Cronograma Agua - Obra

4
CRONOGRAMA VALORIZADO DE AVANCE DE OBRA FORMULA :REDES DE AGUA POTABLE FECHA: DICIEMBRE 2006 ITEM DESCRIPCION UND METRADO PRECIO PARCIAL MES 1 MES 2 01.00.00 OBRAS PROVISIONALES 01.01.01 CASETA DE GUARDIANIA Y ALMACEN GLB 1.00 1,200.00 1,200.00 1,200.00 100.00% 01.02.00 GUARDIANIA DIA 60.00 80.00 4,800.00 2,400.00 2,400.00 50.00% 50.00% 01.03.00 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60X2.40M UND 1.00 880.97 880.97 880.97 100.00% 01.04.00 TRANSPORTE DE TUBERIAS Y ACCESORIOS TON 5.17 75.00 387.75 193.88 193.88 50.00% 50.00% 02.00.00 TRABAJOS PRELIMINARES 02.01.00 TRAZO Y REPLANTEO EN OBRA M 5,850.00 1.03 6,025.50 3,012.75 3,012.75 50.00% 50.00% 02.02.00 TRAZO, NIVELACION Y REPLANTEO DE ZANJAS DIA 60.00 38.19 2,291.40 1,145.70 1,145.70 50.00% 50.00% 03.00.00 MOVIMIENTO DE TIERRAS 03.01.00 EXCAVACION DE ZANJA MANUAL TN H MAX=1.00 ANCHO 0.60 EN TERRENO NORMAL M 5,850.00 7.27 42,529.50 21,264.75 21,264.75 50.00% 50.00% 03.02.00 EXCAVACION C/I(MAQUINAS) EN TERRENO SEMIROCOSO M 5,850.00 3.08 18,018.00 9,009.00 9,009.00 50.00% 50.00% 03.03.00 REFINE, NIVELACION Y FONDO TUB. MENOR 4" M 5,850.00 0.49 2,866.50 1,433.25 1,433.25 50.00% 50.00% 03.04.00 CAMA DE APOYO TUB. MENOR A 4" M 5,850.00 3.50 20,475.00 10,237.50 10,237.50 50.00% 50.00% 03.05.00 RELLENO PROTECTOR DE ZANJA M 5,850.00 2.73 15,970.50 7,985.25 7,985.25 50.00% 50.00% 03.06.00 RELLENO Y COMP EN ZANJAS TUB. 3" M 5,850.00 3.35 19,597.50 9,798.75 9,798.75 50.00% 50.00% 03.07.00 ELIMINACIÓN DE MATERIAL EXCEDENTE M3 290.20 14.31 4,185.68 2,092.84 2,092.84 50.00% 50.00% 04.00.00 SUMINISTRO E INSTALACION DE TUBERIAS 04.01.00 SUM. E INST. DE TUBERIA PVC Ø 110mm C-A7.5 M 60.00 17.88 1,072.80 1,072.80 100.00% 04.02.00 SUM. E INST. DE TUBERIA PVC Ø 90mm C-A7.5 M 2,056.00 9.75 20,046.00 10,023.00 10,023.00 50.00% 50.00% 04.03.00 SUM. E INST. DE TUBERIA PVC Ø 63mm C-A7.5 M 3,734.00 7.07 26,399.38 13,199.69 13,199.69 50.00% 50.00% 05.00.00 SUMINISTRO DE ACCESORIOS 05.01.00 SUMINISTRO DE CRUZ 90 MM * 90 MM PVC TIPO UFLEX UND 10.00 25.30 253.00 126.50 126.50 50.00% 50.00% 05.02.00 SUMINISTRO DE CRUZ 63 MM * 63 MM PVC TIPO UFLEX UND 9.00 13.65 122.85 122.85 100.00% 05.03.00 SUMINISTRO DE TEE 90 MM * 90 MM PVC TIPO UFLEX UND 29.00 11.20 324.80 162.40 162.40 50.00% 50.00% 05.04.00 SUMINISTRO DE TEE 63 MM * 63 MM PVC TIPO UFLEX UND 12.00 4.25 51.00 51.00 100.00% 05.05.00 SUMINISTRO DE CODO 90º 90 MM PVC TIPO UFLEX UND 7.00 7.65 53.55 53.55 100.00% 05.06.00 SUMINISTRO DE CODO 90º 63 MM PVC TIPO UFLEX UND 5.00 3.60 18.00 18.00 100.00% 05.07.00 SUMINISTRO DE TAPON DE PVC 90 MM KM UND 3.00 14.30 42.90 21.45 21.45 50.00% 50.00% 05.08.00 SUMINISTRO DE TAPON DE P.V.C. 1/2" PZA 565.00 0.60 339.00 169.50 169.50 50.00% 50.00% 05.09.00 SUMINISTRO DE REDUCCIONES PVC TIPO UFLEX UND 36.00 5.10 183.60 183.60 100.00% 05.10.00 SUMINISTRO DE VALVULA COMPUERTA DE Ø110MM UND 1.00 160.00 160.00 160.00 100.00% 05.11.00 SUMINISTRO DE VALVULA COMPUERTA DE Ø 90 MM UND 17.00 75.00 1,275.00 1,275.00 100.00% 05.12.00 SUMINISTRO DE VALVULA COMPUERTA DE Ø 63 MM UND 22.00 33.00 726.00 726.00 100.00% 06.00.00 INSTALACION DE ACCESORIOS 06.01.00 INSTALACION DE ACCESORIOS - INCLUYE DADO DE ANCLAJE UND 111.00 23.75 2,636.25 1,318.13 1,318.13 50.00% 50.00% 07.00.00 PRUEBAS HIDRAULICAS 07.01.00 PRUEBA HIDRAULICA M 5,850.00 2.13 12,460.50 12,460.50 100.00%

description

en formato excel

Transcript of Cronograma Agua - Obra

Page 1: Cronograma Agua - Obra

CRONOGRAMA VALORIZADO DE AVANCE DE OBRA

FORMULA :REDES DE AGUA POTABLE FECHA: DICIEMBRE 2006

ITEM DESCRIPCION UND METRADO PRECIO PARCIAL MES 1 MES 2

01.00.00 OBRAS PROVISIONALES

01.01.01 CASETA DE GUARDIANIA Y ALMACEN GLB 1.00 1,200.00 1,200.00 1,200.00

100.00%

01.02.00 GUARDIANIA DIA 60.00 80.00 4,800.00 2,400.00 2,400.00

50.00% 50.00%

01.03.00 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60X2.40M UND 1.00 880.97 880.97 880.97

100.00%

01.04.00 TRANSPORTE DE TUBERIAS Y ACCESORIOS TON 5.17 75.00 387.75 193.88 193.88

50.00% 50.00%

02.00.00 TRABAJOS PRELIMINARES

02.01.00 TRAZO Y REPLANTEO EN OBRA M 5,850.00 1.03 6,025.50 3,012.75 3,012.75

50.00% 50.00%

02.02.00 TRAZO, NIVELACION Y REPLANTEO DE ZANJAS DIA 60.00 38.19 2,291.40 1,145.70 1,145.70

50.00% 50.00%

03.00.00 MOVIMIENTO DE TIERRAS

03.01.00 EXCAVACION DE ZANJA MANUAL TN H MAX=1.00 ANCHO 0.60 EN TERRENO NORMAL M 5,850.00 7.27 42,529.50 21,264.75 21,264.75

50.00% 50.00%

03.02.00 EXCAVACION C/I(MAQUINAS) EN TERRENO SEMIROCOSO M 5,850.00 3.08 18,018.00 9,009.00 9,009.00

50.00% 50.00%

03.03.00 REFINE, NIVELACION Y FONDO TUB. MENOR 4" M 5,850.00 0.49 2,866.50 1,433.25 1,433.25

50.00% 50.00%

03.04.00 CAMA DE APOYO TUB. MENOR A 4" M 5,850.00 3.50 20,475.00 10,237.50 10,237.50

50.00% 50.00%

03.05.00 RELLENO PROTECTOR DE ZANJA M 5,850.00 2.73 15,970.50 7,985.25 7,985.25

50.00% 50.00%

03.06.00 RELLENO Y COMP EN ZANJAS TUB. 3" M 5,850.00 3.35 19,597.50 9,798.75 9,798.75

50.00% 50.00%

03.07.00 ELIMINACIÓN DE MATERIAL EXCEDENTE M3 290.20 14.31 4,185.68 2,092.84 2,092.84

50.00% 50.00%

04.00.00 SUMINISTRO E INSTALACION DE TUBERIAS

04.01.00 SUM. E INST. DE TUBERIA PVC Ø 110mm C-A7.5 M 60.00 17.88 1,072.80 1,072.80

100.00%

04.02.00 SUM. E INST. DE TUBERIA PVC Ø 90mm C-A7.5 M 2,056.00 9.75 20,046.00 10,023.00 10,023.00

50.00% 50.00%

04.03.00 SUM. E INST. DE TUBERIA PVC Ø 63mm C-A7.5 M 3,734.00 7.07 26,399.38 13,199.69 13,199.69

50.00% 50.00%

05.00.00 SUMINISTRO DE ACCESORIOS

05.01.00 SUMINISTRO DE CRUZ 90 MM * 90 MM PVC TIPO UFLEX UND 10.00 25.30 253.00 126.50 126.50

50.00% 50.00%

05.02.00 SUMINISTRO DE CRUZ 63 MM * 63 MM PVC TIPO UFLEX UND 9.00 13.65 122.85 122.85

100.00%

05.03.00 SUMINISTRO DE TEE 90 MM * 90 MM PVC TIPO UFLEX UND 29.00 11.20 324.80 162.40 162.40

50.00% 50.00%

05.04.00 SUMINISTRO DE TEE 63 MM * 63 MM PVC TIPO UFLEX UND 12.00 4.25 51.00 51.00

100.00%

05.05.00 SUMINISTRO DE CODO 90º 90 MM PVC TIPO UFLEX UND 7.00 7.65 53.55 53.55

100.00%

05.06.00 SUMINISTRO DE CODO 90º 63 MM PVC TIPO UFLEX UND 5.00 3.60 18.00 18.00

100.00%

05.07.00 SUMINISTRO DE TAPON DE PVC 90 MM KM UND 3.00 14.30 42.90 21.45 21.45

50.00% 50.00%

05.08.00 SUMINISTRO DE TAPON DE P.V.C. 1/2" PZA 565.00 0.60 339.00 169.50 169.50

50.00% 50.00%

05.09.00 SUMINISTRO DE REDUCCIONES PVC TIPO UFLEX UND 36.00 5.10 183.60 183.60

100.00%

05.10.00 SUMINISTRO DE VALVULA COMPUERTA DE Ø110MM UND 1.00 160.00 160.00 160.00

100.00%

05.11.00 SUMINISTRO DE VALVULA COMPUERTA DE Ø 90 MM UND 17.00 75.00 1,275.00 1,275.00

100.00%

05.12.00 SUMINISTRO DE VALVULA COMPUERTA DE Ø 63 MM UND 22.00 33.00 726.00 726.00

100.00%

06.00.00 INSTALACION DE ACCESORIOS

06.01.00 INSTALACION DE ACCESORIOS - INCLUYE DADO DE ANCLAJE UND 111.00 23.75 2,636.25 1,318.13 1,318.13

50.00% 50.00%

07.00.00 PRUEBAS HIDRAULICAS

07.01.00 PRUEBA HIDRAULICA M 5,850.00 2.13 12,460.50 12,460.50

100.00%

Page 2: Cronograma Agua - Obra

08.00.00 CONEXIONES DOMICILIARIAS DE AGUA

08.01.00 MATERIALES y ACCESORIOS

08.01.01 SUMINISTRO DE TUBERIA PVC 1/2" CLASE A-10 M 1,695.00 1.40 2,373.00 2,373.00

100.00%

08.01.02 ABRAZADERA DE FF CON EMPAQUE DE GOMA P/TUBO DE 2" CON SALIDA DE 1/2" UND 416.00 5.04 2,096.64 2,096.64

100.00%

08.01.03 ABRAZADERA DE FF CON EMPAQUE DE GOMA P/TUBO DE 3"CON SALIDA DE 1/2" UND 149.00 5.71 850.79 850.79

100.00%

08.01.04 LLAVE COORPORATION DE 1/2" PVC UND 565.00 6.30 3,559.50 3,559.50

100.00%

08.01.05 CAJA DE PROTECCION DE LLAVE CORPORATION UND 565.00 8.40 4,746.00 4,746.00

100.00%

08.02.00 INSTALACION

08.02.01 INSTALACION DE TUBERIA PVC 1/2" M 1,695.00 2.45 4,152.75 4,152.75

100.00%

08.02.02 INSTALACION LLAVE COORPORATION Y ABRAZADERA FF UND 565.00 12.42 7,017.30 7,017.30

100.00%

COSTO DIRECTO 230,188.91 97,177.10 133,011.81

IMPUESTO IGV 19%(No incluye mano de Obra) 19,954.75

------------------

SUB TOTAL 250,143.66

GASTOS GENERALES (8%) 20,011.49

============

TOTAL PRESUPUESTO 270,155.15

42.22% 57.78%

PORCENTAJE DE AVANCE 42.22% 100.00%

PORCENTAJE ACUMULADO

Page 3: Cronograma Agua - Obra

CRONOGRAMA VALORIZADO DE AVANCE DE OBRA

TOTAL

1,200.00

4,800.00

880.97

387.75

6,025.50

2,291.40

42,529.50

18,018.00

2,866.50

20,475.00

15,970.50

19,597.50

4,185.68

1,072.80

20,046.00

26,399.38

253.00

122.85

324.80

51.00

53.55

18.00

42.90

339.00

183.60

160.00

1,275.00

726.00

2,636.25

12,460.50

Page 4: Cronograma Agua - Obra

2,373.00

2,096.64

850.79

3,559.50

4,746.00

4,152.75

7,017.30

230,188.91

100.00%

100.00%