CRONOGRAMA DE OBRA ACELERADO OBRA: MEJORAMIENTO DE LA CARRETERA HUANCANE - MOHO - CONIMA - TILALI (HANCCO HANCCO) DESCRIPCION AGOSTO % SETIEMBRE % OCTUBRE % NOVIEMBRE % DICIEMBRE % PRESUPUESTO OBRAS PROVISIONALES CAMPAMENTO DE OBRA 15,292.80 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 15,292.80 OBRAS PRELIMINARES MOVILIZACION Y DEMOVILIZACION DE MAQUINARIA Y/O EQUIPO 10,000.00 25.00% 5,000.00 12.50% 0.00 0.00% 5,000.00 12.50% 20,000.00 50.00% 40,000.00 SEÑALIZACION DE SEGURIDAD Y/O DESVIO DE TRAFICO EN OBRA 4,000.00 25.00% 4,000.00 25.00% 4,000.00 25.00% 4,000.00 25.00% 0.00 0.00% 16,000.00 TRAZO Y REPLANTEO INICIAL 15,276.96 33.17% 4,981.03 10.82% 3,698.00 8.03% 2,264.60 4.92% 19,834.39 43.07% 46,054.99 EXPLANACIONES EXTRACCION DE ROCA POR APLICACION DE VOLADURA 0.00 0.00% 0.00 0.00% 0.00 0.00% 24,288.00 25.00% 72,864.00 75.00% 97,152.00 DEQUINCHE Y CARGUIO DE ROCA 0.00 0.00% 0.00 0.00% 0.00 0.00% 29,367.78 25.00% 88,103.34 75.00% 117,471.12 TRANPORTE DE ROCA 0.00 0.00% 0.00 0.00% 0.00 0.00% 25,474.80 25.00% 76,424.40 75.00% 101,899.20 CHANCADO 0.00 0.00% 0.00 0.00% 0.00 0.00% 32,884.02 25.00% 98,652.06 75.00% 131,536.08 ZARANDEO DE MATERIAL 0.00 0.00% 0.00 0.00% 0.00 0.00% 8,055.06 25.00% 24,165.18 75.00% 32,220.24 CARGUIO DE MATERIAL CHANCADO 0.00 0.00% 0.00 0.00% 0.00 0.00% 4,951.44 25.00% 14,854.32 75.00% 19,805.76 TRANSPORTE DE MATERIAL CHANCADO 0.00 0.00% 0.00 0.00% 0.00 0.00% 18,944.64 25.00% 56,833.92 75.00% 75,778.56 PAVIMENTOS SUB BASE (Reposicion) TRAZO Y REPLANTEO. 62,853.75 30.00% 14,351.61 6.85% 52,378.13 25.00% 45,045.19 21.50% 34,883.83 16.65% 209,512.50 PERFILADO Y COMPACTADO SUB RASANTE 57,757.50 30.00% 13,187.96 6.85% 48,131.25 25.00% 41,392.88 21.50% 32,055.41 16.65% 192,525.01 RIEGO C/AGUA 18,686.25 30.00% 4,266.69 6.85% 15,571.88 25.00% 13,391.81 21.50% 10,370.87 16.65% 62,287.50 EXTRACCION Y APILAMIENTO DE MATERIAL SELECCIONADDO 21,445.41 42.20% 3,531.89 6.95% 12,704.63 25.00% 11,434.16 22.50% 1,702.42 3.35% 50,818.51 ZARANDEO DE MATERIAL 23,533.17 42.20% 3,875.72 6.95% 13,941.45 25.00% 12,547.31 22.50% 1,868.15 3.35% 55,765.80 CARGUIO DE MATERIAL SELECCIONADO 14,465.82 42.20% 2,382.40 6.95% 8,569.80 25.00% 7,712.82 22.50% 1,148.35 3.35% 34,279.20 TRANPORTE DE MATERIAL SELECCIONADO 55,347.50 42.20% 9,115.29 6.95% 32,788.80 25.00% 29,509.92 22.50% 4,393.70 3.35% 131,155.21 CONFORMACION DE SUB BASE C/EQUIPO PESADO 34,155.00 30.00% 7,798.73 6.85% 28,462.50 25.00% 24,477.75 21.50% 18,956.03 16.65% 113,850.01 BASE TRAZO Y REPLANTEO 0.00 0.00% 22,941.62 10.95% 24,827.23 11.85% 39,702.62 18.95% 122,041.03 58.25% 209,512.50 EXTRACCION Y APILAMIENTO DE MATERIAL SELECCIONADO 0.00 0.00% 31,006.13 13.05% 33,976.07 14.30% 48,754.47 20.52% 123,858.22 52.13% 237,594.90 ZARANDEO DE MATERIAL 0.00 0.00% 34,024.66 13.05% 37,283.72 14.30% 53,500.84 20.52% 135,916.11 52.13% 260,725.33 CARGUIO DE MATERIAL SELECCIONADO 0.00 0.00% 20,914.93 13.05% 22,918.28 14.30% 32,886.93 20.52% 83,547.55 52.13% 160,267.69 TRANPORTE DE MATERIAL SELECCIONADO 0.00 0.00% 80,022.35 13.05% 87,687.33 14.30% 125,828.25 20.52% 319,660.16 52.13% 613,198.09 EXTRACCION Y APILAMIENTO DE MATERIAL HORMIGON Y/O PIEDRA CHANCADA 0.00 0.00% 4,932.73 13.05% 5,405.21 14.30% 7,756.29 20.52% 19,704.44 52.13% 37,798.66 CARGUIO DE MATERIAL HORMIGON Y/O PIEDRA CHANCADA 0.00 0.00% 3,559.30 13.05% 3,900.23 14.30% 5,596.69 20.52% 14,218.10 52.13% 27,274.32 TRANSPORTE DE MATERIAL HORMIGON 0.00 0.00% 9,620.42 13.05% 10,541.92 14.30% 15,127.29 20.52% 38,430.09 52.13% 73,719.72 MEZCLADO DE MATERIAL SELECCIONADO C/HORM. Y/O PIEDRA CHANCADA 0.00 0.00% 42,254.99 13.05% 46,302.41 14.30% 66,442.34 20.52% 168,793.32 52.13% 323,793.06 CARGUIO DE MATERIAL MEZCLADO 0.00 0.00% 27,058.88 13.05% 29,650.73 14.30% 42,547.76 20.52% 108,090.39 52.13% 207,347.76 TRANSPORTE DE MATERIAL MEZCLADO 0.00 0.00% 53,333.45 13.05% 58,442.02 14.30% 83,862.25 20.52% 213,047.73 52.13% 408,685.45 RIEGO C/AGUA 0.00 0.00% 6,820.48 10.95% 7,381.07 11.85% 11,803.48 18.95% 36,282.46 58.25% 62,287.49 CONFORMACION DE BASE C/EQUIPO PESADO 0.00 0.00% 51,153.61 10.95% 55,358.02 11.85% 88,526.11 18.95% 272,118.52 58.25% 467,156.25 PAVIMENTO FLEXIBLE TRAZO Y REPLANTEO. 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 4,758.01 100.00% 4,758.01 BARRIDO DE PLATAFORMA 0.00 0.00% 4,869.75 5.00% 9,739.50 10.00% 14,609.25 15.00% 68,176.50 70.00% 97,395.00 IMPRIMACION 0.00 0.00% 52,982.13 5.00% 105,964.25 10.00% 158,946.38 15.00% 741,749.75 70.00% 1,059,642.50 EXTRACCION Y APILAMIENTO DE ARENA 0.00 0.00% 121.29 5.00% 242.58 10.00% 363.87 15.00% 1,698.07 70.00% 2,425.82 CARGUIO DE ARENA 0.00 0.00% 72.93 5.00% 145.87 10.00% 218.80 15.00% 1,021.06 70.00% 1,458.66 TRANSPORTE DE ARENA 0.00 0.00% 197.13 5.00% 394.26 10.00% 591.39 15.00% 2,759.82 70.00% 3,942.60 ARENADO 0.00 0.00% 1,057.00 5.00% 2,114.00 10.00% 3,171.00 15.00% 14,797.99 70.00% 21,139.99 PREPARACION DE MEZCLA ASFALTICA E=2" EN CALIENTE 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 6,131,355.00 100.00% 6,131,355.00 TRANSPORTE DE MEZCLA ASFALTICA 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,270,399.54 100.00% 1,270,399.54 LIMPIEZA DE LA SUPERFICIE 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 203,850.00 100.00% 203,850.00 ESPARCIDO Y COMPACTADO 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 385,050.00 100.00% 385,050.00 OBRA DE ARTE - CUNETA TRIANGULAR TRABAJOS PRELIMINARES TRAZO Y REPLANTEO 0.00 0.00% 0.00 0.00% 593.07 25.55% 1,625.14 70.00% 103.42 4.45% 2,321.63 CUNETA DE CONCRETO FC=175 KG/CM2 0.00 0.00% 0.00 0.00% 0.00 0.00% 98,729.69 70.00% 42,312.73 30.00% 141,042.42 ENCOFRADO Y DESENCOFRADO DE CUNETA 0.00 0.00% 0.00 0.00% 0.00 0.00% 4,404.51 70.00% 1,887.65 30.00% 6,292.16 JUNTA ASFALTICA 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 7,395.40 100.00% 7,395.40 SEÑALIZACION SEÑALES INFORMATIVAS 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,000.60 100.00% 1,000.60 SEÑALES PREVENTIVAS 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,282.12 100.00% 1,282.12 SEÑALES REGLAMENTARIAS 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 10,490.55 100.00% 10,490.55 DEMARCACION EN EL PAVIMENTO 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 68,516.25 100.00% 68,516.25 PRUEBA DE CONTROL DE CALIDAD PRUEBA DE CALIDAD EN CONFORMACION DE SUB BASE Y BASE 3,000.00 20.00% 3,000.00 20.00% 3,000.00 20.00% 3,000.00 20.00% 3,000.00 20.00% 15,000.00 PRUEBA DE CALIDAD DE CONCRETO 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,500.00 50.00% 1,500.00 50.00% 3,000.00 FLETE TERRESTRE FLETE TERRESTRE 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,720.93 100.00% 2,720.93 COSTO DIRECTO 335,814.17 522,435.11 766,114.19 1,250,237.52 11,198,643.90 14,073,244.89 GASTOS GENERALES 11,122.40 17,303.42 25,374.25 41,408.76 370,907.07 466,115.90 SUPERVISION 7,969.83 12,398.88 18,182.09 29,671.72 265,775.96 333,998.49 LIQUIDACION 939.99 1,462.37 2,144.46 3,499.59 31,346.59 39,393.00 EXPEDIENTE TECNICO 3,147.50 4,896.65 7,180.59 11,718.15 104,961.96 131,904.84 TOTAL 358,993.90 558,496.43 818,995.57 1,336,535.75 11,971,635.47 15,044,657.12

description

cronograma de obra

Transcript of CRONOGRAMA----

Page 1: CRONOGRAMA----

CRONOGRAMA DE OBRA ACELERADOOBRA: MEJORAMIENTO DE LA CARRETERA HUANCANE - MOHO - CONIMA - TILALI (HANCCO HANCCO)

DESCRIPCION AGOSTO % SETIEMBRE % OCTUBRE % NOVIEMBRE % DICIEMBRE % PRESUPUESTOOBRAS PROVISIONALES

CAMPAMENTO DE OBRA 15,292.80 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 15,292.80

OBRAS PRELIMINARES

MOVILIZACION Y DEMOVILIZACION DE MAQUINARIA Y/O EQUIPO 10,000.00 25.00% 5,000.00 12.50% 0.00 0.00% 5,000.00 12.50% 20,000.00 50.00% 40,000.00

SEÑALIZACION DE SEGURIDAD Y/O DESVIO DE TRAFICO EN OBRA 4,000.00 25.00% 4,000.00 25.00% 4,000.00 25.00% 4,000.00 25.00% 0.00 0.00% 16,000.00

TRAZO Y REPLANTEO INICIAL 15,276.96 33.17% 4,981.03 10.82% 3,698.00 8.03% 2,264.60 4.92% 19,834.39 43.07% 46,054.99

EXPLANACIONES

EXTRACCION DE ROCA POR APLICACION DE VOLADURA 0.00 0.00% 0.00 0.00% 0.00 0.00% 24,288.00 25.00% 72,864.00 75.00% 97,152.00

DEQUINCHE Y CARGUIO DE ROCA 0.00 0.00% 0.00 0.00% 0.00 0.00% 29,367.78 25.00% 88,103.34 75.00% 117,471.12

TRANPORTE DE ROCA 0.00 0.00% 0.00 0.00% 0.00 0.00% 25,474.80 25.00% 76,424.40 75.00% 101,899.20

CHANCADO 0.00 0.00% 0.00 0.00% 0.00 0.00% 32,884.02 25.00% 98,652.06 75.00% 131,536.08

ZARANDEO DE MATERIAL 0.00 0.00% 0.00 0.00% 0.00 0.00% 8,055.06 25.00% 24,165.18 75.00% 32,220.24

CARGUIO DE MATERIAL CHANCADO 0.00 0.00% 0.00 0.00% 0.00 0.00% 4,951.44 25.00% 14,854.32 75.00% 19,805.76

TRANSPORTE DE MATERIAL CHANCADO 0.00 0.00% 0.00 0.00% 0.00 0.00% 18,944.64 25.00% 56,833.92 75.00% 75,778.56

PAVIMENTOS

SUB BASE (Reposicion)

TRAZO Y REPLANTEO. 62,853.75 30.00% 14,351.61 6.85% 52,378.13 25.00% 45,045.19 21.50% 34,883.83 16.65% 209,512.50

PERFILADO Y COMPACTADO SUB RASANTE 57,757.50 30.00% 13,187.96 6.85% 48,131.25 25.00% 41,392.88 21.50% 32,055.41 16.65% 192,525.01

RIEGO C/AGUA 18,686.25 30.00% 4,266.69 6.85% 15,571.88 25.00% 13,391.81 21.50% 10,370.87 16.65% 62,287.50

EXTRACCION Y APILAMIENTO DE MATERIAL SELECCIONADDO 21,445.41 42.20% 3,531.89 6.95% 12,704.63 25.00% 11,434.16 22.50% 1,702.42 3.35% 50,818.51

ZARANDEO DE MATERIAL 23,533.17 42.20% 3,875.72 6.95% 13,941.45 25.00% 12,547.31 22.50% 1,868.15 3.35% 55,765.80

CARGUIO DE MATERIAL SELECCIONADO 14,465.82 42.20% 2,382.40 6.95% 8,569.80 25.00% 7,712.82 22.50% 1,148.35 3.35% 34,279.20

TRANPORTE DE MATERIAL SELECCIONADO 55,347.50 42.20% 9,115.29 6.95% 32,788.80 25.00% 29,509.92 22.50% 4,393.70 3.35% 131,155.21

CONFORMACION DE SUB BASE C/EQUIPO PESADO 34,155.00 30.00% 7,798.73 6.85% 28,462.50 25.00% 24,477.75 21.50% 18,956.03 16.65% 113,850.01

BASE

TRAZO Y REPLANTEO 0.00 0.00% 22,941.62 10.95% 24,827.23 11.85% 39,702.62 18.95% 122,041.03 58.25% 209,512.50

EXTRACCION Y APILAMIENTO DE MATERIAL SELECCIONADO 0.00 0.00% 31,006.13 13.05% 33,976.07 14.30% 48,754.47 20.52% 123,858.22 52.13% 237,594.90

ZARANDEO DE MATERIAL 0.00 0.00% 34,024.66 13.05% 37,283.72 14.30% 53,500.84 20.52% 135,916.11 52.13% 260,725.33

CARGUIO DE MATERIAL SELECCIONADO 0.00 0.00% 20,914.93 13.05% 22,918.28 14.30% 32,886.93 20.52% 83,547.55 52.13% 160,267.69

TRANPORTE DE MATERIAL SELECCIONADO 0.00 0.00% 80,022.35 13.05% 87,687.33 14.30% 125,828.25 20.52% 319,660.16 52.13% 613,198.09

EXTRACCION Y APILAMIENTO DE MATERIAL HORMIGON Y/O PIEDRA CHANCADA 0.00 0.00% 4,932.73 13.05% 5,405.21 14.30% 7,756.29 20.52% 19,704.44 52.13% 37,798.66

CARGUIO DE MATERIAL HORMIGON Y/O PIEDRA CHANCADA 0.00 0.00% 3,559.30 13.05% 3,900.23 14.30% 5,596.69 20.52% 14,218.10 52.13% 27,274.32

TRANSPORTE DE MATERIAL HORMIGON 0.00 0.00% 9,620.42 13.05% 10,541.92 14.30% 15,127.29 20.52% 38,430.09 52.13% 73,719.72

MEZCLADO DE MATERIAL SELECCIONADO C/HORM. Y/O PIEDRA CHANCADA 0.00 0.00% 42,254.99 13.05% 46,302.41 14.30% 66,442.34 20.52% 168,793.32 52.13% 323,793.06

CARGUIO DE MATERIAL MEZCLADO 0.00 0.00% 27,058.88 13.05% 29,650.73 14.30% 42,547.76 20.52% 108,090.39 52.13% 207,347.76

TRANSPORTE DE MATERIAL MEZCLADO 0.00 0.00% 53,333.45 13.05% 58,442.02 14.30% 83,862.25 20.52% 213,047.73 52.13% 408,685.45

RIEGO C/AGUA 0.00 0.00% 6,820.48 10.95% 7,381.07 11.85% 11,803.48 18.95% 36,282.46 58.25% 62,287.49

CONFORMACION DE BASE C/EQUIPO PESADO 0.00 0.00% 51,153.61 10.95% 55,358.02 11.85% 88,526.11 18.95% 272,118.52 58.25% 467,156.25

PAVIMENTO FLEXIBLE

TRAZO Y REPLANTEO. 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 4,758.01 100.00% 4,758.01

BARRIDO DE PLATAFORMA 0.00 0.00% 4,869.75 5.00% 9,739.50 10.00% 14,609.25 15.00% 68,176.50 70.00% 97,395.00

IMPRIMACION 0.00 0.00% 52,982.13 5.00% 105,964.25 10.00% 158,946.38 15.00% 741,749.75 70.00% 1,059,642.50

EXTRACCION Y APILAMIENTO DE ARENA 0.00 0.00% 121.29 5.00% 242.58 10.00% 363.87 15.00% 1,698.07 70.00% 2,425.82

CARGUIO DE ARENA 0.00 0.00% 72.93 5.00% 145.87 10.00% 218.80 15.00% 1,021.06 70.00% 1,458.66

TRANSPORTE DE ARENA 0.00 0.00% 197.13 5.00% 394.26 10.00% 591.39 15.00% 2,759.82 70.00% 3,942.60

ARENADO 0.00 0.00% 1,057.00 5.00% 2,114.00 10.00% 3,171.00 15.00% 14,797.99 70.00% 21,139.99

PREPARACION DE MEZCLA ASFALTICA E=2" EN CALIENTE 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 6,131,355.00 100.00% 6,131,355.00

TRANSPORTE DE MEZCLA ASFALTICA 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,270,399.54 100.00% 1,270,399.54

LIMPIEZA DE LA SUPERFICIE 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 203,850.00 100.00% 203,850.00

ESPARCIDO Y COMPACTADO 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 385,050.00 100.00% 385,050.00

OBRA DE ARTE - CUNETA TRIANGULAR

TRABAJOS PRELIMINARES

TRAZO Y REPLANTEO 0.00 0.00% 0.00 0.00% 593.07 25.55% 1,625.14 70.00% 103.42 4.45% 2,321.63

CUNETA DE CONCRETO FC=175 KG/CM2 0.00 0.00% 0.00 0.00% 0.00 0.00% 98,729.69 70.00% 42,312.73 30.00% 141,042.42

ENCOFRADO Y DESENCOFRADO DE CUNETA 0.00 0.00% 0.00 0.00% 0.00 0.00% 4,404.51 70.00% 1,887.65 30.00% 6,292.16

JUNTA ASFALTICA 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 7,395.40 100.00% 7,395.40

SEÑALIZACION

SEÑALES INFORMATIVAS 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,000.60 100.00% 1,000.60

SEÑALES PREVENTIVAS 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,282.12 100.00% 1,282.12

SEÑALES REGLAMENTARIAS 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 10,490.55 100.00% 10,490.55

DEMARCACION EN EL PAVIMENTO 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 68,516.25 100.00% 68,516.25

PRUEBA DE CONTROL DE CALIDAD

PRUEBA DE CALIDAD EN CONFORMACION DE SUB BASE Y BASE 3,000.00 20.00% 3,000.00 20.00% 3,000.00 20.00% 3,000.00 20.00% 3,000.00 20.00% 15,000.00

PRUEBA DE CALIDAD DE CONCRETO 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,500.00 50.00% 1,500.00 50.00% 3,000.00

FLETE TERRESTRE

FLETE TERRESTRE 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,720.93 100.00% 2,720.93

COSTO DIRECTO 335,814.17 522,435.11 766,114.19 1,250,237.52 11,198,643.90 14,073,244.89

GASTOS GENERALES 11,122.40 17,303.42 25,374.25 41,408.76 370,907.07 466,115.90

SUPERVISION 7,969.83 12,398.88 18,182.09 29,671.72 265,775.96 333,998.49

LIQUIDACION 939.99 1,462.37 2,144.46 3,499.59 31,346.59 39,393.00

EXPEDIENTE TECNICO 3,147.50 4,896.65 7,180.59 11,718.15 104,961.96 131,904.84

TOTAL 358,993.90 558,496.43 818,995.57 1,336,535.75 11,971,635.47 15,044,657.12

Page 2: CRONOGRAMA----

AVANCE 2.39% 3.71% 5.44% 8.88% 79.57%

Page 3: CRONOGRAMA----

CRONOGRAMA DE OBRA ACELERADOOBRA: MEJORAMIENTO DE LA CARRETERA HUANCANE - MOHO - CONIMA - TILALI (HANCCO HANCCO)

DESCRIPCION AGOSTO % SETIEMBRE % OCTUBRE % NOVIEMBRE % DICIEMBRE % PRESUPUESTOOBRAS PROVISIONALES

CAMPAMENTO DE OBRA 15,292.80 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 15,292.80

OBRAS PRELIMINARES

MOVILIZACION Y DEMOVILIZACION DE MAQUINARIA Y/O EQUIPO 10,000.00 25.00% 5,000.00 12.50% 0.00 0.00% 5,000.00 12.50% 20,000.00 50.00% 40,000.00

SEÑALIZACION DE SEGURIDAD Y/O DESVIO DE TRAFICO EN OBRA 4,000.00 25.00% 4,000.00 25.00% 4,000.00 25.00% 4,000.00 25.00% 0.00 0.00% 16,000.00

TRAZO Y REPLANTEO INICIAL 15,276.96 33.17% 4,981.03 10.82% 3,698.00 8.03% 2,264.60 4.92% 19,834.39 43.07% 46,054.99

EXPLANACIONES

EXTRACCION DE ROCA POR APLICACION DE VOLADURA 0.00 0.00% 0.00 0.00% 0.00 0.00% 24,288.00 25.00% 72,864.00 75.00% 97,152.00

DEQUINCHE Y CARGUIO DE ROCA 0.00 0.00% 0.00 0.00% 0.00 0.00% 29,367.78 25.00% 88,103.34 75.00% 117,471.12

TRANPORTE DE ROCA 0.00 0.00% 0.00 0.00% 0.00 0.00% 25,474.80 25.00% 76,424.40 75.00% 101,899.20

CHANCADO 0.00 0.00% 0.00 0.00% 0.00 0.00% 32,884.02 25.00% 98,652.06 75.00% 131,536.08

ZARANDEO DE MATERIAL 0.00 0.00% 0.00 0.00% 0.00 0.00% 8,055.06 25.00% 24,165.18 75.00% 32,220.24

CARGUIO DE MATERIAL CHANCADO 0.00 0.00% 0.00 0.00% 0.00 0.00% 4,951.44 25.00% 14,854.32 75.00% 19,805.76

TRANSPORTE DE MATERIAL CHANCADO 0.00 0.00% 0.00 0.00% 0.00 0.00% 18,944.64 25.00% 56,833.92 75.00% 75,778.56

PAVIMENTOS

SUB BASE (Reposicion)

TRAZO Y REPLANTEO. 62,853.75 30.00% 14,351.61 6.85% 52,378.13 25.00% 45,045.19 21.50% 34,883.83 16.65% 209,512.50

PERFILADO Y COMPACTADO SUB RASANTE 57,757.50 30.00% 13,187.96 6.85% 48,131.25 25.00% 41,392.88 21.50% 32,055.41 16.65% 192,525.01

RIEGO C/AGUA 18,686.25 30.00% 4,266.69 6.85% 15,571.88 25.00% 13,391.81 21.50% 10,370.87 16.65% 62,287.50

EXTRACCION Y APILAMIENTO DE MATERIAL SELECCIONADDO 21,445.41 42.20% 3,531.89 6.95% 12,704.63 25.00% 11,434.16 22.50% 1,702.42 3.35% 50,818.51

ZARANDEO DE MATERIAL 23,533.17 42.20% 3,875.72 6.95% 13,941.45 25.00% 12,547.31 22.50% 1,868.15 3.35% 55,765.80

CARGUIO DE MATERIAL SELECCIONADO 14,465.82 42.20% 2,382.40 6.95% 8,569.80 25.00% 7,712.82 22.50% 1,148.35 3.35% 34,279.20

TRANPORTE DE MATERIAL SELECCIONADO 55,347.50 42.20% 9,115.29 6.95% 32,788.80 25.00% 29,509.92 22.50% 4,393.70 3.35% 131,155.21

CONFORMACION DE SUB BASE C/EQUIPO PESADO 34,155.00 30.00% 7,798.73 6.85% 28,462.50 25.00% 24,477.75 21.50% 18,956.03 16.65% 113,850.01

BASE

TRAZO Y REPLANTEO 0.00 0.00% 22,941.62 10.95% 24,827.23 11.85% 39,702.62 18.95% 122,041.03 58.25% 209,512.50

EXTRACCION Y APILAMIENTO DE MATERIAL SELECCIONADO 0.00 0.00% 31,006.13 13.05% 33,976.07 14.30% 48,754.47 20.52% 123,858.22 52.13% 237,594.90

ZARANDEO DE MATERIAL 0.00 0.00% 34,024.66 13.05% 37,283.72 14.30% 53,500.84 20.52% 135,916.11 52.13% 260,725.33

CARGUIO DE MATERIAL SELECCIONADO 0.00 0.00% 20,914.93 13.05% 22,918.28 14.30% 32,886.93 20.52% 83,547.55 52.13% 160,267.69

TRANPORTE DE MATERIAL SELECCIONADO 0.00 0.00% 80,022.35 13.05% 87,687.33 14.30% 125,828.25 20.52% 319,660.16 52.13% 613,198.09

EXTRACCION Y APILAMIENTO DE MATERIAL HORMIGON Y/O PIEDRA CHANCADA 0.00 0.00% 4,932.73 13.05% 5,405.21 14.30% 7,756.29 20.52% 19,704.44 52.13% 37,798.66

CARGUIO DE MATERIAL HORMIGON Y/O PIEDRA CHANCADA 0.00 0.00% 3,559.30 13.05% 3,900.23 14.30% 5,596.69 20.52% 14,218.10 52.13% 27,274.32

TRANSPORTE DE MATERIAL HORMIGON 0.00 0.00% 9,620.42 13.05% 10,541.92 14.30% 15,127.29 20.52% 38,430.09 52.13% 73,719.72

MEZCLADO DE MATERIAL SELECCIONADO C/HORM. Y/O PIEDRA CHANCADA 0.00 0.00% 42,254.99 13.05% 46,302.41 14.30% 66,442.34 20.52% 168,793.32 52.13% 323,793.06

CARGUIO DE MATERIAL MEZCLADO 0.00 0.00% 27,058.88 13.05% 29,650.73 14.30% 42,547.76 20.52% 108,090.39 52.13% 207,347.76

TRANSPORTE DE MATERIAL MEZCLADO 0.00 0.00% 53,333.45 13.05% 58,442.02 14.30% 83,862.25 20.52% 213,047.73 52.13% 408,685.45

RIEGO C/AGUA 0.00 0.00% 6,820.48 10.95% 7,381.07 11.85% 11,803.48 18.95% 36,282.46 58.25% 62,287.49

CONFORMACION DE BASE C/EQUIPO PESADO 0.00 0.00% 51,153.61 10.95% 55,358.02 11.85% 88,526.11 18.95% 272,118.52 58.25% 467,156.25

PAVIMENTO FLEXIBLE

TRAZO Y REPLANTEO. 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 4,758.01 100.00% 4,758.01

BARRIDO DE PLATAFORMA 0.00 0.00% 4,869.75 5.00% 9,739.50 10.00% 14,609.25 15.00% 68,176.50 70.00% 97,395.00

IMPRIMACION 0.00 0.00% 52,982.13 5.00% 105,964.25 10.00% 158,946.38 15.00% 741,749.75 70.00% 1,059,642.50

EXTRACCION Y APILAMIENTO DE ARENA 0.00 0.00% 121.29 5.00% 242.58 10.00% 363.87 15.00% 1,698.07 70.00% 2,425.82

CARGUIO DE ARENA 0.00 0.00% 72.93 5.00% 145.87 10.00% 218.80 15.00% 1,021.06 70.00% 1,458.66

TRANSPORTE DE ARENA 0.00 0.00% 197.13 5.00% 394.26 10.00% 591.39 15.00% 2,759.82 70.00% 3,942.60

ARENADO 0.00 0.00% 1,057.00 5.00% 2,114.00 10.00% 3,171.00 15.00% 14,797.99 70.00% 21,139.99

PREPARACION DE MEZCLA ASFALTICA E=2" EN CALIENTE 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 6,131,355.00 100.00% 6,131,355.00

TRANSPORTE DE MEZCLA ASFALTICA 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,270,399.54 100.00% 1,270,399.54

LIMPIEZA DE LA SUPERFICIE 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 203,850.00 100.00% 203,850.00

ESPARCIDO Y COMPACTADO 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 385,050.00 100.00% 385,050.00

OBRA DE ARTE - CUNETA TRIANGULAR

TRABAJOS PRELIMINARES

TRAZO Y REPLANTEO 0.00 0.00% 0.00 0.00% 593.07 25.55% 1,625.14 70.00% 103.42 4.45% 2,321.63

CUNETA DE CONCRETO FC=175 KG/CM2 0.00 0.00% 0.00 0.00% 0.00 0.00% 98,729.69 70.00% 42,312.73 30.00% 141,042.42

ENCOFRADO Y DESENCOFRADO DE CUNETA 0.00 0.00% 0.00 0.00% 0.00 0.00% 4,404.51 70.00% 1,887.65 30.00% 6,292.16

JUNTA ASFALTICA 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 7,395.40 100.00% 7,395.40

SEÑALIZACION

SEÑALES INFORMATIVAS 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,000.60 100.00% 1,000.60

SEÑALES PREVENTIVAS 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,282.12 100.00% 1,282.12

SEÑALES REGLAMENTARIAS 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 10,490.55 100.00% 10,490.55

DEMARCACION EN EL PAVIMENTO 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 68,516.25 100.00% 68,516.25

PRUEBA DE CONTROL DE CALIDAD

PRUEBA DE CALIDAD EN CONFORMACION DE SUB BASE Y BASE 3,000.00 20.00% 3,000.00 20.00% 3,000.00 20.00% 3,000.00 20.00% 3,000.00 20.00% 15,000.00

PRUEBA DE CALIDAD DE CONCRETO 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,500.00 50.00% 1,500.00 50.00% 3,000.00

FLETE TERRESTRE

FLETE TERRESTRE 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,720.93 100.00% 2,720.93

COSTO DIRECTO 335,814.17 522,435.11 766,114.19 1,250,237.52 11,198,643.90 14,073,244.89

GASTOS GENERALES 11,122.40 17,303.42 25,374.25 41,408.76 370,907.07 466,115.90

SUPERVISION 7,969.83 12,398.88 18,182.09 29,671.72 265,775.96 333,998.49

LIQUIDACION 939.99 1,462.37 2,144.46 3,499.59 31,346.59 39,393.00

EXPEDIENTE TECNICO 3,147.50 4,896.65 7,180.59 11,718.15 104,961.96 131,904.84

TOTAL 358,993.90 558,496.43 818,995.57 1,336,535.75 11,971,635.47 15,044,657.12

Page 4: CRONOGRAMA----

AVANCE 2.39% 3.71% 5.44% 8.88% 79.57%

Page 5: CRONOGRAMA----

PLAN DE TRABAJO 01OBRA: MEJORAMIENTO DE LA CARRETERA HUANCANE - MOHO - CONIMA - TILALI (HANCCO HANCCO)

DESCRIPCIONNOVIEMBRE

SEMANA 1

BASE

EXTRACCION, CARGUIO Y TRANSPORTE DE MATERIAL SELECCIONADO 12000 - 16914

CONFORMACION DE BASE 9000 - 13725

PAVIMENTO FLEXIBLE

BARRIDO DE PLATAFORMA, IMPRIMADO Y ARENADO 6000 - 10500

PREPARACION, TRANSPORTE, ESPARCIDO Y COMPACTADO DE MEZCLA ASFALTICA 0 - 5000

MAQUINARIA A UTILIZAR CANTIDAD

CONFORMACION DE TERRAPLEN

VOLQUETES 26

MOTONIVELADORAS 3

RODILLOS 6

CISTERNAS 6

CARGADOR FRONTAL 2

EXCAVADORA 2

TRACTOR ORUGA 1

IMPRIMACION

COMPRESORA 1

CAMION IMPRIMADOR 1

MEZCLA ASFALTICA

PLANTA ASFALTADORA 1

ESPARCIDORA 1

RODILLOS TANDEM Y NEUMATICO 2

MODALIDAD DE TRABAJO: LOS VOLQUETES TRABAJAN A DOBLE TURNO A 09 HORAS X TURNO, LOS DEMAS EQUIPOS EN HORARIO NORMAL

Page 6: CRONOGRAMA----

PLAN DE TRABAJO 01OBRA: MEJORAMIENTO DE LA CARRETERA HUANCANE - MOHO - CONIMA - TILALI (HANCCO HANCCO)

NOVIEMBRE DICIEMBRE

SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6

16914 - 21828 21828 - 26742 26742 - 31656 31656 - 36570 36570 - 37700

13725 - 18450 18450 - 23175 23175 - 27900 27900 - 32625 32625 - 37350

10500 - 15000 15000 - 19500 19500 - 24000 24000 - 28500 28500 - 33000

5000 - 10000 10000 - 15000 15000 - 20000 20000 - 25000 25000 - 30000

REND./DIA HORAS TRAB./DIA REND./DIA/MAQ.

936 m 18 36

900 m 8 300

900 m 8 300

900 m 8 300

18

8

8

1500 m 8

1500 m 8

1000 m 8 1000

1000 m 8 1000

1000 m 8 1000

MODALIDAD DE TRABAJO: LOS VOLQUETES TRABAJAN A DOBLE TURNO A 09 HORAS X TURNO, LOS DEMAS EQUIPOS EN HORARIO NORMAL

Page 7: CRONOGRAMA----

PLAN DE TRABAJO 01OBRA: MEJORAMIENTO DE LA CARRETERA HUANCANE - MOHO - CONIMA - TILALI (HANCCO HANCCO)

DICIEMBRE

SEMANA 7 SEMANA 8

37350 - 37700

33000 - 37500 37500 - 37700

30000 - 35000 35000 - 37700

Page 8: CRONOGRAMA----

PLAN DE TRABAJO 02OBRA: MEJORAMIENTO DE LA CARRETERA HUANCANE - MOHO - CONIMA - TILALI (HANCCO HANCCO)

DESCRIPCION

BASE

EXTRACCION, CARGUIO Y TRANSPORTE DE MATERIAL SELECCIONADO

CONFORMACION DE BASE

PAVIMENTO FLEXIBLE

BARRIDO DE PLATAFORMA, IMPRIMADO Y ARENADO

PREPARACION, TRANSPORTE, ESPARCIDO Y COMPACTADO DE MEZCLA ASFALTICA

MAQUINARIA A UTILIZAR

CONFORMACION DE TERRAPLEN

VOLQUETES

MOTONIVELADORAS

RODILLOS

CISTERNAS

CARGADOR FRONTAL

EXCAVADORA

TRACTOR ORUGA

IMPRIMACION

COMPRESORA

CAMION IMPRIMADOR

MEZCLA ASFALTICA

PLANTA ASFALTADORA

ESPARCIDORA

RODILLOS TANDEM Y NEUMATICO

MODALIDAD DE TRABAJO: LOS VOLQUETES TRABAJAN A TURNO Y MEDIO, LOS DEMAS EQUIPOS EN HORARIO NORMAL

Page 9: CRONOGRAMA----

PLAN DE TRABAJO 02OBRA: MEJORAMIENTO DE LA CARRETERA HUANCANE - MOHO - CONIMA - TILALI (HANCCO HANCCO)

NOVIEMBRE DICIEMBRE

SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5

12000 - 13638 13638 - 15276 15276 - 16914 16914 - 18552 18552 - 20190

9000 - 12000 12000 - 15000 15000 - 16000 16000 - 18000 18000 - 20000

6000 - 8250 8250 - 10500 10500 - 12750 12750 - 15000 15000 - 17250

0 - 2500 2500 - 5000 5000 - 7500 7500 - 10000 10000 - 12500

CANTIDAD REND./DIA HORAS TRAB./DIA REND./DIA/MAQ.

13 312 m 12 24

2 600 m 8 300

3 600 m 8 300

3 600 m 8 300

1 12

1 8

1 8

1 1500 m 8

1 1500 m 8

1 500 m 4 500

1 500 m 4 500

2 500 m 4 500

MODALIDAD DE TRABAJO: LOS VOLQUETES TRABAJAN A TURNO Y MEDIO, LOS DEMAS EQUIPOS EN HORARIO NORMAL

Page 10: CRONOGRAMA----

PLAN DE TRABAJO 02OBRA: MEJORAMIENTO DE LA CARRETERA HUANCANE - MOHO - CONIMA - TILALI (HANCCO HANCCO)

DICIEMBRE

SEMANA 6 SEMANA 7 SEMANA 8

20190 - 21828 21828 - 23466 23466 - 25104

20000 - 21800 21800 - 23000 23000 - 25000

17250 - 19500 19500 - 21750 21750 - 24000

12500 - 15000 15000 - 17500 17500 - 20000

Page 11: CRONOGRAMA----

PLAN DE TRABAJO 03OBRA: MEJORAMIENTO DE LA CARRETERA HUANCANE - MOHO - CONIMA - TILALI (HANCCO HANCCO)

DESCRIPCION

BASE

EXTRACCION, CARGUIO Y TRANSPORTE DE MATERIAL SELECCIONADO

CONFORMACION DE BASE

PAVIMENTO FLEXIBLE

BARRIDO DE PLATAFORMA, IMPRIMADO Y ARENADO

PREPARACION, TRANSPORTE, ESPARCIDO Y COMPACTADO DE MEZCLA ASFALTICA

MAQUINARIA A UTILIZAR

CONFORMACION DE TERRAPLEN

VOLQUETES

MOTONIVELADORAS

RODILLOS

CISTERNAS

CARGADOR FRONTAL

EXCAVADORA

TRACTOR ORUGA

IMPRIMACION

COMPRESORA

CAMION IMPRIMADOR

MEZCLA ASFALTICA

PLANTA ASFALTADORA

ESPARCIDORA

RODILLOS TANDEM Y NEUMATICO

MODALIDAD DE TRABAJO: LOS VOLQUETES TRABAJAN TODOS LOS DIAS DE LA SEMANA A 10 HORAS X DIA, LOS DEMAS EQUIPOS EN HORARIO NORMAL

Page 12: CRONOGRAMA----

PLAN DE TRABAJO 03OBRA: MEJORAMIENTO DE LA CARRETERA HUANCANE - MOHO - CONIMA - TILALI (HANCCO HANCCO)

NOVIEMBRE DICIEMBRE

SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5

12000 - 15640 15640 - 19280 19280 - 22920 22920 - 26560 26560 - 30200

9000 - 13500 13500 - 18000 18000 - 22500 22500 - 26000 26000 - 30000

6000 - 10500 10500 - 15000 15000 - 19500 19500 - 24000 24000 - 28500

0 - 5000 5000 - 10000 10000 - 15000 15000 - 20000 20000 - 25000

CANTIDAD REND./DIA HORAS TRAB./DIA REND./DIA/MAQ.

26 520 m 10 20

3 900 m 8 300

6 900 m 8 300

6 900 m 8 300

2 10

2 8

1 8

1 1500 m 8

1 1500 m 8

1 1000 m 8 1000

1 1000 m 8 1000

2 1000 m 8 1000

MODALIDAD DE TRABAJO: LOS VOLQUETES TRABAJAN TODOS LOS DIAS DE LA SEMANA A 10 HORAS X DIA, LOS DEMAS EQUIPOS EN HORARIO NORMAL

Page 13: CRONOGRAMA----

PLAN DE TRABAJO 03OBRA: MEJORAMIENTO DE LA CARRETERA HUANCANE - MOHO - CONIMA - TILALI (HANCCO HANCCO)

DICIEMBRE

SEMANA 6 SEMANA 7 SEMANA 8

30200 - 33840 33840 - 37480 37480 - 37700

30000 - 33000 33000 - 37000 37000 - 37700

28500 - 33000 33000 - 37000 37000 - 37700

25000 - 30000 30000 - 35000 35000 - 37700

Page 14: CRONOGRAMA----

PLAN DE TRABAJO 02OBRA: MEJORAMIENTO DE LA CARRETERA HUANCANE - MOHO - CONIMA - TILALI (HANCCO HANCCO)

DESCRIPCION

BASE

EXTRACCION, CARGUIO Y TRANSPORTE DE MATERIAL SELECCIONADO

CONFORMACION DE BASE

PAVIMENTO FLEXIBLE

BARRIDO DE PLATAFORMA, IMPRIMADO Y ARENADO

PREPARACION, TRANSPORTE, ESPARCIDO Y COMPACTADO DE MEZCLA ASFALTICA

MAQUINARIA A UTILIZAR

CONFORMACION DE TERRAPLEN

VOLQUETES

MOTONIVELADORAS

RODILLOS

CISTERNAS

CARGADOR FRONTAL

EXCAVADORA

TRACTOR ORUGA

IMPRIMACION

COMPRESORA

CAMION IMPRIMADOR

MEZCLA ASFALTICA

PLANTA ASFALTADORA

ESPARCIDORA

RODILLOS TANDEM Y NEUMATICO

MODALIDAD DE TRABAJO: LOS VOLQUETES TRABAJAN A TURNO Y MEDIO Y LOS 07 DIAS DE LA SEMANA, LOS DEMAS EQUIPOS EN HORARIO NORMAL

Page 15: CRONOGRAMA----

PLAN DE TRABAJO 02OBRA: MEJORAMIENTO DE LA CARRETERA HUANCANE - MOHO - CONIMA - TILALI (HANCCO HANCCO)

NOVIEMBRE DICIEMBRE

SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5

12000 - 14184 14184 - 16368 16368 - 18552 18552 - 20736 20736 - 22920

9000 - 12000 12000 - 15000 15000 - 18000 18000 - 20000 20000 - 22000

6000 - 9000 9000 - 12000 12000 - 15000 15000 - 18000 18000 - 21000

0 - 2500 2500 - 5000 5000 - 7500 7500 - 10000 10000 - 12500

CANTIDAD REND./DIA HORAS TRAB./DIA REND./DIA/MAQ.

13 312 m 12 24

2 600 m 8 300

3 600 m 8 300

3 600 m 8 300

1 12

1 8

1 8

1 1500 m 8

1 1500 m 8

1 500 m 4 500

1 500 m 4 500

2 500 m 4 500

MODALIDAD DE TRABAJO: LOS VOLQUETES TRABAJAN A TURNO Y MEDIO Y LOS 07 DIAS DE LA SEMANA, LOS DEMAS EQUIPOS EN HORARIO NORMAL

Page 16: CRONOGRAMA----

PLAN DE TRABAJO 02OBRA: MEJORAMIENTO DE LA CARRETERA HUANCANE - MOHO - CONIMA - TILALI (HANCCO HANCCO)

DICIEMBRE

SEMANA 6 SEMANA 7 SEMANA 8

22920 - 25104 25104 - 27288 27288 - 29472

22000 - 25000 25000 - 27000 27000 - 29000

21000 - 24000 24000 - 27000 27000 - 29000

12500 - 15000 15000 - 17500 17500 - 20000

Page 17: CRONOGRAMA----

PLAN DE TRABAJO MES DE NOVIEMBREOBRA: MEJORAMIENTO DE LA CARRETERA HUANCANE - MOHO - CONIMA - TILALI (HANCCO HANCCO)

DESCRIPCION

BASE

EXTRACCION, CARGUIO Y TRANSPORTE DE MATERIAL SELECCIONADO

CONFORMACION DE BASE

PAVIMENTO FLEXIBLE

BARRIDO DE PLATAFORMA, IMPRIMADO Y ARENADO

PREPARACION, TRANSPORTE, ESPARCIDO Y COMPACTADO DE MEZCLA ASFALTICA

MAQUINARIA A UTILIZAR

CONFORMACION DE TERRAPLEN

VOLQUETES

MOTONIVELADORAS

RODILLOS

CISTERNAS

CARGADOR FRONTAL

EXCAVADORA

TRACTOR ORUGA

IMPRIMACION

COMPRESORA

CAMION IMPRIMADOR

MEZCLA ASFALTICA

PLANTA ASFALTADORA

ESPARCIDORA

RODILLOS TANDEM Y NEUMATICO

MODALIDAD DE TRABAJO: LOS VOLQUETES TRABAJAN A TURNO Y MEDIO, LOS DEMAS EQUIPOS EN HORARIO NORMAL

Page 18: CRONOGRAMA----

PLAN DE TRABAJO MES DE NOVIEMBREOBRA: MEJORAMIENTO DE LA CARRETERA HUANCANE - MOHO - CONIMA - TILALI (HANCCO HANCCO)

NOVIEMBRE

SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 DIAS/TRA.

12000 14,031.25 16,062.50 18,093.75

14,031.25 16,062.50 18,093.75 20,125.00 5

12000 - 14031 14031 - 16063 16063 - 18094 18094 - 20125

9,000.00 12,000.00 15,000.00 18,000.00

12,000.00 15,000.00 18,000.00 21,000.00 5

9000 - 12000 12000 - 15000 15000 - 18000 18000 - 21000

6,500.00 9,500.00 12,500.00 15,500.00

9,500.00 12,500.00 15,500.00 18,500.00 2

6500 - 9500 9500 - 12500 12500 - 15500 15500 - 18500

0.00 2,500.00 5,000.00 7,500.00

2,500.00 5,000.00 7,500.00 10,000.00 5

0 - 2500 2500 - 5000 5000 - 7500 7500 - 10000

CANTIDAD REND./DIA HORAS TRAB./DIA REND./DIA/MAQ.

13 406 m 12 31.25

2 600 m 8 300

3 600 m 8 300

3 600 m 8 300

2 12

1 8

1 8

1 1500 m 8

1 1500 m 8

1 500 m 4 500

1 500 m 4 500

2 500 m 4 500

MODALIDAD DE TRABAJO: LOS VOLQUETES TRABAJAN A TURNO Y MEDIO, LOS DEMAS EQUIPOS EN HORARIO NORMAL

Page 19: CRONOGRAMA----

VIAJES VOLUMEN PARCIAL METROS

5 12 50.00 31.25 4062.5

Page 20: CRONOGRAMA----

PROYECCION DE LOS TRABAJOS PARA EL MES DE NOVIEMBRE

OBRA: MEJORAMIENTO DE LA CARRETERA HUANCANE-MOHO-CONIMA-TILALI (HANCCO HANCCO)

COD DESCRIPCION UND D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

01.00.00 OBRAS PROVISIONALES

01.01.00 CAMPAMENTO DE OBRA m2

02.00.00 OBRAS PRELIMINARES

02.01.00 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA Y/O EQUIPO GLB

02.02.00 SEÑALIZACION DE SEGURIDAD Y/O DESVIO DE TRAFICO EN OBRA GLB

02.03.00 TRAZO Y REPLANTEO INICIAL. m

03.00.00 EXPLANACIONES

03.01.00 EXTRACCION DE ROCA POR APLICACION DE VOLADURA m3

03.02.00 DESQUINCHE Y CARGUIO DE ROCA m3

03.03.00 TRANSPORTE DE ROCA m3

03.04.00 CHANCADO m3

03.05.00 ZARANDEO DE MATERIAL m3

03.06.00 CARGUIO DE MATERIAL CHANCADO m3

03.07.00 TRANSPORTE DE MATERIAL CHANCADO m3

04.00.00 PAVIMENTOS

04.02.00 BASE

04.02.01 TRAZO Y REPLANTEO. m2 55,200.00

04.02.02 EXTRACCION Y APILAMIENTO DE MATERIAL SELECCIONADDO m3 11,040.00

04.02.03 ZARANDEO DE MATERIAL m3 13,248.00

04.02.04 CARGUIO DE MATERIAL SELECCIONADO m3 13,248.00

04.02.05 TRANSPORTE DE MATERIAL SELECCIONADO m3 13,248.00

12+

000

13+

500

13+

500

15+

200

15+

200

16+

900

16+

900

18+

600

18+

900

Long. = 1,500.00 ml Long. = 1,700.00 ml Long. = 1,700.00 ml Long. = 1,700.00 ml

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

20

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

20

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

20

0 m

l/dia

30

0 m

l/dia

12+

300

12+

600

12+

900

13+

200

13+

500

13+

800

14+

100

14+

400

14+

700

15+

000

15+

200

15+

500

15+

800

16+

100

16+

400

16+

700

16+

900

17+

200

17+

500

17+

800

18+

100

18+

400

18+

600

18+

900

04.02.12 RIEGO C/AGUA m2 57,600.00

04.02.13 CONFORMACION DE BASE C/EQUIPO PESADO m2 57,600.00

7+8

00

9+3

00

9+3

00

11+

100

11+

100

12+

900

12+

900

14+

700

15+

000

Long. = 1,500.00 ml Long. = 1,800.00 ml Long. = 1,800.00 ml Long. = 1,800.00 ml

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

8+1

00

8+4

00

8+7

00

9+0

00

9+3

00

9+6

00

9+9

00

10+

200

10+

500

10+

800

11+

100

11+

400

11+

700

12+

000

12+

300

12+

600

12+

900

13+

200

13+

500

13+

800

14+

100

14+

400

14+

700

15+

000

04.03.00 PAVIMENTO FLEXIBLE

04.03.01 TRAZO Y REPLANTEO. KM 7.40

04.03.02 BARRIDO DE PLATAFORMA m2 59,200.00

04.03.03 IMPRIMACION m2 59,200.00

METRADO A

EJECUTAR EN EL MES

Page 21: CRONOGRAMA----

PROYECCION DE LOS TRABAJOS PARA EL MES DE NOVIEMBRE

OBRA: MEJORAMIENTO DE LA CARRETERA HUANCANE-MOHO-CONIMA-TILALI (HANCCO HANCCO)

COD DESCRIPCION UND D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

METRADO A

EJECUTAR EN EL MES

04.03.04 EXTRACCION Y APILAMIENTO DE ARENA m3 2,960.00

04.03.05 CARGUIO DE ARENA m3 2,960.00

04.03.06 TRANSPORTE DE ARENA m3 2,960.00

04.03.07 ARENADO m2 59,200.00

6+5

00

8+2

00

8+2

00

10+

000

10+

000

11+

800

11+

800

13+

600

13+

900

Long. = 1,700.00 ml Long. = 1,800.00 ml Long. = 1,800.00 ml Long. = 1,800.00 ml

50

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

30

0 m

l/dia

7+0

00

7+3

00

7+6

00

7+9

00

8+2

00

8+5

00

8+8

00

9+1

00

9+4

00

9+7

00

10+

000

10+

300

10+

600

10+

900

11+

200

11+

500

11+

800

12+

100

12+

400

12+

700

13+

000

13+

300

13+

600

13+

900

05.00.00 OBRAS DE ARTE - CUNETAS TRIANGULAR

05.01.00 TRABAJOS PRELIMINARES

05.01.01 TRAZO Y REPLANTEO m 1,700.00

05.01.02 CUNETAS DE CONCRETO FC=175 KG/CM2 m3 150.00

05.01.03 ENCOFRADO Y DESENCOFRADO DE CUNETAS m2 350.00

05.01.04 JUNTAS ASFALTICAS m 700.00

07.00.00 PRUBA DE CONTROL DE CALIDAD

07.01.00 PRUEBAS DE CALIDAD EN CONFORMACION DE SUB BASE Y BASE GLB 0.25

07.02.00 PRUEBAS DE CALIDAD DE CONCRETOS GLB 0.25

08.00.00 FLETE TERRESTRE

08.01.00 FLETE TERRESTRE GLB 0.25