By: Cory Sauvé, Lacy Powers, Jesse Jones, Louis Sick, and Glenn Wolfe Johnson Creek Assessment and Restoration Plan

Transcript of PowerPoint Presentation(1)

Page 1: PowerPoint Presentation(1)

By:Cory Sauvé, Lacy Powers, Jesse Jones, Louis Sick, and Glenn Wolfe

Johnson Creek Assessment and Restoration Plan

Page 2: PowerPoint Presentation(1)

Goal is to restore the Johnson Creek Watershed through:Stream bank stabilization projectsAbandoned mine drainage remediation

Project area will focus on a two mile portion of Johnson Creek and its tributariesRt. 15 bridge to the mouth at the Tioga River

Watershed Vision

Page 3: PowerPoint Presentation(1)

Improve water quality and aquatic habitat to increase the diversity and health of fish and macroinvertebrate communities.Will improve the recreational opportunities found in the

watershed

Increase community education on the importance of the Johnson Creek Watershed through interactive seminars and opportunities to volunteer.Will encourage stewardship for generations to come

Goals

Page 4: PowerPoint Presentation(1)

Johnson Creek WatershedDrainage basin is 17.4 square milesBloss and Hamilton TownshipBlossburg and Cherry Flats USGS topographic maps

Project Area2 Mile section of Johnson Creek and its tributaries

Bellman Run, Boone Run, Mills Creek, and several unnamed tributaries

Drainage area is 5.6 square miles

Location

Page 5: PowerPoint Presentation(1)

Johnson Creek Watershed

Page 6: PowerPoint Presentation(1)

Johnson Creek Watershed

Page 7: PowerPoint Presentation(1)

Johnson Creek Project Area

Page 8: PowerPoint Presentation(1)

Johnson Creek Project Area

Page 9: PowerPoint Presentation(1)

Johnson Creek is on the 303d list Impaired for metals: Iron, manganese, and aluminum Result of coal mining operations in the watershed

The Department of Environmental Protection has conducted studies on Johnson Creek.

Studies showed high levels of tolerant taxa indicative of impaired water bodies.

Habitat assessments identified stream bank erosion and poor riparian buffer zones as recurring issues in the watershed.

History

Page 10: PowerPoint Presentation(1)

Mainly forested , no agricultural activities Residential and industrial land use near Arnot and Blossburg

Sewage discharges, increased erosion, stream channelization, and bank cementation

Abandoned strip minesMain source of pollution

36 acres of abandoned mine land in project area.

Little recreational uses in watershed besides hunting.

Land Use

Page 11: PowerPoint Presentation(1)

Sampling Plan Site Descriptions

Page 12: PowerPoint Presentation(1)

Sampling Sites

Page 13: PowerPoint Presentation(1)

Located approximately 100 meters upstream of bridge at South Williamson Road.

Good tree cover over the stream and healthy riparian buffer zone.

Small amounts of undercutting along the stream.

The substrate is most cobble and boulder , very little silt

A strong presence of macroinvertebrates

Site 1 : Bellman Run

Page 14: PowerPoint Presentation(1)

Located about 1 mile upstream of the confluence with Johnson creek.

Forested riparian zone, completely shadedAbandoned mine land upstream of siteSubstrate consisted of mostly cobble with no silt prevalent.

Woody debris in streamVisual iron and aluminum precipitate were presentNo marcoinvertebrate communities were present

Site 2: Unnamed Tributary of Johnson Creek

Page 15: PowerPoint Presentation(1)

Located 100 meters upstream of the confluence with Bellman Run.

Stream channel was mostly shadedGood riparian buffer on both banks; some bank erosion. The substrate consisted of gravel with little cobble. Some silt

and sand were presentMacroinvertebrate communities was present.

Taxa consisted of mainly caddis and midges.

Site 3: Johnson Creek Upstream of Bellman Run

Page 16: PowerPoint Presentation(1)

Located 100 meters upstream from the confluence with the unnamed tributary.

Stream channel was mostly shaded with about 50 percent residential and forested land use.

Little to no riparian zone on the south bank from residential structuresSevere erosion was present along the exposed bank.

Substrate was very poor consisting of silt and sands. Some gravel and boulder formations were present.

Macroinvertebrate communities were present.

Site 4: Johnson Creek Upstream of UNT

Page 17: PowerPoint Presentation(1)

Located 300 meters downstream from the unnamed tributary and Johnson creek confluence.

Partly shaded and mostly residential and forested land use.Severe stream bank erosion along both banksMacroinvertebrate communities were present at the site

Site 5: Johnson Creek Downstream of UNT

Page 18: PowerPoint Presentation(1)

Located 50 meters upstream of the Tabor Street bridge in Blossburg.

Limited canopy cover and marginal riparian zones were present.

Multiple industrial and storm water discharges were found within this site location.

The substrate consisted of mostly silt and sand. Very small amounts of gravel and boulder were present.

Site 6: Johnson Creek at Tabor Street

Page 19: PowerPoint Presentation(1)

Located 100 meters upstream of the mouth at the Tioga River. The steam was partially shaded and had marginal riparian

zones on either side of the creek.There were several discharge points along both stream banks.The substrate consisted of mostly silt and sand with very

small amounts of gravel and cobble.Limited macroinvertabrate communities were present. Visible iron and aluminum precipitate was present at the

confluence with the Tioga River.

Site 7: Johnson Creek UPS of Tioga River

Page 20: PowerPoint Presentation(1)
Page 21: PowerPoint Presentation(1)

Restoration Projects

Page 22: PowerPoint Presentation(1)

Located 1 mile upstream of the confluence of Johnson Creek.Significant abandoned mine land in the area.Remainder of the land is forested.Site is completely shaded and has large forested riparian

buffer zones.Substrate is composed of cobble, with no silt.

Site 1: Unnamed Tributary of Johnson Creek

Page 23: PowerPoint Presentation(1)
Page 24: PowerPoint Presentation(1)

Surface Mine Reclamation above AMD Discharge

Page 25: PowerPoint Presentation(1)

Abandoned Mine Land upstream of AMD Discharge

Page 26: PowerPoint Presentation(1)

Abandoned Mine Land upstream of AMD Discharge

Page 27: PowerPoint Presentation(1)

Abandoned Mine Land upstream of AMD Discharge

Page 28: PowerPoint Presentation(1)

AMD Discharge Point

Page 29: PowerPoint Presentation(1)

UNT Below AMD Impacts

Page 30: PowerPoint Presentation(1)

Passive treatment system parameters50 gpm design flowpH= 3.48Iron = 1.50 mg/LAluminum = 9.00 mg/LManganese = 1.20 mg/LAlkalinity = 0.00 mg/L

Restoration Recommendation

Page 31: PowerPoint Presentation(1)

Treatment Train1. Vertical Flow Wetland

162 ft X 93 ft at top of freeboard3 ft of limestone, 2 feet of OM, and 3 ft of waterPiping system to flush Aluminum

2. Settling Pond3. Limestone Bed4. Polishing aerobic wetland

131 ft X 68 ft at top of freeboard

Restoration Recommendation cont.

Page 32: PowerPoint Presentation(1)

Stream bank stability reduced by limited riparian zone and residential structures

Stream stabilization project will take place along a 250 ft section that is experiencing stream bank erosion.

Site 2: Johnson Creek Upstream UNT

Page 33: PowerPoint Presentation(1)
Page 34: PowerPoint Presentation(1)

Bank Erosion

Page 35: PowerPoint Presentation(1)

Bank Erosion

Page 36: PowerPoint Presentation(1)

Bank Erosion

Page 37: PowerPoint Presentation(1)

Construction of a brush mattress to protect the eroding bank is recommended .Help to capture sediment during flood eventsRestore the marginal riparian vegetation Allow native plants to colonize area to increase habitat

Bank Stabilization Project Design

Page 38: PowerPoint Presentation(1)

250 ft section of stream bank will be graded to desirable slope8-12 inch trench will be constructed below water line

Brush will be placed in trench6-9 ft cuttings ; 4 inches thick when compressedAnchored by riprap rock to protect toe of brush mattress

Live and dead stakes will be placed at 3 ft intervals on the bankHeld together by 16 gauge wire Stakes will be a minimum of 2.5 ft

Branches and soil will fill void space between stakes

Brush Mattress Design

Page 39: PowerPoint Presentation(1)
Page 40: PowerPoint Presentation(1)
Page 41: PowerPoint Presentation(1)

Stream bank eroding due to limited riparian zones and concentrated flows

The erosion project will encompass 210 feet of the eroding bank

Site 3: Johnson Creek Downstream of UNT

Page 42: PowerPoint Presentation(1)
Page 43: PowerPoint Presentation(1)

Erosion at beginning of Project Area

Page 44: PowerPoint Presentation(1)

Main Bank Erosion

Page 45: PowerPoint Presentation(1)

Combination of a soil terrace and biologs is recommended.Soil terrace will stabilize eroding stream bank.Biologs will prevent erosion along channel bottom.

Bank Stabilization Project Design

Page 46: PowerPoint Presentation(1)

Biologs will be installed along the first 60 ft of the graded bank.

Soil Terrace along remaining 150 ft of eroding bank.Banks will be graded to a favorable slopeLayer of riprap stone will be placed at bottom layer to protect

toe of terraceSoil terraces will be compacted and covered by heavy jute

blankets Layers of brush will be placed between soil layers to increase

stabilitySoil will be fastened by wood stakes

Project will give bank stability and increase the riparian vegetation along the stream bank.

Bank Stabilization Project Design

Page 47: PowerPoint Presentation(1)
Page 48: PowerPoint Presentation(1)

The steam banks are eroding at this site due to limited riparian zones from industrial activity in the area.

Erosion project will include a 475 ft section of the east bank of the stream.

Site 4: Johnson Creek at Tabor Street

Page 49: PowerPoint Presentation(1)
Page 50: PowerPoint Presentation(1)

Stream Bank Erosion

Page 51: PowerPoint Presentation(1)

A soil terrace at the 475 ft section is recommended to increase the bank stability and promote increased riparian buffer zones from native vegetation.

A soil terrace with the same components from Site 3 will be used with the exception of the 60 ft of biologs.

Bank Stabilization Project Design