  • CATALOGO DE CONCEPTOS

    CLAVE CONCEPTO UNIDAD CANTIDAD

    CONSTRUCCION DE EDIFICIOPRELIMINARES

    1.1 TRAZO Y NIVELACION CON EQUIPO TOPOGRAFICO M2 350.001.2 RELLENO CON TEPETATE COMPACTADO AL 90% PROCTOR CO M3 2,000.001.3 EXCAVACION EN CEPA PARA DESPALNTE DE CIMENTACION C M3 3,000.00

    ALBAILERIA Y ESTRUCTURA2.1 PZA 39.002.2 MURO DE BLOCK DE 20 CMS DE ESPESOR, C/MORTERO CEM-A M2 1,800.002.3 SUM. Y COLOC. PLACA DE ACERO 20x20 CMS 4 BARRENOS, I PZA 100.00

    ACABADOS3.1 MURO DE TABLAROCA A 2 CARAS DE 9 CMS DE ESP. M2 1,800.003.2 PISO DE LOSETA DE CERAMICA DE 33x33 MARCA INTERCERA M2 1,500.003.3 PINTURA VINILICA EN MUROS MARCO COMEX TIPO VINIMEX M2 5,000.00

    INSTALACIONES4.1 SUM. E INST. TUBO CONDUIT PARED GRUESA 19 MM M 45.004.2 SUM. E INST. CABLE THW CAL. 10 M 17.00

    FACTOR DE SOBRECOSTO = PRECIO UNITARIO / COSTO DIRECTO1.3035 UN % DE SOBRECOSTO = FACTOR DE SOBRECOSTO -1 (Formato de la celda en %)30.35%

    (Aportacion a la SFP Secretaria de la Funcion Publica = 5 al millar) % CARGOS ADICIONALES

    CONSTRUCCION DE ZAPATA AISLADA DE 2.00 MTS x 2.00 MTS DE SECCION Y 0.20 MTS DE ESPESOR, DE CONCRETO F'C=250 KG/CM2 HECHO EN OBRA CON REVOLVEDORA DE 1 SACO ( 8 HP), AGREGADO MAXIMO DE 3/4" (19 MM), ARMADA CON VARILLA DEL No. 3 (3/8"), A CADA 15 CMS DE SEPARACION EN AMBOS SENTIDOS Y 2 LECHOS; EL PRECIO INCLUYE: CONSTRUCCION DE DADO DE CIMENTACION DE 0.50 MTS x 0.50 MTS DE SECCION Y 1.60 MTS DE ALTURA, DE CONCRETO F'C=250 KG/CM2 HECHO EN OBRA CON REVOLVEDORA DE 1 SACO (8 HP), AGREGADO MAXIMO DE 3/4" (19 MM), ARMADO CON 8 VARILLAS DEL No. 6 (3/4") Y ESTRIBOS DE VARILLA DEL No. 3 (3/8") A CADA 12 CMS; ACARREO DE TODOS LOS MATERIALES NECESARIOS PARA SU EJECUCION A CUALQUIER DISTANCIA; RETIRO Y LIMPIEZA DE SOBRANTES AL FINALIZAR LA ACTIVIDAD; ARMADO, CIMBRADO COMUN CON MADERA DE PINO DE 3RA, ACARREOS Y COLADO DE CONCRETO, VIBRADO CON EQUIPO (VIBRADOR PARA CONCRETO DE 5.5 HP), DESCIMBRADO Y CURADO CON MEMBRANA; MATERIALES, MANO DE OBRA, HERRAMIENTA, EQUIPO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION; P. U. O. T.

  • IMPORTE A PRECIO UNITARIO

    $11.15 $3,902.50 $14.53 $5,085.50$433.56 $867,120.00 $565.14 $1,130,283.55$35.00 $105,000.00 $45.62 $136,866.61

    $5,475.82 $213,556.92 $7,137.68 $278,369.63$325.00 $585,000.00 $423.63 $762,542.53$140.31 $14,031.00 $182.89 $18,289.29

    $280.94 $505,692.00 $366.20 $659,165.22$450.00 $675,000.00 $586.57 $879,856.76$45.00 $225,000.00 $58.66 $293,285.59

    $4,500.00 $202,500.00 $5,865.71 $263,957.03$9,000.00 $153,000.00 $11,731.42 $199,434.20TOTALES $3,549,802.42 1.3035 $4,627,135.91

    PRESUPUESTO TOTAL SIN IVA $4,627,135.91% DE IVA (16%) $740,341.75

    PRESUPUESTO TOTAL CON IVA $5,367,477.66

    COSTO DIRECTO $3,549,802.42% DE INDIRECTOS 17.4934% $620,981.14

    UN % DE SOBRECOSTO = FACTOR DE SOBRECOSTO -1 (Formato de la celda en %) SUBTOTAL 1 $4,170,783.56% DE FINANCIAMIENTO 0.3543% $14,777.09

    SUBTOTAL 2 $4,185,560.64% DE UTILIDAD 10.0000% $418,556.06

    SUBTOTAL 3 $4,604,116.71(Aportacion a la SFP Secretaria de la Funcion Publica = 5 al millar) % CARGOS ADICIONALES 0.5000% $23,020.58

    PRECIO UNITARIO $4,627,137.29

    COSTO DIRECTO

    IMPORTE A COSTO DIRECTO

    PRECIO UNITARIO

  • GENERALIDADES : ART. 185 AL 188

  • CATALOGO DE CONCEPTOS

    CLAVE CONCEPTO UNIDAD CANTIDAD

    CONSTRUCCION DE CASA HABITACIONPRELIMINARES

    1.1 TRAZO Y NIVELACION CO M2 350.00 $11.15

    1.2 RELLENO CON TEPETATE M3 2,000.00 $433.56

    1.3 EXCAVACION EN CEPA PAR M3 3,000.00 $35.00

    ALBAILERIA Y ESTRUCTURA2.1 PZA 39.00 $5,475.82

    2.2 MURO DE BLOCK DE 20 CM M2 1,800.00 $325.00

    2.3 SUM. Y COLOC. PLACA DE PZA 100.00 $140.31

    ACABADOS3.1 MURO DE TABLAROCA A 2 M2 1,800.00 $280.94

    3.2 PISO DE LOSETA DE CERA M2 1,500.00 $450.00

    3.3 PINTURA VINILICA EN MU M2 5,000.00 $45.00

    INSTALACIONES4.1 SUM. E INST. TUBO COND M 45.00 $4,500.00

    4.2 SUM. E INST. CABLE THW C M 17.00 $9,000.00

    TOTALES

    FACTOR DE SOBRECOSTO = PRECIO UNITARIO / COSTO DIRECTO1.3035 % DE INDIRECTOS UN % DE SOBRECOSTO = FACTOR DE SOBRECOSTO -1 (Formato de30.35% % DE FINANCIAMIENTO

    COSTO DIRECTO

    CONSTRUCCION DE ZAPATA AISLADA DE 2.00 MTS x 2.00 MTS DE SECCION Y 0.20 MTS DE ESPESOR, DE CONCRETO F'C=250 KG/CM2 HECHO EN OBRA CON REVOLVEDORA DE 1 SACO ( 8 HP), AGREGADO MAXIMO DE 3/4" (19 MM), ARMADA CON VARILLA DEL No. 3 (3/8"), A CADA 15 CMS DE SEPARACION EN AMBOS SENTIDOS Y 2 LECHOS; EL PRECIO INCLUYE: CONSTRUCCION DE DADO DE CIMENTACION DE 0.50 MTS x 0.50 MTS DE SECCION Y 1.60 MTS DE ALTURA, DE CONCRETO F'C=250 KG/CM2 HECHO EN OBRA CON REVOLVEDORA DE 1 SACO (8 HP), AGREGADO MAXIMO DE 3/4" (19 MM), ARMADO CON 8 VARILLAS DEL No. 6 (3/4") Y ESTRIBOS DE VARILLA DEL No. 3 (3/8") A CADA 12 CMS; ACARREO DE TODOS LOS MATERIALES NECESARIOS PARA SU EJECUCION A CUALQUIER DISTANCIA; RETIRO Y LIMPIEZA DE SOBRANTES AL FINALIZAR LA ACTIVIDAD; ARMADO, CIMBRADO COMUN CON MADERA DE PINO DE 3RA, ACARREOS Y COLADO DE CONCRETO, VIBRADO CON EQUIPO (VIBRADOR PARA CONCRETO DE 5.5 HP), DESCIMBRADO Y CURADO CON MEMBRANA; MATERIALES, MANO DE OBRA, HERRAMIENTA, EQUIPO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION; P. U. O. T.

  • (Aportacion a la SFP Secretaria de la Funcion Publica = 5 al millar) % CARGOS ADICIONALESPRECIO UNITARIO

  • MES 1 MES 2

    $3,902.50 $14.53 $5,086.88 100.00%$5,086.88

    $867,120.00 $565.14 $1,130,283.55 30.00% 70.00%$339,085.07 $791,198.49

    $105,000.00 $45.62 $136,866.61 100.00%$136,866.61

    $213,556.92 $7,137.68 $278,369.63 70.00% 30.00%$194,858.74 $83,510.89

    $585,000.00 $423.63 $762,542.53 20.00%$152,508.51

    $14,031.00 $182.89 $18,289.29 100.00%$18,289.29

    $505,692.00 $366.20 $659,165.22

    $675,000.00 $586.57 $879,856.76

    $225,000.00 $58.66 $293,285.59

    $202,500.00 $5,865.71 $263,957.03

    $153,000.00 $11,731.42 $199,434.20

    $3,549,802.42 1.3035 $4,627,137.29

    IMPORTE POR PERIODO $675,897.29 $1,045,507.17IMPORTE ACUMULADO POR PERIODO $675,897.29 $1,721,404.46

    % POR PERIODO 14.61% 22.60%% ACUMULADO POR PERIODO 14.61% 37.20%

    COSTO DIRECTO $3,549,802.42% DE INDIRECTOS 17.4934% $620,981.14

    SUBTOTAL 1 $4,170,783.56% DE FINANCIAMIENTO 0.3543% $14,777.09

    SUBTOTAL 2 $4,185,560.64% DE UTILIDAD 10.0000% $418,556.06

    SUBTOTAL 3 $4,604,116.71

    IMPORTE A COSTO DIRECTO

    PRECIO UNITARIO

    IMPORTE A PRECIO UNITARIO

  • (Aportacion a la SFP Secretaria de la Funcion Publica = 5 al millar) % CARGOS ADICIONALES 0.5000% $23,020.58PRECIO UNITARIO $4,627,137.29

  • MES 3 MES 4 MES 5 TOTAL

    100.00%$5,086.88100.00%

    $1,130,283.55100.00%

    $136,866.61

    100.00%$278,369.63

    80.00% 100.00%$610,034.02 $762,542.53

    100.00%$18,289.29

    70.00% 30.00% 100.00%$461,415.66 $197,749.57 $659,165.22

    60.00% 40.00% 100.00%$527,914.06 $351,942.71 $879,856.76

    100.00% 100.00%$293,285.59 $293,285.59

    50.00% 50.00% 100.00%$131,978.51 $131,978.51 $263,957.0350.00% 50.00% 100.00%

    $99,717.10 $99,717.10 $199,434.20

    $1,303,145.30 $957,359.24 $645,228.29$3,024,549.75 $3,981,908.99 $4,627,137.29

    28.16% 20.69% 13.94%65.37% 86.06% 100.00%

  • Row 35

    Row 33

  • Row 35

    Row 33

  • ANALISIS, CALCULO E INTEGRACION DEL PRECIO UNITARIO

    CLAVE2.1

    CLAVE

    MAVAR3MAVAR6MAALARMAPOLMABARMADUEMACLAMADIEMACUR

    MO1A1AAMO1F1AFMO1C1AC

    EQVIB

    HEREQS

    MACON250

    FACTOR DE SOBRECOSTO = PRECIO UNITARIO / COSTO DIRECTO1.3035 UN % DE SOBRECOSTO = FACTOR DE SOBRECOSTO -1 (Formato de la celda en %)30.35%

  • CONSIDERANDO PAGO DE ESTIMACIONES (se estarian ejecunatdo del mes 3 hasta el final con el

  • ANALISIS, CALCULO E INTEGRACION DEL PRECIO UNITARIO

    CONCEPTOCONSTRUCCION DE ZAPATA AISLADA DE 2.00 MTS x 2.00 MTS DE SECCION Y 0.20 MTS DE ESPESOR, DE CONCRETO F'C=250 KG/CM2 H

    DESCRIPCION

    ACERO DE REFUERZO DEL No. 3 (3/8")ACERO DE REFUERZO DEL No. 6 (3/4")ALAMBRE RECOCIDOPOLIN DE MADERA DE PINO DE 3RA DE 4" x 4" x 8'BARROTE DE MADERA DE PNO DE 3RA DE 2" x 4" x 8'DUELA DE MADERA DE PINO DE 3RA DE 1" x 4" x 8'CLAVOS DE 2 1/2" HASTA 4"DIESELMEMBRANA DE CURADO

    CUADRILLA DE 1 OFICIAL ALBAIL + 5 AYUDANTES DE ALBAIL + CABO DE OFICIOSCUADRILLA DE 1 OFICIAL FIERRERO + 1 AYUDANTE DE FIERRERO + CABO DE OFICIOS

    MAQUINARIA Y EQUIPOVIBRADOR PARA CONCRETO DE 5.5 HP

    HERRAMIENTA DE MANO Y EQUIPO DE SEGURIDADHERRAMIENTA DE MANOEQUIPO DE SEGURIDAD

    SUBTOTAL DE HERRAMIENTA DE MANO Y EQUIPO DE SEGURIDAD

    FACTOR DE SOBRECOSTO = PRECIO UNITARIO / COSTO DIRECTO

    UN % DE SOBRECOSTO = FACTOR DE SOBRECOSTO -1 (Formato de la celda en %)

    (Aportacion a la SFP Secretaria de la Funcion Publica = 5 al millar) % CARGOS ADICIONALES

    MATERIALES (ART. 193 RLOPSRM) (Materiales de adquisicion)

    MANO DE OBRA (ART. 190 RLOPSRM)

    CUADRILLA DE 1 OFICIAL CARPINTERO DE OBRA NEGRA + 1 AYUDANTE DE CARPINTERO DE OBRA NEGRA + CABO DE OFICIOS

    BASICOS DE MATERIALES (ART. 193 RLOPSRM) (Materiales fabricados en sitio)CONCRETO F'C=250 KG/CM2 HECHO EN OBRA CON REVOLVEDORA DE 1 SACO (8HP), AGREGADO MAXIMO DE 3/4"

  • TASA DE INTERES ANUALTASA DE INTERES MENSUAL

    TASA DE INTERES A 4.5 MESESCONSIDERANDO UN ANTICIPO (con el anticipo se ejecuta un 1er mes)

    CONSIDERANDO PAGO DE ESTIMACIONES (se estarian ejecunatdo del mes 3 hasta el final con el cobro de estimaciones)

  • CUANTIFICACIONUNIDAD CONCRETO

    CONSTRUCCION DE ZAPATA AISLADA DE 2.00 MTS x 2.00 MTS DE SECCION Y 0.20 MTS DE ESPESOR, DE CONCRETO F'C=250 KG/CM2 H PZA ZAPATA = 2.00 MTS x 2.00 MTS x 0.20 MTSDADO = 0.50 MTS x 0.50 MTS x 1.60 MTS

    UNIDAD COSTO CANTIDAD IMPORTE TOTAL = 0.80 M3 + 0.40 M3 + 2% DESPERDICIO

    TON $10,500.00 * 0.081 $850.50 CALCULO RENDIMIENTO PARA CUADRILLA DE 1 OF. ALBAIL + 5 AYUD. ALBAILTON $10,500.00 * 0.053 $556.50 1.22 M3 DE CONCRETOKG $11.50 * 6.03 $69.35 1,220.00 LTS DE CONCRETOPZA $96.60 * 1.60 $154.56 65.00 BOTES / 5 AYUDANTESPZA $52.90 * 1.60 $84.64 13 VUELTAS x 50 SEGUNDOSPZA $32.20 * 6.67 $214.67 650.00 SEGUNDOS / 60 SEGKG $16.00 * 2.00 $32.00 TIEMPO PARA VIBRADOLT $11.54 * 2.40 $27.70 NIVELADO Y EMPAREJADOLT $27.00 * 2.40 $64.80 VACIADO DE CONCRETO

    COLADO DE ZAPATASUBTOTAL DE MATERIALES $2,054.71 RENDIMIENTO = 8.00 HRS / 0.50 HRS

    RENDIMIENTO EN CONDICIONES NORMALES DE EJECUCION (BASE DE DATOS NEODATA)JORNADA $2,105.61 / 4.10 $513.77 5.00 M3 / JOR JORNADA $997.24 / 1.50 $663.16 0.20 TON / JORJORNADA $997.24 / 1.88 $531.86 9.00 M2 / JOR

    SUBTOTAL DE MANO DE OBRA $1,708.79 ACERODESTAJO MAXIMO $987.74 ZAPATA (VARILLA DEL No. 3)

    HORA $54.58 / 0.5125 $106.50 L=2.00 MTS / 0.15 MTS14.00 x 2.00 MTS x 2 SENTIDOS x 2 LECHOS

    SUBTOTAL DE MAQUINARIA Y EQUIPO $106.50 112.00 ML x 0.557 KG/ML + 5% DESPERDICIO65.50 KG/1000 KG

    % $1,708.79 * 0.03 $51.26% $1,708.79 * 0.02 $34.18 DADO (VARILLA DEL No. 6)

    SUBTOTAL DE HERRAMIENTA DE MANO Y EQUIPO DE SEGURIDAD $85.44 LONG. VARILLA = 1.60 MTS (dado)+0.20MTS(zapata)+1.00MT (escuadra)LONG. VARILLA =

    M3 $1,246.21 * 1.22 $1,520.37 2.80 ML x 8.00 x 2.25 KG/ML

    50.40 KG + 5% DESPERDICIOSUBTOTAL DE BASICOS DE MATERIALES $1,520.37 52.92 KG / 1000 KG

    COSTO DIRECTO $5,475.82 DADO (VARILLA DEL No. 3)% DE INDIRECTOS 17.4934% $957.91 LONG. ESTRIBOS = 0.46 MTS x 4 LADOS

    SUBTOTAL 1 $6,433.73 ALTURA DADO= 1.60 MTS / 0.12 MTS SEPARACION% DE FINANCIAMIENTO 0.3543% $22.79 14.00 x 1.84 ML x 0.557 KG/ML + 5% DESPERDICIO

    SUBTOTAL 2 $6,456.52 15.07 KG/1000 KG% DE UTILIDAD 10.0000% $645.65

    SUBTOTAL 3 $7,102.17 TOTALES(Aportacion a la SFP Secretaria de la Funcion Publica = 5 al millar) % CARGOS ADICIONALES 0.5000% $35.51 #3 = 0.066 TON + 0.015 TON

  • PRECIO UNITARIO $7,137.68 #6 = 0.053 TON

    CIMBRAZAPATA = 2.00 MTS x 0.20 MTS x 4 LADOSDADO = 0.50 MTS x 1.60 MTS x 4 LADOS

    1 PT = LARGO EN PULGADAS x ANCHO EN PULGADAS x ALTURA EN PIE / 12

    CETES PT DE POLIN = 4" x 4" x 8' / 122.80%0.23%1.05% financiando los 4.5 meses0.82% se estarian financiando 3.5 mes KG DE ALAMBRE x TON DE ACERO ARMADO0.23% se estraria financiando 1 solo mes PARA VARILLA DEL No. 2.5 Y 3

    PARA VARILLA DEL No. 4 Y 6PARA VARILLA DEL No. 6 EN ADELANTE

  • CUANTIFICACION

    ZAPATA = 2.00 MTS x 2.00 MTS x 0.20 MTS 0.80 M3DADO = 0.50 MTS x 0.50 MTS x 1.60 MTS 0.40 M3TOTAL = 0.80 M3 + 0.40 M3 + 2% DESPERDICIO 1.22 M3

    CALCULO RENDIMIENTO PARA CUADRILLA DE 1 OF. ALBAIL + 5 AYUD. ALBAIL1.22 M3 DE CONCRETO = 1220.00 LTS1,220.00 LTS DE CONCRETO = 64.21 BOTES65.00 BOTES / 5 AYUDANTES 13.00 VUELTAS13 VUELTAS x 50 SEGUNDOS 650.00 SEGUNDOS650.00 SEGUNDOS / 60 SEG 10.83 MINUTOSTIEMPO PARA VIBRADO 10.00 MINUTOSNIVELADO Y EMPAREJADO 10.00 MINUTOSVACIADO DE CONCRETO 15.00 MINUTOSCOLADO DE ZAPATA 45.83 MINUTOSRENDIMIENTO = 8.00 HRS / 0.50 HRS 10.67 ZAPATAS

    RENDIMIENTO EN CONDICIONES NORMALES DE EJECUCION (BASE DE DATOS NEODATA)

    ZAPATA (VARILLA DEL No. 3)L=2.00 MTS / 0.15 MTS 13 14.00 14.00 x 2.00 MTS x 2 SENTIDOS x 2 LECHOS 112.00 ML112.00 ML x 0.557 KG/ML + 5% DESPERDICIO 65.50 KG65.50 KG/1000 KG 0.066 TON

    DADO (VARILLA DEL No. 6)LONG. VARILLA = 1.60 MTS (dado)+0.20MTS(zapata)+1.00MT (escuadra)LONG. VARILLA = 2.80 ML2.80 ML x 8.00 x 2.25 KG/ML 50.40 KG

    50.40 KG + 5% DESPERDICIO 52.92 KG52.92 KG / 1000 KG 0.053 TON

    DADO (VARILLA DEL No. 3)LONG. ESTRIBOS = 0.46 MTS x 4 LADOS 1.84 MLALTURA DADO= 1.60 MTS / 0.12 MTS SEPARACION 13.33 14.00 14.00 x 1.84 ML x 0.557 KG/ML + 5% DESPERDICIO 15.07 KG15.07 KG/1000 KG 0.015 TON

    #3 = 0.066 TON + 0.015 TON 0.081 TON

  • #6 = 0.053 TON 0.053 TONTOTAL 0.133 TON

    ZAPATA = 2.00 MTS x 0.20 MTS x 4 LADOS 1.60 M2DADO = 0.50 MTS x 1.60 MTS x 4 LADOS 3.20 M2

    TOTAL 4.80 M2

    1 PT = LARGO EN PULGADAS x ANCHO EN PULGADAS x ALTURA EN PIE / 12

    PT DE POLIN = 4" x 4" x 8' / 12 10.66666667 PT$8.00

    $85.33

    KG DE ALAMBRE x TON DE ACERO ARMADOPARA VARILLA DEL No. 2.5 Y 3 50 KG ALAMBRE / TONPARA VARILLA DEL No. 4 Y 6 40 KG ALAMBRE / TONPARA VARILLA DEL No. 6 EN ADELANTE 30 KG ALAMBRE / TON

  • 75 PZAS / KG CLAVOS DE 4"249 PZAS / KG CLAVOS DE 2 1/2"

  • ANALISIS, CALCULO E INTEGRACION DE CUADRILLAS

    CLAVE CONCEPTOMO1A1AA CUADRILLA DE 1 OFICIAL ALBAIL + 5 AYUDANTES DE ALBAIL + CABO DE OFICIOS

    CLAVE DESCRIPCION UNIDADSn=SALARIO TABULADO

    MOALB OFICIAL ALBAIL JORNADAMOAYUA AYUDANTE DE ALBAIL JORNADAMOCAB CABO DE OFICIOS JORNADA

    SUBTOTAL DE MANO DE OBRA

    CLAVE CONCEPTOMO1F1AF CUADRILLA DE 1 OFICIAL FIERRERO + 1 AYUDANTE DE FIERRERO + CABO DE OFICIOS

    CLAVE DESCRIPCION UNIDADSn=SALARIO TABULADO

    MOFIE OFICIAL FIERRERO JORNADAMOAYUF AYUDANTE DE FIERRERO JORNADAMOCAB CABO DE OFICIOS JORNADA

    SUBTOTAL DE MANO DE OBRA

    CLAVE CONCEPTOMO1C1AC CUADRILLA DE 1 OFICIAL CARPINTERO DE OBRA NEGRA + 1 AYUDANTE DE CARPINTERO DE OBRA NEGRA

    CLAVE DESCRIPCION UNIDADSn=SALARIO TABULADO

    MOCAR CARPINTERO DE OBRA NEGRA JORNADAMOAYUC AYUDANTE DE CARPINTERO DE OBRA NEGRA JORNADAMOCAB CABO DE OFICIOS JORNADA

    SUBTOTAL DE MANO DE OBRA

    OFICIAL ALBAIL

    SALARIO DE ACUERDO A LA COMISION NACIONAL DE SALARIOS MINIMOS (Sala

    SALARIO DE ACUERDO A TABULADORES DE SINDICATOS (Contrato Colectivo)

    Sn = SALARIO TABULADO

    MANO DE OBRA (ART. 190 RLOPSRM)

    MANO DE OBRA (ART. 190 RLOPSRM)

    MANO DE OBRA (ART. 190 RLOPSRM)

  • ANALISIS, CALCULO E INTEGRACION DE CUADRILLAS

    UNIDAD CLAVECUADRILLA DE 1 OFICIAL ALBAIL + 5 AYUDANTES DE ALBAIL + CABO DE OFICIOS JORNADA MO1A1AA

    COSTO CANTIDAD IMPORTE CLAVESn=SALARIO TABULADO

    $314.29 * 1.00 $314.29 MOALB$171.43 * 1.00 $171.43 MOAYUA$357.14 * 0.10 $35.71 MOCAB

    SUBTOTAL DE MANO DE OBRA $521.43

    UNIDAD CLAVECUADRILLA DE 1 OFICIAL FIERRERO + 1 AYUDANTE DE FIERRERO + CABO DE OFICIOS JORNADA MO1F1AF

    COSTO CANTIDAD IMPORTE CLAVESn=SALARIO TABULADO

    $342.86 * 1.00 $342.86 MOFIE$200.00 * 1.00 $200.00 MOAYUF$357.14 * 0.10 $35.71 MOCAB

    SUBTOTAL DE MANO DE OBRA $578.57

    UNIDAD CLAVECUADRILLA DE 1 OFICIAL CARPINTERO DE OBRA NEGRA + 1 AYUDANTE DE CARPINTERO DE OBRA NEGRA JORNADA MO1C1AC

    COSTO CANTIDAD IMPORTE CLAVESn=SALARIO TABULADO

    $342.86 * 1.00 $342.86 MOCAR$200.00 * 1.00 $200.00 MOAYUC$357.14 * 0.10 $35.71 MOCAB

    SUBTOTAL DE MANO DE OBRA $578.57

    JOR SEMANA CLAVEMO1A2AA

    $98.05 $686.35CLAVE

    $180.00 $1,260.00MOALB

    $314.29 $2,200.03 MOAYUAMOCAB

  • ANALISIS, CALCULO E INTEGRACION DE CUADRILLAS

    CONCEPTOCUADRILLA DE 1 OFICIAL ALBAIL + 5 AYUDANTES DE ALBAIL + CABO DE OFICIOS

    DESCRIPCION UNIDAD COSTOSr=SALARIO REAL

    OFICIAL ALBAIL JORNADA $539.85 *AYUDANTE DE ALBAIL JORNADA $300.92 *CABO DE OFICIOS JORNADA $611.64 *

    SUBTOTAL DE MANO DE OBRA

    CONCEPTOCUADRILLA DE 1 OFICIAL FIERRERO + 1 AYUDANTE DE FIERRERO + CABO DE OFICIOS

    DESCRIPCION UNIDAD COSTOSr=SALARIO REAL

    OFICIAL FIERRERO JORNADA $587.71 *AYUDANTE DE FIERRERO JORNADA $348.36 *CABO DE OFICIOS JORNADA $611.64 *

    SUBTOTAL DE MANO DE OBRA

    CONCEPTOCUADRILLA DE 1 OFICIAL CARPINTERO DE OBRA NEGRA + 1 AYUDANTE DE CARPINTERO DE OBRA NEG

    DESCRIPCION UNIDAD COSTOSr=SALARIO REAL

    CARPINTERO DE OBRA NEGRA JORNADA $587.71 *AYUDANTE DE CARPINTERO DE OBRA NEGRA JORNADA $348.36 *CABO DE OFICIOS JORNADA $611.64 *

    SUBTOTAL DE MANO DE OBRA

    CONCEPTOCUADRILLA DE 1 OFICIAL ALBAIL + 2 AYUDANTES DE ALBAIL + CABO DE OFICIOS

    DESCRIPCION UNIDAD COSTOSr=SALARIO REAL

    OFICIAL ALBAIL JORNADA $539.85 *AYUDANTE DE ALBAIL JORNADA $300.92 *CABO DE OFICIOS JORNADA $611.64 *

    SUBTOTAL DE MANO DE OBRA

    MANO DE OBRA (ART. 190 RLOPSRM)

    MANO DE OBRA (ART. 190 RLOPSRM)

    MANO DE OBRA (ART. 190 RLOPSRM)

    MANO DE OBRA (ART. 190 RLOPSRM)

  • UNIDADJORNADA

    CANTIDAD IMPORTE

    1.00 $539.855.00 $1,504.600.10 $61.16

    SUBTOTAL DE MANO DE OBRA $2,105.61

    UNIDADJORNADA

    CANTIDAD IMPORTE

    1.00 $587.711.00 $348.360.10 $61.16

    SUBTOTAL DE MANO DE OBRA $997.24

    UNIDADCUADRILLA DE 1 OFICIAL CARPINTERO DE OBRA NEGRA + 1 AYUDANTE DE CARPINTERO DE OBRA NEG JORNADA

    CANTIDAD IMPORTE

    1.00 $587.711.00 $348.360.10 $61.16

    SUBTOTAL DE MANO DE OBRA $997.24

    UNIDADJORNADA

    CANTIDAD IMPORTE

    1.00 $539.852.00 $601.840.10 $61.16

    SUBTOTAL DE MANO DE OBRA $1,202.85

  • se deber entender al factor de salario real Fsrcomo la relacin de los das realmente pagados en un periodo anual, de enero a diciembre, divididosentre los das efectivamente laborados durante el mismo periodo, de acuerdo con la siguiente expresin:

    FSR = [ Ps ( Tp / Tl ) ] + ( Tp / Tl )

    Donde:Fsr Representa el factor de salario real.Ps Representa, en fraccin decimal, las obligaciones obrero-patronales derivadas de la Ley delSeguro Social y de la Ley del Instituto del Fondo Nacional de la Vivienda para losTrabajadores.Tp Representa los das realmente pagados durante un periodo anual.Tl Representa los das realmente laborados durante el mismo periodo anual utilizado en Tp.

    CALCULO DE LA VARIABLE "Tl" (DIAS REALMENTE LABORADOS DURANTE EL PERIODO ANUAL)

    DIAS CALENDARIOMENOS DIAS NO LABORADOS AL AO

    DIAS POR COSTUMBREDIAS POR CLIMA (LLUVIAS)DIAS POR SINDICATO (de acuerdo al Contrato Colectivo)DIAS POR PERMISO Y ENFERMEDAD NO PROFESIONALDIAS EQUIVALENTES POR ARRASTREDIAS POR GUARDIA (contratos pemex (plataformas))

    TOTAL DIAS NO LABORADOS AL AO

    "Tl" = DIAS CALENDARIO - TOTAL DIAS NO LABORADOS AL AO

    CALCULO DE LA VARIABLE "Tp" ( DIAS REALMENTE PAGADOS EN UN PERIODO ANUAL)

    DIAS CALENDARIO

    HORAS EXTRAS (PARA TRABAJOS DE EMERGENCIA)TOTAL DE DIAS PAGADOS EN UN PERIODO ANUAL

    CALCULO DE LA VARIABLE "Ps" (OBLIGACIONES OBRERO-PATRONALES DERIVADAS DE LA LEY DEL IMSS E INFONAVIT)

    PARA APLICAR ESTAS OBLIGACIONES O PRESTACIONES DEL IMSS E INFONAVIT SE DEBE CALCULAR UN SALARIO BASE DE COTIZACION

    ANALISIS, CALCULO E INTEGRACION DEL FACTOR DE SALARIO REAL (ART. 191 RLOPSRM)

    DIAS DE DESCANSO OBLIGATORIO (Domingos) (ART. 69 LFT)DIAS FESTIVOS POR LEY (ART. 74 LFT)DIAS LUNES POR LEY (ART. 74 LFT)VACACIONES (ART. 76 LFT)

    AGUINALDO (ART. 87 LFT)PRIMA VACACIONAL (ART. 80 LFT) (25% DE 6 DIAS DE VACACIONES)

  • SALARIO BASE DE COTIZACION (SBC) = SALARIO TABULADO (Sn) x FACTOR SALARIO BASE DE COTIZACION (FSBC)FSBC = DIAS REALMENTE PAGADOS EN UN PERIODO ANUAL / DIAS CALENDARIOFSBC = 381.50 DIAS / 365.00 DIAS

    SALARIO MINIMO GENERAL VIGENTE DEL DF (SMGVDF) $67.293 VECES EL SALARIO MINIMO GENERAL VIGENTE DEL DF (3VSMGVDF) $201.87

    CATEGORIA

    A B C DSn FSBC SBC

    Sn x FSBCB x C

    OFICIAL ALBAIL $314.29 1.0452 $328.50AYUDANTE DE ALBAIL $171.43 1.0452 $179.18CABO DE OFICIOS $357.14 1.0452 $373.28OFICIAL FIERRERO $342.86 1.0452 $358.36AYUADNTE DE FIERRERO $200.00 1.0452 $209.04OFICIAL CARPINTERO DE O. N. $342.86 1.0452 $358.36AYUDANTE DE CARPINTERO DE O. N. $200.00 1.0452 $209.04OPERADOR DE REVOLVEDORA $190.00 1.0452 $198.59

    El salario base de cotizacin se integra con los pagos hechos en efectivo por cuotadiaria, gratificaciones, percepciones, alimentacin, habitacin, primas, comisiones, prestaciones enespecie y cualquiera otra cantidad o prestacin que se entregue al trabajador por su trabajo

    El rgimen obligatorio comprende los seguros de:I. Riesgos de trabajo;II. Enfermedades y maternidad;III. Invalidez y vida;IV. Retiro, cesanta en edad avanzada y vejez, yV. Guarderas y prestaciones sociales.

    ART. 106 FRACC. I LEY DEL IMSSCUOTA FIJA 13.90%

    CADA AO AUMENTA 0.65%

    1998 13.90%1999 14.55%2000 15.20%

    SALARIO TABULADO

    FACTOR DE SALARIO BASE DE

    COTIZACION

    SALARIO BASE DE

    COTIZACION

    SALARIO BASE DE COTIZACION : (Artculo 27 LEY DEL IMSS)

    PRESTACIONES OBLIGATORIAS PARA INCLUIR EN EL CALCULO Artculo 11 LEY DEL IMSS

  • 2001 15.85%2002 16.50%2003 17.15%2004 17.80%2005 18.45%2006 19.10%2007 19.75%2008 20.40%

    2009 20.40%2010 20.40%2011 20.40%2012 20.40%2013 20.40%2014 20.40%

    ART. DECIMONOVENO

    TRANSITORIOLEY DEL

    IMSS

    ART. SEGUNDOTRANSITORIO

    LEY DELIMSS

  • como la relacin de los das realmente pagados en un periodo anual, de enero a diciembre, divididosentre los das efectivamente laborados durante el mismo periodo, de acuerdo con la siguiente expresin:

    FSR = [ Ps ( Tp / Tl ) ] + ( Tp / Tl )

    Ps Representa, en fraccin decimal, las obligaciones obrero-patronales derivadas de la Ley del

    Tl Representa los das realmente laborados durante el mismo periodo anual utilizado en Tp.

    CALCULO DE LA VARIABLE "Tl" (DIAS REALMENTE LABORADOS DURANTE EL PERIODO ANUAL)AO 2014

    365.00

    52.004.00 1 ENERO, 1 MAYO, 16 SEPTIEMBRE, 25 DICIEMBRE3.00 1er lunes FEBRERO, 3er lunes MARZO, 3er lunes NOVIEMBRE6.002.00 VIERNES SANTO, 12 DICIEMBRE, 3 DE MAYO, 2 NOVIEMBRE4.000.000.000.000.00

    TOTAL DIAS NO LABORADOS AL AO 71.00

    294.00 "Tl"

    CALCULO DE LA VARIABLE "Tp" ( DIAS REALMENTE PAGADOS EN UN PERIODO ANUAL)

    365.0015.001.500.00

    TOTAL DE DIAS PAGADOS EN UN PERIODO ANUAL 381.50 "Tp"

    CALCULO DE LA VARIABLE "Ps" (OBLIGACIONES OBRERO-PATRONALES DERIVADAS DE LA LEY DEL IMSS E INFONAVIT)

    PARA APLICAR ESTAS OBLIGACIONES O PRESTACIONES DEL IMSS E INFONAVIT SE DEBE CALCULAR UN SALARIO BASE DE COTIZACION

    (ART. 191 RLOPSRM)

  • SALARIO BASE DE COTIZACION (SBC) = SALARIO TABULADO (Sn) x FACTOR SALARIO BASE DE COTIZACION (FSBC)

    1.0452 FSBC

    CUOTA FIJA

    E F G H I J1.50% 20.40% 0.95% 1.425% 2.375%

    SBC-3VSMGDFF x E G x SMGVDG H x D I x D J x D

    $126.63 $1.90 $13.73 $3.12 $4.68 $7.80$13.73 $1.70 $2.55 $4.26

    $171.41 $2.57 $13.73 $3.55 $5.32 $8.87$156.49 $2.35 $13.73 $3.40 $5.11 $8.51

    $7.17 $0.11 $13.73 $1.99 $2.98 $4.96$156.49 $2.35 $13.73 $3.40 $5.11 $8.51

    $7.17 $0.11 $13.73 $1.99 $2.98 $4.96$13.73 $1.89 $2.83 $4.72

    El salario base de cotizacin se integra con los pagos hechos en efectivo por cuotadiaria, gratificaciones, percepciones, alimentacin, habitacin, primas, comisiones, prestaciones enespecie y cualquiera otra cantidad o prestacin que se entregue al trabajador por su trabajo

    ART. 106 FRACC. II LEY DEL IMSSEXCEDENTE DE 3 VECES SALARIO MINIMO 8.00%

    CADA AO REDUCE 0.65%

    1998 8.00%1999 7.35%2000 6.70%

    ART. 106 FRACC. II LEY DEL IMSS

    ART. 106 FRACC. I LEY

    DEL IMSSART. 107 FRACC. I Y II LEY DEL IMSS

    ART. 25 PARRAFO II LEY

    DEL IMSSART. 147 LEY

    DEL IMSS

    EXCEDENTE DE 3 VECES EL SALARIO

    MINIMO GENERAL DEL D.F.

    % AL EXCEDENTE DE 3 VECES EL SALARIO

    MINIMO GENERAL DEL D.F.

    PRESTACIONES EN DINERO

    PRESTACIONES EN ESPECIE DE

    LOS PENSIONADOS

    INVALIDEZ Y VIDA

    Artculo 11 LEY DEL IMSS

  • 2001 6.05%2002 5.40%2003 4.75%2004 4.10%2005 3.45%2006 2.80%2007 2.15%2008 1.50%

    2009 1.50%2010 1.50%2011 1.50%2012 1.50%2013 1.50%2014 1.50%

    ART. DECIMONOVENO

    TRANSITORIOLEY DEL

    IMSS

    ART. SEGUNDOTRANSITORIO

    LEY DELIMSS

  • 1er lunes FEBRERO, 3er lunes MARZO, 3er lunes NOVIEMBRE

  • GUARDERIAS

    K L M N O P4.275% 1.00% 7.58875% 2.00% 5.00% 3.00%

    K x D L x D M x D N x D O x D P x D

    $14.04 $3.28 $24.93 $6.57 $16.42 $9.85$7.66 $1.79 $13.60 $3.58 $8.96 $5.38

    $15.96 $3.73 $28.33 $7.47 $18.66 $11.20$15.32 $3.58 $27.19 $7.17 $17.92 $10.75$8.94 $2.09 $15.86 $4.18 $10.45 $6.27

    $15.32 $3.58 $27.19 $7.17 $17.92 $10.75$8.94 $2.09 $15.86 $4.18 $10.45 $6.27$8.49 $1.99 $15.07 $3.97 $9.93 $5.96

    ART. 168 FRACC. II LEY

    DEL IMSSART. 211 Y 212 LEY DEL IMSS

    ART. 73 Y 74 LEY DEL IMSS

    ART. 168 FRACC. I LEY

    DEL IMSS

    ART. 29 FRACC. II LEY DEL

    INFONATVITART. 158 CODIGO FISCAL DEL DF

    CESANTIA EN EDAD

    AVANZADA Y VEJEZ

    RIESGO DE TRABAJO

    SISTEMA DE AHORRO PARA

    EL RETIRO (SAR)

    INSTITUTO DEL FONDO NACIONAL

    PARA LA VIVIENDA DE LOS TRABAJADORES

    IMPUESTO SOBRE NOMINA

  • Ps EN FACTOR Ps ( Tp / Tl )

    Q R S T U VPs Ps / SBC FSI FSR Sn x FSR

    SUMA F:P Q / D R x S T + S

    $106.34 0.3237 1.2976 0.4200 1.7177 $539.85$63.21 0.3527 1.2976 0.4577 1.7554 $300.92$119.38 0.3198 1.2976 0.4150 1.7126 $611.64$115.03 0.3210 1.2976 0.4165 1.7141 $587.71$71.56 0.3423 1.2976 0.4442 1.7418 $348.36$115.03 0.3210 1.2976 0.4165 1.7141 $587.71$71.56 0.3423 1.2976 0.4442 1.7418 $348.36$68.57 0.3453 1.2976 0.4480 1.7456 $331.67

    $730.66 1.98$3,653.32

    135.00$493,197.65

    SUMA DE PRESTACIONES

    Tp / Tl = FACTOR DE SALARIO

    INTEGRADO

    FSR = [ Ps ( Tp / Tl ) ] + ( Tp / Tl )

    SALARIO REAL

  • ANALISIS, CALCULO E INTEGRACION DEL PRECIO UNITARIO

    CLAVEMACON250

    CLAVE

    MACEMMAGRAMAAREMAAGU

    MO1A2AA

    EQREV

    HEREQS

  • ANALISIS, CALCULO E INTEGRACION DEL PRECIO UNITARIO

    CONCEPTOCONCRETO F'C=250 KG/CM2 HECHO EN OBRA CON REVOLVEDORA DE 1 SACO (8HP), AGREGADO MAXIMO DE 3/4"

    DESCRIPCION

    CEMENTO GRIS PORTLAND TIPO II PUZOLANICOGRAVA DE MINA T.M.A. 19 MM (3/4), M3ARENA DE MINAAGUA DE PIPA

    CUADRILLA DE 1 OFICIAL ALBAIL + 2 AYUDANTES DE ALBAIL + CABO DE OFICIOS

    MAQUINARIA Y EQUIPOREVOLVEDORA PARA CONCRETO DE 1 SACO (8 HP)

    HERRAMIENTA DE MANO Y EQUIPO DE SEGURIDADHERRAMIENTA DE MANOEQUIPO DE SEGURIDAD

    SUBTOTAL DE HERRAMIENTA DE MANO Y EQUIPO DE SEGURIDAD

    MANO DE OBRA (ART. 190 RLOPSRM)

    BASICOS DE MATERIALES (ART. 193 RLOPSRM) (Materiales fabricados en sitio)

  • UNIDADCONCRETO F'C=250 KG/CM2 HECHO EN OBRA CON REVOLVEDORA DE 1 SACO (8HP), AGREGADO MAXIMO DE 3/4" M3

    UNIDAD COSTO CANTIDAD IMPORTE

    TON $1,900.00 * 0.39 $741.00M3 $242.90 * 0.63 $153.03M3 $228.60 * 0.53 $121.16M3 $60.00 * 0.21 $12.60

    SUBTOTAL DE MATERIALES $1,027.79

    JORNADA $1,202.85 / 8.00 $150.36

    SUBTOTAL DE MANO DE OBRA $150.36DESTAJO MAXIMO $86.91

    HORA $60.55 / 1.00 $60.55

    SUBTOTAL DE MAQUINARIA Y EQUIPO $60.55

    % $150.36 * 0.03 $4.51% $150.36 * 0.02 $3.01

    SUBTOTAL DE HERRAMIENTA DE MANO Y EQUIPO DE SEGURIDAD $7.52

    SUBTOTAL DE BASICOS DE MATERIALES

    COSTO DIRECTO $1,246.21

  • ANALISIS, CALCULO E INTEGRACION DEL COSTO HORARIO

    COSTO HORARIO COSTO POR HORA EFECTIVA DE TRABAJO DE LA UTILIZACION Y MANEJO DEUNA MAQUINA O EQUIPO CONSIDERADOS COMO NUEVOS

    DEPRECIACIONCOSTOS INVERSIONFIJOS SEGUROS

    MANTENIMIENTO

    COSTO COMBUSTIBLESHORARIO COSTOS POR LUBRICANTES OTROS CONSUMOS

    CONSUMO LLANTAS OTRAS FUENTES DE ENERGIA (Energia electrica)PIEZAS ESPECIALES

    COSTOS POR SALARIOS DEOPERACIN OPERACIN

    CLAVE DESCRIPCIONEQREV REVOLVEDORA PARA CONCRETO DE 1 SACO

    DATOS GENERALESVALOR DE ADQUISICION $10,500.00 POTENCIA DEL MOTOR EN HPPn=VALOR DE LAS LLANTAS (JGO) $1,000.00 % DE OPERACINVm=VALOR DE LA MAQUINA $9,500.00 COEFICIENTE DE CONSUMO (Gasolina)Hea=HORAS TRABAJADAS POR AO 2,000.00 Pc=PRECIO DE COMBUSTIBLE (Gasolina)Ve=VIDA ECONOMICA EN HORAS 10,000.00 COEFICIENTE DE CONSUMO (Aceite)% DE RESCATE 20.00% CAPACIDAD DEL CARTER EN LTSVr=VALOR DE RESCATE $2,100.00 HORAS ENTRE CAMBIOS SUCESIVOSi=TASA DE INTERES ANUAL 2.80% Pa=PRECIO DEL ACEITE (Motor gasolina)INDICADOR ECONOMICO ESPECIFICO CETES Vn=VIDA ECONOMICA DE LLANTAS EN HRSs=PRIMA ANUAL PROMEDIO DE SEGUROS 6.00% Sr= SALARIO REAL DEL OPERADOR DE REVOLVEDORAKo=COEFICIENTE DE MANTENIMIENTO 0.55 Ht=HORAS EFECTIVAS DE TRABAJO

    D = ( Vm - Vr ) / VeD = ( $9,500.00 - $2,100.00 ) / 10,000.00 HRS

    Im = [ ( Vm + Vr ) i ] / ( 2 x Hea )Im = [ ( $9,500.00 + $2,100.00 ) 2.80% ] / ( 2 x 2,000.00 )

    Sm = [ ( Vm + Vr ) s ] / ( 2 x Hea )

    COSTOS FIJOS (ART. 195 RLOPSRM)DEPRECIACION (ART. 196 RLOPSRM)

    INVERSION (ART. 197 RLOPSRM)

    SEGUROS (ART. 198 RLOPSRM)

  • Sm = [ ( $9,500.00 + $2,100.00 ) 6.00% ] / ( 2 x 2,000.00 )

    Mn = Ko x DMn = 0.55 x $ 0.74

    TOTAL COSTOS FIJOS

    Co = Gh x PcGh = POTENCIA NOMINAL DEL MOTOR EN HP x % DE OPERACIN x COEFICIENTE DE CONSUMO (Gasolina)Gh = 8.00 HP x 80.00% x 0.2271 1.45 LTS/HRCo = 1.45 LTS/HR x $11.09

    Lb = ( Ah + Ga ) PaAh = POTENCIA NOMINAL DEL MOTOR EN HP x % DE OPERACIN x COEFICIENTE DE CONSUMO (Aceite)Ga = CAPACIDAD DEL CARTER EN LTS / HORAS ENTRE CAMBIOS SUCESIVOSAh = 8.00 HP x 80.00% x 0.003 0.019 LTS/HRGa = 2.00 LTS / 350.00 HRS 0.006 LTS/HRLb = ( 0.019 LTS/HR + 0.006 LTS/HR ) $55.00

    N = Pn / VnN = $1,000.00 / 5,000.00 HRS

    TOTAL COSTOS POR CONSUMO

    Po = Sr / HtPo = $331.67 / 8.00 HRS

    TOTAL COSTOS POR OPERACIN

    TOTAL COSTO HORARIO

    MANTENIMIENTO (ART. 199 RLOPSRM)

    COSTOS POR CONSUMOS (ART. 200 RLOPSRM)COMBUSTIBLES (ART. 201 RLOPSRM)

    LUBRICANTES (ART. 203 RLOPSRM)

    LLANTAS (ART. 204 RLOPSRM)

    COTSOS POR OPERACIN (ART. 206 RLOPSRM)OPERACIN (ART. 206 RLOPSRM)

  • COSTO POR HORA EFECTIVA DE TRABAJO DE LA UTILIZACION Y MANEJO DEUNA MAQUINA O EQUIPO CONSIDERADOS COMO NUEVOS

    OTRAS FUENTES DE ENERGIA (Energia electrica)

    UNIDADHORA

    POTENCIA DEL MOTOR EN HP 8.0080.00%

    COEFICIENTE DE CONSUMO (Gasolina) 0.2271Pc=PRECIO DE COMBUSTIBLE (Gasolina) $11.09COEFICIENTE DE CONSUMO (Aceite) 0.003CAPACIDAD DEL CARTER EN LTS 2.00HORAS ENTRE CAMBIOS SUCESIVOS 350.00Pa=PRECIO DEL ACEITE (Motor gasolina) $55.00Vn=VIDA ECONOMICA DE LLANTAS EN HRS 5,000.00Sr= SALARIO REAL DEL OPERADOR DE REVOLVEDORA $331.67 Sn= $ 190.00Ht=HORAS EFECTIVAS DE TRABAJO 8.00

    $0.74 10,000.00 $7,400.00$2,100.00$9,500.00

    $0.08 10,000.00 $812.00

  • $0.17 10,000.00 $1,740.00

    $0.41 10,000.00 $4,070.00

    TOTAL COSTOS FIJOS $1.40

    $400.00 POR SERVICIOS$800.00 POR 2 SERVICIOS AL AO

    $4,000.00 POR SERVICIOS EN 5 AOSGh = POTENCIA NOMINAL DEL MOTOR EN HP x % DE OPERACIN x COEFICIENTE DE CONSUMO (Gasolina)

    $16.12

    Ah = POTENCIA NOMINAL DEL MOTOR EN HP x % DE OPERACIN x COEFICIENTE DE CONSUMO (Aceite)

    $1.37

    $0.20

    TOTAL COSTOS POR CONSUMO $17.69

    $41.46TOTAL COSTOS POR OPERACIN $41.46

    TOTAL COSTO HORARIO $60.55

  • POR SERVICIOS EN 5 AOS

  • ANALISIS, CALCULO E INTEGRACION DEL COSTO HORARIO

    COSTO HORARIO COSTO POR HORA EFECTIVA DE TRABAJO DE LA UTILIZACION Y MANEJO DEUNA MAQUINA O EQUIPO CONSIDERADOS COMO NUEVOS

    DEPRECIACIONCOSTOS INVERSIONFIJOS SEGUROS

    MANTENIMIENTO

    COSTO COMBUSTIBLESHORARIO COSTOS POR LUBRICANTES OTROS CONSUMOS

    CONSUMO LLANTAS OTRAS FUENTES DE ENERGIA (Energia electrica)PIEZAS ESPECIALES

    COSTOS POR SALARIOS DEOPERACIN OPERACIN

    CLAVE DESCRIPCIONEQVIB VIBRADOR PARA CONCRETO

    DATOS GENERALESVALOR DE ADQUISICION $6,550.00 POTENCIA DEL MOTOR EN HPPn=VALOR DE LAS LLANTAS (JGO) $0.00 % DE OPERACINVm=VALOR DE LA MAQUINA $6,550.00 COEFICIENTE DE CONSUMO (Gasolina)Hea=HORAS TRABAJADAS POR AO 2,000.00 Pc=PRECIO DE COMBUSTIBLE (Gasolina)Ve=VIDA ECONOMICA EN HORAS 8,000.00 COEFICIENTE DE CONSUMO (Aceite)% DE RESCATE 10.00% CAPACIDAD DEL CARTER EN LTSVr=VALOR DE RESCATE $655.00 HORAS ENTRE CAMBIOS SUCESIVOSi=TASA DE INTERES ANUAL 2.80% Pa=PRECIO DEL ACEITE (Motor gasolina)INDICADOR ECONOMICO ESPECIFICO CETES Vn=VIDA ECONOMICA DE LLANTAS EN HRSs=PRIMA ANUAL PROMEDIO DE SEGUROS 6.00% Sr= SALARIO REAL DEL OPERADOR DE VIBRADORKo=COEFICIENTE DE MANTENIMIENTO 0.40 Ht=HORAS EFECTIVAS DE TRABAJO

    D = ( Vm - Vr ) / VeD = ( $9,500.00 - $2,100.00 ) / 10,000.00 HRS

    Im = [ ( Vm + Vr ) i ] / ( 2 x Hea )Im = [ ( $9,500.00 + $2,100.00 ) 2.80% ] / ( 2 x 2,000.00 )

    Sm = [ ( Vm + Vr ) s ] / ( 2 x Hea )

    COSTOS FIJOS (ART. 195 RLOPSRM)DEPRECIACION (ART. 196 RLOPSRM)

    INVERSION (ART. 197 RLOPSRM)

    SEGUROS (ART. 198 RLOPSRM)

  • Sm = [ ( $9,500.00 + $2,100.00 ) 6.00% ] / ( 2 x 2,000.00 )

    Mn = Ko x DMn = 0.55 x $ 0.74

    TOTAL COSTOS FIJOS

    Co = Gh x PcGh = POTENCIA NOMINAL DEL MOTOR EN HP x % DE OPERACIN x COEFICIENTE DE CONSUMO (Gasolina)Gh = 8.00 HP x 80.00% x 0.2271 1.00 LTS/HRCo = 1.45 LTS/HR x $11.09

    Lb = ( Ah + Ga ) PaAh = POTENCIA NOMINAL DEL MOTOR EN HP x % DE OPERACIN x COEFICIENTE DE CONSUMO (Aceite)Ga = CAPACIDAD DEL CARTER EN LTS / HORAS ENTRE CAMBIOS SUCESIVOSAh = 8.00 HP x 80.00% x 0.003 0.013 LTS/HRGa = 2.00 LTS / 350.00 HRS 0.002 LTS/HRLb = ( 0.019 LTS/HR + 0.006 LTS/HR ) $55.00

    N = Pn / VnN = $1,000.00 / 5,000.00 HRS

    TOTAL COSTOS POR CONSUMO

    Po = Sr / HtPo = $331.67 / 8.00 HRS

    TOTAL COSTOS POR OPERACIN

    TOTAL COSTO HORARIO

    MANTENIMIENTO (ART. 199 RLOPSRM)

    COSTOS POR CONSUMOS (ART. 200 RLOPSRM)COMBUSTIBLES (ART. 201 RLOPSRM)

    LUBRICANTES (ART. 203 RLOPSRM)

    LLANTAS (ART. 204 RLOPSRM)

    COTSOS POR OPERACIN (ART. 206 RLOPSRM)OPERACIN (ART. 206 RLOPSRM)

  • COSTO POR HORA EFECTIVA DE TRABAJO DE LA UTILIZACION Y MANEJO DEUNA MAQUINA O EQUIPO CONSIDERADOS COMO NUEVOS

    OTRAS FUENTES DE ENERGIA (Energia electrica)

    UNIDADHORA

    POTENCIA DEL MOTOR EN HP 5.5080.00%

    COEFICIENTE DE CONSUMO (Gasolina) 0.2271Pc=PRECIO DE COMBUSTIBLE (Gasolina) $11.09COEFICIENTE DE CONSUMO (Aceite) 0.003CAPACIDAD DEL CARTER EN LTS 0.80HORAS ENTRE CAMBIOS SUCESIVOS 350.00Pa=PRECIO DEL ACEITE (Motor gasolina) $55.00Vn=VIDA ECONOMICA DE LLANTAS EN HRS 0.00Sr= SALARIO REAL DEL OPERADOR DE VIBRADOR $331.67 Sn= $ 190.00Ht=HORAS EFECTIVAS DE TRABAJO 8.00

    $0.74 10,000.00 $7,368.75$2,100.00$9,468.75

    $0.05 10,000.00 $504.35

  • $0.11 10,000.00 $1,080.75

    $0.29 10,000.00 $2,947.50

    TOTAL COSTOS FIJOS $1.19

    $400.00 POR SERVICIOS$800.00 POR 2 SERVICIOS AL AO

    $4,000.00 POR SERVICIOS EN 5 AOSGh = POTENCIA NOMINAL DEL MOTOR EN HP x % DE OPERACIN x COEFICIENTE DE CONSUMO (Gasolina)

    $11.08

    Ah = POTENCIA NOMINAL DEL MOTOR EN HP x % DE OPERACIN x COEFICIENTE DE CONSUMO (Aceite)

    $0.85

    TOTAL COSTOS POR CONSUMO $11.93

    $41.46TOTAL COSTOS POR OPERACIN $41.46

    TOTAL COSTO HORARIO $54.58

  • POR SERVICIOS EN 5 AOS

  • ANALISIS, CALCULO E INTEGRACION DEL % DE INDIRECTOS

    GASTO x MES

    a) Personal directivo;b) Personal tcnico;c) Personal administrativo;

    a) Edificios y locales; $15,000.00b) Locales de mantenimiento y guarda;c) Bodegas; $5,000.00d) Instalaciones generales;e) Equipos, muebles y enseres; $1,071.43f) Depreciacin o renta, y operacin de vehculos, y $2,500.00g) Campamentos;

    III. Servicios de los siguientes conceptos:a) Consultores, asesores, servicios y laboratorios, yb) Estudios e investigaciones;

    IV. Fletes y acarreos de los siguientes conceptos:a) Campamentos;b) Equipo de construccin;c) Plantas y elementos para instalaciones, yd) Mobiliario;

    V. Gastos de oficina de los siguientes conceptos:a) Papelera y tiles de escritorio; $1,500.00

    $2,000.00c) Equipo de computacin; $3,000.00d) Situacin de fondos; $1,500.00e) Copias y duplicados; $500.00f) Luz, gas y otros consumos, y $2,000.00g) Gastos de la licitacin pblica;

    VI. Capacitacin y adiestramiento; $10,000.00

    VII. Seguridad e higiene; $8,000.00

    VIII. Seguros y fianzas, y

    IX. Trabajos previos y auxiliares de los siguientes conceptos:a) Construccin y conservacin de caminos de acceso;b) Montajes y desmantelamientos de equipo, y

    I. Honorarios, sueldos y prestaciones de los siguientes conceptos:

    d) Cuota patronal del seguro social y del Instituto del Fondo Nacional de la Vivienda para los Trabajadores;e) Prestaciones a que obliga la Ley Federal del Trabajo para el personal enunciado en los incisos a), b) y c) de esta fraccin;f) Pasajes y viticos del personal enunciado en los incisos a), b) y c) de esta fraccin, yg) Los que deriven de la suscripcin de contratos de trabajo para el personal enunciado en los incisos a), b) y c) de esta fraccin;II. Depreciacin, mantenimiento y rentas de los siguientes conceptos:

    b) Correo, fax, telfonos, telgrafos, radio y otros gastos de comunicaciones;

  • c) Construccin de las siguientes instalaciones generales:1. Campamentos;2. Equipo de construccin, y3. Plantas y elementos para instalaciones.

    POR LO GENERAL SE COBRAN EN UN 2 AL MILLAR SOBRE EL MONTO TOTAL DEL CONTRATO

  • % DE APLICACINNo. DE PERIODOS IMPORTE PORCENTAJE GASTO x MES

    $58,500.00 1.65%$31,950.00 0.90%$8,775.00 0.25%

    2.80%

    10.00% 4.50 $6,750.00 $10,000.00

    10.00% 4.50 $2,250.00 $500.00$250.00

    10.00% 4.50 $482.14 $1,690.4810.00% 4.50 $1,125.00 $2,916.67

    $9,000.00

    $1,800.00

    $350.00

    10.00% 4.50 $675.00 $500.0010.00% 4.50 $900.00 $1,200.0010.00% 4.50 $1,350.00 $1,500.0010.00% 4.50 $675.0010.00% 4.50 $225.00 $500.0010.00% 4.50 $900.00 $1,000.00

    $4,500.00

    10.00% 4.50 $4,500.00 $2,000.00

    10.00% 4.50 $3,600.00 $6,000.00

    GASTOS DE ADMINISTRACION DE OFICINA CENTRAL

  • SUBTOTALES $122,657.14

    GASTO TOTAL DE INDIRECTOS = SUBTOTAL GASTOS DE OFICINA CENTRAL + SUBTOTAL GASTOS DE OFICINA DE CAMPO

    % DE INDIRECTOS = GASTO TOTAL DE INDIRECTOS / COSTO DIRECTO TOTAL

    FIANZA DE CUMPLIMIENTO POR EL 10% DEL MONTO TOTAL DEL CONTRATOFIANZA DE ANTICIPO POR EL 100% DEL IMPORTE DEL ANTICIPO

    FIANZA DE CVICIOS OCULTOS POR EL 10% DEL MONTO TOTAL DEL CONTRATO

    POR LO GENERAL SE COBRAN EN UN 2 AL MILLAR SOBRE EL MONTO TOTAL DEL CONTRATO

    $4,627,137.29

    0.002

    $9,254.27 x 3 FIANZAS $27,762.82

  • COSTO DIRECTO TOTAL $3,549,802.42

    % DE APLICACIN No. DE PERIODOS IMPORTE PORCENTAJE

    $216,000.00 6.08%$67,500.00 1.90%

    7.99%

    100.00% 4.50 $45,000.00

    100.00% 4.50 $2,250.00100.00% 4.50 $1,125.00100.00% 4.50 $7,607.14100.00% 4.50 $13,125.00

    100.00% 4.50 $40,500.00

    100.00% 4.50 $8,100.00

    100.00% 4.50 $1,575.00

    100.00% 4.50 $2,250.00100.00% 4.50 $5,400.00100.00% 4.50 $6,750.00

    100.00% 4.50 $2,250.00100.00% 4.50 $4,500.00100.00% 4.50 $20,250.00

    100.00% 4.50 $9,000.00

    100.00% 4.50 $27,000.00

    $28,168.37

    GASTOS DE ADMINISTRACION DE OFICINA DE CAMPO

  • SUBTOTALES $508,350.51

    GASTO TOTAL DE INDIRECTOS = SUBTOTAL GASTOS DE OFICINA CENTRAL + SUBTOTAL GASTOS DE OFICINA DE CAMPO $631,007.66

    % DE INDIRECTOS = GASTO TOTAL DE INDIRECTOS / COSTO DIRECTO TOTAL 17.7759%

  • OFICINA DE CAMPOPERSONAL TECNICOCATEGORIA No. DE SALARIO POR % DE

    PERSONAS PERIODO PARTICIPACIONSUPERINTENDENTE 1.00 $30,000.00 100.00%AUX. DE SUPERINTENDENTE 1.00 $18,000.00 100.00%ANALISTA DE COSTOS 0.00 $16,000.00 100.00%

    PERSONAL ADMINISTRATIVOCATEGORIA No. DE SALARIO POR % DE

    PERSONAS PERIODO PARTICIPACIONCONTADOR 0.00 $8,000.00 100.00%SECRETARIA 0.00 $4,500.00 100.00%ALMACENISTA 1.00 $3,000.00 100.00%CHOFER 1.00 $5,000.00 100.00%VELADOR 1.00 $4,000.00 100.00%AUX. LIMPIEZA 1.00 $3,000.00 100.00%

    OFICINA DE CENTRALPERSONAL DIRECTIVOCATEGORIA No. DE SALARIO POR % DE

    PERSONAS PERIODO PARTICIPACIONDIRECTOR GENERAL 1.00 $50,000.00 10.00%GERENTE DE CONSTRUCCION 1.00 $40,000.00 10.00%GERENTE DE CONTROL 1.00 $40,000.00 10.00%

    PERSONAL TECNICOCATEGORIA No. DE SALARIO POR % DE

    PERSONAS PERIODO PARTICIPACIONJEFE DE COSTOS 1.00 $25,000.00 10.00%JEFE DE RECURSOS MATERIALES 1.00 $20,000.00 10.00%ANALISTA DE PRECIOS UNITARIOS 1.00 $16,000.00 10.00%CAPTURISTA DE DATOS 1.00 $10,000.00 10.00%

    PERSONAL ADMINISTRATIVOCATEGORIA No. DE SALARIO POR % DE

    PERSONAS PERIODO PARTICIPACIONCONTADOR 1.00 $8,000.00 10.00%SECRETARIA 1.00 $4,500.00 10.00%MENSAJERO 1.00 $4,000.00 10.00%AUX. LIMPIEZA 1.00 $3,000.00 10.00%

  • OBRA 1 $15,000,000.00 33.33%OBRA 2 $25,500,000.00 56.67%

    (ESTE PRESUPUESTO) OBRA 3 $4,500,000.00 10.00%

    TOTAL $45,000,000.00

  • No. DE IMPORTEPERIODOS

    4.50 $135,000.004.50 $81,000.004.50 $0.00

    TOTAL $216,000.00

    No. DE IMPORTEPERIODOS

    4.50 $0.004.50 $0.004.50 $13,500.004.50 $22,500.004.50 $18,000.004.50 $13,500.00

    TOTAL $67,500.00

    No. DE IMPORTEPERIODOS

    4.50 $22,500.004.50 $18,000.004.50 $18,000.00

    TOTAL $58,500.00

    No. DE IMPORTEPERIODOS

    4.50 $11,250.004.50 $9,000.004.50 $7,200.004.50 $4,500.00

    TOTAL $31,950.00

    No. DE IMPORTEPERIODOS

    4.50 $3,600.004.50 $2,025.004.50 $1,800.004.50 $1,350.00

    TOTAL $8,775.00

  • ANALISIS, CALCULO E INTEGRACION DEL % DE FINANCIAMIENTO

    COSTO DIRECTO TOTAL $3,549,802.42 TASA DE INTERES ANUAL% DE INDIRECTOS 17.7759% INDICADOR ECONOMICO ESPECIFICOCOSTO TOTAL DE INDIRECTOS $631,007.66 % DE ANTICIPOCOSTO DIRECTO + INDIRECTOS $4,180,810.07 MONTO DEL ANTICIPOMONTO TOTAL $4,627,137.29 DIAS DE PAGO PARA ESTIMACIONES (ART. 54 LOPSRM)PERIODO DE COBRO DE LA 1RA ESTIMACION 3 TASA DE INTERES APLICABLE AL CALCULO

    PERIODO ANTICIPO ESTIMACIONES

    $694,070.59 $694,070.59MES 1 $675,897.29MES 2 $1,045,507.17MES 3 $1,303,145.30 $675,897.29 $101,384.59 $574,512.69MES 4 $957,359.24 $1,045,507.17 $156,826.08 $888,681.09MES 5 $645,228.29 $1,303,145.30 $195,471.79 $1,107,673.50

    $957,359.24 $143,603.89 $813,755.35$645,228.29 $96,784.24 $548,444.05

    TOTALES $4,627,137.29 $694,070.59 $4,627,137.29

    % DE FINANCIAMIENTO = INTERES O FINANCIAMIENTO TOTAL / (COSTO DIRECTO + INDIRECTOS)

    POR LO TANTO SE APLICA AL PRECIO UNITARIO CON SIGNO INVERSO

    OBRA EJECUTADA

    AMORTIZACION DEL ANTICIPO

    INGRESO O COBRO (Importe

    total)

  • TASA DE INTERES ANUAL 2.80%INDICADOR ECONOMICO ESPECIFICO CETES

    15.00%MONTO DEL ANTICIPO $694,070.59DIAS DE PAGO PARA ESTIMACIONES (ART. 54 LOPSRM) 41TASA DE INTERES APLICABLE AL CALCULO 0.3145%

    $694,070.59 $694,070.59$610,701.18 ### $83,369.42$944,659.00 ### -$861,289.59 -$2,708.93

    $1,177,445.72 ### -$1,464,222.61 -$4,605.28$865,013.70 $23,667.39 -$1,440,555.22 -$4,530.84$582,990.47 $524,683.03 -$915,872.19 -$2,880.61

    $813,755.35 -$102,116.84 -$321.18$548,444.05 $446,327.21

    $4,180,810.07 -$15,046.84

    % DE FINANCIAMIENTO = INTERES O FINANCIAMIENTO TOTAL / (COSTO DIRECTO + INDIRECTOS) -0.3599%

    POR LO TANTO SE APLICA AL PRECIO UNITARIO CON SIGNO INVERSO 0.3599%

    EGRESO O GASTO

    (CD+IND)

    DIFERENCIA INGRESO-EGRESO

    DIFERENCIA ACUMULADA

    INTERES O FINANCIAMIENTO

    TOTAL

  • ANALISIS, CALCULO E INTEGRACION DEL % DE UTILIDADIMPORTE

    COSTO DIRECTO $3,549,802.42

    INDIRECTOS $631,007.66

    FINANCIAMIENTO $15,046.84

    SUBTOTAL $4,195,856.91

    UTILIDAD PROPUESTA

    ISR : IMPUESTP SOBRE LA RENTA

    PTU : PARTICIPACION DE LOS TRABAJADORES EN LA UTILIDAD DE LA EMPRESA

    UTILIDAD TOTAL EN PORCENTAJE = UTILIDAD PROPUESTA / (1- (ISR+PTU))

    IMPORTE DE UTILIDAD TOTAL = % UTILIDAD TOTAL x SUBTOTAL $419,585.69

  • PORCENTAJE

    17.7759%

    0.3599%

    6.0000%

    30.0000% LEY DEL IMPUESTO SOBRE LA RENTA ART. 9

    10.0000% ART. 117 LEY FEDERAL DEL TRABAJO

    10.0000%

  • ANALISIS, CALCULO E INTEGRACION DEL % DE CARGOS ADICIONALES

    COSTO DIRECTO $3,549,802.42

    INDIRECTOS $631,007.66

    FINANCIAMIENTO $15,046.84

    UTILIDAD $419,585.69

    SUBTOTAL $4,615,442.60

    Artculo 191. Por el servicio de vigilancia, inspeccin y control que las leyes de la materiaencomiendan a la Secretara de la Funcin Pblica, los contratistas con quienes se celebren contratos deobra pblica y de servicios relacionados con la misma, pagarn un derecho equivalente al cinco al millarsobre el importe de cada una de las estimaciones de trabajo.

    CARGOS ADICIONALES (CA) = ( SUBTOTAL / (1-0.005) ) - SUBTOTALCA = ( $ 4,678,461.98 / (0.995) ) - $ 4,678,461.98 $23,193.18

    % DE CARGOS ADICIONALES = CA / SUBTOTAL

    ESTE PORCENTAJE DE CARGOS ADICIONALES SOLO APLICA PARA PRESUPUESTOS A PRECIO UNITARIO DE OBRA PUBLICANUNCA PARA PRESUPUESTOS DE PARTICULARES U OBRA PRIVADA

  • 17.78%

    0.36%

    10.00%

    Artculo 191. Por el servicio de vigilancia, inspeccin y control que las leyes de la materiaencomiendan a la Secretara de la Funcin Pblica, los contratistas con quienes se celebren contratos deobra pblica y de servicios relacionados con la misma, pagarn un derecho equivalente al cinco al millar

    0.50%

    ESTE PORCENTAJE DE CARGOS ADICIONALES SOLO APLICA PARA PRESUPUESTOS A PRECIO UNITARIO DE OBRA PUBLICANUNCA PARA PRESUPUESTOS DE PARTICULARES U OBRA

    PRESUPUESTOPROGRAMA DE OBRAPRECIO UNITARIOCUADRILLASFASARBASICO CONCRETOCOSTO HORARIO REVOLVEDORACOSTO HORARIO VIBRADORINDIRECTOSFINANCIAMIENTOUTILIDADCARGOS ADICIONALES