JICA Presentation 1 Used 01Timor Lesteundp
-
Upload
mindo-silva -
Category
Documents
-
view
217 -
download
0
Transcript of JICA Presentation 1 Used 01Timor Lesteundp
-
8/9/2019 JICA Presentation 1 Used 01Timor Lesteundp
1/22
Action Plan
Waste Water Treatment Plan Design
MINISTERIO DAS INFRA-ESTRUTURAS
SECRETARIO DO ESTADO DA ELECTRICIDADE, AGUA E URBANIZACAO
DIRECCAO NACIONAL DOS SERVICOS AGUA E SANEAMENTO (DN-SAS)
-
8/9/2019 JICA Presentation 1 Used 01Timor Lesteundp
2/22
1.1: A: Current Situation
Since 1999 Government established Waste Ponds nearby
the Capital main Town, at the present the condition iscollapsed.
In that cases resulted in to environment degradation and
pollution of the beaches around and fisheries, of cause the
BOD,COD Ph and E-coli high concentration.
According the theme above the Sanitation Division at the
current, good Initiative should be repairing of the Tasitolu
Waste Water Ponds for discharging of the Waste water assoon if possible.
-
8/9/2019 JICA Presentation 1 Used 01Timor Lesteundp
3/22
CURRENT SITUATION of TASITOLU
WASTE WATER PONDS
Vacuum truck
Drain Existing
-
8/9/2019 JICA Presentation 1 Used 01Timor Lesteundp
4/22
Tasitolu WW Ponds ExistingLayout
Discharging
Long Section
Facultative PondMaturation Pond 01Maturation Pond 02
SludgeSludge Sludge
Bank Soil
filled Auto Cad Converted Scale: NTS
Design By: Joao N. de P. Bras
Long Section
50m 50m 50m
30m
-
8/9/2019 JICA Presentation 1 Used 01Timor Lesteundp
5/22
1.2 : Objectives
A: Short- Medium Term Planning.
Rehabilitation WW Ponds, Such subside for Privatecompany for collection WW from house holds.
Establish house connection sewage pipe aspossible.
Reconstruction Septic tank.
-
8/9/2019 JICA Presentation 1 Used 01Timor Lesteundp
6/22
B: Long Term Planning
Establishment Low regarding Waste Water.
Proposed to DONORS as possible.
Consultation Relevant Ministry.
Community Educated by media electronic, Newspaper etc.
-
8/9/2019 JICA Presentation 1 Used 01Timor Lesteundp
7/22
0%
5%
10%
15%
20%
25%
30%
35%
40%
1999 2002
Year
2004 2005 2007
Rural Area Sanitation System
Urban Area Sanitation System
1:3 : Main Constraints
Urban Area
400THS peoples In Urban Area
40% access to the Sanitation System
60% nothing access to the Sanitation System
Such Rural 40% + Urban 40%
Total of Population aces to toilet flush
The Financial constraints, rehabilitation ofTasitolu Waste Water Ponds alone estimated thecost $ USD 1,5M.
Rural Area
- 1 Million peoples In Rural Area
- 40% access to the Sanitation System
- 60% non access to the Sanitation System
0%
5%
10%
15%
20%
25%
30%
35%
40%
1999 2002 2004 2005 2007
-
8/9/2019 JICA Presentation 1 Used 01Timor Lesteundp
8/22
2. Detail of Action Plan 2.1: Description A: Facilitate To facilitate the safe disposal of sewage and wastewater in
the Dili urban area. To facilitate the collection and safe disposal ofnuisance
surface waste water from the Dili urban area. To facilitate the collection and safe disposal of hazardous
waste from the Dili urban area.
Finalisation and promulgation of the Sanitation ManagementDecree;
Finalisation, approval and objective of the SanitationManagement Plan for Dili;
B: Technologies Appropriate
Flowing Appropriate technologies as Well as Hiagari andKumamoto WASTE WATER TREATMENT PLANT. Themention above as separate system and filtration, chlorinationbefore discharging.
-
8/9/2019 JICA Presentation 1 Used 01Timor Lesteundp
9/22
NORTH
Final Sedimentation and
Chlorine process
Anaerobic 02/facultative 02
Anaerobic 01/facultative 01
Gate
Man Hole
Controlling
Gate
DESIGN OF WASTE WATER POND REHAB.
Discharging
Outlet Drain ( Concrete 1:2:3)
Band Sea
60.00 m 60.00m
60.00m
40.00m
20.00 m
Section A
Man hole
Section BAnnex 03
Final Sedimentation
Sands and coursePalm tree
Aerobic/Biological
sed. tanks
Aerobic/Biological sed.tanks
Sludge Removal
Twice/month/ top
chlorite Process,
-
8/9/2019 JICA Presentation 1 Used 01Timor Lesteundp
10/22
Note:
Volume of
Ponds
V = 18 m3
Cleaning
Once/M
T= Wall Thickness/wade = Partition Definition for Foundation Structure
P = w
H
P = 18.4 tone
T= .P/H
T= 0.5x18/2.5
T = 7.2 = 70 cm = 0. 7m
Note: H = high
W=P= Pressure Of Weight
T = Thickness
Note: Rolling Reaction not to include
P =WT
Annex 02
GL
-
8/9/2019 JICA Presentation 1 Used 01Timor Lesteundp
11/22
Chlorine and Final sediment
Facultative Ponds 1 and 2/Unaerobic01 - 02
Discharging
to SEA
BANDA SEA
NORTH
Perspective View
Inlet Pipe (Poly Pipe)
Gate Valve
Existing Waste Water Ponds
Used Local Materila in
Filtration/Sedimentation
Tank
a. Palm tree ( Tali mertan)
b. Mountain Stone
c. Sand and Gravel
PE
200mm
Annex 04
biological /
Aerobic ponds
Final Sedimentationtank
-
8/9/2019 JICA Presentation 1 Used 01Timor Lesteundp
12/22
Ponds Profile Section
1.0m
2.0m
3.0m
4.0m
5.0m
2
1
No.
Ww.
W.
t.
Wh.
H
w Ww Wh t H Total of Length
0.25 m 1.00m 0.30m 0.10m 2.50m 420 m1I.
2.25m
2.50m
0.25m
0.30m
WT.
WB
WT. WB
20-30 m 20 -25m
Annex 05
Table Sizes:
2
1
-
8/9/2019 JICA Presentation 1 Used 01Timor Lesteundp
13/22
CROSS SECTION
NORTH
Concrete1:2:3
Section A
Final Sedimentation
Auto Cad Converted Scale: NTS
Design By : Joao N. de Piedade Bras
Sedimentation filtersands course
Annex 06
Main Work:Excavation work
Construction StoneMasonry 1:3
Concrete work 1:2:3
Plastering Work 1:2
Gate Work 8 unitsWelding Work
Surrounding Fence Work
Security Office
Finishing Work
-
8/9/2019 JICA Presentation 1 Used 01Timor Lesteundp
14/22
Longitudinal Section
Filtration Door Section 6 Unit
Auto Cad Converted Scale: NTS
Design By: Joao N. de Pieade Bras
Gate FilitrationDetail A:A
ClorinTreatment MicroOrganismPrevention
Annex 07
GateFilitrationD etailA:A
Concrete1:2:3
StoneMasonry 1:3
GateFilitration DetailA:A
Main Work Item
Should be Done
Palm tree gravel
sand mountain
stoneExcavation work
Construction
Stone Masonry
1:3
Concrete work
1:2:3
Plastering Work
1:2
Gate Work 8
units
Welding Work
Surrounding
Fence Work
Security Office
Finishing Work
Instrumentsusers
Theodolite
Hand Level
Altimeter
Etc.
N0.1N0.2N0.3N0.4
-
8/9/2019 JICA Presentation 1 Used 01Timor Lesteundp
15/22
2.2 - A: Implementation and Schedule
Description Technical Designer and Financial Preparation
Technical Survey&Stakeholders
preparation
Design and FinancialPreparation
Competitive Bidding
Document Evaluation
Preparation DocumentContract
Project.-Implementation
Finishing -Hand Over
Period of Work 19 Months
-
8/9/2019 JICA Presentation 1 Used 01Timor Lesteundp
16/22
Description Schedule for Project Implementation Activity
Period of Work 12 MonthsEXCAVATION
WORK
LAND FILLBACK and
BANK REPAIR
REINFORCEWORK
CONCRETEWORK 1:2:3
STONEMASONRY
WORK
FLOOR WORK1:2:3
FILTRATIONPONDS
Finishing Work
2.2 - B: Implementation and Schedule
0%
80%
70%
60%
50%
100.%
90.%
10%
20%
30%
40%
1% 2% 2% 3%5%
8%
14%
18%21%
25%
29%
34%
38%
48%
54%
62%
79%
87%
96%99%100
70%
0% 1%1% 1%
11%
42%
-
8/9/2019 JICA Presentation 1 Used 01Timor Lesteundp
17/22
2.3 : Finance ( Estimated budget & Financialresource) Table Bellow.
Government Annual budget - CFET -(Consolidation
Fund for East Timor) for strategic planning of
wastewater management.
Minor capital improvements to the wastewater lagoons
including fencing and construction of a small office for
operations staff.
-
8/9/2019 JICA Presentation 1 Used 01Timor Lesteundp
18/22
No. DescriptionQuantities
Total UnitPrices
TOTAL BUDGET : 1 Unit $ 1,5 M
2.5(1)- Sanitation Division Annual Budget Allocation(US$)
Item
Urban Sanitation Section Total SAS
CFET
Wages & Salaries for staff 19,000
Goods & services 504,269
Capital Include Tasitolu waste water
Ponds Rehabilitation
1,251.878
Subtotal 523,269
TFET NA
Bilateral NA
Other NA
TOTAL 1,5 USD
Bill Of Quantity Dili Tasitolu Waste Water Ponds Rehabilitation
-
8/9/2019 JICA Presentation 1 Used 01Timor Lesteundp
19/22
2.4: Human Resource
The SAS Organization Structure is shown in. There is asection responsible for Urban Sanitation (urbanwastewater, solid waste and drainage). It has a total staffof 9 including the appropriate staff section.
SAS staff of 156). The approved organization structureincludes 13 staff positions (compared with a total of SASStaff in 174 persons). Current Sanitation staff Availablemore than 15 persons.
-
8/9/2019 JICA Presentation 1 Used 01Timor Lesteundp
20/22
2.5: My Role and Responsibility.
My role and responsibility for this Theme is as well asSanitation Engineer in Chief if the Action plan is successshould be implementing. I express that it will success forour own country especial the human health.
My main Work is Preparation for the Bidding documents,evaluation monitoring to ensure of the contractorsactivity according with the Technical Specificationavailable such ( PHO FHO)
-
8/9/2019 JICA Presentation 1 Used 01Timor Lesteundp
21/22
Conclusion
In this training course it is very useful for me should befollowing appropriate technologies.
Encourage Develop Country for improvement our ownenvironmental problem.
Following Japanese experience regarding Managementsystem and Environment management.
Regarding Action will be help us to thinking about theEnvironment problem in our own country as necessarily.
-
8/9/2019 JICA Presentation 1 Used 01Timor Lesteundp
22/22
* Obrigado - Graas aAdeus* Thank s
.