PDD Alembic

download PDD Alembic

of 61

Transcript of PDD Alembic

  • 8/12/2019 PDD Alembic

    1/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    1

    CLEAN DEVELOPMENT MECHANISM

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD)

    Version 03 - in effect as of: 22 December 2006

    CONTENTS

    A. General description of the small scale project activity

    B. Application of a baseline and monitoring methodology

    C. Duration of the project activity / crediting period

    D. Environmental impacts

    E. Stakeholders comments

    Annexes

    Annex 1: Contact information on participants in the proposed small scale project activity

    Annex 2: Information regarding public funding

    Annex 3: Baseline information

    Annex 4: Monitoring Information

    Annex 5: Supportives

    Enclosure 1 : IRR Calculation

  • 8/12/2019 PDD Alembic

    2/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    2

    Revision history of this document

    VersionNumber

    Date Description and reason of revision

    01 21 January

    2003

    Initial adoption

    02 8 July 2005 The Board agreed to revise the CDM SSC PDD to reflectguidance and clarifications provided by the Board since

    version 01 of this document.

    As a consequence, the guidelines for completing CDM SSCPDD have been revised accordingly to version 2. The latest

    version can be found at

    .03 22 December

    2006 The Board agreed to revise the CDM project design

    document for small-scale activities (CDM-SSC-PDD), taking

    into account CDM-PDD and CDM-NM.

  • 8/12/2019 PDD Alembic

    3/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    3

    SECTION A. General description of small-scale project activity

    A.1 Title of the small-scale project activity:

    >>

    5 MW Wind Power Project of Alembic Ltd at Bhavnagar , Gujarat, India

    Version 04,

    02nd

    November 2007

    A.2. Description of the small-scale project activity:

    >>

    Alembic Limited (henceforth referred to as Alembic in the PDD) was started in 1907 at Vadodara. It is

    ISO 9001 and ISO 14001 certified company and one of the Asia's most respected integrated

    pharmaceutical companies with manufacturing practices and facilities that conform to WHO GMP

    guidelines. Alembic is in the business of improving the quality of life and healthcare in over 75 countries

    around the world.

    Alembic considers the protection of the environment as its direct responsibility and all its processes and

    technologies incorporate this feature. A clean and a green environment is an absolute necessity and

    Alembic has ensured this by using renewable energy through the considered project activity of

    conceptualization and installation of the 5 MW Wind Power Project to satisfy a part of its energy

    requirements.

    The group has developed this project keeping in consideration of the funding available under the Clean

    Development Mechanism (CDM) of the United Nations Framework Convention on Climate Change.

    This is because the project activity qualifies as a CDM project because it would reduce the power

    consumption from the electricity grid (Western grid, India) thereby helping in significant reduction of

    GHG emissions.

    The project activity is also responsible for sustainable economic growth and conservation of environment

    through use of wind as a renewable source.

    The Project activity would generate 5 MW of electricity with efficient utilization of the available wind

    energy through adoption of the latest, efficient and modern technology. The generated electricity was to

    displace equivalent electricity procured from Gujarat Urja Vikas Nigam Limited (GUVNL) in the

    Panelav and Vadodara plants, shared between the plants in a ratio of 35:65 plant of Alembic Ltd. With

  • 8/12/2019 PDD Alembic

    4/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    4

    effect from 1 April 2006 the entire amount of electricity generated will be used to displace an equivalent

    amount of electricity from the Vadodara and Panelav plants1, as per the Alembic Limiteds requirements.

    M/S Alembic Ltd., Vadodara would have the ownership rights for the project activity and would be the

    sole transaction entity with the Executive Board of the United Nations Framework Convention on

    Climate Change.

    The 5 MW Wind Power Project comprises of Wind Energy Generators (WEGs) each of capacities 1.25

    MW supplied by M/S Suzlon Energy Ltd.

    The contributions of the project to sustainable development are:

    Generation of eco-friendly power;

    Conserving fossil fuel reserves in vision of long-term sustainability;

    Reducing GHG emissions compared to a business-as-usual scenario;

    Reducing other pollutants (SOx, NOx, PM, etc.) resulting from power generation in the grid;

    A.3. Project participants:

    >>

    Name of Party involved ((host)indicates a host Party)

    Private and/or public entity(ies)project participants (as

    applicable)

    Kindly indicate if the Partyinvolved wishes to be considered

    as project participant (Yes/No)

    India (Host) Alembic Limited (Private

    entity)

    No

    A.4. Technical description of the small-scale project activity:

    The technology applied for project activity is the power generation from renewable energy i.e. wind.

    The project proponent used the highly efficient technology for wind power generation. The

    technology is supplied by Suzlon limited.

    A.4.1. Location of the small-scale project activity:

    >> The detailed location of the site is shown in the map below:

    1GETCO Wheeling Agreement.

  • 8/12/2019 PDD Alembic

    5/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    5

    Project

    activity site

  • 8/12/2019 PDD Alembic

    6/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    6

    A.4.1.1. Host Party(ies):

    >> India

    A.4.1.2. Region/State/Province etc.:

    >> Gujarat

    A.4.1.3. City/Town/Community etc:

    >> Ukharla, Trambak, District Bhavnagar, PIN 364001

    A.4.1.4. Details of physical location, including information allowing the

    unique identification of this small-scale project activity :

    >>

    The project site is located at Ukharla Trambak in the district of Bhavnagar and in the Indian state of

    GUJARAT. Bhavnagar is approximately at 250 kms from AHMEDABAD. The site Ukharla has a

    latitude and longitude of around 21 34 23.2 N & 72 05 52.1 E respectively. It is located at

    approximately 225 meters from the mean sea level. These sites have been identified as ideally suited for

    wind power generation based on the studies and data analysis carried out by eminent agencies like M/S

    Suzlon Energy Ltd. The feasibility of these sites for wind power production has been established by

    Ministry of Non Conventional Energy Sources, Govt. of India

    A.4.2. Type and category(ies) and technology/measure of the small-scale project activity:

    >>

    Type & Category

    The project meets the applicability criteria of the small-scale CDM project activity category, Type I:

    Renewable Energy Projects (D: Grid connected renewable electricity generation) of the Indicative

    simplified baseline and monitoring methodologies for selected small scale CDM project activity

    categories

    Main Category: Type I Renewable energy projects.

    Sr.

    No

    Turbine Survey number as per Power

    Wheeling Agreement with

    GETCO

    1 S4 46/P1

    2 S5 30/P1

    3 S6 30/P2

    4 S7 30/P3

  • 8/12/2019 PDD Alembic

    7/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    7

    Sub Category: D Grid connected renewable electricity generation.

    As per the provisions of appendix B of simplified modalities and procedures for small scale CDM project

    activities (version 11), Type I D comprises renewable energy generation units, such as photovoltaics,

    hydro, tidal / wave, wind, geothermal, and renewable biomass, that supply electricity to and / or displace

    electricity from an electricity distribution system that is or would have been supplied by at least one

    fossil fuel fired generating unit. The project activity is within the threshold values stated by the

    methodology.

    The baseline and emission reduction calculations from the project would be based on paragraphs 9 of

    AMS-I.D (version 11) and the monitoring methodology would be based on guidance provided in

    paragraph 13 of AMS-I.D.

    Technology

    Alembic has procured the Wind Energy Generators (WEGs) from Indian company M/S. Suzlon Energy

    Ltd. The technology is a clean and safe technology since there are no GHG emissions associated with the

    electricity generation.

    A direct grid-connected high-speed horizontal axis generator, in combination with the multiple-stage

    combined spur / planetary gearbox delivers harmonics-free and grid-friendly power. The technical details

    of the WEG are as follows:

    Operating DataS.64/1250

    (50 Hz)

    Rotor diameter 64 m

    Hub height 65 m (variable as per requirement)

    Installed elec. Output 1250 kW

    Cut-in wind speed 3 m/s

    Rated wind speed 12 m/s

    Cut-out wind speed 25 m/s

    Survival wind speed 67 m/s

    RotorS.64/1250

    (50 Hz)

    Blade 3 bladed horizontal axis

  • 8/12/2019 PDD Alembic

    8/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    8

    Swept area 3217 m

    Rotational speed 13.9 / 20.8 rpm

    Regulation Pitch-regulated

    GeneratorS.64/1250

    (50 Hz)

    Type Asynchronous 4/6 poles

    Rated output 250 / 1250 kW

    Rotational speed 1006/1506 rpm

    Frequency 50 Hz

    GearboxS.64/1250

    (50 Hz)

    Type Integrated (1 planetary & 2 helical)

    Ratio 74.917 : 1

    Yaw SystemS.64/1250

    (50 Hz)

    Drive 4 electrically driven planetary gearboxBearings Polyamide slide bearings

    Braking SystemS.64/1250

    (50 Hz)

    Aerodynamic brake 3 independent systems with blade pitching

    Mechanical brake Hydraulic fail-safe disc brake system

    Control UnitS.64/1250

    (50 Hz)

    Type

    Programmable microprocessor-based; high speed data

    communication, active multilevel security, sophisticated operating

    software, advance data collection remote monitoring & control

    option, UPS back up, Real time operation indication

    TowerS.64/1250

    (50 Hz)

  • 8/12/2019 PDD Alembic

    9/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    9

    Type Lattice / Tubular, Hot Dip Galvanized, Epoxy / PU coated

    ErectionS.64/1250

    (50 Hz)

    Type With crane

    The salient features of the WEGs are as follows:

    Higher Efficiency

    Designed to achieve increased efficiency and co-efficient of power (Cp)

    Minimum Stress and LoadStatic stresses are taken care of by a well-balanced weight distribution design while wind

    induced dynamic radial loads are picked up by the separate main shaft bearing, which is

    integrated into the gearbox housing.

    Shock Load-free Operation

    Peak loads are compensated by a torque adjustable advanced hydrodynamic fluid coupling which

    also acts as an excellent vibration separation and shock-dampening device.

    Intelligent Control

    Next gen technologies applied by extensive operational experience maximizes yield

    Maximum Power Factor

    High-speed asynchronous generator with a multi-stage intelligent switching compensation system

    delivers power factor up to 0.99

    Climatic Shield

    Hermetically sheltered against thermal stresses, moisture, salinity, dust, snow, lightning strikes

    and extreme wind conditions, advanced over-voltage and lightning protection system

    Unique Micro-Pitching Control

    Unmatched fine pitching with 0.1 resolution to extract every possible unit of power

    Grid-friendly

    Grid friendly design generates harmonics-free pure sinusoidal power

    The WEG is designed according to the Germanischer Lloyd (GL) design standards.

    A.4.3 Estimated amount of emission reductions over the chosen crediting period:

    >>

    The project activity would result into CO2emission reduction of 89698 tons for 10 years crediting

    period.

  • 8/12/2019 PDD Alembic

    10/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    10

    Years Annual estimation of emission reductions in tonnes

    of CO2-e

    20089247

    20099247

    20109247

    20119247

    20128785

    20138785

    2014 8785

    20158785

    20168785

    20178785

    Total estimated reductions (tonnes of CO2e) 89698

    Total no of crediting years 10

    Annual average over the crediting period of

    Estimated reductions (tonnes of CO2e)

    8969

    A.4.4. Public funding of the small-scale project activity:

    >>

    No public funding from parties included in Annex I to the UNFCCC, is available to the project.

    A.4.5. Confirmation that the small-scale project activity is not a debundled component of a

    large scale project activity:

    According to appendix C of simplified modalities and procedures for small-scale CDM project activities,

    debundling

    is defined as the fragmentation of a large project activity into smaller parts. A small-scaleproject activity that is part of a large project activity is not eligible to use the simplified modalities and

    procedures for small-scale CDM project activities.

    According to para 2 of appendix C2

    2Appendix C to the simplified M&P for the small-scale CDM project activities,

    http://cdm.unfccc.int/Projects/pac/ssclistmeth.pdf

  • 8/12/2019 PDD Alembic

    11/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    11

    A proposed small-scale project activity shall be deemed to be a debundled component of a large project

    activity if there is a registered small-scale CDM project activity or an application to register another

    small-scale CDM project activity:

    With the same project participants;

    In the same project category and technology/measure;

    Registered within the previous 2 years; and

    Whose project boundary is within 1 km of the project boundary of the proposed small- scale

    activity at the closest point

    Since there is no small-scale activity registered and/or applied for registration in the name of project

    participant, which belongs to any of the categories of small-scale CDM project or meeting any of the de-

    bundling criteria stated above, the Alembics project activity therefore considered as small scale CDM

    project activity.

  • 8/12/2019 PDD Alembic

    12/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    12

    SECTION B. Application of a baseline and monitoring methodology

    B.1. Title and reference of the approved baseline and monitoring methodology applied to the

    small-scale project activity:

    >>

    The methodology used for this project is I. D. Grid connected renewable electricity generation

    (version 11)under the small scale methodologies Type I Renewable energy projects.

    For calculation of the combined margin baseline emission factor, the approved consolidated baseline

    methodology ACM0002 Consolidated baseline methodology for grid-connected electricity generation

    from renewable sources, Version 06 is applied.

    For additionality

    Attachment A to Appendix B of the simplified modalities and procedures for small-scale CDM project

    activities; Indicative simplified baseline and monitoring methodologies for selected small-scale CDM

    project activity categories

    Reference:http://cdm.unfccc.int/methodologies/SSCmethodologies/AppB_SSC_AttachmentA.pdf

    B.2 Justification of the choice of the project category:>>

    As per the provisions of simplified modalities and procedures for small scale CDM project activities

    (version 11), Type I. D comprises renewable energy generation units, such as photovoltaics, hydro,

    tidal/wave, wind, geothermal, and renewable biomass, that supply electricity to and/or displace electricity

    from an electricity distribution system that is or would have been supplied by at least one fossil fuel fired

    generating unit. If the unit added has both renewable and non-renewable components (e.g.a wind/diesel

    unit), the eligibility limit of 15 MW for a small-scale CDM project activity applies only to the renewable

    component. If the unit added co-fires fossil fuel, the capacity of the entire unit shall not exceed the limit

    of 15 MW.

    Project activity meets the applicability conditions of the methodology in following manner:

    S. No. Methodological requirement Justification

    1 This category comprises renewable energy

    generation units, such as photovoltaics, hydro,

    tidal/wave, wind, geothermal and renewable

    biomass, that supply electricity to and/or

    displace electricity from an electricity

    The project is a wind mill project hence

    applicable to this category. Due to

    project activity, there is an equivalent

    displacement of electricity (which is

    generated by fossil fuel) by renewable

  • 8/12/2019 PDD Alembic

    13/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    13

    distribution system that is or would have been

    supplied by at least one fossil fuel fired

    generating unit.

    source (wind) by using WTG

    technology.

    2 If the unit added has both renewable and non-

    renewable components (e.g.. a wind/diesel

    unit), the eligibility limit of 15MW for a small-

    scale CDM project activity applies only to the

    renewable component. If the unit added co-fires

    fossil fuel1, the capacity of the entire unit shall

    not exceed the limit of 15MW.

    There is neither non-renewable

    component added, nor co-firing is

    required for the proposed project

    activity. The renewable project capacity

    is 5 MW, well below the limit of 15

    MW.

    3 Combined heat and power (co-generation)

    systems are not eligible under this category.

    Not applicable. This project is not a

    Combined heat and power (co-

    generation) systems. Project activity is

    displacing partial grid power (which is

    dominated by fossil fuel) by renewable

    source (wind) by using WTG

    technology

    4 In the case of project activities that involve the

    addition of renewable energy generation

    units at an existing renewable power generation

    facility, the added capacity of the units added by

    the project should be lower than 15 MW and

    should be physically distinct from the existing

    units.

    Not applicable, the entire windmills are

    new and this project is not capacity

    enhancement or up gradation project.

    5 Project activities that seek to retrofit or modify

    an existing facility for renewable energy

    generation are included in this category. To

    qualify as a small scale project, the total output

    of the modified or retrofitted unit shall not

    exceed the limit of 15 MW.

    Not applicable. This project is not a

    retrofit or modification of existing

    facility.

  • 8/12/2019 PDD Alembic

    14/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    14

    B.3. Description of the project boundary:

    >>As per the methodology, the project boundary encompasses the physical, geographical site of the

    renewable generation source.

    In this project the project boundary would include the WEGs, main transformer, sub station, western

    region grid and the power receiving plant

    B.4. Description of baseline and its development:

    >>

    The baseline methodology has followed the one specified under Project Category I.D. in Appendix B of

    the Simplified M&P for small scale CDM project activities.

    All existing sources of power generation have been considered from various sources like the WREB web-

    site, CEA web-site and other power related websites. Percentage share of power generation from

    different fuel sources has been calculated. The IPCC emission factors for different sources of power

    generation have been considered.

    The NET BASELINE EMISSION FACTOR as per COMBINED MARGIN (ACM002 Ver06)

    Calculation of Operating Margin

    Based on CEA data3

    3http://www.cea.nic.in/planning/c%20and%20e/Government%20of%20India%20website.htm

    Project

    BoundaryPLANTs (Vadodara & Panelav)

    Wind mills S4, S5, S6, S7

    Ukharla

    WR GRID

  • 8/12/2019 PDD Alembic

    15/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    15

    2003-04 0.990

    2004-05 1.012

    2005-06 0.993

    Average 0.998

    Build margin

    2005-06 0.630

    Emission factor = (0.75 x OM + 0.25 x BM)

    = (0.75 x 0.998 + 0.25 x 0.63)

    = 0.906 kg CO2/kWh

    The baseline calculations are CEA data base CENTRAL ELECTRICITY AUTHORITY: CO2

    BASELINE DATABASE.

    B.5. Description of how the anthropogenic emissions of GHG by sources are reduced below

    those that would have occurred in the absence of the registered small-scaleCDM project activity:

    The project reduces anthropogenic emissions of greenhouse gases by sources below those that would

    have occurred in absence of the proposed CDM project activity.

    As per the decision 17/cp.7 Para 43, a CDM project activity is additional if anthropogenic emissions of

    greenhouse gases by sources are reduced below those that would have occurred in the absence of the

    proposed CDM project activity.

    Barriers and Additionality

    Referring to attachment A to appendix B document of indicative simplified baseline and monitoring

    methodologies for selected small scale CDM project activity categories, project participants are required

    to provide a qualitative explanation to show that the project activity would not have occurred anyway, at

    least one of the listed elements. should be identified in concrete terms to show that the activity is either

    beyond the regulatory and policy requirement or improves compliance to the requirement by removing

    barrier(s); The guidance provided herein has been used to establish project additionality. The barriers

    that were considered are listed below:

    a) Investment barrier

    b) Technological barrier

    c) Barrier due to prevailing practice

    d) Other barriers

  • 8/12/2019 PDD Alembic

    16/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    16

    The following section addresses some barriers faced by Alembic to implement the new retrofit

    technology in their plant.

    Investment Barrier

    The power situation in India is particularly grim due to reliance on financially weak State Electricity

    Boards. The situation is particularly acute in Gujarat state. According to a study done by a premier

    institute4, captive power generation in 2002 amounted to 20% of total electricity produced in Gujarat, a

    response to the poor quality supply from GEB. In the year 2003, Alembic decided to go ahead with

    implementation of wind turbine generators to meet power demand in its manufacturing units. The source

    of finance for the project was 70% from loan and 30% from internal accruals5. The decision on the

    project was based on CDM revenues and the same is reflected from management note6.

    To have self reliance on electricity, Alembic went ahead with analyzing different alternative captive

    power options. It could have either continued to use current generation mix of electricity or set up a

    captive unit based on coal or diesel7. There was also an option going for WTGs considering CDM

    benefits to achieve project approval.

    The project proponent identified the following options as the source of power to meet its electrical

    energy requirement

    Alt 1: Continuation of current practice

    Alt-2: Thermal power plant based on lignite / coal as fuel.

    Alt-3: Captive power plant based on Natural Gas

    Alt-4: Energy generation using renewable source of wind power.

    Continuous of current practice: This option was the cheapest option for the project proponent. In this

    option there was no capital investment was requirement. Other than no capital investment there was no

    barriers associated with this option because of the project proponent was already using these options.

    Therefore this option was one of the baseline scenario for proposed project activity.

    4Captive Power Plants: Case Study of Gujarat, India

    5Estimated sources of finance V.H.Gandhi and CO. (Charted Accountants), dated 20/04/2006.

    6Capital Expenditure Authorization dated 02/04/2003.

    Copy of resolution passed by the Board of directors of the company in its meeting held at Vadodara dated

    24/07/2003.

    7Alembic was having three type of power sources during the decision making process:

    1. Grid electricity

    2. Natural gas based cogeneration turbines

    3. Diesel generating (DG) set (It was used in emergency conditions)

  • 8/12/2019 PDD Alembic

    17/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    17

    Coal based power generation may be a preferred option for the project proponent for the reasons

    It is the most economical option for generating electrical power. Technology is available in the country,

    which are the latest and the most efficient one from these systems. The load factor is a certainty with

    these power plants and is the highest. Coal based captive power generation is preferred option in state of

    Gujarat. Captive power plants based on natural gas was another option for the alembic as they were

    already using the natural gas based turbine generators. This was not feasible due to unavailability of

    Natural Gas. The letters for declining gas is submitted to DOE.

    Alternatively Alembic could also invest into wind energy and wheel the power to its manufacturing unit.

    Although this wasnt the best possible option to meet power requirements, however after considering

    CDM benefits, a decision to invest in wind energy was taken. Wind energy is clean energy as there is no

    GHG emission from it and this makes it an option for the project proponent. The board approval is

    submitted for same.

    Out of various options available to the project promoter wind is not the most attractive option to generate

    power. Though wind energy is a clean energy, it is a costlier option, especially in India where availability

    of coal is abundance. Due to high capital cost & low PLF per unit power generation cost is higher

    compared to other fuel options such as coal or diesel/FO. A comparative study of costs of electricity

    generation from different alternatives of power production is given below.

    S No. Source Power Generation cost/ kWh

    Alt-1 Coal Rs 2.27/ kWh

    Alt-2 Fuel Oil Rs 3.57/ kWh

    Alt-3 Wind Energy Rs 4.24/ kWh

    Reference Nagda hills Registered wind PDD (Annex 4)

    Also according to the World Energy Council report8Indias Energy Scenario In 2020 wind remains a

    costly option to generate power than other conventional fossil fuel based sources. Wind power projects

    provide lower IRR as these projects entail high project cost and low PLF. To promote these technologies state

    government provides incentives like accelerated depreciation, wheeling of power to user etc, however even

    with these incentives the return from wind energy projects is lower than that from the other generation options.

    The above unit generation cost is can be cross verified with one other study available for the Gujarat.

    According to one study9in Gujarat for the same period the following results are obtained:

    8INDIA'S ENERGY SCENARIO IN 2020 by SARMA, E.A.S., Secretary, Ministry of Power, Government of India;

    MAGGO, J.N., Joint Adviser, Planning Commission, Government of India

    SACHDEVA, A.S., Deputy Adviser, Planning Commission, Government of India

    9Captive Power Plants: Case Study of Gujarat, India, P.R. Shukla, Debashish Biswas, Tirthankar Nag,

    Amee Yajnik, Thomas Heller and David G. Victor, Working paper.

  • 8/12/2019 PDD Alembic

    18/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    18

    Fuel Type Installation cost (million rupees

    per MW)

    Generation cost (rupees per

    unit)

    Lignite 50 - 52.5 1.59 1.90

    Coal 42.5 45 1.78 1.92

    Natural Gas 42.5 - 50 2.3 - 3.3

    Wind 40 > 510

    According to the analysis the lignite and coal based power plats were the best options for the Alembic.

    The project proponent would have opted for the coal and lignite based power plant in absence of the

    project activity. Looking forward the environmental benefit and CDM revenue project proponent decided

    to go for the wind energy. Although the IRR for wind power project was well below the weighted

    average cost of capital of alembic power. The same is discussed below in details:

    Before accepting any project, the finance department at Alembic conducts a thorough evaluation of the

    project. The Internal Rate of Return (IRR) for the project is calculated and then compared with the

    annualized Return on Capital. Specifically for the wind mill project previous three years annualized

    Return on Capital was considered. The project activity commenced on 01 June 2003, hence the Return on

    Capital for this project would be considered for the years 2000 01; 2001 02 and 2002 03.

    Following is the detailed calculation for the return on capital for the above mentioned years:

    2000 2001 2001 2002 2002 2003

    Equity + Free reserves 10.57 % 5.49 % 8.69 %

    Borrowings 8.77 % 7.55 % 6.68 %

    Total 19.34 % 13.04 % 15.37 %

    Average Return on Capital 15.92 %

    10Comparison of options for distributed generation in India

  • 8/12/2019 PDD Alembic

    19/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    19

    Table 8: Barrier analysis

    Alternative scenario Investmentbarriers

    Technologicalbarriers

    Barriers due toprevailing

    practices

    Other barriers

    Alt 1: Continuation of

    current practice

    No initial capital

    investment

    required. In the

    absence of the

    project activity

    this is a most

    likely scenario.

    No technological

    barriers. The

    plant will operate

    with this scenario

    in absence of the

    project activity.

    This is the

    prevailing

    practice. No

    barriers.

    No

    Alt-2: Thermal power

    plant based on lignite /

    coal as fuel.

    Initial capital

    investment.

    May be

    technological

    barriers, project

    proponent is not

    having

    experience for

    operation of

    coal/lignite based

    power plant.

    There will not be

    any barrier due to

    prevailing

    practice because

    this is prevailing

    practice in

    Gujarat.

    No

    Alt-3: Captive power

    plant based on Natural

    Gas

    Capital

    investment

    No Not possible due

    to unavailability

    of natural gas.

    No

    Alt-4: Energy

    generation using

    renewable source of

    wind power.

    Huge capital

    investment

    May be

    technological

    barriers, project

    proponent is not

    having

    experience for

    operation of wind

    power plant.

    The project

    activity was first

    in the region.

    No

    It is clear that the alternative 1 is the baseline scenario for the project activity as this is facing no barrier.

    IRR calculation:

    Rangan Banerjee,1

  • 8/12/2019 PDD Alembic

    20/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    20

    IRR of the project is calculated as per the standard industrial practice. The project IRR is calculated

    based on cash inflow and outflow without the consideration of source of financing (as per tool for

    demsonstration and assessment of additionality page 5, footer 6 and Please refer enclosure 1 IRR an CER

    calculations submitted along with this document).

    For the calculation of Project IRR following assumptions considered:

    Basic Data/ Assumptions Unit Value Source

    Investment cost Rs Mill/MW 42.40 Suzlon proposal

    Capacity MW 5 Suzlon proposal

    No of WEG No 4 Based on management decision

    Average PLF % 26.48 Calculated based on the

    guaranteed generation given by

    technology supplier;

    conservatively higher based on

    the published literature

    Grid unavailability % 4 Suzlon proposal

    Wheeling Charges % 4 Suzlon proposal, wheeling

    agreement

    Transmission Losses

    (between substation and

    WEG)

    % 4 Suzlon proposal

    O&M for first 4 years % 2 Purchase order given to suzlon

    O&M from 4th year % 2 Purchase order given to suzlon

    Annual escalation in O&M

    after 4 years

    % 5 Purchase order given to suzlon

    De-rating of equipment

    post 5th years

    % 5.0 Referred from purchase order

    Working Capital (Days Days 100 Based on industry standard

  • 8/12/2019 PDD Alembic

    21/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    21

    sale) Days 100

    Interest rate % 12 Based on industrial rates

    applicable for the project

    Minimum alternative tax

    (MAT)

    % 8 Based on last three years data of

    actual tax paid

    The IRR of the project is 14.80 % considering the cash inflow as savings due to electricity generated by

    wind mills and cash outflow as operational & maintenance cost, insurance cost and interest to be paid on

    loan.

    When the project was conceived, CDM funds were considered as cash inflow with criteria of cost of

    CERs to be 9 Euros per ton equivalent of CO2emission reduction.

    After considering the CDM funds the IRR of the project improved to 16.39 % (more than the average

    value of return on capital calculated earlier as 15.92 %).

    The IRR calculation for the project was based on certain assumptions for considering power cost and on

    the actual market conditions. Together these were factored in by finance experts of Alembic Ltd.

    The power cost used for IRR calculation was considered as INR 3.67 for the entire life time of theproject. This was done as per the weighted average cost of the power used by the plant in the year 2000-

    01, 2001-02, 2002-03. The detailed calculation is submitted here:

    Weighted Average

    Cost

    2002-03 2001-02 2000-01 Reference

    Gross generation kWh 77852400 98786250 65358720 Balance sheet

    Net unit generated kWh 71233432 90281366 60602136

    Auxiliary kWh 6618968 8504884 4756584 Yearly

    statement of

    power

    generation

    Total cost for cogen

    power generation

    INR 312575352 343925225 243461512 As per SAP

    standard report

  • 8/12/2019 PDD Alembic

    22/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    22

    Quantity of steam

    generated

    ton/year 191206 229368 202991 Yearly

    statement of

    power

    generation

    Steam cost INR/ton 445.0 612 516.0

    Steam credit INR 85094888 140368625 104744519

    Net cost for power

    genration

    INR 227480463.

    6

    203556599 138716993

    Unit cost of power

    generation

    INR/unit 3.19 2.25 2.29

    Generation Unit 113012 131784 32290 Balance sheet

    Cost per unit INR/unit 8.85 6.02 5.41 Balance sheet

    Total cost of power

    generation

    1000156.2 793340 174689

    GEB purchase kWh 27796640 16340053 30575298 Balance sheet

    Total amount INR 166960664 135357856 193136177 Balance sheet

    Cost per unit of GEB

    power

    INR/kWh 6.0 8.3 6.3

    Gross unit

    generated/puchased

    kWh 99143084 106753203 91209724

    Line loss kWh 1982862 2135064 1824194

    Net unit generated kWh 97160222 104618139 89385530

    Total cost for power

    generation

    INR 395441284 339707795 332027859

    Weighted average

    cost of power

    generation/purchase

    INR/kWh 4.1 3.20 3.70 3.67 (Average

    cost)

    The detailed IRR working is submitted as separate excel sheet working and same is attached in PDD.

    Sensitivity Analysis

  • 8/12/2019 PDD Alembic

    23/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    23

    The project proponent has done sensitivity analysis for the robustness of financial calculation. Plant load

    factor of the wind mill is the most important factor in sensitivity analysis. The plant load factor is varied

    from 1 to 5% up and down and the following table is prepared for project IRR.

    Plant load factor (+) up) / (-) down by Project IRR

    +5% 15.70%

    +4% 15.52%

    +3% 15.34%

    +2% 15.16%

    +1% 14.98%

    0 14.80%

    -1% 14.61%

    -2% 14.43%

    -3% 14.25%

    -4% 14.07%

    -5% 13.89%

    It is clear from above table than the project activity is not crossing the benchmark even after

    increasing the PLF by 5%.

    Barriers due to prevailing practice

    B: Regulatory Risks:

    The state of Gujarat has witnessed a growth in wind turbine installations till the year 1998. The Wind

    Power sector witnessed nil installation over next four years up to December 2002. The WTGs installed

    by alembic were among the first few installed after a slump in investments in the Wind power sector in

    Gujarat.

    Wind Installations in Gujarat over the years11

    :

    Years Till

    1992

    92-

    93

    93-

    94

    94-

    95

    95-

    96

    96-

    97

    97-

    98

    98-

    99

    99-

    00

    00-

    01

    01-02 02-03

    Installation

    s (MW)

    14.5 1.6 10.6 37.7 51.2 31.1 20.1 0 0 0 0 0

    11Wind power India-year wise installations statistics http://www.windpowerindia.com/statyear.asp

  • 8/12/2019 PDD Alembic

    24/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    24

    As clearly seen the Wind energy installations came to stand still after year 1998 till 2002-03. The slump

    in investments was attributed to poor state policy12

    as shown below-

    Year Policy Remarks

    Jan1993 - Sep2001 1. Tariff rate of Rs.1.75/KWH

    2. Banking for 6 months as

    compared to other states with

    banking option of 12 months.

    3. No third party sales optionavailable.

    Policy attracted investments till

    1998, but there after failed to

    attract investors due to stagnant

    policy.

    Oct2001 - Jun2002 1. Tariff rate of Rs.2.25/KWH

    2. Wheeling charges doubled

    from2%to 4%.

    The policy failed to attract

    investments and was changed

    within 9 months of

    implementation.

    Jun2002-till date 1. Tariff of Rs.2.60/KWH

    2. Banking period again reduced

    to 6 months.

    A marginal growth in 2002-03

    and in 2003-04 was observed

    after this policy.

    This table shows the irregular and non-conducive nature of government policy. The banking period is

    only six months in comparison to twelve months in states of Maharashtra, Tamilnadu and Karnataka. The

    tariff in state is among lowest in country13

    . Any change in the near future will have effect on the returns

    expected by project proponent and thereby added to the apprehensions. Similar policy planning affects

    have been observed in other states.

    Other barriers

    Among all energy sources available wind energy is never considered as base-load option. It is mainly due

    to the fact that wind power is infirm and is dependent on a number of factors which are beyond the

    control of power producer such as availability of wind, wind velocity and wind direction. The Wind

    12Wind Power Policy 2002; Government of Gujarat; Energy and Petrochemicals Department Government

    Resolution No.EDA-102001-3054-B Sachivalaya, Gandhinagar. Dated the 28 June, 2002.

    13Incentives Declared by the State Governments for Private Sector Wind Power Projects http://www.infraline.com/

  • 8/12/2019 PDD Alembic

    25/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    25

    turbines were installed in Gujarat after a gap of four years; this was the first time megawatt class wind

    mill was installed in state14

    . Since this was first time megawatt class WTG was installed in state the

    project proponent had apprehended technical issues relating to new technology. The main technological

    barrier apprehended were non-compliance of local components and foreign parts which in a way weakens

    the reliability of entire system. Since most of wind farms are located in far flung areas, failures due to

    lightning and control system damages are often marred by lengthy repair time and off-line periods.

    Apart from above the only available authentic source of wind data for the Sanodar site is the Wind

    Energy Resources Survey in India, Vol. V based on the data collected in the period from September 1996

    to August 1997.

    Based on the same outdated data, Alembic Ltd. was the first company to take a risk and install the wind

    mills on project site. In spite of the IRR not being viable without CDM funds, Alembic Ltd. took the risk

    of installing the wind mill only because of Alembics commitment towards a clean and green

    environment.

    Till Alemic Ltd. installed their wind mill on the site, no other organization had taken the risk to install a

    wind mill on the site. The fact that Alembic Ltd. was the first to install the wind mills on the site can be

    verified by the certificate issued by M/S Suzlon Energy Ltd. stating the same (certificate attached in

    annexure V of this PDD).

    The wind mill installation by Alembic Ltd. created a demonstration effect for other organizations who

    have now started installing their wind mills on the site.

    The project faced many barriers during its construction phase like transportation of the raw material and

    equipment, installation of the equipment and the auxiliary machinery required for installation of the wind

    mills over the mountainous terrain at site location.

    B.6. Emission reductions:

    B.6.1. Explanation of methodological choices:

    >>

    The procedure followed for estimating the emissions reductions from this project activity during the

    crediting period are as per the following steps which corresponds with AMS-I.D.

    The project category is Grid connected renewable electricity generation system hence as per Appendix

    B- indicative simplified baseline and monitoring methodologies for selected small-scale CDM project

    activity categories, Version- 10 of the simplified modalities and procedures for small scale CDM project

    activities (FCCC/KP/2005/8/ADD.1), the proposed CDM project falls under category I.D Grid

    connected renewable electricity generation. The applicability of the project activity as small scale as per

    approved methodologyAMS I.D (Version 11) has been demonstrated in section B.2

    14Wind power India-year wise installations statistics http://www.windpowerindia.com/statyear.asp

  • 8/12/2019 PDD Alembic

    26/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    26

    Baseline Estimation:

    Baseline methodology for project category I.D has been detailed in paragraphs 7-11 of the approved

    small scale methodologyAMS I.D. (Version 11, date: EB31) Paragraph 9 of the approved methodology

    applies to this project activity, which states that:

    For all other systems, the baseline is the kWh produced by the renewable generating unit multiplied by

    an emission coefficient (measured in kg CO2equ/kWh) calculated in a transparent and conservative

    manner as:

    a) A combined margin (CM), consisting of the combination of operating margin (OM) and build

    margin (BM) according to the procedures prescribed in the approved methodology ACM0002.

    Any of the four procedures to calculate the operating margin can be chosen, but the restrictions

    to use Simple OM and the Average OM calculations must be considered.

    OR

    b) The weighted average emissions (in kg CO2equ/kWh) of the current generation mix.

    Project proponent has opted for option (a) to calculate grid emission coefficient i.e Combined

    Margin (CM) consisting of the combination of operating margin (OM) and build margin (BM).

    CM has been estimated based on guidance in Baseline section detailed between page no. 4 to

    page no. 10 of approved methodology ACM0002, Version 06.

    Baseline emissions are calculated as the kWh produced by the renewable generating unit multiplied by an

    emission co-efficient for the Western region Grid, calculated in a transparent and conservative manner.

    ACM0002 provides two options for calculation of grid emission co-efficient for such project activities:

    The baseline emission (BEy in tCO2) is the product of the baseline emission factor (EFyin tCO2/MWh)

    times the electricity supplied by the project activity to the grid (EGy in MWh) minus the baseline

    electricity supplied to the grid in the case of modified or retrofit facilities (EG baseline in MWh), as

    follows:

    BEy = (EGy EGbaseline) x EF,y

    Since the following project does not involve any modification or retrofit of the existing generation

    facility hence EGbaseline= 0

  • 8/12/2019 PDD Alembic

    27/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    27

    EFgrid,yis determined as follows:

    EFy = 0.75 x EF,OM + 0.25 x EF,BM,

    Where

    EF, OM, = Operating Margin Emission Factor

    EF, BM = Build Margin Emission Factor

    1. Calculation of operating margin emission factor for the region based on simple OM

    For calculation of operating margin four options are available:

    (a) Simple operating margin;

    (b) Simple adjusted operating margin;

    (c) Dispatch data analysis operating margin;

    (d) Average operating margin.

    According to ACM0002 / version 06 dispatch data analysis should be the first choice but for the current

    project, dispatch data analysis cannot be used because of unavailability of data.

    The simple OM method was used as the low-cost/must run resources constitute less than 50% of the total

    grid generation of Western and Southern Grid in average of the five most recent years.

    The simple OM emission factor (EFOM,simple, y) is calculated as the generation-weighted average emissions

    per electricity unit (tCO2/MWh or MU) of all generating sources serving the system, not including low-

    operating cost and must-run power plants.

    F i, j , y * COEF i,j y

    EF, OM =GENj, y

    Where:

    Fi, j, y -is the amount of fuel i (in a mass or volume unit) consumed by relevant power sources j in

    year(s) y, j refers to the power sources delivering electricity to the grid, not including low-

    operating cost and must run power plants, and including imports to the grid,

  • 8/12/2019 PDD Alembic

    28/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    28

    COEFi,j y -is the CO2emission coefficient of fuel i (tCO2/ mass or volume unit of the fuel), taking into

    account the carbon content of the fuels used by relevant power sources j and the percent

    oxidation of the fuel in year(s) y, and

    GENj,y -is the electricity (MWh or MU) delivered to the grid by source j.

    The CO2emission coefficient COEFiis obtained as

    COEFi= NCVi* EFCO2,i* OXIDi

    Where:

    NCVi - is the net calorific value (energy content) per mass or volume unit of a fuel i,

    OXIDi - is the oxidation factor of the fuel.

    EFCO2 , i -is the CO2emission factor per unit of energy of the fuel i.

    2. Calculation of build margin Factor for the region (ex ante):

    Build margin can be calculated as the generation weighted average emission factor (tCO 2/MWh or MU)

    of a sample of power plant m, as follows:

    EF, BM = Fi,m, y* COEFi, m

    GENm, y

    Where,

    Fi,m,,y, COEFi,m are analogous to the variables described for the simple OM method for plants m.

    Baseline emission factor (EF y)

    The baseline emission factor EFy is calculated as the weighted average of the operating margin emission

    factor (EFOM, simple) and the build margin emission factor (EF, BM,), where the weights wOMand wBM, by

    default, are 75% wOM and 25% wBM and EF,OM,and EF,BM,are calculated as described in Steps 1 and 2

    of consolidated methodology ACM0002 and are expressed in tCO2/MWh or MU.

    EF GRID,Y = 0.75 x EF,OM, + 0.25 x EF, BM

  • 8/12/2019 PDD Alembic

    29/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    29

    Values for all regional grids for FY 2000-2001 until FY 2005-2006, including inter-regional and

    cross-border electricity transfers. (CEA, User Guide: Version 2.0)

    BE = EGy * EFgrid

    Where:

    Egy - is the net quantity of electricity generated by the project in year y, and

    EFgrid is the carbon emission factor of the Grid

  • 8/12/2019 PDD Alembic

    30/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    30

    For the calculations for emission factor the unit for OM and BM are used in terms of tCO2/GWh and

    same is specified under each calculation.

    Emission Estimation:

    Emission factor= Net Generation * CEF for fuel * Net Heat Rate * Conversion Factor

    (tonnes of CO2) (GWh) (tonnes CO2/TJ) (TJ/GWh) (44/12)

    Baseline Emission Co-efficient calculation:

    Baseline Emission Co-efficient = Total Baseline Emissions / Total Net Generation

    (tonnes of CO2/GWh) (tonnes of CO2) (GWh)

    The grid emission factor for Indian power sector for the year 2006 has been calculated by CEA.

    Emission reduction due to project activity

    Emission Reduction = Baseline Emission Project Emission Leakage

    As wind power projects fall under clean energy sources for electricity generation, the emission from the

    project is taken as zero.

    Leakage estimation is also not required.

    Therefore:

    Grid Emission Factor

    Western Regional Grid 906 tCO2/GWh

    Baseline emissions or CERs generated by the project are estimated to be:

    Baseline Emissions(project) = Grid Emission Factor * Power Generated from the Project

    (tons of CO2) (tons of CO2/GWh) (GWh/year)

    Steps Description Equation Used Methodological Choices

  • 8/12/2019 PDD Alembic

    31/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    31

    1. Procedure followed for

    calculating baselineemissions (BE) in line

    with ACM0002- version

    6.

    The baseline emission is calculated as

    per equation BEy= EGy* EFy

    The EFy has been calculated

    using operating and builtmargin emission factor (ex-

    ante) taken from CEA

    published data.

    2. Procedure followed for

    estimating project

    emissions (PE)

    No Project emissions

    3. Procedure followed for

    calculating emission

    reductions (ER)

    The emission reductions are calculated

    as per equation ERy= (BE PE)

    -

    B.6.2. Data and parameters that are available at validation:

    (Copy this table for each data and parameter)

    Data / Parameter: EF,OM

    Data unit: tCO2/MWh

    Description: Operating Margin Grid Emission factor

    Source of data used: CEA reviews

    Value applied: 0.998

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures

    actually applied :

    The value applied is taken from the CEA reviews of three years. The detailed

    calculation is shown in the baseline section above.

    Any comment: Data will be kept for crediting period + 2 years.

    Data / Parameter: EF,BM

    Data unit: tCO2/MWhDescription: Built Margin Grid Emission factor

    Source of data used: CEA report

    Value applied: 0.63

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures

    actually applied :

    The value applied is taken from the plant from CEA reviews.

    Any comment: Data will be kept for crediting period + 2 years.

  • 8/12/2019 PDD Alembic

    32/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    32

    Data / Parameter: EF,yData unit: tCO2/MWh

    Description: Combined Margin Grid Emission factor

    Source of data used: CEA reviews

    Value applied: 0.906

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures

    actually applied :

    The value applied is taken from the plant from CEA reviews. The weights used

    for calculating combined margin emission factor are 0.75 and 0.25 for

    operating margin and built margin respectively

    Any comment: Data will be kept for crediting period + 2 years.

    B.6.3 Ex-ante calculation of emission reductions:

    >>

    Combined Margin Emission Factor:

    EFy= 0.75 * EFOM+ 0.25 * EFBM

    Applying the values given in section B.6.2 the value of EFy comes out to be 0.906 tCO 2/MWh.

    Baseline Emission Calculations:

    The baseline emission is calculated as: BEy= EGy* EFy

    where,

    BEy= Baseline Emissions due to displacement of electricity during the year y (in tons of CO2)

    EGy= Net units of electricity substituted in the grid during the year y (in MWh)

    EFy= Emission Factor of the grid (in tCO2/ MWh) and y is any year within the crediting period of the

    project activity

    Applying the values given in section B.6.2 and B.7.1 the value of BE comes out to be 9247 tCO 2.

    Emission Reduction Calculations:

    ER = BE - PE

    Applying the values given in section B.6.2 and B.7.1 the value of ER comes out to be 9247 tCO 2.

  • 8/12/2019 PDD Alembic

    33/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    33

    While calculating emission reduction below assumptions was considered:

    1. Plant load factor = 26.48% (Suzlon proposal letter)

    2. Availability of WTG = 100% for first four years then 95% for remaining crediting period (Suzlon

    purchase order)

    B.6.4 Summary of the ex-ante estimation of emission reductions:

    >>

    Year Estimated Project

    Activity

    Emissions (tonnes

    of CO2e)

    Estimated Baseline

    Emissions (tonnes

    of CO2e)

    Estimated

    leakage(tonne

    s of CO2e)

    Estimated

    Emission

    Reduction

    (tonnes of

    CO2e)

    2008 0 9247 0 9247

    2009 0 9247 0 9247

    2010 0 9247 0 9247

    2011 0 9247 0 9247

    2012 0 8785 0 8785

    2013 0 8785 0 8785

    2014 0 8785 0 8785

    2015 0 8785 0 8785

    2016 0 8785 0 8785

    2017 0 8785 0 8785

    Total estimated reductions

    (tonnes of CO2 e)

    0 89698 0 89698

    B.7 Application of a monitoring methodology and description of the monitoring plan:

    As per the provisions of paragraph 14 of Draft simplified modalities and procedures for small scale CDM

    project activities [FCCC/CP/2002/7/Add.3, English, Page 21] the Project participants may use the

    simplified baseline and monitoring methodologies specified in appendix B for their project category ifthey meet the applicability criteria of small scale CDM project activity.

    Since the project activity is a small-scale CDM project of Type I.D. category, the monitoring

    methodology and plan has been developed in line with the guidance provided in paragraph 9 of category

    I.D. of Appendix B.

    As per the methodology, monitoring shall consist of metering of electricity generation.

  • 8/12/2019 PDD Alembic

    34/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    34

    Monitoring plan:

    The sole objective of having a monitoring system is to have a constant watch on the emission reductions.

    The delivered energy will be metered by Alembic Ltd., Vadodara; Gujarat Energy Development Agency,

    Porbandar; GETCO (66 KV S/S), Bhav Nagar; and PGVCL, Mamsa at the high voltage side of the step

    up transformer installed at the receiving station. Metering equipment shall be electronic trivector meters.

    The metering equipment shall be maintained in accordance with electricity standards and have the

    capability of recording half-hourly and monthly readings, which in turn are produced to Alembic Ltd.,

    Vadodara. The meters installed should be capable of recording and storing the parameters for a minimum

    period of 35 days with digital output. The monthly meter readings at the project sites and the receiving

    station shall be taken simultaneously and jointly by the parties.

    At the conclusion of each meter reading, an appointed representative of GETCO (66 KV S/S), Bhav

    Nagar, PGVCL Mamsa and Gujarat Energy Development Agency, Porbandar will sign a document

    indicating the number of kilowatt-hours indicated by the meter.

    Each meter shall be jointly inspected and sealed on behalf of GETCO (66 KV S/S), Bhav Nagar, PGVCL

    Mamsa and Gujarat Energy Development Agency, Porbandar, in the presence of its authorised

    representatives.

    All the Main and Check meters shall be tested for accuracy every calendar quarter with reference to a

    portable standard meter. As the instruments are calibrated and marked at regular intervals, the accuracy

    of measurement can be assured at all times. To ensure accurate and continuous monitoring, Alembic Ltd.

    has a standby meter, calibrated by an authorised agency.

    The allocation of electricity is executed as per the following procedure:

    1. Enter the value of electricity received from W/M at 33 KV (kWh).

    2. Enter the value of electricity supplied to W/M at 33 KV (kWh).

    3. Take the difference of electricity received and supplied to W/F at 33 KV (kWh).4. Take the total of difference calculated as per step 3.

    5. Divide individual difference by total calculated as per step 4 and multiply by 100 to find %.

    6. Enter the value of electricity received from W/M at 66 KV (kWh).

    7. Enter the value of electricity supplied to W/M at 66 KV (kWh).

    8. Take the difference of electricity received and supply to W/F at 66 KV (kWh).

    9. Multiply the value calculated as per step 8 by % allocation calculated as per step 5.

    B.7.1 Data and parameters monitored:

  • 8/12/2019 PDD Alembic

    35/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    35

    (Copy this table for each data and parameter)

    Data / Parameter: EGy,

    Data unit: MWh

    Description: Net units of electricity substituted in the grid

    during the year y

    Source of data to be used: Joint meter reading.

    Value of data 10206.45

    Description of

    measurement methods

    and procedures to be

    applied:

    Monitoring: Trivector meter will be used for

    monitoring

    Data Type: measured

    Frequency: hourly measuredRecording: Monthly from joint meter

    Archiving Policy: Paper & Electronic

    Responsibility: Manager (Wind Project) would be

    responsible for regular calibration of the meter.

    Calibration Frequency: Once a year.

    QA/QC procedures to be applied: Yes, Quality Management System will be used and

    the same procedures would be available at the

    project site. The net electricity exported to the grid

    can be cross verified with the sales receipts

    received by electricity board.Any comment: Data archived: Data will be archived for two years

    after the end of crediting period or of the last

    issuance of CERs for this project activity,

    whichever occurs later

    B.7.2 Description of the monitoring plan:

    >>

    Roles and responsibilities:

    General Manager:In the project management structure General Manager is responsible for the project

    management. He is responsible to plan and allocate the annual budget for operation, estimation of the

    likely operating cost, electricity dispatch, organizing third party contractors, revenue collection etc.

    General Manager will check the monthly electricity generated and annual emission reduction

    calculations. He is responsible for any leakage of emissions in the project boundary.

    Operation and maintenance of wind generators will be done by Suzlon energy Limited and they will be

    responsible to General Manager.

    General Manager

    DGM

    Asst. Manager

  • 8/12/2019 PDD Alembic

    36/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    36

    Deputy General Manager: DGM is assisting to General Manager for completing the task discussed

    above. He is responsible for the electricity generations at the individual wind turbine installations. He

    will crosscheck the log book regularly and report to General Manager for any abnormality.

    Sr. Executive/Ass Manager:Sr. Executive/asst. manger is responsible for recording the electricity meter

    reading.

    Record Handling:OEM contractors are collecting daily report obtained from hourly monitoring with all

    the related parameters. All the records are given to General Manager every month. The GM has final

    responsibility for record keeping.

    Internal Audits and performance review

    These records are regularly audited and checked by the senior officials from Alembic Limited during

    their visits to the site. The senior officials visit once in a year and audit the records. The officials will

    crosscheck the emissions reductions claimed in PDD with respect to actual emissions reduction.

    For any deviation from the actual emission reduction values and reported values corrective action will be

    suggested by senior official to calculate the conservative emission reduction. All corrective actions will

    be recorded in the logbook.

    Monitoring and Calibration

    As emission reductions from the project are determined by the number of units exported to the grid, it is

    mandatory to have a monitoring system in place and ensure that the project activity produces and exports

    Direction of flow of information

    Internal Audit Team OEM Contractors

  • 8/12/2019 PDD Alembic

    37/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    37

    the rated power at the stipulated norms. The sole objective of having monitoring system is to have a

    constant watch on the emission reductions.

    The delivered energy shall be metered by Suzlon and state electricity board at the high voltage side of the

    step up transformers. Metering is done either for two /three / more wind mills depending on the location

    of wind mills and service connection number. Metering equipment is electronic trivector meters. The

    metering equipment is maintained in accordance with electricity standards and has the capability of

    recording hourly and monthly readings. Records of joint meter reading are maintained at site and a copy

    is maintained at the head office. All the meters shall be tested for accuracy every calendar year with

    reference to a portable standard meter. As the instruments are calibrated and marked at regular intervals,

    the accuracy of measurement can be assured at all times. Necessary records of calibration are maintained

    by state electricity board.

    B.8 Date of completion of the application of the baseline and monitoring methodology and the

    name of the responsible person(s)/entity(ies)

    >>

    Date of completion of baseline: 01/10/2007

    Name of person/entity determining the baseline: The baseline has been prepared by Alembic Ltd

    (Please refer Annex I for detailed contact information for the person involved in baseline determination).

  • 8/12/2019 PDD Alembic

    38/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    38

    SECTION C. Duration of the project activity / crediting period

    C.1 Duration of the project activity:

    C.1.1. Starting date of the project activity:

    >>

    The project activity started on 08thJuly 2003 (Date of purchase order released).

    C.1.2. Expected operational lifetime of the project activity:

    >> Lifetime of the project: 20 y 0 m

    C.2 Choice of the crediting period and related information:

    C.2.1. Renewable crediting period

    C.2.1.1. Starting date of the first crediting period:

    >> Not applicable

    C.2.1.2. Length of the first crediting period:

    >> Not applicable

    C.2.2. Fixed crediting period:

    C.2.2.1. Starting date:

    >> Starting date of crediting period is 01/01/2008 or date of registration of PDD whichever will be later.

    C.2.2.2. Length:

    >> 10 years 0 months

  • 8/12/2019 PDD Alembic

    39/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    39

    SECTION D. Environmental impacts

    >>

    D.1. If required by the host Party, documentation on the analysis of the environmental impacts

    of the project activity:

    >>

    This project activity does not fall under the purview of Environmental Impact Assessment notification of

    the Ministry of Environment and Forests -Government of India, but due consideration has been given to

    environmental aspects. Alembic Ltd., Vadodara already has an Environment Management system in

    place. All environmental related issues were identified and necessary steps to mitigate them have been

    put in place by the implementation of the Environmental Management system.

    D.2. If environmental impacts are considered significant by the project participants or the host

    Party, please provide conclusions and all references to support documentation of an environmental

    impact assessment undertaken in accordance with the procedures as required by the host Party:

    >>

    The project activity is wind based power generation and therefore no significant environmental impacts

    are envisaged from the project activity.

    The impacts are given as follows:

    The minor quantity of solid / liquid discharge, generated during the construction phase has no

    noticeable impact on soil use and the project proponent had made arrangements to dispose them in an

    environmentally acceptable manner.

    Wind Power plants are known to contribute to zero atmospheric pollution as no fuel combustion is

    involved during any stage of the operation.

    The project site is a barren land and unproductive area with no application and habitat. There are no

    migratory birds / endangered species in the region of project activity. Therefore, no harm on the

    ecological environment is envisaged.

    Noise is generated due to the movement of rotor blades. It has no direct effect on the population, as

    the area is less populated and noise generated will be attenuated by ambient conditions.

    The net impact under environmental pollution category would be positive as all necessary abatement

    measures would be adopted and periodically monitored. The project activity does not have any major

    adverse impacts on environment during its construction or operational phase.

    SECTION E. Stakeholders comments

    >>

  • 8/12/2019 PDD Alembic

    40/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    40

    E.1. Brief description how comments by local stakeholders have been invited and compiled:

    >>Alembic Ltd., Vadodara has put up the 5 MW wind power project in Dist. Bhavnagar (Gujarat). Alembic

    Ltd., Vadodara communicated with the relevant stakeholders their plan to implement the 5 MW Wind

    Power Project. Representatives of Alembic Ltd., Vadodara approached all the stakeholders seeking their

    comments and support for the project.

    The identified stakeholders are:

    Local government representatives.

    Designated National Authority, Government of India.

    Ministry of Non Conventional Energy Sources, Government of India. Local villagers

    O&M contractors

    GEDA

    GUVNL

    The identified stakeholders were interviewed by relevant officials from Alembic Ltd. to understand their

    comments and reactions about the wind mill project. These interviews were recorded and converted in to

    a video CD which is available with Alembic Ltd. The stakeholders who were interviewed were asked to

    sign a declaration at the time of interview to establish the credibility of the interview. The stakeholdermeeting was conducted on 03-12-2005 for local villagers, O & M contractors. From other stakeholders

    letters were obtained and the same has been attached with the PDD. A brief summary of the stakeholder

    comments is given in the next section.

    E.2. Summary of the comments received:

    >>

    The local people are direct beneficiaries of the project. The construction and continuous operation of the

    mill constituted local manpower. The project does not require any major displacement of any local

    population. Also, the installation of transmission lines would not create any inconvenience to the local

    population. In summing up, the project activity has received complete support from the local populace.

    The government of India, through Ministry of Non-conventional Energy Sources (MNES), has been

    promoting energy conservation, demand side management and renewable energy projects including wind,

    small hydro and hydro / bio-mass power. This implementation of the wind power project has been highly

    appreciated by them.

  • 8/12/2019 PDD Alembic

    41/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    41

    The Ministry of Environment & Forests is the Designated National Authority in India. The government

    of India, through Ministry of Environment and Forests (MoEF) is encouraging project participants to take

    up such Climate Change initiatives.

    Stakeholders had no objections from installations of WTGs instead they have openly said that wind

    power projects helped to them by

    Additional revenue generated thro land / lease to outsiders like contractors & their employees.

    Job opportunities for day -to - day maintenance and security of WTGs

    Development of roads.

    No any adverse impact on rains, agriculture.

    E.3. Report on how due account was taken of any comments received:

    >>

    In summing up, the project has not received any negative or discouraging feedback from the stakeholders

    concerned.

    All the stakeholders have appreciated and encouraged M/S Alembic Ltd., Vadodara for taking up this

    project activity.

    In view of various direct and indirect benefits (social, economical & environmental), all the stakeholders

    have supported the project activity.

  • 8/12/2019 PDD Alembic

    42/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    42

    Annex 1

    CONTACT INFORMATION ON PARTICIPANTS IN THE PROJECT ACTIVITY

    Organization: Alembic Limited.

    Street/P.O.Box: Alembic Road

    Building: -----

    City: Vadodara

    State/Region: Gujarat

    Postfix/ZIP: 390003

    Country: India

    Telephone: 0091 0265 2280550

    FAX: 0091 0265 2281508

    E-Mail: [email protected]

    URL: http://www.alembic-india.com/

    Represented by:

    Title: Director & President

    Salutation: Mr.

    Last Name: Baheti

    Middle Name: K

    First Name: R

    Department: Finance

    Mobile: +91 98243 99359

    Direct FAX: 0091 265 228 2506

    Direct tel: 0091 265 228 5124

    Personal E-Mail: [email protected]

  • 8/12/2019 PDD Alembic

    43/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    43

    Annex 2

    INFORMATION REGARDING PUBLIC FUNDING

    No funding from any party is available for the project.

  • 8/12/2019 PDD Alembic

    44/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version

    CDM Executive Board

    44

    Annex 3

    BASELINE INFORMATION

    Western Grid Emission Factors

    CENTRAL ELECTRICITY AUTHORITY: CO2 BASELINE

    DATABASE15

    VERSION 2.0

    DATE

    21 June

    2007

    BASELINE METHODOLOGY ACM0002 /

    Ver 06

    EMISSION FACTORS

    Weighted Average Emission Rate (tCO2/MWh) (excl. Imports) Weighted Average Emission Rate

    2000-01 2001-02 2002-03 2003-04

    2004-

    05

    2005-

    06 2000-01

    North 0.72 0.73 0.74 0.71 0.71 0.71 North 0.72

    East 1.09 1.06 1.11 1.10 1.08 1.08 East 1.09

    South 0.73 0.75 0.82 0.84 0.78 0.74 South 0.74

    West 0.90 0.92 0.90 0.90 0.92 0.87 West 0.90

    North-East 0.42 0.41 0.40 0.43 0.32 0.33 North-East 0.42

    India 0.82 0.83 0.85 0.85 0.84 0.82 India 0.82

    Simple Operating Margin (tCO2/MWh) (excl. Imports) Simple Operating Margin (tCO2/M

    2000-01 2001-02 2002-03 2003-04

    2004-

    05

    2005-

    06 2000-01

    North 0.98 0.98 1.00 0.99 0.97 0.99 North 0.98

    East 1.22 1.22 1.20 1.23 1.20 1.16 East 1.22

    South 1.02 1.00 1.01 1.00 1.00 1.01 South 1.03

    15http://www.cea.nic.in/

  • 8/12/2019 PDD Alembic

    45/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version

    CDM Executive Board

    45

    West 0.98 1.01 0.98 0.99 1.01 0.99 West 0.98

    North-East 0.73 0.71 0.74 0.74 0.71 0.70 North-East 0.73

    India 1.02 1.02 1.02 1.03 1.03 1.02 India 1.01

    Build Margin (tCO2/MWh) (excl. Imports) Build Margin (tCO2/MWh) (not a

    2000-01 2001-02 2002-03 2003-04

    2004-

    05

    2005-

    06 2000-01

    North 0.53 0.60 North

    East 0.90 0.97 East

    South 0.71 0.71 South

    West 0.77 0.63 West

    North-East 0.15 0.15 North-East

    India 0.70 0.68 India

    Combined Margin (tCO2/MWh) (excl. Imports) Combined Margin in tCO2/MWh

    2000-01 2001-02 2002-03 2003-04

    2004-

    05

    2005-

    06 2000-01

    North 0.76 0.76 0.77 0.76 0.75 0.80 North 0.76

    East 1.06 1.06 1.05 1.07 1.05 1.06 East 1.06

    South 0.87 0.85 0.86 0.86 0.85 0.86 South 0.87

    West 0.87 0.89 0.88 0.88 0.89 0.81 West 0.87

    North-East 0.44 0.43 0.44 0.44 0.43 0.42 North-East 0.44

    India 0.86 0.86 0.86 0.86 0.86 0.85 India 0.85

    GENERATION DATA EMISSION DATA

    Gross Generation Total (GWh) Absolute Emissions Total (tCO2)

    2000-01 2001-02 2002-03 2003-04

    2004-

    05

    2005-

    06 2000-01

    North 144,292 151,185 155,385 165,735 168,438 179,751 North 97,866,565

    East 58,936 64,048 66,257 75,374 85,776 93,902 East 58,026,488

    South 129,035 131,902 136,916 138,517 144,086 147,355 South 89,019,263

    West 162,329 165,805 177,399 172,682 183,955 188,606 West

    135,192,15

    3

    North-East 5,319 5,332 5,808 5,867 7,883 7,778 North-East 2,202,108

  • 8/12/2019 PDD Alembic

    46/61

  • 8/12/2019 PDD Alembic

    47/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version

    CDM Executive Board

    47

    East 10,670 11,619 11,968 13,686 15,594 17,203 East 489

    South 24,232 24,726 25,558 25,675 26,935 27,666 South 1,162

    West 30,082 30,625 32,890 31,956 34,145 35,201 West 321

    North-East 1,039 1,043 1,134 1,150 1,552 1,531 North-East 0

    India 93,069 96,296 100,498 103,475 109,685 115,241

    Net Generation in Build Margin (GWh) Share of Net Imports (% of Net G

    2000-01 2001-02 2002-03 2003-04

    2004-

    05

    2005-

    06 2000-01

    North 32,064 34,340 North 0.0%

    East 15,818 17,567 East 0.9%

    South 27,987 28,158 South 1.0%

    West 35,257 35,425 West 0.2%

    North-East 2,055 1,793 North-East 0.0%

    India 113,181 117,283

  • 8/12/2019 PDD Alembic

    48/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version

    CDM Executive Board

    48

    Annex 4

    MONITORING INFORMATION

    Sr.

    no.

    Data

    description

    Procedure for

    monitoring the

    parameter

    Traceability of

    calibration method/

    standard

    Tag no OR

    equipment

    serial no of

    instrument

    Service & Tech

    def. Of instru

    and measuring

    Make of

    instrument

    1 Net Electricity

    Exported

    Secure Metre of

    Alembic Ltd. at (33kv)

    ERDA DOC. FOR

    CALLIBRATION AT

    regular interval of 6

    Months

    GJU03992 Service:

    Electrical energy

    measurement

    Tech. Def:

    Energy Meter

    Secure Meter

    Ltd.

    2 Net units of

    electricity

    substituted

    in the grid

    during the

    year y (in

    MWh)(EGy)

    Secure Metre of M/S

    GETCO at (66kv)

    Monthly Genertaion

    Certificate issued by

    GEDA

    GJB 00265 Service:

    Electrical energy

    measurement

    Tech. Def:

    Energy Meter

    Secure Meter

    Ltd.

  • 8/12/2019 PDD Alembic

    49/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    49

    Annex 5

    Supportives

  • 8/12/2019 PDD Alembic

    50/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    50

  • 8/12/2019 PDD Alembic

    51/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    51

  • 8/12/2019 PDD Alembic

    52/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    52

  • 8/12/2019 PDD Alembic

    53/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    53

  • 8/12/2019 PDD Alembic

    54/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    54

    IRR calculation

  • 8/12/2019 PDD Alembic

    55/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    55

    Alembic Ltd IRR calculation without CDM

    Wind Mills Financials

    Basic Data/ Assumptions

    Investment cost RsMill/MW

    42.40 Purchase order, suzlon

    Capacity MW 5 Purchase order, suzlon

    No of WEG 4

    Average PLF % 26.48% As guranteed by Suzlon-26.48%

    Grid unavailability % 4.0% Suzlon proposal

    Wheeling Charges % 4.0% Suzlon proposal and PPA

    Transmission Losses (betweensubstation and WEG)

    % 4.0% Suzlon proposal

    O&M for first 4 years % 2.0% Purchase order, suzlonO&M from 4th year % 2.0% Purchase order, suzlon

    Annual escalation in O&M after4 years

    % 5.0% Purchase order, suzlon

    Derating of equipment post 5thyears

    % 5.0% Purchase order, suzlon

    Working Capital (Days sale) Days 100

    Depreciation rate 5.28% Depreciation

    Tariff for power 3.67 Weightedaverage

    cost ofpower;Given insuzlonproposal

    Esclation 2.50% Per year

    Minimum Alternative Tax rate 8.00% Balancesheet

    ProfitStatement

    Year 0 1 2 3 4 5 6 7 8

    Power tariff 3.67 3.76 3.85 3.95 4.05 4.15 4.25 4.36

    PowerGeneration

    MillUnits

    10.21 10.21 10.21 10.21 9.70 9.70 9.70 9.70

    Free cash flowforecast

    Rs Mill

    Salesrealizations

    Rs Mill 37.42 38.36 39.32 40.30 39.24 40.22 41.23 42.26

    Less:

    O&M, Insurance& others

    Rs Mill 4.20 4.20 4.20 4.20 4.41 4.63 4.86 5.10

    Depreciation(Availed forMAT)

    Rs Mill 10.98 10.98 10.98 10.98 10.98 10.98 10.98 10.98

    EBIT 22.24 23.18 24.14 25.12 23.85 24.61 25.39 26.18

  • 8/12/2019 PDD Alembic

    56/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    56

    Interest 17.81 16.14 11.69 7.23 2.78 0.00 0.00 0.00

    PBT 4.44 7.04 12.45 17.89 21.07 24.61 25.39 26.18

    Tax (MAT) 0.35 0.56 1.00 1.43 1.69 1.97 2.03 2.09PAT 4.08 6.48 11.46 16.46 19.39 22.64 23.36 24.08

    CummulativeP/L

    4.08 10.56 22.01 38.47 57.85 80.50 103.86 127.94

    Cash Flow

    Year 0 1 2 3 4 5 6 7 8

    OperatingCashflow

    Rs Mill32.87 33.60 34.12 34.67 33.15 33.63 34.34 35.06

    Less:

    Increase inWorking Capital

    Rs Mill10.25 0.26 0.26 0.27 (0.29) 0.27 0.28 0.28

    Capital

    Expenditure 212.00 - - - - - - - -

    Free CashFlows toProject

    Rs Mill(212.00)

    22.62 33.34 33.86 34.40 33.44 33.36 34.06 34.78

    IRR of Project 14.80%

    InterestCalculations

    Debt Opening 148.4 148.4 111.3 74.2 37.1 0.0

    Debt Repayment 37.1 37.1 37.1 37.1

    Interest 17.8 16.1 11.7 7.2 2.8

    WorkingCapital

    Working Capital 10.3 10.5 10.8 11.0 10.8 11.0 11.3 11.6

    9 10 11 12 13 14 15 16 17 18 19 20

    4.47 4.58 4.69 4.81 4.93 5.05 5.18 5.31 5.44 5.58 5.72 5.86

    9.70 9.70 9.70 9.70 9.70 9.70 9.70 9.70 9.70 9.70 9.70 9.70

    43.32 44.40 45.51 46.65 47.81 49.01 50.23 51.49 52.78 54.10 55.45 56.84

    5.36 5.63 5.91 6.20 6.51 6.84 7.18 7.54 7.92 8.31 8.73 9.16

    10.98 10.98 10.98 10.98 10.98 10.98 10.98 10.98 10.98 10.98 10.32 0.00

    26.98 27.79 28.62 29.46 30.32 31.19 32.07 32.97 33.88 34.80 36.40 47.67

    0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

    26.98 27.79 28.62 29.46 30.32 31.19 32.07 32.97 33.88 34.80 36.40 47.67

    2.16 2.22 2.29 2.36 2.43 2.50 2.57 2.64 2.71 2.78 2.91 3.81

    24.82 25.57 26.33 27.11 27.89 28.69 29.51 30.33 31.17 32.02 33.49 43.86

    152.76

    178.33

    204.66

    231.77

    259.66 288.35 317.86 348.19 379.36 411.38 444.87

    488.73

  • 8/12/2019 PDD Alembic

    57/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    57

    9 10 11 12 13 14 15 16 17 18 19 20

    35.80 36.55 37.31 38.09 38.88 39.68 40.49 41.31 42.15 43.00 43.81 43.86

    0.29 0.30 0.30 0.31 0.32 0.33 0.34 0.34 0.35 0.36 0.37 0.38

    - - - - - - - - - - - 14.40

    35.51 36.25 37.01 37.78 38.56 39.35 40.15 40.97 41.80 42.64 43.44 29.08

    11.9 12.2 12.5 12.8 13.1 13.4 13.8 14.1 14.5 14.8 15.2 15.6

    Sensitivity Analysis based on PLF

    Variation

    5% 4% 3% 2% 1% 0 -1% -2% -3% -4% -5%

    PLF 27.80% 27.54% 27.27% 27.01% 26.74% 26.48% 26.22% 25.95% 25.69% 25.43% 25.17%

    IRR 15.70% 15.52% 15.34% 15.16% 14.98% 14.80% 14.61% 14.43% 14.25% 14.07% 13.89%

    Project costdetails Rs mn

    Comm. Loan amountProject (MWcapacity)

    Towers

    Date Disbursed

    ProjectCost

    5,00 1.25 x

    4

    22/12/00 148,40 212,00

    Per MW CostMn 42,40

    Project Cost Mn 212,00

    Debt Mn 148,40

    INTERESTRATE 12,00%

    Weighted Average Cost of capital

  • 8/12/2019 PDD Alembic

    58/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    58

    Alembic Ltd.(Rs. in Lacs)

    Year 1999 2000 2001-022002-

    03Period

    (Months) 12 12 15 12

    Return onShareholders Fund:

    Equity ShareCapital 721 721 721 736

    Reserves & Surplus 11,805 14,473 16,509 14,809Less RevaluationReserves (2,175) (2,159) (1,199) (995)

    Total 10,351 13,035 16,031 14,550

    AverageShareholders Fund(Op+Cl)/2 11,693 14,533 15,291

    Profit forShareholders:

    PAT 3,010 2,350 3,152Less: PreferenceDividend+CorpDiv.Tax - - -Profit forShareholders 3,010 2,350 3,152

    Annualised Profitp.a. 3,010 1,880 3,152

    Return onShareholders Fund% p.a.

    25.74% 12.94% 20.61%

    Net of Tax Cost ofBorrowings:

  • 8/12/2019 PDD Alembic

    59/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    59

    Total Borrowings

    Sch C + D 13,556 19,998 19,476 22,493

    Total 13,556 19,998 19,476 22,493

    AverageBorrowings(Op+Cl)/2 16,777 19,737 20,985

    Total Interest Paid 2,603 3,325 2,457Bank Charges &Brokerages Paid 125 177 173

    Total for period 2,728 3,502 2,630

    Annualised InterestPaid p.a. 2,728 2,802 2,630

    Rate of Avg.Interest p.a. %

    16.26% 14.20% 12.53%

    Less:ApplicableTax Rates % 8.475 7.650 7.875

    Net of Tax InterestRate p.a.

    14.88% 13.11% 11.55%

    Assessment Yr. 2000-01 01-02 02-03 03-04Taxable

    Income 30% of Book

    Profit,Tax Rate35 % on

    AboveBook Profit

    +,

  • 8/12/2019 PDD Alembic

    60/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    60

    +Surcharge

    of 10 % &Nil

    EducationTax.

    Note asAbove 7.500 7.500 7.500

    10.00%13.00% 2.00% 5.00%

    0.975 0.150 0.375

    8.475 7.650 7.875

    0.00% 0.00% 0.00% 0.00%

    - - - -

    Total % - 8.475 7.650 7.875

    Net ofTax Weight

    Year 2000 Weight Int. Rate X Int. Rate

    Equity+ Free Reserves (Average ) 11,693 0.41 25.74% 10.57%

    Borrowings (Average ) 16,777 0.59 14.88% 8.77%

    28,470 1.00 19.34%

    Year 2001-02

    Equity+ Free Reserves (Average ) 14,533 0.42 12.94% 5.49%

    Borrowings (Average ) 19,737 0.58 13.11% 7.55%

    34,270 1.00 13.04%

    Year 2002-03

    Equity+ Free Reserves (Average ) 15,291 0.42 20.61% 8.69%

    Borrowings (Average ) 11.55% 6.68%

  • 8/12/2019 PDD Alembic

    61/61

    PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

    CDM Executive Board

    20,985 0.58

    36,275 1.00 15.37%

    WACC 15.92%

    - - - - -