Pre Supuesto
description
Transcript of Pre Supuesto
PRESUPUESTO
PRESUSPUESTO: CONSTRUCCION DE CERCO PERIMETRICO EN LA I.E ANTONIO RAYMONDI-DISTRITO DE CASMA
CLIENTE: MUNICIPALIDAD DISTRITAL DE CASMA
LUGAR: ANCASH - CASMA- CASMA
ITEM DESCRIPCION UNDCANTIDA
D PUSUB
TOTALTOTAL
1 OBRAS PROVISIONALES
1.1 CARTEL DE OBRA DE 7.20 X 6.00M 1.00 757.18 757.18
1.2 CASETA PARA GUARDIANIA Y ALMACEN 1
2,500.00 2,500.00
3,257.18 3,257.182 OBRAS PRELIMINARES
2.1 LIMPIEZA DE TERRENO - Manual m2 346.51 2.47 855.88
2.2 TRAZO, NIVELES Y REPLANTEO m2 207.91 0.64 133.06
SUB TOTAL 988.94 988.94
3 MOVIMIENTO DE TIERRAS
3.1 EXCAVACIÓN DE ZANJAS PARA CIMIENTOS m3 150.10 25.01 3,754.00
3.2ELIMINACIÓN DE MATERIAL EXCEDENTE -Distancia 5.00 km m3 195.12 1.25 243.90
SUB TOTAL 3,997.90 3,997.90
4 CIMIENTO CORRIDO
4.1 CIMIENTOS
4.1.1 CONCRETO CICLÓPEO FC = 140 KG/CM2 + 70 % PG. m3 150.1 438.1065,758.8
1
4.2 SOBRECIMIENTOS
4.2.1 CONCRETO CICLÓPEO FC=140KG/CM2 + 30% PM m3 14.31 372.10 5,324.75
4.2.2 ENCOFRADO Y DESENCOFRADO - SOBRECIMIENTO m2 190.80 31.09 5,931.97
SUB TOTAL 77,015.5
3 77015.533
5 CONCRETO ARMADO
5.1 COLUMNAS
5.1.1 CONCRETO f'c = 175Kg/Cm2 m3 32.43 341.0511,060.2
5
5.1.2 ENCOFRADO Y DESENCOFRADO - Columnas m2 324 66.9521,691.8
0
5.1.3 ACERO GRADO60 - Columnas Kg 1146.74 3.83 4,392.01
SUB TOTAL 37,144.0
7 37,144.076 ALBAÑILERIA
6.1 MURO DE SOGA - Ladrillo KK ARTESANAL m2 699.50 42.1329,469.9
4
SUB TOTAL 29,469.9
4 29,469.94
7 CARPINTERÍA DE METÁLICA
7.1 PORTON DE FERRO 3.00 X 2.50 M Und 2.001,500.0
0 3,000.00
SUB TOTAL 3,000.00 3,000.00
8 FLETE TERRESTRE
8.1 FLETE TERRESTRE Kg 150,218.96 0.0812,017.5
2
SUB TOTAL 12,017.5
2 12,017.52
TOTA
L 166,891.0
7
ITEM RESUMEN PARTIDASSUB TOTAL
TOTAL
1.00 OBRAS PROVISIONALES 3,257.18
2.00 OBRAS PRELIMINARES 988.94
3.00 MOVIMIENTO DE TIERRAS 3,997.90
4.00 CIMIENTO CORRIDO 77,015.53
5.00 CONCRETO ARMADO 37,144.07
6.00 ALBAÑILERIA 29,469.94
7.00 CARPINTERIA METALICA 3,000.00
8.00 FLETE TERRESTRE 12,017.52
COSTO DIRECTO DE OBRA S/. 166,891.07
GASTOS GENERALES (10 % CD) S/. 16,689.11
UTILIDAD(10 %) S/. 16,689.11
SUB TOTAL S/. 200,269.29
IGV(18%) S/. 36,048.47
TOTAL COSTOS DE INFRAESTRUCTURA S/. 236,317.76