I4ChimeneasConstrucción

download I4ChimeneasConstrucción

of 87

Transcript of I4ChimeneasConstrucción

  • 8/14/2019 I4ChimeneasConstruccin

    1/87

    1

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    PIQUES y CHIMENEAS:Diseo, Construccin y OperacinPIQUES y CHIMENEAS:Diseo, Construccin y Operacin

    Ph. D., P. Eng. TADEUSZ S. [email protected] INTERCADE

    Junio 2008

  • 8/14/2019 I4ChimeneasConstruccin

    2/87

    2

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    4. CHIMENEASRAISES

    4. CHIMENEAS

    RAISES

  • 8/14/2019 I4ChimeneasConstruccin

    3/87

    3

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    MINING APPLICATIONS OF RAISESMINING APPLICATIONS OF RAISES

    Transfer of material.

    Orepasses piques de traspaso. Ventilation.

    Personel access.

    Ore production.

    Slot raises and the like.

    Multitude of civil applications.

  • 8/14/2019 I4ChimeneasConstruccin

    4/87

    4

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    CONVENTIONAL RAISINGCONVENTIONAL RAISING

    Drill- blast vent scaling - rock support

  • 8/14/2019 I4ChimeneasConstruccin

    5/87

    5

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    FEATURESFEATURES

    Done in fairly competent rocks only.

    No large water inflow or extensive rock fracturing.

    Raising is independent of production.

    No interference between the two.

    No loading into buckets, no water pumping, greater

    effectiveness of blasting.

  • 8/14/2019 I4ChimeneasConstruccin

    6/87

    6

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Raising with temporary

    lining & delayed

    permanent lining

    1. Chute compartment.2. Ladder compartment.

    3. Bucket compartment.

    4. Muck storage.

    5. Loading station.

    6. Protective rock pillar.7. Ventilation conduit.

    Small diameter

    raise, D < 4 m

    7

  • 8/14/2019 I4ChimeneasConstruccin

    7/87

    7

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Raising with short cuts and

    permanent lining

    1. Loading station.

    2. Protective rock pillar.

    3. Muck storage.

    4. Bucket compartment.

    5. Ladder compartment.

    6. Tubing compartment.7. Ventilation drillhole.

    8

  • 8/14/2019 I4ChimeneasConstruccin

    8/87

    8

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    9

  • 8/14/2019 I4ChimeneasConstruccin

    9/87

    9

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    PROBLEMS?PROBLEMS?

    Laddeer climbing is an inconvenience.

    Unique hazards.

    Rock falling from the face.

    Muck jamming in the chute compartment.

    Time and cost involved in preparation.

    Surveying is difficult.

    10

  • 8/14/2019 I4ChimeneasConstruccin

    10/87

    10

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    COMPARTMENTSCOMPARTMENTS

    Chute compartment.

    Solid construction, strong lining.Rebound niches every 30 to 50 m.

    Filled with rock; only excess muck removed.

    Hoist compartment.

    For supplies.

    Ladder compartment.

    Each platform supported in rock.

    11

  • 8/14/2019 I4ChimeneasConstruccin

    11/87

    11

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    RAISING METHODSRAISING METHODS

    Small diameter ( < 4 m) competent rock.

    Medium diameter, medium strength rock.

    Short cuts with immediate erection of permanent

    lining. Large diameter shafts (> 4 m) high to medium strength

    rock.

    Raise @ reduced diamer up, widen downwards to

    required size.

    12

  • 8/14/2019 I4ChimeneasConstruccin

    12/87

    12

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    RISE CLIMBERSRISE CLIMBERS

    13

  • 8/14/2019 I4ChimeneasConstruccin

    13/87

    13

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    PRINCIPLEPRINCIPLE

    The machine runs on a guide rail (pin rack).

    Segmented guide rail bolted to the sidewall with rockbolts.

    Platform good for areas up to 8 m2.

    High cost, thus preference for long raises.Or if raise used as a part of a mining method.

    14

  • 8/14/2019 I4ChimeneasConstruccin

    14/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    15

  • 8/14/2019 I4ChimeneasConstruccin

    15/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    16

  • 8/14/2019 I4ChimeneasConstruccin

    16/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    17

  • 8/14/2019 I4ChimeneasConstruccin

    17/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    57 In this part, raise climber means mechanically operated that

    is:

    (a) Suspended from a track;

    (b) Powered by air motors or electric; and

    (c) Used in a raise:

    (i) To transport workers and materials or

    (ii) as a temporary staging from which workers may performmining procedures.

    18

  • 8/14/2019 I4ChimeneasConstruccin

    18/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    FEATURESFEATURES

    Very long raises.

    Vertical or inclined.Curved or straight.

    Platform easily adjusted for height

    and angle.

    All equipment lifted by a raise climber.

    People protected when travelling.

    19

  • 8/14/2019 I4ChimeneasConstruccin

    19/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    FEATURESFEATURES

    Short mobilization times.

    Minimal preparation time.

    No restriction on raise angles. No restriction on raise sizes.

    No excessive power demands.

    Ideal in any ground conditionsor rock types.

    No requirement for reinforced concrete

    foundations. No second entry cost to install ground support or rehabilitation.

    Significantly reduced underground excavation costs.

    No expensive and time consuming directional drilling required.

    20

  • 8/14/2019 I4ChimeneasConstruccin

    20/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    ALIMAK RAISINGALIMAK RAISING

    Ventilation raises.

    Stope slot raises.

    Ore and waste pass systems.

    Raise bore rehabilitation.

    Ventilation shafts. Manway raises.

    Emergency ladder way installations.

    21

  • 8/14/2019 I4ChimeneasConstruccin

    21/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    OTHER TASKSOTHER TASKS MINE DEVELOPMENT

    - Decline and level development

    - Mechanised stoping.

    -Airleg and hand held mining.

    - Diamond drilling.

    - Shotcreting services.

    ALIMAK STOPING METHOD

    - Mechanised narrow vein Alimak long holestoping.

    - Mechanised bulk Alimak long hole stoping.

    SHAFT SINKING- Shaft sinking and equipping.

    -Alimak pilot raising and strip to size.

    - Shaft rehabilitation.

    - Exploration bulk sample shafts.

    22

  • 8/14/2019 I4ChimeneasConstruccin

    22/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    SAFETY PRECAUTIONS (WA)SAFETY PRECAUTIONS (WA)

    The Alimak Raise Climber should not be used in ground conditions such

    that climbing rack anchorage may be suspect. As for cage (gig) rising, the

    Alimak method should not be used in other than good ground conditions,

    where the risk of rockfall from the face during travel to the face, (afterblasting and clearance with an air/water blast), is reduced to the lowest

    practicable levels.

    A high standard of drilling and blasting practice is required to ensure a

    clean face after blasting. The muck pile should be inspected after each blastto assess whether the full round has been pulled.

    The risk of injury from falling rock to persons travelling to the face after

    each blastincreases with the cross-section of the rise, for any given set of ground

    conditions. It is essential to ensure that adequate strength and penetration

    resistance is built into the decking above the travel cage, to provide

    protection against any rocks which may fall during travel to the face.

    23

  • 8/14/2019 I4ChimeneasConstruccin

    23/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    MORE ON SAFETY (WA)MORE ON SAFETY (WA)

    The cross-section should be kept down to the least practicable, and if a

    large opening is required, the rise can be str ipped after completion and

    securely supported by working down from the top access.

    Cage raising involves a higher level of risk than the Alimak raise climber

    method. One aspect of this is that overhead protection for the miner when

    travelling to the face is less robust than that afforded by the Alimak

    climber.

    Moreover, particularly in raises of large cross-section, there is a

    significant risk of the rope breaking if the cage (gig) is struck by a rock

    falling from the face or sidewalls above due to the "shock" or " impact"

    load which may suddenly be applied to the rope. Cage rise diameter must

    be kept to the minimum practicable, to reduce the potential for rock fall,

    and the method used only in good ground condit ions.

    24

  • 8/14/2019 I4ChimeneasConstruccin

    24/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    DATA, FEATURESDATA, FEATURES

    Worldwide more than 2,300 Alimak raise climbers have

    been distributed.

    Used to drive more shafts and raises than any other

    system.

    The longest Alimak raise developed to date is more than

    1000 m in length.

    25

  • 8/14/2019 I4ChimeneasConstruccin

    25/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    2m x 2m x 40m long - Alimak slot raise

    Alimak pilot raise strip and support to

    5 metre diameter

    Mt Isa Mine used a fleet of 7

    climbers during the early major

    expansion which included a 360m

    long ventilation pilot raise to

    surface.

    26

    RAISEBORINGRAISEBORING

  • 8/14/2019 I4ChimeneasConstruccin

    26/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    RAISEBORINGRAISEBORING

  • 8/14/2019 I4ChimeneasConstruccin

    27/87

    28

  • 8/14/2019 I4ChimeneasConstruccin

    28/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    ADVANTAGESADVANTAGES

    Safety

    No people in the raise during excavation.

    Speed of raise excavation.

    Rates in the order of 50 m / week.

    Mine planning (next dia): faster development. More stable rock.

    No blasting.

    Mechanization: less manpower.

    29

  • 8/14/2019 I4ChimeneasConstruccin

    29/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    30

  • 8/14/2019 I4ChimeneasConstruccin

    30/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    DISADVANTAGES?DISADVANTAGES?Increased risk of exposed rock instability

    31

  • 8/14/2019 I4ChimeneasConstruccin

    31/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    OTHER RAISEBORING METHODSOTHER RAISEBORING METHODS

    Down reaming.

    Blind shaft boring.

    Pilot up, ream down.

    Pilot down, ream down.

    Boxhole boring.

    .

    32

  • 8/14/2019 I4ChimeneasConstruccin

    32/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Do

    wnwa

    rdsbo

    ring

    Downwa

    rdsbo

    ring

    Mud rushes at the

    bottom of the hole

    Rock cuttings

    flushed down

    Risk of blocking the

    pilot hole with drill ings

    33

    B h l B iB h l B i

  • 8/14/2019 I4ChimeneasConstruccin

    33/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Boxhole Boring

    Limited or no access to upperlevel

    Boxhole Boring

    Limited or no access to upperlevel

    34

    gg

  • 8/14/2019 I4ChimeneasConstruccin

    34/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Upwards(B

    oxhole)bo

    ring

    Upwa

    rds(B

    oxho

    le)bo

    ring

    Popular whereno access to

    upper level

    availableOften used for

    raises of 30 to90 m high,

    max 200m

    Cuttings fall down;

    directed into muckcars

    35

  • 8/14/2019 I4ChimeneasConstruccin

    35/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    BorPak

    Assembly

    BorPak

    Assembly

    36

  • 8/14/2019 I4ChimeneasConstruccin

    36/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    CONVENTIONAL RAISEBORINGCONVENTIONAL RAISEBORING

    Reaming head size from

    1.2 m to 7.1 m in

    diameter.

    The max loading capacityof drillstring limits the dia

    and depth of shaft.

    37

  • 8/14/2019 I4ChimeneasConstruccin

    37/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    PILOT HOLE DRILLINGPILOT HOLE DRILLING

    Tri-cone rotary bit is common.

    Diameters vary from 9 to 15 (381 mm).

    15 (381 mm) bit used on long holes.

    With 12-3/7(327 mm) integral drillsteel string and 10-

    1/8 tool joints.

    for more see below.

    38

  • 8/14/2019 I4ChimeneasConstruccin

    38/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    39

  • 8/14/2019 I4ChimeneasConstruccin

    39/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Hooking up

    the reamer

    40

  • 8/14/2019 I4ChimeneasConstruccin

    40/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    41

  • 8/14/2019 I4ChimeneasConstruccin

    41/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    7.1 M Diameter Reamer Head

    42

    S O G G O S

  • 8/14/2019 I4ChimeneasConstruccin

    42/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    RAISEBORING UNDERGROUND SITERAISEBORING UNDERGROUND SITE

    43

    EQUIPMENT POSITIONINGEQUIPMENT POSITIONING

  • 8/14/2019 I4ChimeneasConstruccin

    43/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    EQUIPMENT POSITIONINGEQUIPMENT POSITIONING

    44

  • 8/14/2019 I4ChimeneasConstruccin

    44/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    45

    CONVENTIONAL PILOT HOLE DRILLINGCONVENTIONAL PILOT HOLE DRILLING

  • 8/14/2019 I4ChimeneasConstruccin

    45/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    CONVENTIONAL PILOT HOLE DRILLINGCONVENTIONAL PILOT HOLE DRILLING

    Normally a tri-cone bit.

    Hole diameter up to 15 (381 mm).With 12-7/8 drill steel (327 mm).

    Drilling fluid used for hole flushing.Normal circulation.

    Drillings settled out and the fluid reused.

    46

    DIRECTIONAL PILOT HOLE DRILLINGDIRECTIONAL PILOT HOLE DRILLING

  • 8/14/2019 I4ChimeneasConstruccin

    46/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    DIRECTIONAL PILOT HOLE DRILLINGDIRECTIONAL PILOT HOLE DRILLING

    Used in applications where high degree of accuracy

    is needed.

    Best accuracies are in the 0.036% range.

    47

    CONTROL OF PILOT HOLE DEVIATIONCONTROL OF PILOT HOLE DEVIATION

  • 8/14/2019 I4ChimeneasConstruccin

    47/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    CONTROL OF PILOT HOLE DEVIATIONCONTROL OF PILOT HOLE DEVIATION

    48

    PILOT HOLE DEVIATIONPILOT HOLE DEVIATION

  • 8/14/2019 I4ChimeneasConstruccin

    48/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    PILOT HOLE DEVIATIONPILOT HOLE DEVIATION

    Influenced by factors as listed above.

    The measure: Build-up rate.

    Degrees of deflection per 100 m of hole length.

    Often 0.25 deg per 100 m.

    Deviation becomes exponential with depth.

    Often evidenced by vibrations of the drill string.

    Can be measured by survey tools.

    Inclination down to 0.05 degrees.

    0.5 degrees in azimuth.

    49

    DEVIATION CONTROLDEVIATION CONTROL

  • 8/14/2019 I4ChimeneasConstruccin

    49/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    DEVIATION CONTROLDEVIATION CONTROL

    (Some) deviation always occur:

    For high accuracy holes frequent survey is needed:

    each 10 m?

    What deviation is acceptable?

    In some applications 1% is ok; this is relatively easy

    to control.

    In long raises / shafts the limit can be 0.05%

    How to control it?

    50

    MORE DEVIATION CONTROLMORE DEVIATION CONTROL

  • 8/14/2019 I4ChimeneasConstruccin

    50/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    MORE DEVIATION CONTROLMORE DEVIATION CONTROL

    Ensure good bailing action

    Manipulate rotational speed and bit force.

    Use highest rotational speed consistent with smoothdrilling.

    Penetration rate is the function of the speed and force;one compensates for the other.

    Limit the rate of penetration.

    Slow the speed, lower the force; max 50 mm perminute?

    Important when vibrations indicate changing strata.

    51

    MEASURING DEFLECTIONMEASURING DEFLECTION

  • 8/14/2019 I4ChimeneasConstruccin

    51/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    MEASURING DEFLECTIONMEASURING DEFLECTION

    Frequent checks may be needed

    As often as each 10 m of hole advance?

    This slows the rate of drilling!

    Survey tool

    Connected to on-line data logger.

    Descends through the swivel and gearbox via an

    automatic winch.

    Drill string pieces adjacent to the bit must be non

    magnetic.

    52

    DEFLECTION CORRECTIONDEFLECTION CORRECTION

  • 8/14/2019 I4ChimeneasConstruccin

    52/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    DEFLECTION CORRECTIONDEFLECTION CORRECTION

    Navigational drilling

    equipment

    Deflection corrected by use ofa special head that can drill in

    any direction.

    Head rotation propelled by

    high density drilling mud;string stays stationary.

    To install/remove the head (to

    rectify the deflection) the drill

    rods need to be removed from

    the hole.

    Sophisticated equipment and expertise needed: time delays facedSophisticated equipment and expertise needed: time delays faced

    53

  • 8/14/2019 I4ChimeneasConstruccin

    53/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    An Example

    54

    INCLINED HOLESINCLINED HOLES

  • 8/14/2019 I4ChimeneasConstruccin

    54/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    INCLINED HOLESINCLINED HOLES

    Correction may be corrected by:

    Varying the bit force.

    Changing the position and number of stabilizers.

    Increasing the bit force causes the bit to move upwards.

    Decreasing the bit force causes allows the bit to drop.

    55

    ROTARY VERTICAL DRILLING SYSTEMROTARY VERTICAL DRILLING SYSTEM

  • 8/14/2019 I4ChimeneasConstruccin

    55/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    ROTARY VERTICAL DRILLING SYSTEMROTARY VERTICAL DRILLING SYSTEM

    Self-steering directional drill

    Two sensors measure holeinclination.

    If limits of deflectionexceeded the steeringfunction is initiated.

    Stabilizer wings generateradial forces.

    No need to remove drillrods.

    Accuracy down to 0.04%

    56

    SELF-STEERING DIRECTIONAL DRILLSELF-STEERING DIRECTIONAL DRILL

  • 8/14/2019 I4ChimeneasConstruccin

    56/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    SELF STEERING DIRECTIONAL DRILLSELF STEERING DIRECTIONAL DRILL

    Dump Sub Power Unit(Rotor and Stator

    Transmision

    Unit

    Bearing Section

    Assembly

    Tubular Housings

    And Stabilizer

    57

    McCracken & Stacey Raisebore Risk

  • 8/14/2019 I4ChimeneasConstruccin

    57/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    SOME ROCK MECHANICSSOME ROCK MECHANICS

    McCracken & Stacey Raisebore Risk

    Assessment Method

    McCracken and Stacey published the method in 1989 and it was successfully

    applied to the planned Airshaft No.5 at Broken Hill that same year. The method

    predicted severe instability i f raiseboring was attempted at the planned 6m

    diameter. It indicated that some overbreak would occur even if raisebored at

    1.8m diameter, a conclusion supported by an analysis using the Q-System. The

    McCracken and Stacey method gained signif icant credibil ity when the predicted

    overbreak occurred during reaming at 1.8m diameter, prior to enlargement to

    6.7m diameter by V-mole (Bennet & de Bruin, 1993) .

    58

  • 8/14/2019 I4ChimeneasConstruccin

    58/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    To obtain the raise drilled hole quality index, QR from Q, the

    following adjustments factors, which are acumulative, must

    be applied.

    Wall adjustment.

    Discontinuity orientation adjustment factor.

    Weathering adjusment.

    59

  • 8/14/2019 I4ChimeneasConstruccin

    59/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    60

  • 8/14/2019 I4ChimeneasConstruccin

    60/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    61

    Suggested levels of reliability; R, and probabilities of failure

  • 8/14/2019 I4ChimeneasConstruccin

    61/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    gg y; , p

    P(f), that are considered acceptable for the raise wall stabilityof diferent types of excavations are presented in Table I.

    These provide guidelines for other raise drill shafts.

    EXCAVATION

    TYPE

    Service

    Life

    (years)

    Reliability

    R

    (%)

    Probability

    of failure

    P(f)

    Unlined hosting shaft

    Ventilation shaft

    Ore Pass

    Ore Pass

    99

    10

    > 2

    1

    > 15

    95

    85

    75

    0,01

    0,05

    0,15

    0,25

    62

    SHAFT BORINGSHAFT BORING

  • 8/14/2019 I4ChimeneasConstruccin

    62/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    SHAFT BORINGSHAFT BORING

    Shaft? Raise?

    What is the difference?

  • 8/14/2019 I4ChimeneasConstruccin

    63/87

    64

  • 8/14/2019 I4ChimeneasConstruccin

    64/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    A travs de nuestra casa matriz en Sudfrica contamos con el equipo

    Raise Borer marca Wirth modelo HG 380, capaz de excavar hasta 6,0

    mts de dimetro y 1.000 metros de profundidad.

    Perforaciones en descenso de pozos de drenaje o paso de servicios de

    aire, agua o energa, en dimetros de 250 mm. hasta 381 mm.

    Perforacin Direccional, que se aplica para asegurar la precisin de la

    perforacin de tiros pilotos y excavaciones de piques o chimeneas de

    gran longitud y que por diseo aceptan un mnimo de deflexin.

    65

    L dif t i i K l S A f t t l

  • 8/14/2019 I4ChimeneasConstruccin

    65/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Los diferentes servicios que Kala S.A. ofrece con esta tecnologa

    son:

    Chimeneas de ventilacin, de servicios, de traspaso de minerales o

    estril de un nivel a otro, y chimeneas de acceso de personal.

    Chimeneas de cara libre o slot, que participan directamente en la

    lnea de produccin en mtodos como el Sub Level Stoping.

    Chimeneas de relleno de caserones mineros que intervienen en

    mtodos como el Cut and Fill.

    Las dimensiones de estas excavaciones pueden ser de 1,0 mt. hasta

    4,5 mts. de dimetro con inclinaciones de 40 a 90 y en longitudes

    hasta 600 mts.

    66

    TECNOLOGIA CON EQUIPOS BLIND HOLE

  • 8/14/2019 I4ChimeneasConstruccin

    66/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    Kala S.A. incorpor, en ao 1997, la Tecnologa Blind Hole en la industriaminera en la Divisin El Teniente de Codelco Chile, para la excavacin de

    chimeneas mineras.

    El mtodo consiste en la excavacin de chimeneas, en forma ascendente,perforando el tiro gua y realizando el ensanche de la chimenea al

    dimetro deseado, en forma conjunta.

    El equipo se instala en una galera al interior de una mina subterrnea y la

    excavacin se realiza en ascenso sin tener la necesidad de contar con un

    nivel o galera superior. Esta modalidad permite el desarrollo de la galera

    superior en forma anticipada.

    67

    Estas excavaciones pueden se de 0,7 mts. hasta 1,5 mts.

    d di t l it d d h t 80 t

  • 8/14/2019 I4ChimeneasConstruccin

    67/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    de dimetro con una longitud de hasta 80 mts.

    Perforaciones ascendentes de pozos de drenaje o paso

    de servicios de aire, agua, en dimetros de 250 a 311mm.

    La excavacin de chimeneas con equipos Blind Hole se

    realiza siguiendo rigurosos procedimientos de trabajo y

    como la operacin de los equipos se realiza a distancia,desde un panel de control, lo transforma en un mtodo

    altamente seguro, ya que el personal siempre estar fuera

    de la lnea de excavacin.

    68

    Los diferentes servicios que ofrece Kala S.A. con esta

    tecnologa son:

  • 8/14/2019 I4ChimeneasConstruccin

    68/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    tecnologa son:

    Excavaciones de chimeneas pilotos para zanjas utilizadas

    en el mtodo Block Caving.

    Excavaciones de chimeneas ascendentes para sistemas de

    buzones de mineral.

    Chimeneas de ventilacin, servicios o traspaso de minerales

    o estril.

    Chimeneas Slot o de cara libre para la explotacin mediante

    el mtodo Sub Level Stoping.

    69

  • 8/14/2019 I4ChimeneasConstruccin

    69/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    70

    Robins 52R in El Teniente

  • 8/14/2019 I4ChimeneasConstruccin

    70/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

  • 8/14/2019 I4ChimeneasConstruccin

    71/87

    72

  • 8/14/2019 I4ChimeneasConstruccin

    72/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    In relatively hard rock, the speed of the variousoperations might be as follows:

    Pilot hole drilling 15 m/day.

    Enlarging pilot hole to 1.8 metres 7.5 m/day. Enlarging to 6.5 metres with V-mole 6 m/day.

    Assuming a 1,000-metre deep shaft and neglecting thetime to set up the V-mole, a completed shaft would take

    368 days an advance rate of 2.7 m/day which is

    no faster than conventional sinking.

    73

    ADVANCESADVANCES

  • 8/14/2019 I4ChimeneasConstruccin

    73/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    In relatively hard rock, the speed of the various operations

    might be as follows:

    pilot hole drilling 15 m/day

    enlarging pilot hole to 1.8 metres 7.5 m/day.

    enlarging to 6.5 metres with V-mole 6 m/day.

    Assuming a 1,000-metre deep shaft and neglecting the time

    to set up the V-mole, a completed shaft would take 368 days.

    an advance rate of 2.7 m/day which is no faster than

    conventional sinking.

    74

  • 8/14/2019 I4ChimeneasConstruccin

    74/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    REGULATIONSREGULATIONS

    Good guideline to what to do

    and how to do it

    75

    58 (1) If reasonably practicable, an employer or contractor

    must:

  • 8/14/2019 I4ChimeneasConstruccin

    75/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    (a) The top every ore pass, manway or other opnening into

    which a worker colud step or fall is:

    (i) Covered with a securely installed covering; or

    (ii) Guarded by an adequate barrier; and

    (b) The top of every raise or other opening to a level into

    wich powered mobile equipment coul fall is protected bya barrier that has been designed by a professional

    engineer and built to the design specifications

  • 8/14/2019 I4ChimeneasConstruccin

    76/87

    77

    59 (1) If a worker is required to pull a chute, the employer orcontractor must ensure that:

  • 8/14/2019 I4ChimeneasConstruccin

    77/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    (a) The volume of any liquid entering a mine opening usedfor the passage or ore, waste or other material by gravity isminimized to the extent that is reasonably practicable; that thegates may be locked in either the opne or closed position; and

    (b)A mechanical locking device is installed on poweroperated chute gates so that the gates may be locked in

    either the open or clsed position, and(c) The chute is designed so that a power failure will not

    cause the chute gates open.

    (2)An employer or contractor must ensure that no workerpulling a chute is postioned so that the workers safe exit isimpeded by an uncontrolled discharge of liquid or solid

    material from the chute.

    78

    (3) If a worker is required or permitted to work in a chute or at

    a worksite that my be affected by the flow of material from the

  • 8/14/2019 I4ChimeneasConstruccin

    78/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    y y

    chute, the meployer or contractor must ensure that:

    (a) The power supply to conveyor or a gate that controls the

    flow of material into the chute is disconnected locked andtagged; and

    (b) Subject to subsection (4), gates in the closed position to

    prevent the flow of material.

    (4) If it is necessary for a woeker to work with a chute opne,

    the employer or contractor must ensure that a suitablebulkhead is installed above the worker to divert or arrest the

    flow of maerial.

    79

    60(1) Subject to subsection (2), if material is hung up in a mine

    opening that is used for the passage of ore, waste or other

  • 8/14/2019 I4ChimeneasConstruccin

    79/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    material by gravity, the employer or contractor must ensurethat no worker is required or permitted to enter the opening

    until a competent person authorized by the employer or

    contractor.

    (a) Examines the stability of the hang-up;

    (b) Determiner the method of safety removing the hang-up,

    and(c) Supervises the removal of the hang-up.

    (2)An employer or contractor may permit a worker who issupervised by the authorized person mentioned in subsection

    (1) to enter a mine opening mentioned in subsection (1) for

    the purpose of removing the hang-up.

  • 8/14/2019 I4ChimeneasConstruccin

    80/87

  • 8/14/2019 I4ChimeneasConstruccin

    81/87

    82

    (3) Except where the track on which a raise climber operates is

    being extended, the employer or contractor must ensure that

  • 8/14/2019 I4ChimeneasConstruccin

    82/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    a raise climber has a stop block installed to prevent the raiseclimber from being taken beyond the end of the track.

    (4)An employer or contractor must ensure that:(a) The raise climber service area is designed and operated

    to prevent workers from exiting the raise while it is below the

    open raise; and

    (b) an emergency procedure is developed, and the means to

    carry out the procedure are available, to remove workers

    safely from a raise climber that is stalled at a position otherthat at the raise climber service area.

  • 8/14/2019 I4ChimeneasConstruccin

    83/87

    84

    68(1)At the commencement of each shift, an employer or

  • 8/14/2019 I4ChimeneasConstruccin

    84/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    contractor must ensure that the brakes of a raise climber areinspected and tested by a competent worker to ensure that

    the brakes are in a safe working condition.

    (2) Before a raise climber is started, an employer or contractor

    must ensure that a competent worker makes a complete

    visual of the raise climber and the surrounding area to ensure

    that no worker is endagered by the start up of the raise

    climber.

    (3)An employer or contractor must ensure that a raise climberis inspected weekly by competent person to indentify any

    defects or unsafe conditions.

    85

    69(1) In this section, Crtitical part means each part of a

    raise climber that, if it failed, would cause the

  • 8/14/2019 I4ChimeneasConstruccin

    85/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    uncontrolled descent of the raise climber.

    (2)An employer or contractor must ensure that the

    crtiical parts of a raise climber are subjected to athorough inspection, including non-destructive testing,

    under the supervision of a professional engineer.

    (a) Before the raise clmber is first put into service;

    (b) during every mayor overhaul, and

    (c)At least once in every 4,000 hours of use or every 12

    months, whichever occurs first.

    86

    70An employer or contractor must:

    (a) Provide a raise climber log book for each raise climber and

  • 8/14/2019 I4ChimeneasConstruccin

    86/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    ensure that the raise climber log book is kept available;

    (b) Ensure that the details of each inspection required pursuant

    to section 68, including any defects discovered as a result of

    the raise climber log book by the person who conducted theinspection; and

    (c) Countersign the entries made pursuant to clause (b) on a

    regular basis.

    72 If a raise climber provides the only means of exit from

    worksite, the employer or contractor must ensure that noworker is required or permitted to remain in that worksite if

    the climber is removed from the for any reason.

    87

    71(1)An employer or contractor must:

  • 8/14/2019 I4ChimeneasConstruccin

    87/87

    Ph. D. Eng. TADEUSZ S. GOLOSINSKI - [email protected] - Consultor Intercade

    (a) Designate a worker to operate a raise climber;

    (b) Ensure that the designated operator is trained in the safe

    operation of the raise climber; and

    (c) Ensure that no worker other that a designated operator a

    raise climber.

    (2)An operator of a raise climber must not operate the raise

    climber unless:

    (a) The operator has determined the weight of the load; and

    (b) The load is less than the rated load for the operatingconditons.