76%
SUBTOTAL M 0.06 0.76%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.20 0.56 7.69%
AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.20 0.56 7.59%
SUBTOTAL N 1.12 15.28%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
POLILIMPIA LT 0.020 8.550 0.17 2.33%
POLIPEGA LT 0.020 10.550 0.21 2.88%
TUBO PVC 110 MM DESAGUE U 0.333 13.350 4.45 60.65%
ACCESORIOS DE PVC 110 MM U 0.500 2.600 1.30 17.74%
SUBTOTAL O 6.13 83.60%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
POLILIMPIA LT 0.020 0.01 0.00 0.00%
POLIPEGA LT 0.020 0.01 0.00 0.00%
TUBO PVC 110 MM DESAGUE U 0.333 0.05 0.02 0.23%
ACCESORIOS DE PVC 110 MM U 0.500 0.01 0.01 0.07%
SUBTOTAL P 0.02 0.30%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 7.33 100%
INDIRECTOS Y UTILIDAD 29.0% 2.13 29.0%
COSTO TOTAL DEL RUBRO 9.46 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:BAJANTES DE AGUAS LLUVIAS 110MM. UNION CODO m
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.056 0.06 0.76%
SUBTOTAL M 0.06 0.76%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.20 0.56 7.69%
AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.20 0.56 7.59%
SUBTOTAL N 1.12 15.28%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
POLILIMPIA LT 0.020 8.550 0.17 2.33%
POLIPEGA LT 0.020 10.550 0.21 2.88%
TUBO PVC 110 MM DESAGUE U 0.333 13.350 4.45 60.65%
ACCESORIOS DE PVC 110 MM U 0.500 2.600 1.30 17.74%
SUBTOTAL O 6.13 83.60%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
POLILIMPIA LT 0.020 0.01 0.00 0.00%
POLIPEGA LT 0.020 0.01 0.00 0.00%
TUBO PVC 110 MM DESAGUE U 0.333 0.05 0.02 0.23%
ACCESORIOS DE PVC 110 MM U 0.500 0.01 0.01 0.07%
SUBTOTAL P 0.02 0.30%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 7.33 100%
INDIRECTOS Y UTILIDAD 29.0% 2.13 29.0%
COSTO TOTAL DEL RUBRO 9.46 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:TUBERIA PVC 110MM DESAGUE (MAT/TRAN/INST) m
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.056 0.06 0.76%
SUBTOTAL M 0.06 0.76%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.20 0.56 7.69%
AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.20 0.56 7.59%
SUBTOTAL N 1.12 15.28%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
POLILIMPIA LT 0.020 8.550 0.17 2.33%
POLIPEGA LT 0.020 10.550 0.21 2.88%
TUBO PVC 110 MM DESAGUE U 0.333 13.350 4.45 60.65%
ACCESORIOS DE PVC 110 MM U 0.500 2.600 1.30 17.74%
SUBTOTAL O 6.13 83.60%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
POLILIMPIA LT 0.020 0.01 0.00 0.00%
POLIPEGA LT 0.020 0.01 0.00 0.00%
TUBO PVC 110 MM DESAGUE U 0.333 0.05 0.02 0.23%
ACCESORIOS DE PVC 110 MM U 0.500 0.01 0.01 0.07%
SUBTOTAL P 0.02 0.30%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 7.33 100%
INDIRECTOS Y UTILIDAD 29.0% 2.13 29.0%
COSTO TOTAL DEL RUBRO 9.46 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:REJILLA INTERIOR DE PISO 50MM u
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.112 0.11 1.37%
SUBTOTAL M 0.11 1.37%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
ALBANIL (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.40 1.13 13.81%
PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.40 1.11 13.61%
SUBTOTAL N 2.24 27.42%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
REJILLA DE PISO CROMADA FV U 1.000 5.690 5.69 69.65%
ARENA M3 0.001 3.500 0.00 0.04%
CEMENTO SACO 0.010 6.723 0.07 0.82%
SUBTOTAL O 5.76 70.51%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
REJILLA DE PISO CROMADA FV U 1.000 0.05 0.05 0.61%
ARENA M3 0.001 8.50 0.01 0.10%
CEMENTO SACO 0.010 0.50 0.01 0.06%
SUBTOTAL P 0.06 0.78%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 8.17 100%
INDIRECTOS Y UTILIDAD 29.0% 2.37 29.0%
COSTO TOTAL DEL RUBRO 10.54 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:TABLERO CONTROL GE4-8 PTO.S BREAKER 1 POLO 15-50 A u
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 1.065 1.07 0.93%
SUBTOTAL M 1.07 0.93%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 3.00 8.33 7.25%
ELECTRICISTA (Est. Ocup. D2) 1.00 322.33 2.10 2.82 3.00 8.45 7.35%
MAESTRO MAY. (Est. Ocup. C1) 1.00 346.62 2.09 3.02 1.50 4.52 3.94%
SUBTOTAL N 21.30 18.53%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
TABLERO DE DISTRIBUCION 4 CIRCUITOS U 1.000 50.000 50.00 43.50%
BREAKERS 20 A U 8.000 5.250 42.00 36.54%
SUBTOTAL O 92.00 80.03%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
TABLERO DE DISTRIBUCION 4 CIRCUITOS U 1.000 0.50 0.50 0.43%
BREAKERS 20 A U 8.000 0.01 0.08 0.07%
SUBTOTAL P 0.58 0.50%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 114.95 100%
INDIRECTOS Y UTILIDAD 29.0% 33.34 29.0%
COSTO TOTAL DEL RUBRO 148.29 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:ILUMINACION. CONDUCTOR N° 12 pto.
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.775 0.78 2.59%
SUBTOTAL M 0.78 2.59%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 1.00 2.78 9.28%
AYUDANTE (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 18.56%
ELECTRICISTA (Est. Ocup. D2) 2.00 322.33 2.10 2.82 2.00 5.64 18.83%
MAESTRO MAY. (Est. Ocup. C1) 1.00 346.62 2.09 3.02 0.50 1.51 5.04%
SUBTOTAL N 15.49 51.72%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
TUBO PVC PESADO DE 1/2" * 3 M U 1.500 1.330 2.00 6.66%
CABLE # 12 SOLIDO ML 10.000 0.480 4.80 16.03%
INTERRUPTOR SIMPLE LUMINEX U 1.000 4.911 4.91 16.40%
BOQUILLA PLAFON U 1.000 0.900 0.90 3.01%
CAJETIN RECTANGULAR PROFUNDO U 1.000 0.480 0.48 1.60%
CAJETIN OCTOGONAL U 1.000 0.350 0.35 1.17%
SUBTOTAL O 13.44 44.86%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
TUBO PVC PESADO DE 1/2" * 3 M U 1.500 0.05 0.08 0.25%
CABLE # 12 SOLIDO ML 10.000 0.01 0.10 0.33%
INTERRUPTOR SIMPLE LUMINEX U 1.000 0.02 0.02 0.07%
BOQUILLA PLAFON U 1.000 0.02 0.02 0.07%
CAJETIN RECTANGULAR PROFUNDO U 1.000 0.01 0.01 0.03%
CAJETIN OCTOGONAL U 1.000 0.01 0.01 0.03%
SUBTOTAL P 0.24 0.78%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 29.95 100%
INDIRECTOS Y UTILIDAD 29.0% 8.69 29.0%
COSTO TOTAL DEL RUBRO 38.64 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:SALIDA PARA TELEFONOS. ALAMBRE TELEFONICO, ALUG 2 x20 pto.
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.527 0.53 3.69%
SUBTOTAL M 0.53 3.69%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
PEON (Est. Ocup. E2) 2.00 318.00 2.10 2.78 1.00 2.78 19.44%
AYUDANTE (Est. Ocup. E2) 3.00 318.00 2.10 2.78 1.50 4.17 29.16%
ELECTRICISTA (Est. Ocup. D2) 2.00 322.33 2.10 2.82 1.00 2.82 19.72%
MAESTRO MAY. (Est. Ocup. C1) 1.00 346.62 2.09 3.02 0.25 0.76 5.28%
SUBTOTAL N 10.53 73.60%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
TUBO PVC PESADO DE 1/2" * 3 M U 1.000 1.330 1.33 9.30%
ALAMBRE # 20 DE TELEFONO ML 6.500 0.200 1.30 9.09%
CAJETIN RECTANGULAR PROFUNDO U 1.000 0.480 0.48 3.36%
SUBTOTAL O 3.11 21.75%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
TUBO PVC PESADO DE 1/2" * 3 M U 1.000 0.05 0.05 0.35%
ALAMBRE # 20 DE TELEFONO ML 6.500 0.01 0.07 0.45%
CAJETIN RECTANGULAR PROFUNDO U 1.000 0.01 0.01 0.07%
SUBTOTAL P 0.13 0.87%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 14.30 100%
INDIRECTOS Y UTILIDAD 29.0% 4.15 29.0%
COSTO TOTAL DEL RUBRO 18.45 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:SALIDAS ANTENAS TV u
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.560 0.56 3.50%
SUBTOTAL M 0.56 3.50%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 2.00 5.56 34.79%
ELECTRICISTA (Est. Ocup. D2) 1.00 322.33 2.10 2.82 2.00 5.64 35.29%
SUBTOTAL N 11.20 70.09%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
TUBO PVC PESADO DE 1/2" * 3 M U 1.000 1.330 1.33 8.32%
CABLE COAXIAL TV CABLE ML 6.500 0.350 2.28 14.24%
CAJETIN RECTANGULAR PROFUNDO U 1.000 0.480 0.48 3.00%
SUBTOTAL O 4.09 25.56%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
TUBO PVC PESADO DE 1/2" * 3 M U 1.000 0.05 0.05 0.31%
CABLE COAXIAL TV CABLE ML 6.500 0.01 0.07 0.41%
CAJETIN RECTANGULAR PROFUNDO U 1.000 0.01 0.01 0.06%
SUBTOTAL P 0.13 0.78%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 15.98 100%
INDIRECTOS Y UTILIDAD 29.0% 4.63 29.0%
COSTO TOTAL DEL RUBRO 20.61 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:TOMACORRIENTE DOBLE 2#10 T.CONDUIT EMT. 1/2" pto
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.775 0.78 2.93%
SUBTOTAL M 0.78 2.93%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
ELECTRICISTA (Est. Ocup. D2) 2.00 322.33 2.10 2.82 2.00 5.64 21.32%
AYUDANTE (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 21.02%
PEON (Est. Ocup. E2) 1.00 318.00 2.10 2.78 1.00 2.78 10.51%
MAESTRO MAY. (Est. Ocup. C1) 1.00 346.62 2.09 3.02 0.50 1.51 5.71%
SUBTOTAL N 15.49 58.56%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
TUBO PVC PESADO DE 1/2" * 3 M U 1.000 1.330 1.33 5.03%
CABLE # 12 SOLIDO ML 9.000 0.480 4.32 16.33%
TOMACORRIENTE DOBLE POLARIZADO LUMINEX U 1.000 3.880 3.88 14.67%
CAJETIN RECTANGULAR PROFUNDO U 1.000 0.480 0.48 1.81%
SUBTOTAL O 10.01 37.84%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
TUBO PVC PESADO DE 1/2" * 3 M U 1.000 0.05 0.05 0.19%
CABLE # 12 SOLIDO ML 9.000 0.01 0.09 0.34%
TOMACORRIENTE DOBLE POLARIZADO LUMINEX U 1.000 0.02 0.02 0.08%
CAJETIN RECTANGULAR PROFUNDO U 1.000 0.01 0.01 0.04%
SUBTOTAL P 0.17 0.64%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 26.45 100%
INDIRECTOS Y UTILIDAD 29.0% 7.67 29.0%
COSTO TOTAL DEL RUBRO 34.12 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:PUERTAS PRICIPALES LACADAS u
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.429 0.43 0.20%
SUBTOTAL M 0.43 0.20%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 2.65%
CARPINTERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 1.00 3.02 1.44%
SUBTOTAL N 8.58 4.09%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
PUERTAS DE MADERA PRINCIPAL U 1.000 200.000 200.00 95.23%
SUBTOTAL O 200.00 95.23%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
PUERTAS DE MADERA PRINCIPAL U 1.000 1.00 1.00 0.48%
SUBTOTAL P 1.00 0.48%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 210.01 100%
INDIRECTOS Y UTILIDAD 29.0% 60.90 29.0%
COSTO TOTAL DEL RUBRO 270.91 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:MUEBLE BAJO COCINA (TABLERO TRIPLEX) m
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.290 0.29 0.23%
SUBTOTAL M 0.29 0.23%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 1.00 2.78 2.19%
CARPINTERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 1.00 3.02 2.38%
SUBTOTAL N 5.80 4.56%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
MUEBLES BAJOS DE COCINA ML 1.000 120.000 120.00 94.42%
SUBTOTAL O 120.00 94.42%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
MUEBLES BAJOS DE COCINA ML 1.000 1.00 1.00 0.79%
SUBTOTAL P 1.00 0.79%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 127.09 100%
INDIRECTOS Y UTILIDAD 29.0% 36.86 29.0%
COSTO TOTAL DEL RUBRO 163.95 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:MUEBLES ALTOS DE COCINA (TABLERO TRIPLEX) m
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.429 0.43 0.33%
SUBTOTAL M 0.43 0.33%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 4.28%
CARPINTERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 1.00 3.02 2.32%
SUBTOTAL N 8.58 6.60%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
MUEBLES ALTOS DE COCINA ML 1.000 120.000 120.00 92.30%
SUBTOTAL O 120.00 92.30%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
MUEBLES ALTOS DE COCINA ML 1.000 1.00 1.00 0.77%
SUBTOTAL P 1.00 0.77%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 130.01 100%
INDIRECTOS Y UTILIDAD 29.0% 37.70 29.0%
COSTO TOTAL DEL RUBRO 167.71 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:CLOSET (TABLERO TRIPLEX) m2
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.429 0.43 0.33%
SUBTOTAL M 0.43 0.33%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 4.28%
CARPINTERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 1.00 3.02 2.32%
SUBTOTAL N 8.58 6.60%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CLOSETS M2 1.000 120.000 120.00 92.30%
SUBTOTAL O 120.00 92.30%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CLOSETS M2 1.000 1.00 1.00 0.77%
SUBTOTAL P 1.00 0.77%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 130.01 100%
INDIRECTOS Y UTILIDAD 29.0% 37.70 29.0%
COSTO TOTAL DEL RUBRO 167.71 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:CERRADURA PRINCIPAL (CESA), TIPO NOVA CROMADA u
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.429 0.43 0.46%
SUBTOTAL M 0.43 0.46%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 5.91%
CARPINTERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 1.00 3.02 3.21%
SUBTOTAL N 8.58 9.12%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CERRADURA PRINCIPAL U 1.000 85.000 85.00 90.32%
SUBTOTAL O 85.00 90.32%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CERRADURA PRINCIPAL U 1.000 0.10 0.10 0.11%
SUBTOTAL P 0.10 0.11%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 94.11 100%
INDIRECTOS Y UTILIDAD 29.0% 27.29 29.0%
COSTO TOTAL DEL RUBRO 121.40 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:CERRADURA DORMITORIO (CESA)TIPO, NOVA CROMADA u
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.429 0.43 2.03%
SUBTOTAL M 0.43 2.03%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 26.34%
CARPINTERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 1.00 3.02 14.31%
SUBTOTAL N 8.58 40.64%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CERRADURA LLAVE SEGURO GEO O YALE ITAL. U 1.000 12.000 12.00 56.85%
SUBTOTAL O 12.00 56.85%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CERRADURA LLAVE SEGURO GEO O YALE ITAL. U 1.000 0.10 0.10 0.47%
SUBTOTAL P 0.10 0.47%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 21.11 100%
INDIRECTOS Y UTILIDAD 29.0% 6.12 29.0%
COSTO TOTAL DEL RUBRO 27.23 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:CERRADURA BAÑO (CESA), TIPO NOVA CROMADA u
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.429 0.43 2.24%
SUBTOTAL M 0.43 2.24%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 29.09%
CARPINTERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 1.00 3.02 15.80%
SUBTOTAL N 8.58 44.90%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CERRADURA DE BAÑO U 1.000 10.000 10.00 52.33%
SUBTOTAL O 10.00 52.33%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CERRADURA DE BAÑO U 1.000 0.10 0.10 0.52%
SUBTOTAL P 0.10 0.52%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 19.11 100%
INDIRECTOS Y UTILIDAD 29.0% 5.54 29.0%
COSTO TOTAL DEL RUBRO 24.65 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:CERRADURA PASILLO (CESA), TIPO NOVA CROMADA u
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.429 0.43 2.03%
SUBTOTAL M 0.43 2.03%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 26.34%
CARPINTERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 1.00 3.02 14.31%
SUBTOTAL N 8.58 40.64%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
CERRADURA LLAVE SEGURO GEO O YALE ITAL. U 1.000 12.000 12.00 56.85%
SUBTOTAL O 12.00 56.85%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
CERRADURA LLAVE SEGURO GEO O YALE ITAL. U 1.000 0.10 0.10 0.47%
SUBTOTAL P 0.10 0.47%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 21.11 100%
INDIRECTOS Y UTILIDAD 29.0% 6.12 29.0%
COSTO TOTAL DEL RUBRO 27.23 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:PASAMANO DE HIERRO C/MANGON MADERA m
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.290 0.29 0.43%
SUBTOTAL M 0.29 0.43%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 1.00 2.78 4.14%
INSTALADOR (Est. Ocup. D2) 1.00 322.33 2.10 3.02 1.00 3.02 4.50%
SUBTOTAL N 5.80 8.65%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
MANGON DE MADERA ML 1.000 20.000 20.00 29.81%
PASAMANO DE HIERRO M 1.000 40.000 40.00 205.55%
SUBTOTAL O 60.00 235.36%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
MANGON DE MADERA ML 1.000 0.50 0.50 0.75%
PASAMANO DE HIERRO M 1.000 0.50 0.50 2.57%
SUBTOTAL P 1.00 3.31%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 67.09 250%
INDIRECTOS Y UTILIDAD 29.0% 19.46 29.0%
COSTO TOTAL DEL RUBRO 86.55 279.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:PUERTA DE PLYWOOD TAMBOR 0.70 LACADA, INCLUYE MARCOS Y TAPAMARCOS u
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.429 0.43 0.33%
SUBTOTAL M 0.43 0.33%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 4.28%
CARPINTERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 1.00 3.02 2.32%
SUBTOTAL N 8.58 6.60%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
PUERTAS TAMBORADAS DE 0,70 U 1.000 120.000 120.00 92.30%
SUBTOTAL O 120.00 92.30%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
PUERTAS TAMBORADAS DE 0,70 U 1.000 1.00 1.00 0.77%
SUBTOTAL P 1.00 0.77%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 130.01 100%
INDIRECTOS Y UTILIDAD 29.0% 37.70 29.0%
COSTO TOTAL DEL RUBRO 167.71 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:PUERTA DE PLYWOOD TAMBOR 0.80 LACADA, INCLUYE MARCOS Y TAPAMARCOS u
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.429 0.43 0.30%
SUBTOTAL M 0.43 0.30%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 3.83%
CARPINTERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 1.00 3.02 2.08%
SUBTOTAL N 8.58 5.92%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
PUERTAS TAMBORADAS DE 0,90 U 1.000 135.000 135.00 93.10%
SUBTOTAL O 135.00 93.10%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
PUERTAS TAMBORADAS DE 0,90 U 1.000 1.00 1.00 0.69%
SUBTOTAL P 1.00 0.69%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 145.01 100%
INDIRECTOS Y UTILIDAD 29.0% 42.05 29.0%
COSTO TOTAL DEL RUBRO 187.06 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:PUERTA DE PLYWOOD TAMBOR 0.90 LACADA, INCLUYE MARCOS Y TAPAMARCOS u
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.429 0.43 0.30%
SUBTOTAL M 0.43 0.30%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 2.00 318.00 2.10 2.78 2.00 5.56 3.83%
CARPINTERO (Est. Ocup. D2) 1.00 322.33 2.10 3.02 1.00 3.02 2.08%
SUBTOTAL N 8.58 5.92%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
PUERTAS TAMBORADAS DE 0,90 U 1.000 135.000 135.00 93.10%
SUBTOTAL O 135.00 93.10%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
PUERTAS TAMBORADAS DE 0,90 U 1.000 1.00 1.00 0.69%
SUBTOTAL P 1.00 0.69%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 145.01 100%
INDIRECTOS Y UTILIDAD 29.0% 42.05 29.0%
COSTO TOTAL DEL RUBRO 187.06 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:TANQUE CALENTADOR 30 GL. u
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.280 0.28 0.10%
SUBTOTAL M 0.28 0.10%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 1.00 2.78 1.00%
PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 1.00 2.82 1.02%
SUBTOTAL N 5.60 2.02%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
TANQUE CALENTOR 30 GL U 1.000 263.393 263.39 94.87%
VALVULA CHECKE FV U 1.000 5.500 5.50 1.98%
ACCESORIOS IPS U 4.000 0.300 1.20 0.43%
PERMATEX 3 ONZ. U 0.300 1.950 0.59 0.21%
SUBTOTAL O 270.68 97.49%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
TANQUE CALENTOR 30 GL U 1.000 1.00 1.00 0.36%
VALVULA CHECKE FV U 1.000 0.05 0.05 0.02%
ACCESORIOS IPS U 4.000 0.01 0.04 0.01%
PERMATEX 3 ONZ. U 0.300 0.01 0.00 0.00%
SUBTOTAL P 1.09 0.39%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 277.65 100%
INDIRECTOS Y UTILIDAD 29.0% 80.52 29.0%
COSTO TOTAL DEL RUBRO 358.17 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:PINTURA DE CAUCHO INTERIOR 2 MANOS, LATEX VINYL ACRILICO, CEMENTO BLANCO. EQUIPO: ANDAMIOS m2
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.056 0.06 1.92%
ANDAMIOS 0.040 0.19 0.200 0.00 0.05%
SUBTOTAL M 0.06 1.97%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.20 0.56 19.04%
PINTOR (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.20 0.56 19.32%
SUBTOTAL N 1.12 38.36%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
PINTURA DE CAUCHO PERMALATEX GL 0.080 16.518 1.32 45.25%
LIJA # 60 PLG. 0.200 0.446 0.09 3.06%
CARBONATO DE CALCIO TIPO A KG 0.020 0.230 0.00 0.16%
RESAFLEX GL 0.020 13.393 0.27 9.17%
YESO KG 0.100 0.500 0.05 5.88%
SUBTOTAL O 1.73 63.53%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
PINTURA DE CAUCHO PERMALATEX GL 0.080 0.05 0.00 0.14%
LIJA # 60 PLG. 0.200 0.01 0.00 0.07%
CARBONATO DE CALCIO TIPO A KG 0.020 0.01 0.00 0.01%
RESAFLEX GL 0.020 0.05 0.00 0.03%
YESO KG 0.100 0.01 0.00 0.12%
SUBTOTAL P 0.01 0.36%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 2.92 100%
INDIRECTOS Y UTILIDAD 29.0% 0.85 29.0%
COSTO TOTAL DEL RUBRO 3.77 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:PINTURA DE CAUCHO EXTERIOR 2 MANOS, LATEX VINYL ACRILICO, CEMENTO BLANCO. EQUIPO: ANDAMIOS m2
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.070 0.07 2.18%
ANDAMIOS 0.040 0.19 0.250 0.00 0.06%
SUBTOTAL M 0.07 2.24%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.25 0.70 21.65%
PINTOR (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.25 0.71 21.96%
SUBTOTAL N 1.40 43.61%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
PINTURA DE CAUCHO PERMALATEX GL 0.080 16.518 1.32 41.17%
LIJA # 60 PLG. 0.200 0.446 0.09 2.78%
CARBONATO DE CALCIO TIPO A KG 0.020 0.230 0.00 0.14%
RESAFLEX GL 0.020 13.393 0.27 8.34%
YESO KG 0.100 0.500 0.05 5.38%
SUBTOTAL O 1.73 57.81%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
PINTURA DE CAUCHO PERMALATEX GL 0.080 0.05 0.00 0.12%
LIJA # 60 PLG. 0.200 0.01 0.00 0.06%
CARBONATO DE CALCIO TIPO A KG 0.020 0.01 0.00 0.01%
RESAFLEX GL 0.020 0.05 0.00 0.03%
YESO KG 0.100 0.01 0.00 0.11%
SUBTOTAL P 0.01 0.33%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 3.21 100%
INDIRECTOS Y UTILIDAD 29.0% 0.93 29.0%
COSTO TOTAL DEL RUBRO 4.14 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:PINTURA CAUCHO CIELO RAZO. LATEX VINYL ACRILICO, CEMENTO BLANCO. EQUIPO: ANDAMIOS m2
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.070 0.07 2.18%
ANDAMIOS 0.040 0.19 0.250 0.00 0.06%
SUBTOTAL M 0.07 2.24%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.25 0.70 21.65%
PINTOR (Est. Ocup. D2) 1.00 322.33 2.10 2.82 0.25 0.71 21.96%
SUBTOTAL N 1.40 43.61%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
PINTURA DE CAUCHO PERMALATEX GL 0.080 16.518 1.32 41.17%
LIJA # 60 PLG. 0.200 0.446 0.09 2.78%
CARBONATO DE CALCIO TIPO A KG 0.020 0.230 0.00 0.14%
RESAFLEX GL 0.020 13.393 0.27 8.34%
YESO KG 0.100 0.500 0.05 5.38%
SUBTOTAL O 1.73 57.81%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
PINTURA DE CAUCHO PERMALATEX GL 0.080 0.05 0.00 0.12%
LIJA # 60 PLG. 0.200 0.01 0.00 0.06%
CARBONATO DE CALCIO TIPO A KG 0.020 0.01 0.00 0.01%
RESAFLEX GL 0.020 0.05 0.00 0.03%
YESO KG 0.100 0.01 0.00 0.11%
SUBTOTAL P 0.01 0.33%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 3.21 100%
INDIRECTOS Y UTILIDAD 29.0% 0.93 29.0%
COSTO TOTAL DEL RUBRO 4.14 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:TEJA COMUN INC. TIRAS EUCALIP.MORTERO 1:3 m2
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.211 0.21 1.07%
SUBTOTAL M 0.21 1.07%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 0.73 2.02 10.20%
INSTALADOR (Est. Ocup. D2) 1.00 322.33 2.10 3.02 0.73 2.20 11.08%
SUBTOTAL N 4.22 21.29%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
ECUATEJA CLASICA M2 1.050 9.821 10.31 52.06%
TIRAS DE MADERA U 3.000 1.500 4.50 22.72%
CLAVOS DE ACERO 1.5 " NEGRO U 0.250 0.030 0.01 0.04%
SUBTOTAL O 14.82 74.81%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
ECUATEJA CLASICA M2 1.050 0.50 0.53 2.65%
TIRAS DE MADERA U 3.000 0.01 0.03 0.15%
CLAVOS DE ACERO 1.5 " NEGRO U 0.250 0.01 0.00 0.01%
SUBTOTAL P 0.56 2.81%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 19.81 100%
INDIRECTOS Y UTILIDAD 29.0% 5.74 29.0%
COSTO TOTAL DEL RUBRO 25.55 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:LAVAMANOS POMPANO BLANCO u
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.448 0.45 0.50%
SUBTOTAL M 0.45 0.50%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 1.60 4.45 4.99%
PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 1.60 4.51 5.06%
SUBTOTAL N 8.96 10.05%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
LAVAMANOS CHELSEA AZUL COBALTO O SIMILAR U 1.000 40.000 40.00 44.87%
LLAVE FV 221/78 CROMADA VERSALLES U 1.000 25.000 25.00 28.04%
TUBO DE ABASTO 1/2" DE NYLON U 2.000 4.550 9.10 10.21%
SIFON DESAGUE - LAVAVO U 1.000 4.800 4.80 5.38%
SUBTOTAL O 78.90 88.50%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
LAVAMANOS CHELSEA AZUL COBALTO O SIMILAR U 1.000 0.50 0.50 0.56%
LLAVE FV 221/78 CROMADA VERSALLES U 1.000 0.25 0.25 0.28%
TUBO DE ABASTO 1/2" DE NYLON U 2.000 0.02 0.04 0.04%
SIFON DESAGUE - LAVAVO U 1.000 0.05 0.05 0.06%
SUBTOTAL P 0.84 0.94%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 89.15 100%
INDIRECTOS Y UTILIDAD 29.0% 25.85 29.0%
COSTO TOTAL DEL RUBRO 115.00 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:INODORO TANQUE BAJO TIPO SAVEX u
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.448 0.45 0.22%
SUBTOTAL M 0.45 0.22%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 1.60 4.45 2.17%
PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 1.60 4.51 2.20%
SUBTOTAL N 8.96 4.37%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
INODORO TANQUE BAJO LINEA INTERM. COLOR SUAVE U 1.000 140.000 140.00 68.28%
TUBO DE ABASTO 1/2" DE NYLON U 1.000 4.550 4.55 2.22%
CEMENTO SACO 0.010 6.723 0.07 0.03%
ARENA M3 0.030 3.500 0.11 0.05%
ANILLO DE CERA U 3.000 8.000 24.00 11.71%
TACOS FISHER Y TORNILLO U 3.000 0.700 2.10 1.02%
SUBTOTAL O 170.82 83.31%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
INODORO TANQUE BAJO LINEA INTERM. COLOR SUAVE U 1.000 0.50 0.50 0.24%
TUBO DE ABASTO 1/2" DE NYLON U 1.000 0.02 0.02 0.01%
CEMENTO SACO 0.010 0.50 0.01 0.00%
ARENA M3 0.030 8.50 0.26 0.12%
ANILLO DE CERA U 3.000 8.00 24.00 11.71%
TACOS FISHER Y TORNILLO U 3.000 0.01 0.03 0.01%
SUBTOTAL P 24.81 12.10%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 205.04 100%
INDIRECTOS Y UTILIDAD 29.0% 59.46 29.0%
COSTO TOTAL DEL RUBRO 264.50 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:LAVAPLATOS COMPLETO, GRIFERIA u
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.839 0.84 0.28%
SUBTOTAL M 0.84 0.28%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 3.00 8.33 2.78%
PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 3.00 8.45 2.82%
SUBTOTAL N 16.78 5.61%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
FREGADERO TEKA O SIMILAR 1* .50 M U 1.000 98.500 98.50 32.93%
MEZCLADORA DE COCINA CROMO-ORO U 1.000 166.786 166.79 55.76%
PERMATEX 3 ONZ. U 0.100 1.950 0.20 0.07%
TUBO DE ABASTO 1/2" DE NYLON U 2.000 4.550 9.10 3.04%
SIFON DESAGUE - FREGADERO U 1.000 5.800 5.80 1.94%
SUBTOTAL O 280.38 93.74%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
FREGADERO TEKA O SIMILAR 1* .50 M U 1.000 0.50 0.50 0.17%
MEZCLADORA DE COCINA CROMO-ORO U 1.000 0.50 0.50 0.17%
PERMATEX 3 ONZ. U 0.100 0.01 0.00 0.00%
TUBO DE ABASTO 1/2" DE NYLON U 2.000 0.02 0.04 0.01%
SIFON DESAGUE - FREGADERO U 1.000 0.05 0.05 0.02%
SUBTOTAL P 1.09 0.36%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 299.09 100%
INDIRECTOS Y UTILIDAD 29.0% 86.74 29.0%
COSTO TOTAL DEL RUBRO 385.83 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:ACCESORIOS DE BAÑO jg
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.302 0.30 0.72%
SUBTOTAL M 0.30 0.72%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
INSTALADOR (Est. Ocup. D2) 1.00 322.33 2.10 3.02 2.00 6.04 14.37%
SUBTOTAL N 6.04 14.37%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
JUEGO DE ACCESORIOS SPAZZIO U 1.000 28.384 28.38 67.55%
TACOS FISHER Y TORNILLO U 10.000 0.700 7.00 16.66%
SUBTOTAL O 35.38 84.21%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
JUEGO DE ACCESORIOS SPAZZIO U 1.000 0.20 0.20 0.48%
TACOS FISHER Y TORNILLO U 10.000 0.01 0.10 0.24%
SUBTOTAL P 0.30 0.71%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 42.02 100%
INDIRECTOS Y UTILIDAD 29.0% 12.19 29.0%
COSTO TOTAL DEL RUBRO 54.21 129.00%
ANALISIS DE PRECIOS UNITARIOS
UNIDAD:
RUBRO:DUCHA SENCILLA CROMADA COMPLETA - INCL. MEZCLADORA Y GRIFERIA u
DETALLE: 0
EQUIPOS
DESCRIPCION No. COSTO/HORA HORAS EQUIPO COSTO %
HERRAMIENTA MANUAL 5 % M.O. 0.560 0.56 0.59%
SUBTOTAL M 0.56 0.59%
MANO DE OBRA
DESCRIPCION (CATEGORIA) No. JORNAL N. F.S.R. JORNAL/HORA COSTO HORA COSTO UNITARIO %
AYUDANTE (Est. Ocup. E2) 1.00 318.00 2.10 2.78 2.00 5.56 5.90%
PLOMERO (Est. Ocup. D2) 1.00 322.33 2.10 2.82 2.00 5.64 5.99%
SUBTOTAL N 11.20 11.89%
MATERIALES
DESCRIPCION UNIDAD CANTIDAD UNITARIO COSTO %
MEZCLADORA DE DUCHA MALENA U 1.000 82.000 82.00 87.04%
PERMATEX 3 ONZ. U 0.100 1.950 0.20 0.21%
SUBTOTAL O 82.20 87.25%
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO %
MEZCLADORA DE DUCHA MALENA U 1.000 0.25 0.25 0.27%
PERMATEX 3 ONZ. U 0.100 0.01 0.00 0.00%
SUBTOTAL P 0.25 0.27%
TOTAL COSTOS DIRECTOS X=(M+N+O+P) 94.21 100%
INDIRECTOS Y UTILIDAD 29.0% 27.32 29.0%
COSTO TOTAL DEL RUBRO 121.53 129.00%
(hora/und) EQUIPO MANO DE OBRA COSTO HO
0.320 1 HERRAMIENTA MANUAL 5 % M.O. 1 PEON (Est. Ocup. E2) 2.78
2 CARGADORA FRONTAL 40.00 2 AYUDANTE (Est. Ocup. E2) 2.78
25 1 3 VOLQUETE 10 M3 30.00 3 ALBANIL (Est. Ocup. D2) 2.82
4 MOTONIVELADORA 35.00 4 ADOQUINADOR (Est. Ocup. D 2.82
5 RODILLO VIBRATORIO LISO 25.00 5 FIERRERO (Est. Ocup. D2) 2.82
6 PLANCHA VIBROCOMPAC. 3.00 6 MAESTRO MAY. (Est. Ocup. C 3.02
7 TANQUERO 15.00 7 CHOFER TIPO E VOLQUETAS( 4.16
8 ENCOFRADO METALICO 0.05 8 OPERADOR EQUIPO PESADO G 3.02
9 CONCRETERA 6.50 9 OPERADOR EQUIPO PESADO G 2.94
10 VIBRADOR 4.00 10 PLOMERO (Est. Ocup. D2) 2.82
11 EXCAVADORA 30.00 11 PINTOR (Est. Ocup. D2) 2.82
12 ACABADORA DE ASFALTO 35.00 12 AY. MAQUINARIA (Est. Ocup. 2.82
13 DISTRIBUIDOR DE ASFALTO 25.00 13 ENLUCIDOR (Est. Ocup. D2) 2.82
14 RODILLO NEUMATICO 18.00 14 ELECTRICISTA (Est. Ocup. D2 2.82
15 PLANTA ASFALTICA + GENERADOR 100.00 15 MAESTRO SOL. ESP. (Est. Ocu 3.02
16 ESCOBA MECANICA 10.00 16 INSTALADOR (Est. Ocup. D2) 2.82
17 COMPRESOR 12.00 17 CARPINTERO (Est. Ocup. D2) 2.82
18 ESTACION TOTAL 2.50 18 TOPOGRAFO 2 (Est. Ocup. C1 3.02
19 PULIDORA 4.00 19 CADENERO (Est. Ocup. D2) 2.82
20 ELEVADOR 5.00
21 EQUIPO DE SUELDA Y PINTURA 1.20
22 ENCOFRADO DE MADERA 5.000
23 ANDAMIOS 0.188
MATERIALES
1 CEMENTO 6.72 SACO 1
2 ARENA 3.50 M3 2
3 RIPIO 4.50 M3 3
4 AGUA 0.220 M3 4
5 PIEDRA BOLA 4.50 M3 5
6 ALAMBRE DE AMARRE # 18 2.22 KG 6
7 ACERO DE REFUERZO 1.08 KG 7
8 ACERO ESTRUCTURAL 1.06 KG 8
9 TABLA DURA DE ENCOFRADO 1.60 U 9
10 RIELES DE EUCALIPTO 2.23 U 10
11 CLAVOS 2 - 2.5, 3 " 1.57 KG 11
12 PINGOS 2.5 1.43 U 12
13 LADRILLO TIPO CHAMBO 0.12 U 13
14 IMPERMEABILIZANTE SIKA 1 1.25 KG 14
15 MARMOL PULIDO Y ABRILLANTADO IMPORTADO 150.00 ML 15
16 CERAMICA EN PARED 12.08 M2 16
17 CERAMICA EN PISO 12.54 M2 17
18 EMPORADOR 1.44 KG 18
19 CENEFA DE CERAMICA 10.72 ML 19
20 ECUATEJA CLASICA 9.82 M2 20
21 TIRAS DE MADERA 1.50 U 21
22 CLAVOS DE ACERO 1.5 " NEGRO 0.03 U 22
23 PARQUET CHANUL O COLORADO PULIDO Y LACADO 3 MANOS 45.00 M2 23
24 PINTURA DE CAUCHO PERMALATEX 16.52 GL 24
25 BROCHA 5.36 U 25
26 LIJA # 60 0.45 PLG. 26
27 CARBONATO DE CALCIO TIPO A 0.23 KG 27
28 RESAFLEX 13.39 GL 28
29 PINTURA ANTICORROSIVA 18.58 GL 29
30 VENTANAS DE AL. Y VIDRIO CORREDIZA 45.00 M2 30
31 MUEBLES BAJOS DE COCINA 120.00 ML 31
32 MUEBLES ALTOS DE COCINA 120.00 ML 32
33 CLOSETS 120.00 M2 33
34 CERRADURA DE BAÑO 10.00 U 34
35 CERRADURA PRINCIPAL 85.00 U 35
36 CERRADURA LLAVE SEGURO GEO O YALE ITAL. 12.00 U 36
37 MANGON DE MADERA 20.00 ML 37
(hora/und) 38 PASAMANO DE HIERRO 40.00 M 38
0.140 39 PLATINA DE 1/2 * 1/8 * 6 M 2.80 U 39
REND 40 SUELDA 60 11 2.40 KG 40
57 2 41 TUBO RECTANGULAR 20 * 40 * 6 M 16.12 U 41
42 VARILLA CUADRADA DE 1/2 " * 6 M 5.60 U 42
43 TOL LAMINADO AL FRIO 1/32 29.00 PL. 43
44 PUERTAS TAMBORADAS DE 0,90 135.00 U 44
45 PUERTAS DE MADERA PRINCIPAL 200.00 U 45
46 PUERTAS TAMBORADAS DE 0,70 120.00 U 46
47 CHAPA ELECTRICA VIRO 80.00 U 47
48 LLAVE DE PASO FV 8.50 U 48
49 LLAVE DE MANGUERA DE PICO 9.00 U 49
50 LLAVE VALVULA ITAL. DE 1/2" 4.50 U 50
51 TUBO ROSCABLE 1/2" AGUA FRIA 8.00 U 51
52 TUBO HIDRO 3 1/2" AGUA CALIENTE 8.00 U 11.52 52
53 TEFLON 0.45 U 16.13 53
54 PERMATEX 3 ONZ. 1.95 U 27.66 54
55 ACCESORIOS IPS 0.30 U 55
56 MEDIDOR DE AGUA 90.00 U 56
57 ACCESORIOS DE PVC 110 MM 2.60 U 57
58 ACCESORIOS DE PVC 75 MM 2.25 U 58
59 ACCESORIOS PVC 50 MM 1.20 U 59
60 POLIPEGA 10.55 LT 60
61 POLILIMPIA 8.55 LT 61
62 TUBERIA DE H.S. 150 MM M.C. 2.50 U 62
63 REJILLA DE PISO CROMADA FV 5.69 U 63
64 CAJETIN RECTANGULAR PROFUNDO 0.48 U 64
65 CAJETIN OCTOGONAL 0.35 U 65
66 TUBO PVC PESADO DE 1/2" * 3 M 1.33 U 66
67 TUBO PVC LIVIANO DE 1/2" * 3 M 1.21 U 67
68 TUBO PVC PESADO DE 3/4" * 3 M 1.79 U 68
69 CABLE # 12 SOLIDO 0.48 ML 69
70 CABLE # 14 SOLIDO 0.35 ML 70
71 CABLE # 8 VARIOS HILOS 1.36 ML 71
72 ALAMBRE # 20 DE TELEFONO 0.20 ML 72
73 CABLE COAXIAL TV CABLE 0.35 ML 73
74 CABLE 8 HILOS PORTERO ELECTRICO 1.65 ML 74
75 BOQUILLA PLAFON 0.90 U 75
76 TOMACORRIENTE DOBLE POLARIZADO LUMINEX 3.88 U 76
77 INTERRUPTOR SIMPLE LUMINEX 4.91 U 77
78 CONMUTADOR LUMINEX 5.46 U 78
79 TOMA ESPECIAL ELECTRICA TV CABLE - TELEF. 5.80 U 79
80 PORTERO ELECTRICO 1 DPTO. + 1 EXTENSION 133.93 U 80
81 CODOS PVC 1/2" 0.18 U 81
82 CODOS PVC 3/4 0.22 U 82
83 TABLERO DE DISTRIBUCION 4 CIRCUITOS 50.00 U 83
84 BREAKERS 20 A 5.25 U 84
85 MEDIDOR DE LUZ 120.00 U 85
86 FREGADERO TEKA O SIMILAR 1* .50 M 98.50 U 86
87 MEZCLADORA DE COCINA CROMO-ORO 166.79 U 87
88 TUBO DE ABASTO 1/2" DE NYLON 4.55 U 88
89 SIFON DESAGUE - FREGADERO 5.80 U 89
90 INODORO TANQUE BAJO LINEA INTERM. COLOR SUAVE 140.00 U 90
91 INODORO TANQUE BAJO LINEA INTERM. COLOR FUERTE 150.00 U 91
92 LAVAMANOS EMPOTRABLE OACKBROOK COL. SUAVE 30.00 U 92
93 LAVAMANOS CHELSEA AZUL COBALTO O SIMILAR 40.00 U 93
94 MEZCLADORA DE LAVAVO FV FUTURA 67/102 4" 130.36 U 94
95 LLAVE FV 221/78 CROMADA VERSALLES 25.00 U 95
96 SIFON DESAGUE - LAVAVO 4.80 U 96
97 JUEGO DE ACCESORIOS SPAZZIO 28.38 U 97
98 TANQUE CALENTOR 30 GL 263.39 U 98
99 VALVULA CHECKE FV 5.50 U 99
100 MANGUERA - SALIDA DE GAS 1.60 ML 100
(hora/und) 101 DERIVACION DE COBRE PARA COCINA - CALEFON 4.50 U 101
0.800 102 ABRAZADERAS 0.16 U 102
REND 103 EXTRACTOR DE OLORES JET AIR 125.00 U 103
10 3 104 CHAMPEADORA MANUAL 1.60 U 104
105 YESO 0.50 KG 105
106 BLOQUE ALIVIANADO PARA LOSA E=15 CM. 0.35 U 106
107 SUBBASE CLASE 3 2.50 M3 107
108 BARREDERAS INSTALADAS a=9 CM 6.00 ML 108
109 MEDIA DUELA DE CHANDUL MACHIMBRADA 30.00 M2 109
110 PLATINA DE 1" * 3/16 * 6M. 7.07 U 110
111 BISAGRAS 5/8 * 3" PUERTA DE HIERRO 1.00 U 111
112 PICAPORTE HIERRO 5.50 U 112
113 VIDRIO CATEDRAL 4 MM. INSTALADO 9.82 M2 113
114 MEZCLADORA DE DUCHA MALENA 82.00 U 114
115 TUBO PVC 110 MM DESAGUE 13.35 U 115
116 TUBO PVC 75 MM DESAGUE 11.96 U 116
117 TUBO PVC 50 MM DESAGUE 5.33 U 117
118 SILICON DE PISTOLA 4.25 U 118
119 PINTURA ESMALTE COLOR 17.56 GL 119
120 CHAPA PHILIPS SENCILLA O TRAVEX 25.00 U 120
121 ENCOFRADO DE LOSA 1.60 M2 121
122 ADITIVO 2.230 KG 122
123 ENCOFRADO 5.960 M2 123
124 CLAVOS,ALAMBRE, VARIOS 2.000 GLB 124
125 BONDEX 5.600 SACO 125
126 POLIETILENO 1.000 M2 126
127 PORCELANATO 25.000 M2 127
128 BONDEX PREMIUM 10.500 SACO 128
129 TEE PVC 1/2" 0.180 U 129
130 UNION PVC 1/2" 0.180 U 130
131 TACOS FISHER Y TORNILLO 0.700 U 131
132 ANILLO DE CERA 8.000 U 132
(hora/und)
0.040
REND
200 4
(hora/und)
0.533
REND
15 5
(hora/und)
1.000
REND
8 6
(hora/und)
1.333
REND
6 7
(hora/und)
2.667
REND
3 8
(hora/und)
2.667
REND
3 9
(hora/und)
1.600
REND
5 10
(hora/und)
4.000
REND
2 11
0.050.0540.104
0.7488
(hora/und)
1.600
REND
5 12
(hora/und)
0.020
REND
400 13
(hora/und)
0.030
REND
267 14
10.02
(hora/und)
0.500
REND
16 15
(hora/und)
0.333
REND
24 17
(hora/und)
1.000
REND
8 16
(hora/und)
11.940
REND
0.67 18
(hora/und)
2.500
REND
3.2 19
(hora/und)
1.000
REND
8 20
(hora/und)
0.615
REND
13 21
(hora/und)
0.889
REND
9 22
(hora/und)
0.889
REND
9 23
(hora/und)
0.889
REND
9 24
(hora/und)
0.727
REND
11 25
(hora/und)
0.727
REND
11 26
(hora/und)
0.727
REND
11 27
(hora/und)
0.250
REND
32 28
(hora/und)
0.800
REND
10 29
(hora/und)
0.727
REND
11 30
(hora/und)
0.889
REND
9 31
(hora/und)
0.151
REND
53 32
(hora/und)
2.996
REND
2.67 33
(hora/und)
0.500
REND
16 34
(hora/und)
0.320
REND
25 35
(hora/und)
0.320
REND
25 36
(hora/und)
0.320
REND
25 37
(hora/und)
0.320
REND
25 38
(hora/und)
0.500
REND
16 39
(hora/und)
0.500
REND
16 40
(hora/und)
1.600
REND
5 41
(hora/und)
1.600
REND
5 42
(hora/und)
0.200
REND
40 43
(hora/und)
0.200
REND
40 44
(hora/und)
0.200
REND
40 45
(hora/und)
0.400
REND
20 46
(hora/und)
2.996
REND
2.67 47
(hora/und)
1.000
REND
8 48
(hora/und)
0.500
REND
16 49
(hora/und)
2.000
REND
4 50
(hora/und)
1.000
REND
8 51
(hora/und)
1.000
REND
8 52
(hora/und)
1.000
REND
8 53
(hora/und)
1.000
REND
8 54
(hora/und)
1.000
REND
8 55
(hora/und)
1.000
REND
8 56
1.12 4250011000
(hora/und)
1.000
REND
8 57
(hora/und)
1.000
REND
8 58
(hora/und)
1.000
REND
8 59
(hora/und)
1.000
REND
8 60
(hora/und)
1.000
REND
8 61
(hora/und)
1.000
REND
8 62
(hora/und)
1.000
REND
8 63
(hora/und)
1.000
REND
8 64
(hora/und)
0.200
REND
40 65
(hora/und)
0.250
REND
32 66
(hora/und)
0.250
REND
32 67
(hora/und)
0.727
REND
11 68
(hora/und)
1.600
REND
5 69
(hora/und)
1.600
REND
5 70
(hora/und)
2.996
REND
2.67 71
(hora/und)
2.000
REND
4 72
(hora/und)
2.000
REND
4 73
JORNAL NOMI. FSR318.00 2.10 COSTOS INDIRECTOS = 29.00%
318.00 2.10
322.33 2.10
322.33 2.10
322.33 2.10
346.62 2.09
485.64 2.06
346.62 2.09
337.08 2.09
322.33 2.10
322.33 2.10
322.33 2.10
322.33 2.10
322.33 2.10
346.62 2.09
322.33 2.10
322.33 2.10
346.62 2.09
322.33 2.10
TRANSPORTE
CEMENTO 0.50 SACO
ARENA 8.50 M3
RIPIO 8.50 M3
AGUA 0.100 LT
PIEDRA BOLA 8.50 M3
ALAMBRE DE AMARRE # 18 0.05 KG
ACERO DE REFUERZO 0.05 KG
ACERO ESTRUCTURAL 0.05 KG
TABLA DURA DE ENCOFRADO 0.05 U
RIELES DE EUCALIPTO 0.05 U
CLAVOS 2 - 2.5, 3 " 0.01 KG
PINGOS 2.5 0.05 U
LADRILLO TIPO CHAMBO 0.01 U
IMPERMEABILIZANTE SIKA 1 0.01 KG
MARMOL PULIDO Y ABRILLANTADO IMPORTADO 1.00 ML
CERAMICA EN PARED 0.10 M2
CERAMICA EN PISO 0.10 M2
EMPORADOR 0.01 KG
CENEFA DE CERAMICA 0.10 ML
ECUATEJA CLASICA 0.50 M2
TIRAS DE MADERA 0.01 U
CLAVOS DE ACERO 1.5 " NEGRO 0.01 U
PARQUET CHANUL O COLORADO PULIDO Y LACADO 3 MANOS 1.00 M2
PINTURA DE CAUCHO PERMALATEX 0.05 GL
BROCHA 0.01 U
LIJA # 60 0.01 PLG.
CARBONATO DE CALCIO TIPO A 0.01 KG
RESAFLEX 0.05 GL
PINTURA ANTICORROSIVA 0.10 GL
VENTANAS DE AL. Y VIDRIO CORREDIZA 1.00 M2
MUEBLES BAJOS DE COCINA 1.00 ML
MUEBLES ALTOS DE COCINA 1.00 ML
CLOSETS 1.00 M2
CERRADURA DE BAÑO 0.10 U
CERRADURA PRINCIPAL 0.10 U
CERRADURA LLAVE SEGURO GEO O YALE ITAL. 0.10 U
MANGON DE MADERA 0.50 ML
PASAMANO DE HIERRO 0.50 M
PLATINA DE 1/2 * 1/8 * 6 M 0.05 U
SUELDA 60 11 0.05 KG
TUBO RECTANGULAR 20 * 40 * 6 M 0.05 U
VARILLA CUADRADA DE 1/2 " * 6 M 0.05 U
TOL LAMINADO AL FRIO 1/32 0.05 PL.
PUERTAS TAMBORADAS DE 0,90 1.00 U
PUERTAS DE MADERA PRINCIPAL 1.00 U
PUERTAS TAMBORADAS DE 0,70 1.00 U
CHAPA ELECTRICA VIRO 0.05 U
LLAVE DE PASO FV 0.05 U
LLAVE DE MANGUERA DE PICO 0.05 U
LLAVE VALVULA ITAL. DE 1/2" 0.05 U
TUBO ROSCABLE 1/2" AGUA FRIA 0.10 U
TUBO HIDRO 3 1/2" AGUA CALIENTE 0.10 U
TEFLON 0.01 U
PERMATEX 3 ONZ. 0.01 U
ACCESORIOS IPS 0.01 U
MEDIDOR DE AGUA 1.00 U
ACCESORIOS DE PVC 110 MM 0.01 U
ACCESORIOS DE PVC 75 MM 0.01 U
ACCESORIOS PVC 50 MM 0.01 U
POLIPEGA 0.01 LT
POLILIMPIA 0.01 LT
TUBERIA DE H.S. 150 MM M.C. 0.20 U
REJILLA DE PISO CROMADA FV 0.05 U
CAJETIN RECTANGULAR PROFUNDO 0.01 U
CAJETIN OCTOGONAL 0.01 U
TUBO PVC PESADO DE 1/2" * 3 M 0.05 U
TUBO PVC LIVIANO DE 1/2" * 3 M 0.05 U
TUBO PVC PESADO DE 3/4" * 3 M 0.05 U
CABLE # 12 SOLIDO 0.01 ML
CABLE # 14 SOLIDO 0.01 ML
CABLE # 8 VARIOS HILOS 0.01 ML
ALAMBRE # 20 DE TELEFONO 0.01 ML
CABLE COAXIAL TV CABLE 0.01 ML
CABLE 8 HILOS PORTERO ELECTRICO 0.01 ML
BOQUILLA PLAFON 0.02 U
TOMACORRIENTE DOBLE POLARIZADO LUMINEX 0.02 U
INTERRUPTOR SIMPLE LUMINEX 0.02 U
CONMUTADOR LUMINEX 0.02 U
TOMA ESPECIAL ELECTRICA TV CABLE - TELEF. 0.02 U
PORTERO ELECTRICO 1 DPTO. + 1 EXTENSION 0.25 U
CODOS PVC 1/2" 0.01 U
CODOS PVC 3/4 0.01 U
TABLERO DE DISTRIBUCION 4 CIRCUITOS 0.50 U
BREAKERS 20 A 0.01 U
MEDIDOR DE LUZ U
FREGADERO TEKA O SIMILAR 1* .50 M 0.50 U
MEZCLADORA DE COCINA CROMO-ORO 0.50 U
TUBO DE ABASTO 1/2" DE NYLON 0.02 U
SIFON DESAGUE - FREGADERO 0.05 U
INODORO TANQUE BAJO LINEA INTERM. COLOR SUAVE 0.50 U
INODORO TANQUE BAJO LINEA INTERM. COLOR FUERTE 0.50 U
LAVAMANOS EMPOTRABLE OACKBROOK COL. SUAVE 0.50 U
LAVAMANOS CHELSEA AZUL COBALTO O SIMILAR 0.50 U
MEZCLADORA DE LAVAVO FV FUTURA 67/102 4" 0.25 U
LLAVE FV 221/78 CROMADA VERSALLES 0.25 U
SIFON DESAGUE - LAVAVO 0.05 U
JUEGO DE ACCESORIOS SPAZZIO 0.20 U
TANQUE CALENTOR 30 GL 1.00 U
VALVULA CHECKE FV 0.05 U
MANGUERA - SALIDA DE GAS 0.05 ML
DERIVACION DE COBRE PARA COCINA - CALEFON 0.05 U
ABRAZADERAS 0.01 U
EXTRACTOR DE OLORES JET AIR 1.00 U
CHAMPEADORA MANUAL 0.05 U
YESO 0.01 KG
BLOQUE ALIVIANADO PARA LOSA E=15 CM. 0.01 U
SUBBASE CLASE 3 6.00 M3
BARREDERAS INSTALADAS a=9 CM 0.05 ML
MEDIA DUELA DE CHANDUL MACHIMBRADA 0.50 M2
PLATINA DE 1" * 3/16 * 6M. 0.05 U
BISAGRAS 5/8 * 3" PUERTA DE HIERRO 0.05 U
PICAPORTE HIERRO 0.05 U
VIDRIO CATEDRAL 4 MM. INSTALADO 0.50 M2
MEZCLADORA DE DUCHA MALENA 0.25 U
TUBO PVC 110 MM DESAGUE 0.05 U
TUBO PVC 75 MM DESAGUE 0.05 U
TUBO PVC 50 MM DESAGUE 0.05 U
SILICON DE PISTOLA 0.05 U
PINTURA ESMALTE COLOR 0.10 GL
CHAPA PHILIPS SENCILLA O TRAVEX 0.05 U
ENCOFRADO DE LOSA 0.20 M2
ADITIVO 0.05 KG
ENCOFRADO 0.10 M2
CLAVOS,ALAMBRE, VARIOS 0.05 GLB
BONDEX 0.05 SACO
POLIETILENO 0.05 M2
PORCELANATO 0.50 M2
BONDEX PREMIUM 0.25 SACO
TEE PVC 1/2" 0.01 U
UNION PVC 1/2" 0.01 U
TACOS FISHER Y TORNILLO 0.01 U
ANILLO DE CERA 8.00 U