CRONOGRAMA DE AVANCE DE OBRA VALORIZADO OBRA DIAS CALENDARIOS = 30 Ubicación : LLUPA-INDEPENDENCIA-HUARAZ - ANCASH. SEMANA 01 SEMANA 02 SEMANA 03 SEMANA 04 ACUM Item Descripción Und. Metrado Precio S/. Parcial S/. % MONTO % MONTO % MONTO % MONTO % 01 MANTENIMIENTO DE LA INFRAESTRUCTURA 01.01 OBRAS PROVISIONALES 01.01.01 ALMACEN DE OBRA glb 1.00 120.00 120.00 16.00% 19.20 17.60% 21.12 30.40% 36.48 36.00% 43.20 ### 01.02 PINTURA 01.02.01 PINTURA LATEX EN MUROS INTERIORES m2 286.44 7.81 2,237.10 15.00% 335.57 16.50% 369.12 28.50% 637.57 40.00% 894.84 ### 01.02.02 ANDAMIO PARA PINTADO DE MUROS INTERIORES glb 1.00 50.41 50.41 16.00% 8.07 17.60% 8.87 30.40% 15.32 36.00% 18.15 ### 01.02.03 PINTURA LATEX EN MUROS EXTERIORES m2 121.42 7.81 948.29 18.00% 170.69 19.80% 187.76 34.20% 324.32 28.00% 265.52 ### 01.02.04 ANDAMIO PARA PINTADO DE MUROS EXTERIORES glb 1.00 50.41 50.41 25.00% 12.60 27.50% 13.86 47.50% 23.94 0.00% 0.00 ### 01.02.05 PINTURA ESMALTE SINTETICO EN ZOCALO m2 101.15 7.55 763.68 15.00% 114.55 16.50% 126.01 28.50% 217.65 40.00% 305.47 ### 01.02.06 PINTURA ESMALTE SINTETICO EN MUROS DE PATIO CENTR m2 34.82 7.16 249.31 25.00% 62.33 27.50% 68.56 47.50% 118.42 0.00% 0.00 ### 01.03 REFACCIONAMIENTO DE MUROS 01.03.01 TARRAJEO CON YESO EN MUROS m2 12.00 14.61 175.32 12.00% 21.04 13.20% 23.14 22.80% 39.97 52.00% 91.17 ### 01.04 REFACCIONAMIENTO DE INSTALACIONES SANITARIAS 01.04.01 PICADO DE MURO PARA INSTALACION DE GRIFERIA EN LAV m2 0.32 26.99 8.64 14.00% 1.21 15.40% 1.33 26.60% 2.30 44.00% 3.80 ### 01.04.02 SUMINISTRO DE GRIFERIA PARA LAVATORIOS DE LOZA LLA u 2.00 39.00 78.00 15.00% 11.70 16.50% 12.87 28.50% 22.23 40.00% 31.20 ### 01.04.03 INSTALACION DE GRIFERIA PARA LAVADERO pza 2.00 29.48 58.96 12.00% 7.08 13.20% 7.78 22.80% 13.44 52.00% 30.66 ### 01.04.04 SUMINISTRO DE TUB0 DE ABASTO u 1.00 8.50 8.50 14.00% 1.19 15.40% 1.31 26.60% 2.26 44.00% 3.74 ### 01.04.05 INSTALACION DE TUBOS DE ABASTO u 1.00 19.89 19.89 13.00% 2.59 14.30% 2.84 24.70% 4.91 48.00% 9.55 ### 01.04.06 SUMINISTRO DE GRIFO TIPO CUELLO DE GANSO - AREA DE u 1.00 39.00 39.00 12.00% 4.68 13.20% 5.15 22.80% 8.89 52.00% 20.28 ### 01.04.07 INSTALACION DE GRIFO TIPO CUELLO DE GANSO - AREA D u 1.00 20.00 20.00 11.00% 2.20 12.10% 2.42 20.90% 4.18 56.00% 11.20 ### 01.05 REFACCIONAMIENTO DE INSTALACIONES ELECTRICAS 01.05.01 SUMINISTRO DE DUCHA ELECTRICA u 1.00 75.00 75.00 10.00% 7.50 11.00% 8.25 19.00% 14.25 60.00% 45.00 ### 01.05.02 INSTALACION DE DUCHA ELECTRICA u 1.00 36.36 36.36 9.00% 3.27 9.90% 3.60 17.10% 6.22 64.00% 23.27 ### 01.05.03 SALIDA PARA DUCHA ELECTRICA pto 1.00 34.47 34.47 12.00% 4.14 13.20% 4.55 22.80% 7.86 52.00% 17.92 ### 01.06 MANTENIMIENTO CARPINTERIA DE MADERA 01.06.01 SUMNISTRO DE PUERTA DEMADERA PARA LAVADERO u 1.00 150.00 150.00 15.00% 22.50 16.50% 24.75 28.50% 42.75 40.00% 60.00 ### 01.06.02 PINTADO DE PUERTA PARA LAVADERO m2 1.20 10.87 13.04 18.00% 2.35 19.80% 2.58 34.20% 4.46 28.00% 3.65 ### 01.06.03 INSTALACION DE PUERTA DEMADERA PARA LAVADERO u 1.00 47.25 47.25 17.00% 8.03 18.70% 8.84 32.30% 15.26 32.00% 15.12 ### 01.07 VIDRIOS 01.07.01 ELIMINACION DE VIDRIOS Y LIMPIEZA DE MAZILLA EN VE u 6.00 7.40 44.40 16.00% 7.10 17.60% 7.81 30.40% 13.50 36.00% 15.98 ### 01.07.02 SUMINISTRO DE VIDRIOS CATEDRAL PARA VENTANAS p2 11.63 4.50 52.34 15.00% 7.85 16.50% 8.64 28.50% 14.92 40.00% 20.94 ### 01.07.03 COLOCACION DE VIDRIOS EN VENTANAS pza 6.00 5.61 33.66 13.00% 4.38 14.30% 4.81 24.70% 8.31 48.00% 16.16 ### 01.08 REFACCIONAMIENTO DE CERCO PERIMETRICO 01.08.01 LIMPIEZA Y PREPARACION DE MURO DE ADOBE PARA COLOC m 15.00 6.48 97.20 12.00% 11.66 13.20% 12.83 22.80% 22.16 52.00% 50.54 ### 01.08.02 SUMINISTRO Y COLOCACION DE TEJA EN CERCO PERIMETRI m 15.00 31.91 478.65 11.00% 52.65 12.10% 57.92 20.90% 100.04 56.00% 268.04 ### 01.08.03 ANDAMIO PARA COLOCACION DE TEJAS. glb 1.00 122.26 122.26 15.00% 18.34 16.50% 20.17 28.50% 34.84 40.00% 48.90 ### : «MANTENIMIENTO DE LA INFRAESTRUCTURA DEL PUESTO DE SALUD DE LLUPA»

Transcript of Cronograma Valorizado y Adquicicon de Materiales-llupa

Page 1: Cronograma Valorizado y Adquicicon de Materiales-llupa

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO

OBRA DIAS CALENDARIOS = 30

Ubicación : LLUPA-INDEPENDENCIA-HUARAZ - ANCASH. SEMANA 01 SEMANA 02 SEMANA 03 SEMANA 04

Item Descripción Und. Metrado Precio S/. Parcial S/. % MONTO % MONTO % MONTO % MONTO

01 MANTENIMIENTO DE LA INFRAESTRUCTURA

01.01 OBRAS PROVISIONALES

01.01.01 ALMACEN DE OBRA glb 1.00 120.00 120.00 16.00% 19.20 17.60% 21.12 30.40% 36.48 36.00% 43.20

01.02 PINTURA

01.02.01 PINTURA LATEX EN MUROS INTERIORES m2 286.44 7.81 2,237.10 15.00% 335.57 16.50% 369.12 28.50% 637.57 40.00% 894.84

01.02.02 ANDAMIO PARA PINTADO DE MUROS INTERIORES glb 1.00 50.41 50.41 16.00% 8.07 17.60% 8.87 30.40% 15.32 36.00% 18.15

01.02.03 PINTURA LATEX EN MUROS EXTERIORES m2 121.42 7.81 948.29 18.00% 170.69 19.80% 187.76 34.20% 324.32 28.00% 265.52

01.02.04 ANDAMIO PARA PINTADO DE MUROS EXTERIORES glb 1.00 50.41 50.41 25.00% 12.60 27.50% 13.86 47.50% 23.94 0.00% 0.00

01.02.05 PINTURA ESMALTE SINTETICO EN ZOCALO m2 101.15 7.55 763.68 15.00% 114.55 16.50% 126.01 28.50% 217.65 40.00% 305.47

01.02.06 PINTURA ESMALTE SINTETICO EN MUROS DE PATIO CENTRAL m2 34.82 7.16 249.31 25.00% 62.33 27.50% 68.56 47.50% 118.42 0.00% 0.00

01.03 REFACCIONAMIENTO DE MUROS

01.03.01 TARRAJEO CON YESO EN MUROS m2 12.00 14.61 175.32 12.00% 21.04 13.20% 23.14 22.80% 39.97 52.00% 91.17

01.04 REFACCIONAMIENTO DE INSTALACIONES SANITARIAS

01.04.01 PICADO DE MURO PARA INSTALACION DE GRIFERIA EN LAVADEROS m2 0.32 26.99 8.64 14.00% 1.21 15.40% 1.33 26.60% 2.30 44.00% 3.80

01.04.02 SUMINISTRO DE GRIFERIA PARA LAVATORIOS DE LOZA LLAVE DE 1/2" u 2.00 39.00 78.00 15.00% 11.70 16.50% 12.87 28.50% 22.23 40.00% 31.20

01.04.03 INSTALACION DE GRIFERIA PARA LAVADERO pza 2.00 29.48 58.96 12.00% 7.08 13.20% 7.78 22.80% 13.44 52.00% 30.66

01.04.04 SUMINISTRO DE TUB0 DE ABASTO u 1.00 8.50 8.50 14.00% 1.19 15.40% 1.31 26.60% 2.26 44.00% 3.74

01.04.05 INSTALACION DE TUBOS DE ABASTO u 1.00 19.89 19.89 13.00% 2.59 14.30% 2.84 24.70% 4.91 48.00% 9.55

01.04.06 SUMINISTRO DE GRIFO TIPO CUELLO DE GANSO - AREA DE TOPICO u 1.00 39.00 39.00 12.00% 4.68 13.20% 5.15 22.80% 8.89 52.00% 20.28

01.04.07 INSTALACION DE GRIFO TIPO CUELLO DE GANSO - AREA DE TOPICO u 1.00 20.00 20.00 11.00% 2.20 12.10% 2.42 20.90% 4.18 56.00% 11.20

01.05 REFACCIONAMIENTO DE INSTALACIONES ELECTRICAS

01.05.01 SUMINISTRO DE DUCHA ELECTRICA u 1.00 75.00 75.00 10.00% 7.50 11.00% 8.25 19.00% 14.25 60.00% 45.00

01.05.02 INSTALACION DE DUCHA ELECTRICA u 1.00 36.36 36.36 9.00% 3.27 9.90% 3.60 17.10% 6.22 64.00% 23.27

01.05.03 SALIDA PARA DUCHA ELECTRICA pto 1.00 34.47 34.47 12.00% 4.14 13.20% 4.55 22.80% 7.86 52.00% 17.92

01.06 MANTENIMIENTO CARPINTERIA DE MADERA

01.06.01 SUMNISTRO DE PUERTA DEMADERA PARA LAVADERO u 1.00 150.00 150.00 15.00% 22.50 16.50% 24.75 28.50% 42.75 40.00% 60.00

01.06.02 PINTADO DE PUERTA PARA LAVADERO m2 1.20 10.87 13.04 18.00% 2.35 19.80% 2.58 34.20% 4.46 28.00% 3.65

01.06.03 INSTALACION DE PUERTA DEMADERA PARA LAVADERO u 1.00 47.25 47.25 17.00% 8.03 18.70% 8.84 32.30% 15.26 32.00% 15.12

01.07 VIDRIOS

01.07.01 ELIMINACION DE VIDRIOS Y LIMPIEZA DE MAZILLA EN VENTANAS u 6.00 7.40 44.40 16.00% 7.10 17.60% 7.81 30.40% 13.50 36.00% 15.98

01.07.02 SUMINISTRO DE VIDRIOS CATEDRAL PARA VENTANAS p2 11.63 4.50 52.34 15.00% 7.85 16.50% 8.64 28.50% 14.92 40.00% 20.94

01.07.03 COLOCACION DE VIDRIOS EN VENTANAS pza 6.00 5.61 33.66 13.00% 4.38 14.30% 4.81 24.70% 8.31 48.00% 16.16

01.08 REFACCIONAMIENTO DE CERCO PERIMETRICO

01.08.01 LIMPIEZA Y PREPARACION DE MURO DE ADOBE PARA COLOCACION DEm 15.00 6.48 97.20 12.00% 11.66 13.20% 12.83 22.80% 22.16 52.00% 50.54

01.08.02 SUMINISTRO Y COLOCACION DE TEJA EN CERCO PERIMETRICO m 15.00 31.91 478.65 11.00% 52.65 12.10% 57.92 20.90% 100.04 56.00% 268.04

01.08.03 ANDAMIO PARA COLOCACION DE TEJAS. glb 1.00 122.26 122.26 15.00% 18.34 16.50% 20.17 28.50% 34.84 40.00% 48.90

: «MANTENIMIENTO DE LA INFRAESTRUCTURA DEL PUESTO DE SALUD DE LLUPA»

Page 2: Cronograma Valorizado y Adquicicon de Materiales-llupa

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO

OBRA DIAS CALENDARIOS = 30

Ubicación : LLUPA-INDEPENDENCIA-HUARAZ - ANCASH. SEMANA 01 SEMANA 02 SEMANA 03 SEMANA 04

Item Descripción Und. Metrado Precio S/. Parcial S/. % MONTO % MONTO % MONTO % MONTO

: «MANTENIMIENTO DE LA INFRAESTRUCTURA DEL PUESTO DE SALUD DE LLUPA»

01.09 MEJORAMIENTO DE RELLENO SANITARIO

01.09.01 LIMPIEZA Y DESBROSE DE MALEZA m2 9.00 7.77 69.93 16.00% 11.19 17.60% 12.31 30.40% 21.26 36.00% 25.17

01.09.02 EXCAVACION DE TERRENO NATURAL (LAMPA Y PICO) m3 19.80 25.34 501.73 14.00% 70.24 15.40% 77.27 26.60% 133.46 44.00% 220.76

01.09.03 PERFILADO DEL RELLENO SANITARIO m2 46.20 3.53 163.09 13.00% 21.20 14.30% 23.32 24.70% 40.28 48.00% 78.28

01.09.04 ELIMINACION DE DESMONTE m3 23.76 10.78 256.13 15.00% 38.42 16.50% 42.26 28.50% 73.00 40.00% 102.45

01.10 MEJORAMIENTO DE DRENAJE PLUVIAL

01.10.01 EXCAVACION PARA CANAL DE DRENAJE m3 1.80 19.06 34.31 12.00% 4.12 13.20% 4.53 22.80% 7.82 52.00% 17.84

01.10.02 CONCRETO f'c=175 kg/cm2 PARA CANAL m3 2.16 271.43 586.29 13.00% 76.22 14.30% 83.84 24.70% 144.81 48.00% 281.42

01.10.03 PERFILADO Y COMPACTADO m2 37.20 4.29 159.59 15.00% 23.94 16.50% 26.33 28.50% 45.48 40.00% 63.84

01.11 MEJORAMIENTO DE PATIO PRINCIPAL DE CONCRETO 0.00% 0.00% 0.00%

01.11.01 LIMPIEZA DE TERRENO m2 154.70 3.05 471.84 12.00% 56.62 13.20% 62.28 22.80% 107.58 52.00% 245.36

01.11.02 TRAZO, NIVELACION Y REPLANTEO m2 154.70 2.03 314.04 19.00% 59.67 20.90% 65.63 36.10% 113.37 24.00% 75.37

01.11.03 ENCOFRADO Y DESENCOFRADO DE LOSAS. m2 47.15 34.77 1,639.41 24.00% 393.46 26.40% 432.80 45.60% 747.57 4.00% 65.58

01.11.04 CONCRETO f'c = 100 kg/cm2 (solado) m3 3.87 244.67 946.87 20.00% 189.37 22.00% 208.31 38.00% 359.81 20.00% 189.37

01.11.05 CONCRETO f 'c=210 kg/cm2 m3 9.28 293.82 2,726.65 19.00% 518.06 20.90% 569.87 36.10% 984.32 24.00% 654.40

01.11.06 FROTACHADO Y BRUÑADO DE LOSA m2 154.70 12.56 1,943.03 18.00% 349.75 19.80% 384.72 34.20% 664.52 28.00% 544.05

01.11.07 JUNTAS ASFALTICAS m 157.16 5.95 935.10 14.00% 130.91 15.40% 144.01 26.60% 248.74 44.00% 411.44

01.12 FLETE

01.12.01 FLETE TERRESTRE glb 1.00 1,500.00 1,500.00 20.00% 300.00 22.00% 330.00 38.00% 570.00 20.00% 300.00

COSTO DIRECTO (S/.) 18,260.15 3,167.63 3,484.39 6,018.49 5,589.64

PORCENTAJE DE AVANCE 17.35% 19.08% 32.96% 30.61%

PORCENTAJE DE AVANCE ACUMULADO 17.35% 36.43% 69.39% 100.00%

Page 3: Cronograma Valorizado y Adquicicon de Materiales-llupa

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO

DIAS CALENDARIOS = 30

ACUMULADO

% MONTO

100.00% 120.00

100.00% 2,237.10

100.00% 50.41

100.00% 948.29

100.00% 50.41

100.00% 763.68

100.00% 249.31

100.00% 175.32

100.00% 8.64

100.00% 78.00

100.00% 58.96

100.00% 8.50

100.00% 19.89

100.00% 39.00

100.00% 20.00

100.00% 75.00

100.00% 36.36

100.00% 34.47

100.00% 150.00

100.00% 13.04

100.00% 47.25

100.00% 44.40

100.00% 52.34

100.00% 33.66

100.00% 97.20

100.00% 478.65

100.00% 122.26

Page 4: Cronograma Valorizado y Adquicicon de Materiales-llupa

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO

DIAS CALENDARIOS = 30

ACUMULADO

% MONTO

100.00% 69.93

100.00% 501.73

100.00% 163.09

100.00% 256.13

100.00% 34.31

100.00% 586.29

100.00% 159.59

0.00%

100.00% 471.84

100.00% 314.04

100.00% 1,639.41

100.00% 946.87

100.00% 2,726.65

100.00% 1,943.03

100.00% 935.10

100.00% 1,500.00

18,260.15

100.00%

100.00%

Page 5: Cronograma Valorizado y Adquicicon de Materiales-llupa

CURVAS "S"

N° MESES

PROGRAMADO EJECUTADO

VALORIZACIONES PORCENTAJES VALORIZACION PORCENTAJES

MENSUAL (S/.) ACUMULADO MENSUAL (S/.) ACUMULADO MENSUAL ACUMULADO MENSUAL ACUMULADO

0 Mes 00 0.00 0.00 0.00% 0.00%

1 Mes 01 3,167.63 3,167.63 17.35% 17.35%

2 Mes 02 3,484.39 6,652.02 19.08% 36.43%

3 Mes 03 6,018.49 12,670.51 32.96% 69.39%

4 Mes 04 5,589.64 18,260.15 30.61% 100.00%

TOTAL = 18,260.15

0 1 2 3 40.00%

20.00%

40.00%

60.00%

80.00%

100.00%

0.00%

17.35%

36.43%

69.39%

100.00%

Page 6: Cronograma Valorizado y Adquicicon de Materiales-llupa

CRONOGRAMA DE DESEMBOLSOS (120 DIAS)OBRA

Ubicació: LLUPA-INDEPENDENCIA-HUARAZ - ANCASH.

ÍTEM DESCRIPCIÓN % Adelantos

TOTAL (120 Dias Calendarios)

TOTALVALORIZACION Nº 01 VALORIZACION Nº 02 VALORIZACION Nº 04

SEMANA 01 SEMANA 02 SEMANA 03 SEMANA 04

1.00 ADELANTOS

1.01 Adelanto Directo 0% 0.00 0.00

1.02 Adelanto para Materiales 0% 0.00 0.00

2.00 VALORIZACIONES

2.1.0 1ra. VALORIZACION

2.1.1 1ra. Valorización 3,167.63 3,167.63

2.2.0 2da VALORIZACION

2.2.1 2da Valorización 3,484.39 3,484.39

2.3.0 3era VALORIZACION2.3.1 3era Valorización 6,018.49 6,018.49

2.4.0 4ta VALORIZACION2.4.1 4ta Valorización 5,589.64 5,589.64

PORCENTAJE 0.00% 17.35% 19.08% 32.96% 30.61% 100.00%PORCENTAJE ACUMULADO 0.00% 17.35% 36.43% 69.39% 100.00%

COSTO DIRECTO 0.00 3,167.63 3,484.39 6,018.49 5,589.64 18,260.15GASTOS GENERALES 10% 0.00 316.76 348.44 601.85 558.96 1,826.02UTILIDADES 5% 0.00 158.38 174.22 300.92 279.48 913.01

SUB-TOTAL 0.00 3,642.77 4,007.05 6,921.26 6,428.09 20,999.17

: «MANTENIMIENTO DE LA INFRAESTRUCTURA DEL PUESTO DE SALUD DE LLUPA»

VALORIZACION Nº 03

Page 7: Cronograma Valorizado y Adquicicon de Materiales-llupa

I.G.V 18% 0.00 655.70 721.27 1,245.83 1,157.06 3,779.85TOTAL DEL PRESUPUESTO 0.00 4,298.47 4,728.32 8,167.09 7,585.15 24,779.02

Page 8: Cronograma Valorizado y Adquicicon de Materiales-llupa

CRONOGRAMA DE DESEMBOLSO DE MATERIALES

OBRA

Ubicación : LLUPA-INDEPENDENCIA-HUARAZ - ANCASH.

N° Recurso Unidad Cantidad Precio S/. Parcial S/. Presupuestado S/.MES (30 Dias Calendarios)

SEMANA-1 SEMANA-2 SEMANA-3

00.01 ALAMBRE NEGRO RECOCIDO # 8 kg 14.1450 4.50 63.65 63.65 11.04 12.15 20.9800.02 CLAVOS PARA CEMENTO DE ACERO CON CABEZA DE 3" kg 11.7875 4.50 53.04 53.04 9.20 10.12 17.4800.03 ALMACEN DE OBRA glb 1.0000 120.00 120.00 120.00 20.82 22.90 39.5500.04 ARENA FINA m3 8.9313 95.00 848.47 848.47 147.19 161.90 279.6500.05 PIEDRA CHANCADA DE 3/4" m3 7.8880 90.00 709.92 709.92 123.15 135.47 233.9900.06 GRAVA CANTO RODADO m3 1.6416 85.00 139.54 139.54 24.21 26.63 45.9900.07 ARENA GRUESA m3 1.1016 85.00 93.64 93.64 16.24 17.87 30.8600.08 CABLE TW # 12 AWG - 4 mm2 m 1.7000 2.50 4.25 4.25 0.74 0.81 1.4000.09 DUCHA ELECTRICA u 1.0000 75.00 75.00 75.00 13.01 14.31 24.7200.10 TUBO ABASTO COBRE FLEXIBEL TERM/M-H 1/2" X 1/2"35 cm u 1.0000 8.50 8.50 8.50 1.47 1.62 2.8000.11 GRIFERIA PARA LAVATORIOS DE LOZA TIPO CUELLO DE GANSO DE LLAVE DEu 3.0000 39.00 117.00 117.00 20.30 22.33 38.5600.12 ASFALTO RC-250 gal 20.9023 21.00 438.95 438.95 76.15 83.76 144.6800.13 TEJAS DE ARCILLA DE 32 cm X 15 cm u 240.0000 0.80 192.00 192.00 33.31 36.64 63.2800.14 CEMENTO PORTLAND TIPO I (42.5 kg) bls 165.5400 15.99 2,646.98 2,646.98 459.18 505.09 872.4400.15 CINTA AISLANTE rll 0.1000 2.50 0.25 0.25 0.04 0.05 0.0800.16 YESO EN BOLSAS DE 20 kg Y TIZA u 36.9000 5.00 184.50 184.50 32.01 35.21 60.8100.17 PEGAMENTO PARA PVC L 0.0050 140.00 0.70 0.70 0.12 0.13 0.2300.18 LIJA u 109.0100 2.00 218.02 218.02 37.82 41.60 71.8600.19 FLETE TERRESTRE MOVILIZACION MATERERIAL DE ALMACEN glb 1.0000 1,500.00 1,500.00 1,500.00 260.21 286.23 494.4000.20 TIZA EN BOLSA DE 40 kg u 15.4700 5.00 77.35 77.35 13.42 14.76 25.4900.21 AGUA m3 39.2200 0.50 19.61 19.61 3.40 3.74 6.4600.22 PUERTA DE DOS HOJAS PARA LAVADERO u 1.0000 150.00 150.00 150.00 26.02 28.62 49.4400.23 MADERA PARA ANDAMIO 1" X 8" X 8' pza 2.0000 3.50 7.00 7.00 1.21 1.34 2.3100.24 TRIPLAY DE 4' X 8' X 12 mm pl 2.0463 50.00 102.32 102.32 17.75 19.52 33.7200.25 MADERA TORNILLO INCLUYE CORTE PARA ENCOFRADO p2 188.6000 4.50 848.70 848.70 147.23 161.95 279.7300.26 PINTURA LATEX gal 40.7860 23.00 938.08 938.08 162.73 179.00 309.1900.27 PINTURA ESMALTE SINTETICO gal 13.7170 32.00 438.94 438.94 76.14 83.76 144.6700.28 IMPRIMANTE PARA MUROS gal 36.7071 21.00 770.85 770.85 133.72 147.09 254.0700.29 TUBERIA PVC SAP A-10 DE 1/2" m 2.0200 1.60 3.23 3.23 0.56 0.62 1.0600.30 TAPON HEMBRA PVC SAP PARA AGUA SIMPLE PRESION DE 1/2" u 0.0040 1.20 0.00 0.00 0.00 0.00 0.0000.31 VIDRIO TRANSPARENTE CATEDRAL p2 11.6300 4.50 52.34 52.34 9.08 9.99 17.25

CRONOGRAMA DE DESEMBOLSO DE MATERIALES 1,877.46 2,065.21 3,567.17

: «MANTENIMIENTO DE LA INFRAESTRUCTURA DEL PUESTO DE SALUD DE LLUPA»

Page 9: Cronograma Valorizado y Adquicicon de Materiales-llupa

CRONOGRAMA DE DESEMBOLSO DE MATERIALES

MES (30 Dias Calendarios)

SEMANA-4 TOTAL

19.48 63.6516.24 53.0436.73 120.00259.73 848.47217.31 709.9242.71 139.5428.66 93.641.30 4.2522.96 75.002.60 8.5035.82 117.00134.37 438.9558.77 192.00810.27 2,646.980.08 0.2556.48 184.500.21 0.7066.74 218.02459.17 1,500.0023.68 77.356.00 19.6145.92 150.002.14 7.0031.32 102.32259.80 848.70287.16 938.08134.36 438.94235.97 770.850.99 3.230.00 0.0016.02 52.34

3,312.99 10,822.83