Anexo Acta de Ajustes

13
ANEXO AL ACTA No.006 DE AJUSTE DE PRECIOS AL CONTRATO 199 DE 2008 CORRESPONDIENTE AL ACTA DE RECIBO PARCIAL DE OBRA No. 1 DEL MES DE MARZO AÑO 2009 DATOS BASICOS: MES DE INICIO NOVIEMBRE DE 2008 VALOR TONELADA DE ASFALTO 80/100 INICIAL (6) $ 1,150,405.00 ICCP INICIAL (9) 124.05 ICCP ENERO DE 2009 124.71 MES DE AJUSTE MARZO DE 2009 VALOR TONELADA DE ASFALTO 80/100 MES DE AJUSTE (5) 740,000.00 ICCP MES DE AJUSTE (8) 124.24 AJUSTES POR ASFALTO ITEM DESCRIPCIÓN UND. 3,2,7 M2 2,121.00 924.60 1,196.40 3,735.14 -1,232,034.00 6,865.00 -1,225,169.00 3,2,11 M3 455,112.00 154,154.00 300,958.00 373.80 -20,556,822.00 172,817.00 -20,384,005.00 AJUSTE TOTAL POR ASFALTO -21,609,174.00 AJUSTES OTROS ITEMS VALOR A AJUSTAR SIN ASFALTOS (11) TOTAL AJUSTE (13)=(11)*{(12)-1} 19,551,940.00 1.00532498876601 104,114.00 AJUSTE TOTAL POR OTROS ITEMS 104,114.00 TOTAL AJUSTE -21,505,060.00 AMORTIZACIÓN ANTICIPO 30% - RETENCION EN GARANTIA 10% - TOTAL A PAGAR -21,505,060.00 SON: MENOS VEINTIÚN MILLONES QUINIENTOS CINCO MIL SESENTA PESOS M/CTE. Se firma la presente en Bogotá, D.C. a los Veintisiete (27) días del mes de mayo de 20 GERARDO ESPINOSA S. GUILLERMO EDUARDO ÁVILA ÁLVAREZ DOBLE A INGENIERIA S.A. UNIVERSIDAD NACIONAL DE COLOMBIA CONTRATISTA INTERVENTOR PRECIO UNIT COSTO DIRECTO VALOR DEL ASFALTO DEL ITEM (1) VALOR DE OTROS DEL ITEM (2) CANTIDAD A AJUSTAR (3) VALOR AJUSTE POR ASFALTO (4) = (1)*(3)*{(5)/(6)-1} VALOR AJUSTE POR OTROS (7)=(2)*(3)*{(8)/(9) -1} AJUSTE TOTAL 10 =(4)+(7) Riego de liga con emulsión asfáltica tipo CRR-1 o CRR-2 Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-2 ICCP ENERO/09/ ICCP NOVIEMBRE/2008

Transcript of Anexo Acta de Ajustes

Page 1: Anexo Acta de Ajustes

ANEXO AL ACTA No.006 DE AJUSTE DE PRECIOS AL CONTRATO 199 DE 2008

CORRESPONDIENTE AL ACTA DE RECIBO PARCIAL DE OBRA No. 1 DEL MES DE MARZO AÑO 2009

DATOS BASICOS:

MES DE INICIO NOVIEMBRE DE 2008

VALOR TONELADA DE ASFALTO 80/100 INICIAL (6) $ 1,150,405.00

ICCP INICIAL (9) 124.05

ICCP ENERO DE 2009 124.71

MES DE AJUSTE MARZO DE 2009

VALOR TONELADA DE ASFALTO 80/100 MES DE AJUSTE (5) 740,000.00

ICCP MES DE AJUSTE (8) 124.24

AJUSTES POR ASFALTO

ITEM DESCRIPCIÓN UND.

3,2,7 M2 2,121.00 924.60 1,196.40 3,735.14 -1,232,034.00 6,865.00 -1,225,169.00

3,2,11 M3 455,112.00 154,154.00 300,958.00 373.80 -20,556,822.00 172,817.00 -20,384,005.00

AJUSTE TOTAL POR ASFALTO -21,609,174.00

AJUSTES OTROS ITEMS

TOTAL AJUSTE (13)=(11)*{(12)-1}

19,551,940.00 1.00532498876601 104,114.00

AJUSTE TOTAL POR OTROS ITEMS 104,114.00

TOTAL AJUSTE -21,505,060.00

AMORTIZACIÓN ANTICIPO 30% -

RETENCION EN GARANTIA 10% -

TOTAL A PAGAR -21,505,060.00

SON: MENOS VEINTIÚN MILLONES QUINIENTOS CINCO MIL SESENTA PESOS M/CTE.

Se firma la presente en Bogotá, D.C. a los Veintisiete (27) días del mes de mayo de 2009

GERARDO ESPINOSA S. GUILLERMO EDUARDO ÁVILA ÁLVAREZDOBLE A INGENIERIA S.A. UNIVERSIDAD NACIONAL DE COLOMBIACONTRATISTA INTERVENTOR

PRECIO UNIT

COSTO DIRECTO

VALOR DEL ASFALTO DEL

ITEM (1)

VALOR DE OTROS DEL

ITEM (2)

CANTIDAD A AJUSTAR (3)

VALOR AJUSTE POR ASFALTO (4) = (1)*(3)*{(5)/(6)-1}

VALOR AJUSTE POR OTROS

(7)=(2)*(3)*{(8)/(9)-1}

AJUSTE TOTAL 10 =(4)+(7)

Riego de liga con emulsión asfáltica tipo CRR-1 o CRR-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-2

VALOR A AJUSTAR SIN ASFALTOS (11)

ICCP ENERO/09/ ICCP NOVIEMBRE/2008

Page 2: Anexo Acta de Ajustes

ANEXO AL ACTA No.007 DE AJUSTE DE PRECIOS AL CONTRATO 199 DE 2008

CORRESPONDIENTE AL ACTA DE RECIBO PARCIAL DE OBRA No. 2 DEL MES DE ABRIL AÑO 2009

DATOS BASICOS:

MES DE INICIO NOVIEMBRE DE 2008

VALOR TONELADA DE ASFALTO 80/100 INICIAL (6) $ 1,150,405.00

ICCP INICIAL (9) 124.05

ICCP ENERO DE 2009 124.71

MES DE AJUSTE ABRIL DE 2009

VALOR TONELADA DE ASFALTO 80/100 MES DE AJUSTE (5) 740,000.00

ICCP MES DE AJUSTE (8) 124.03

AJUSTES POR ASFALTO

ITEM DESCRIPCIÓN UND.

3,2,7 M2 2,121.00 924.60 1,196.40 1,027.74 -338,999.00 -193.00 -339,192.00

3,2,11 M3 455,112.00 154,154.00 300,958.00 102.20 -5,620,405.00 -4,820.00 -5,625,225.00

3,2,13 M3 463,168.00 162,207.00 300,961.00 0.86 -49,766.00 -41.00 -49,807.00

AJUSTE TOTAL POR ASFALTO -6,014,224.00

AJUSTES OTROS ITEMS

TOTAL AJUSTE (13)=(11)*{(12)-1}

6,767,468.00 1.00532498876601 36,037.00

AJUSTE TOTAL POR OTROS ITEMS 36,037.00

TOTAL AJUSTE -5,978,187.00

AMORTIZACIÓN ANTICIPO 30% -

RETENCION EN GARANTIA 10% -

TOTAL A PAGAR -5,978,187.00

SON: MENOS CINCO MILLONES NOVECIENTOS SETENTA Y OCHO MIL CIENTO OCHENTA Y SIETE PESOS M/CTE.

Se firma la presente en Bogotá, D.C. a los Veintisiete (27) días del mes de mayo de 2009

GERARDO ESPINOSA S. GUILLERMO EDUARDO ÁVILA ÁLVAREZDOBLE A INGENIERIA S.A. UNIVERSIDAD NACIONAL DE COLOMBIACONTRATISTA INTERVENTOR

PRECIO UNIT

COSTO DIRECTO

VALOR DEL ASFALTO DEL

ITEM (1)

VALOR DE OTROS DEL

ITEM (2)

CANTIDAD A AJUSTAR (3)

VALOR AJUSTE POR ASFALTO (4) = (1)*(3)*{(5)/(6)-1}

VALOR AJUSTE POR OTROS

(7)=(2)*(3)*{(8)/(9)-1}

AJUSTE TOTAL 10 =(4)+(7)

Riego de liga con emulsión asfáltica tipo CRR-1 o CRR-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-3

VALOR A AJUSTAR SIN ASFALTOS (11)

ICCP ENERO/09/ ICCP NOVIEMBRE/2008

Page 3: Anexo Acta de Ajustes

ANEXO AL ACTA No.008 DE AJUSTE DE PRECIOS AL CONTRATO 199 DE 2008

CORRESPONDIENTE AL ACTA DE RECIBO PARCIAL DE OBRA No. 3 DEL MES DE MAYO AÑO 2009

DATOS BASICOS:

MES DE INICIO NOVIEMBRE DE 2008

VALOR TONELADA DE ASFALTO 80/100 INICIAL (6) $ 1,150,405.00

ICCP INICIAL (9) 124.05

ICCP ENERO DE 2009 124.71

MES DE AJUSTE MAYO DE 2009

VALOR TONELADA DE ASFALTO 80/100 MES DE AJUSTE (5) 740,000.00

ICCP MES DE AJUSTE (8) 123.60

AJUSTES POR ASFALTO

ITEM DESCRIPCIÓN UND.

3,2,7 M2 2,121.00 924.60 1,196.40 3,320.49 -1,095,262.00 -14,393.00 -1,109,655.00

3,2,11 M3 455,112.00 154,154.00 300,958.00 307.22 -16,895,310.00 -334,989.00 -17,230,299.00

3,2,13 M3 463,168.00 162,207.00 300,961.00 9.04 -523,118.00 -9,857.00 -532,975.00

AJUSTE TOTAL POR ASFALTO -18,872,929.00

AJUSTES OTROS ITEMS

TOTAL AJUSTE (13)=(11)*{(12)-1}

36,907,889.45 1.00532498876601 196,534.00

AJUSTE TOTAL POR OTROS ITEMS 196,534.00

TOTAL AJUSTE -18,676,395.00

AMORTIZACIÓN ANTICIPO 30% -

RETENCION EN GARANTIA 10% -

TOTAL A PAGAR -18,676,395.00

SON: MENOS DIECIOCHO MILLONES SEISCIENTOS SETENTA Y SEIS MIL TRESCIENTOS NOVENTA Y CINCO PESOS M/CTE.

Se firma la presente en Bogotá, D.C. a los Veintisiete (27) días del mes de mayo de 2009

JOSÉ ALEJANDRO ATUESTA MALDONADO GUILLERMO EDUARDO ÁVILA ÁLVAREZDOBLE A INGENIERIA S.A. UNIVERSIDAD NACIONAL DE COLOMBIACONTRATISTA INTERVENTOR

PRECIO UNIT

COSTO DIRECTO

VALOR DEL ASFALTO DEL

ITEM (1)

VALOR DE OTROS DEL

ITEM (2)

CANTIDAD A AJUSTAR (3)

VALOR AJUSTE POR ASFALTO (4) = (1)*(3)*{(5)/(6)-1}

VALOR AJUSTE POR OTROS

(7)=(2)*(3)*{(8)/(9)-1}

AJUSTE TOTAL 10 =(4)+(7)

Riego de liga con emulsión asfáltica tipo CRR-1 o CRR-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-3

VALOR A AJUSTAR SIN ASFALTOS (11)

ICCP ENERO/09/ ICCP NOVIEMBRE/2008

Page 4: Anexo Acta de Ajustes

ANEXO AL ACTA No.0011 DE AJUSTE DE PRECIOS AL CONTRATO 199 DE 2008

CORRESPONDIENTE AL ACTA DE RECIBO PARCIAL DE OBRA No. 4 DEL MES DE JUNIO AÑO 2009

DATOS BASICOS:

MES DE INICIO NOVIEMBRE DE 2008

VALOR TONELADA DE ASFALTO 80/100 INICIAL (6) $ 1,150,405.00

ICCP INICIAL (9) 124.05

ICCP ENERO DE 2009 124.71

MES DE AJUSTE JUNIO DE 2009

VALOR TONELADA DE ASFALTO 80/100 MES DE AJUSTE (5) 740,000.00

ICCP MES DE AJUSTE (8) 123.08

AJUSTES POR ASFALTO

ITEM DESCRIPCIÓN UND.

3,2,7 M2 2,121.00 924.60 1,196.40 5,623.45 -1,854,892.00 -52,578.00 -1,907,470.00

3,2,11 M3 455,112.00 154,154.00 300,958.00 555.75 -30,563,012.00 -1,307,106.00 -31,870,118.00

3,2,13 M3 463,168.00 162,207.00 300,961.00 - - -

AJUSTE TOTAL POR ASFALTO -33,777,588.00

AJUSTES OTROS ITEMS

TOTAL AJUSTE (13)=(11)*{(12)-1}

42,600,180.66 1.00532498876601 226,845.00

AJUSTE TOTAL POR OTROS ITEMS 226,845.00

TOTAL AJUSTE -33,550,743.00

AMORTIZACIÓN ANTICIPO 30% -

RETENCION EN GARANTIA 10% -

TOTAL A PAGAR -33,550,743.00

SON: MENOS TREINTA Y TRES MILLONES QUINIENTOS CINCUENTA MIL SETECIENTOS CUARENTA Y TRES PESOS M/CTE.

Se firma la presente en Bogotá, D.C. a los Treinta (30) días del mes de junio de 2009

JOSÉ ALEJANDRO ATUESTA MALDONADO GUILLERMO EDUARDO ÁVILA ÁLVAREZDOBLE A INGENIERIA S.A. UNIVERSIDAD NACIONAL DE COLOMBIACONTRATISTA INTERVENTOR

PRECIO UNIT

COSTO DIRECTO

VALOR DEL ASFALTO DEL

ITEM (1)

VALOR DE OTROS DEL

ITEM (2)

CANTIDAD A AJUSTAR (3)

VALOR AJUSTE POR ASFALTO (4) = (1)*(3)*{(5)/(6)-1}

VALOR AJUSTE POR OTROS

(7)=(2)*(3)*{(8)/(9)-1}

AJUSTE TOTAL 10 =(4)+(7)

Riego de liga con emulsión asfáltica tipo CRR-1 o CRR-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-3

VALOR A AJUSTAR SIN ASFALTOS (11)

ICCP ENERO/09/ ICCP NOVIEMBRE/2008

Page 5: Anexo Acta de Ajustes

ANEXO AL ACTA No.0014 DE AJUSTE DE PRECIOS AL CONTRATO 199 DE 2008

CORRESPONDIENTE AL ACTA DE RECIBO PARCIAL DE OBRA No. 5 DEL MES DE JULIO AÑO 2009

DATOS BASICOS:

MES DE INICIO NOVIEMBRE DE 2008

VALOR TONELADA DE ASFALTO 80/100 INICIAL (6) $ 1,150,405.00

ICCP INICIAL (9) 124.05

ICCP ENERO DE 2009 124.71

MES DE AJUSTE JULIO DE 2009

VALOR TONELADA DE ASFALTO 80/100 MES DE AJUSTE (5) 740,000.00

ICCP MES DE AJUSTE (8) 122.89

AJUSTES POR ASFALTO

ITEM DESCRIPCIÓN UND.

3,2,7 M2 2,121.00 924.60 1,196.40 5,271.92 -1,738,940.00 -58,952.00 -1,797,892.00

3,2,11 M3 455,112.00 154,154.00 300,958.00 643.74 -35,401,949.00 -1,810,795.00 -37,212,744.00

3,2,13 M3 463,168.00 162,207.00 300,961.00 13.93 -806,088.00 -39,184.00 -845,272.00

AJUSTE TOTAL POR ASFALTO -39,855,908.00

AJUSTES OTROS ITEMS

TOTAL AJUSTE (13)=(11)*{(12)-1}

48,880,810.38 1.00532498876601 260,290.00

AJUSTE TOTAL POR OTROS ITEMS 260,290.00

TOTAL AJUSTE -39,595,618.00

AMORTIZACIÓN ANTICIPO 30% -

RETENCION EN GARANTIA 10% -

TOTAL A PAGAR -39,595,618.00

SON: MENOS TREINTA Y NUEVE MILLONES QUINIENTOS NOVENTA Y CINCO MIL SEISCIENTOS DIECIOCHO PESOS M/CTE.

Se firma la presente en Bogotá, D.C. a los veintiún (21) días del mes de agosto de 2009

JOSÉ ALEJANDRO ATUESTA MALDONADO GUILLERMO EDUARDO ÁVILA ÁLVAREZDOBLE A INGENIERIA S.A. UNIVERSIDAD NACIONAL DE COLOMBIACONTRATISTA INTERVENTOR

PRECIO UNIT

COSTO DIRECTO

VALOR DEL ASFALTO DEL

ITEM (1)

VALOR DE OTROS DEL

ITEM (2)

CANTIDAD A AJUSTAR (3)

VALOR AJUSTE POR ASFALTO (4) = (1)*(3)*{(5)/(6)-1}

VALOR AJUSTE POR OTROS

(7)=(2)*(3)*{(8)/(9)-1}

AJUSTE TOTAL 10 =(4)+(7)

Riego de liga con emulsión asfáltica tipo CRR-1 o CRR-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-3

VALOR A AJUSTAR SIN ASFALTOS (11)

ICCP ENERO/09/ ICCP NOVIEMBRE/2008

Page 6: Anexo Acta de Ajustes

ANEXO AL ACTA No.0016 DE AJUSTE DE PRECIOS AL CONTRATO 199 DE 2008

CORRESPONDIENTE AL ACTA DE RECIBO PARCIAL DE OBRA No. 6 DEL MES DE AGOSTO AÑO 2009

DATOS BASICOS:

MES DE INICIO NOVIEMBRE DE 2008

VALOR TONELADA DE ASFALTO 80/100 INICIAL (6) $ 1,150,405.00

ICCP INICIAL (9) 124.05

ICCP ENERO DE 2009 124.71

MES DE AJUSTE AGOSTO DE 2009

VALOR TONELADA DE ASFALTO 80/100 MES DE AJUSTE (5) 740,000.00

ICCP MES DE AJUSTE (8) 122.45

AJUSTES POR ASFALTO

ITEM DESCRIPCIÓN UND.

3,2,7 M2 2,121.00 924.60 1,196.40 7,054.31 -2,326,860.00 -108,819.00 -2,435,679.00

3,2,11 M3 455,112.00 154,154.00 300,958.00 991.71 -54,538,272.00 -3,848,250.00 -58,386,522.00

3,2,13 M3 463,168.00 162,207.00 300,961.00 - - -

AJUSTE TOTAL POR ASFALTO -60,822,201.00

AJUSTES OTROS ITEMS

TOTAL AJUSTE (13)=(11)*{(12)-1}

100,801,873.76 1.00532498876601 536,769.00

AJUSTE TOTAL POR OTROS ITEMS 536,769.00

TOTAL AJUSTE -60,285,432.00

AMORTIZACIÓN ANTICIPO 30% -

RETENCION EN GARANTIA 10% -

TOTAL A PAGAR -60,285,432.00

SON: MENOS SESENTA MILLONES DOSCIENTOS OCHENTA Y CINCO MIL CUATROCIENTOS TREINTA Y DOS PESOS M/CTE.

Se firma la presente en Bogotá, D.C. a los Diez (10) días del mes de septiembre de 2009

JOSÉ ALEJANDRO ATUESTA MALDONADO GUILLERMO EDUARDO ÁVILA ÁLVAREZDOBLE A INGENIERIA S.A. UNIVERSIDAD NACIONAL DE COLOMBIACONTRATISTA INTERVENTOR

PRECIO UNIT

COSTO DIRECTO

VALOR DEL ASFALTO DEL

ITEM (1)

VALOR DE OTROS DEL

ITEM (2)

CANTIDAD A AJUSTAR (3)

VALOR AJUSTE POR ASFALTO (4) = (1)*(3)*{(5)/(6)-1}

VALOR AJUSTE POR OTROS

(7)=(2)*(3)*{(8)/(9)-1}

AJUSTE TOTAL 10 =(4)+(7)

Riego de liga con emulsión asfáltica tipo CRR-1 o CRR-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-3

VALOR A AJUSTAR SIN ASFALTOS (11)

ICCP ENERO/09/ ICCP NOVIEMBRE/2008

Page 7: Anexo Acta de Ajustes

ANEXO AL ACTA No.0018 DE AJUSTE DE PRECIOS AL CONTRATO 199 DE 2008

CORRESPONDIENTE AL ACTA DE RECIBO PARCIAL DE OBRA No. 7 DEL MES DE SEPTIEMBRE AÑO 2009

DATOS BASICOS:

MES DE INICIO NOVIEMBRE DE 2008

VALOR TONELADA DE ASFALTO 80/100 INICIAL (6) $ 1,150,405.00

ICCP INICIAL (9) 124.05

ICCP ENERO DE 2009 124.71

MES DE AJUSTE SEPTIEMBRE DE 2009

VALOR TONELADA DE ASFALTO 80/100 MES DE AJUSTE (5) 740,000.00

ICCP MES DE AJUSTE (8) 122.39

AJUSTES POR ASFALTO

ITEM DESCRIPCIÓN UND.

3,2,7 M2 2,121.00 924.60 1,196.40 9,410.40 -3,104,015.00 -150,609.00 -3,254,624.00

3,2,11 M3 455,112.00 154,154.00 300,958.00 1,122.11 -61,709,512.00 -4,517,598.00 -66,227,110.00

3,2,13 M3 463,168.00 162,207.00 300,961.00 - - -

AJUSTE TOTAL POR ASFALTO -69,481,734.00

AJUSTES OTROS ITEMS

TOTAL AJUSTE (13)=(11)*{(12)-1}

132,326,242.65 1.00532498876601 704,636.00

AJUSTE TOTAL POR OTROS ITEMS 704,636.00

TOTAL AJUSTE -68,777,098.00

AMORTIZACIÓN ANTICIPO 30% -

RETENCION EN GARANTIA 10% -

TOTAL A PAGAR -68,777,098.00

SON: MENOS SESENTA Y OCHO MILLONES SETECIENTOS SETENTA Y SIETE MIL NOVENTA Y OCHO PESOS M/CTE.

Se firma la presente en Bogotá, D.C. a los Veintiún (21) días del mes de octubre de 2009

JOSÉ ALEJANDRO ATUESTA MALDONADO GUILLERMO EDUARDO ÁVILA ÁLVAREZDOBLE A INGENIERIA S.A. UNIVERSIDAD NACIONAL DE COLOMBIACONTRATISTA INTERVENTOR

PRECIO UNIT

COSTO DIRECTO

VALOR DEL ASFALTO DEL

ITEM (1)

VALOR DE OTROS DEL

ITEM (2)

CANTIDAD A AJUSTAR (3)

VALOR AJUSTE POR ASFALTO (4) = (1)*(3)*{(5)/(6)-1}

VALOR AJUSTE POR OTROS

(7)=(2)*(3)*{(8)/(9)-1}

AJUSTE TOTAL 10 =(4)+(7)

Riego de liga con emulsión asfáltica tipo CRR-1 o CRR-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-3

VALOR A AJUSTAR SIN ASFALTOS (11)

ICCP ENERO/09/ ICCP NOVIEMBRE/2008

Page 8: Anexo Acta de Ajustes

ANEXO AL ACTA No.0021 DE AJUSTE DE PRECIOS AL CONTRATO 199 DE 2008

CORRESPONDIENTE AL ACTA DE RECIBO PARCIAL DE OBRA No. 8 DEL MES DE OCTUBRE AÑO 2009

DATOS BASICOS:

MES DE INICIO NOVIEMBRE DE 2008

VALOR TONELADA DE ASFALTO 80/100 INICIAL (6) $ 1,150,405.00

ICCP INICIAL (9) 124.05

ICCP ENERO DE 2009 124.71

MES DE AJUSTE OCTUBRE DE 2009

VALOR TONELADA DE ASFALTO 80/100 MES DE AJUSTE (5) 740,000.00

ICCP MES DE AJUSTE (8) 121.94

AJUSTES POR ASFALTO

ITEM DESCRIPCIÓN UND.

3,2,7 M2 2,121.00 924.60 1,196.40 11,198.01 -3,693,658.00 -227,819.00 -3,921,477.00

3,2,11 M3 455,112.00 154,154.00 300,958.00 1,327.06 -72,980,568.00 -6,791,543.00 -79,772,111.00

3,2,13 M3 463,168.00 162,207.00 300,961.00 - - -

AJUSTE TOTAL POR ASFALTO -83,693,588.00

AJUSTES OTROS ITEMS

TOTAL AJUSTE (13)=(11)*{(12)-1}

$ 140,496,559 1.00532498876601 748,143.00

AJUSTE TOTAL POR OTROS ITEMS 748,143.00

TOTAL AJUSTE -82,945,445.00

SON:

Se firma la presente en Bogotá, D.C. a los Veinticinco (25) días del mes de Noviembre de 2009

JOSÉ ALEJANDRO ATUESTA MALDONADO GUILLERMO EDUARDO ÁVILA ÁLVAREZDOBLE A INGENIERIA S.A. UNIVERSIDAD NACIONAL DE COLOMBIACONTRATISTA INTERVENTOR

PRECIO UNIT

COSTO DIRECTO

VALOR DEL ASFALTO DEL

ITEM (1)

VALOR DE OTROS DEL

ITEM (2)

CANTIDAD A AJUSTAR (3)

VALOR AJUSTE POR ASFALTO (4) = (1)*(3)*{(5)/(6)-1}

VALOR AJUSTE POR OTROS

(7)=(2)*(3)*{(8)/(9)-1}

AJUSTE TOTAL 10 =(4)+(7)

Riego de liga con emulsión asfáltica tipo CRR-1 o CRR-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-3

VALOR A AJUSTAR SIN ASFALTOS (11)

ICCP ENERO/09/ ICCP NOVIEMBRE/2008

MENOS OCHENTA Y DOS MILLONES NOVECIENTOS CUARENTA Y CINCO MIL CUATROCIENTOS CUARENTA Y CINCO PESOS M/CTE.

Page 9: Anexo Acta de Ajustes

ANEXO AL ACTA No.0023 DE AJUSTE DE PRECIOS AL CONTRATO 199 DE 2008

CORRESPONDIENTE AL ACTA DE RECIBO PARCIAL DE OBRA No. 9 DEL MES DE NOVIEMBRE AÑO 2009

DATOS BASICOS:

MES DE INICIO NOVIEMBRE DE 2008

VALOR TONELADA DE ASFALTO 80/100 INICIAL (6) $ 1,150,405.00

ICCP INICIAL (9) 124.05

ICCP ENERO DE 2009 124.71

MES DE AJUSTE OCTUBRE DE 2009

VALOR TONELADA DE ASFALTO 80/100 MES DE AJUSTE (5) 740,000.00

ICCP MES DE AJUSTE (8) 121.94

AJUSTES POR ASFALTO

ITEM DESCRIPCIÓN UND.

3,2,7 M2 2,121.00 924.60 1,196.40 13,064.88 -4,309,444.00 -265,799.00 -4,575,243.00

3,2,11 M3 455,112.00 154,154.00 300,958.00 594.94 -32,718,234.00 -3,044,746.00 -35,762,980.00

3,2,13 M3 463,168.00 162,207.00 300,961.00 256.33 -14,833,065.00 -1,311,842.00 -16,144,907.00

AJUSTE TOTAL POR ASFALTO -56,483,130.00

AJUSTES OTROS ITEMS

TOTAL AJUSTE (13)=(11)*{(12)-1}

$ 57,941,009 1.00532498876601 308,535.00

AJUSTE TOTAL POR OTROS ITEMS 308,535.00

TOTAL AJUSTE -56,174,595.00

SON:MENOS CINCUENTA Y SEIS MILLONES CIENTO SETENTA Y CUATRO MIL QUINIENTOS NOVENTA Y CINCO PESOS M/CTE.

Se firma la presente en Bogotá, D.C. a los Diez (10) días del mes de Diciembre de 2009

JOSÉ ALEJANDRO ATUESTA MALDONADO GUILLERMO EDUARDO ÁVILA ÁLVAREZDOBLE A INGENIERIA S.A. UNIVERSIDAD NACIONAL DE COLOMBIACONTRATISTA INTERVENTOR

Nota: para efectos de ajuste se utilizó el ICCP del mes de octubre por no estar publicado aún el de noviembre

PRECIO UNIT

COSTO DIRECTO

VALOR DEL ASFALTO DEL

ITEM (1)

VALOR DE OTROS DEL

ITEM (2)

CANTIDAD A AJUSTAR (3)

VALOR AJUSTE POR ASFALTO (4) = (1)*(3)*{(5)/(6)-1}

VALOR AJUSTE POR OTROS

(7)=(2)*(3)*{(8)/(9)-1}

AJUSTE TOTAL 10 =(4)+(7)

Riego de liga con emulsión asfáltica tipo CRR-1 o CRR-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-3

VALOR A AJUSTAR SIN ASFALTOS (11)

ICCP ENERO/09/ ICCP NOVIEMBRE/2008

Page 10: Anexo Acta de Ajustes

ANEXO AL ACTA No.0026 DE AJUSTE DE PRECIOS AL CONTRATO 199 DE 2008

CORRESPONDIENTE AL ACTA DE RECIBO PARCIAL DE OBRA No. 10 DEL MES DE DICIEMBRE AÑO 2009

DATOS BASICOS:

MES DE INICIO NOVIEMBRE DE 2008

VALOR TONELADA DE ASFALTO 80/100 INICIAL (6) $ 1,150,405.00

ICCP INICIAL (9) 124.05

ICCP ENERO DE 2009 124.71

MES DE AJUSTE DICIEMBRE DE 2009

VALOR TONELADA DE ASFALTO 80/100 MES DE AJUSTE (5) 740,000.00

ICCP MES DE AJUSTE (8) 120.76

AJUSTES POR ASFALTO

ITEM DESCRIPCIÓN UND. CANTIDAD A AJUSTAR (3)

3,2,7 M2 2,121.00 924.60 1,196.40 8,941.30 -2,949,283.00 -283,664.00 -3,232,947.00

3,2,11 M3 455,112.00 154,154.00 300,958.00 417.41 -22,955,118.00 -3,331,161.00 -26,286,279.00

3,2,13 M3 463,168.00 162,207.00 300,961.00 159.91 -9,253,523.00 -1,276,182.00 -10,529,705.00

AJUSTE TOTAL POR ASFALTO -40,048,931.00

AJUSTES OTROS ITEMS

TOTAL AJUSTE (13)=(11)*{(12)-1}

$ 35,867,882 1.00532498876601 190,996.00

AJUSTE TOTAL POR OTROS ITEMS 190,996.00

TOTAL AJUSTE -39,857,935.00

SON:MENOS TREINTA Y NUEVE MILLONES OCHOCIENTOS CINCUENTA Y SIETE MIL NOVECIENTOS TREINTA Y CINCO PESOS M/CTE.

Se firma la presente en Bogotá, D.C. a los Veintiún (21) días del mes de Enero de 2010

JOSÉ ALEJANDRO ATUESTA MALDONADO GUILLERMO EDUARDO ÁVILA ÁLVAREZDOBLE A INGENIERIA S.A. UNIVERSIDAD NACIONAL DE COLOMBIACONTRATISTA INTERVENTOR

PRECIO UNIT

COSTO DIRECTO

VALOR DEL ASFALTO DEL

ITEM (1)

VALOR DE OTROS DEL

ITEM (2)

VALOR AJUSTE POR ASFALTO (4) = (1)*(3)*{(5)/(6)-1}

VALOR AJUSTE POR OTROS

(7)=(2)*(3)*{(8)/(9)-1}

AJUSTE TOTAL 10 =(4)+(7)

Riego de liga con emulsión asfáltica tipo CRR-1 o CRR-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-3

VALOR A AJUSTAR SIN ASFALTOS (11)

ICCP ENERO/09/ ICCP NOVIEMBRE/2008

Page 11: Anexo Acta de Ajustes

ANEXO AL ACTA No.0030 DE AJUSTE DE PRECIOS AL CONTRATO 199 DE 2008

CORRESPONDIENTE AL ACTA DE RECIBO PARCIAL DE OBRA No. 11 DEL MES DE ENERO AÑO 2010

DATOS BASICOS:

MES DE INICIO NOVIEMBRE DE 2008

VALOR TONELADA DE ASFALTO 80/100 INICIAL (6) $ 1,150,405.00

ICCP INICIAL (9) 124.05

ICCP ENERO DE 2010 121.58

MES DE AJUSTE ENERO DE 2010

VALOR TONELADA DE ASFALTO 80/100 MES DE AJUSTE (5) 740,000.00

ICCP MES DE AJUSTE (8) 121.58

AJUSTES POR ASFALTO

ITEM DESCRIPCIÓN UND. CANTIDAD A AJUSTAR (3)

3,2,7 M2 2,121.00 924.60 1,196.40 14,935.98 -4,926,625.00 -355,804.00 -5,282,429.00

3,2,11 M3 455,112.00 154,154.00 300,958.00 646.07 -35,530,086.00 -3,871,557.00 -39,401,643.00

3,2,13 M3 463,168.00 162,207.00 300,961.00 281.75 -16,304,046.00 -1,688,396.00 -17,992,442.00

AJUSTE TOTAL POR ASFALTO -62,676,514.00

AJUSTES OTROS ITEMS

TOTAL AJUSTE (13)=(11)*{(12)-1}

$ 153,485,166 0.980088673921806 -3,056,093.00

AJUSTE TOTAL POR OTROS ITEMS -3,056,093.00

TOTAL AJUSTE -65,732,607.00

SON: MENOS SESENTA Y CINCO MILLONES SETECIENTOS TREINTA Y DOS MIL SEISCIENTOS SIETE PESOS M/CTE.

Se firma la presente en Bogotá, D.C. a los Quince (15) días del mes de Febrero de 2010

JOSÉ ALEJANDRO ATUESTA MALDONADO GUILLERMO EDUARDO ÁVILA ÁLVAREZDOBLE A INGENIERIA S.A. UNIVERSIDAD NACIONAL DE COLOMBIACONTRATISTA INTERVENTOR

PRECIO UNIT

COSTO DIRECTO

VALOR DEL ASFALTO DEL

ITEM (1)

VALOR DE OTROS DEL

ITEM (2)

VALOR AJUSTE POR ASFALTO (4) = (1)*(3)*{(5)/(6)-1}

VALOR AJUSTE POR OTROS

(7)=(2)*(3)*{(8)/(9)-1}

AJUSTE TOTAL 10 =(4)+(7)

Riego de liga con emulsión asfáltica tipo CRR-1 o CRR-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-3

VALOR A AJUSTAR SIN ASFALTOS (11)

ICCP ENERO/10/ ICCP NOVIEMBRE/2008

Page 12: Anexo Acta de Ajustes

ANEXO AL ACTA No.0032 DE AJUSTE DE PRECIOS AL CONTRATO 199 DE 2008

CORRESPONDIENTE AL ACTA DE RECIBO PARCIAL DE OBRA No. 12 DEL MES DE FEBRERO AÑO 2010

DATOS BASICOS:

MES DE INICIO NOVIEMBRE DE 2008

VALOR TONELADA DE ASFALTO 80/100 INICIAL (6) $ 1,150,405.00

ICCP INICIAL (9) 124.05

ICCP ENERO DE 2010 121.58

MES DE AJUSTE FEBRERO DE 2010

VALOR TONELADA DE ASFALTO 80/100 MES DE AJUSTE (5) 814,000.00

ICCP MES DE AJUSTE (8) 122.64

AJUSTES POR ASFALTO

ITEM DESCRIPCIÓN UND. CANTIDAD A AJUSTAR (3)

3,2,7 M2 2,121.00 924.60 1,196.40 13,631.99 -3,685,741.00 -185,378.00 -3,871,119.00

3,2,11 M3 455,112.00 154,154.00 300,958.00 522.64 -23,559,666.00 -1,787,849.00 -25,347,515.00

3,2,13 M3 463,168.00 162,207.00 300,961.00 307.36 -14,579,030.00 -1,051,429.00 -15,630,459.00

AJUSTE TOTAL POR ASFALTO -44,849,093.00

AJUSTES OTROS ITEMS

TOTAL AJUSTE (13)=(11)*{(12)-1}

$ 110,879,790 0.980088673921806 -2,207,764.00

AJUSTE TOTAL POR OTROS ITEMS -2,207,764.00

TOTAL AJUSTE -47,056,857.00

SON: MENOS CUARENTA Y SIETE MILLONES CINCUENTA Y SEIS MIL OCHOCIENTOS CINCUENTA Y SIETE PESOS M/CTE.

Se firma la presente en Bogotá, D.C. a los Diecisiete (17) días del mes de Marzo de 2010

LUIS FERNANDO ATUESTA MALDONADO GUILLERMO EDUARDO ÁVILA ÁLVAREZDOBLE A INGENIERIA S.A. UNIVERSIDAD NACIONAL DE COLOMBIACONTRATISTA INTERVENTOR

PRECIO UNIT

COSTO DIRECTO

VALOR DEL ASFALTO DEL

ITEM (1)

VALOR DE OTROS DEL

ITEM (2)

VALOR AJUSTE POR ASFALTO (4) = (1)*(3)*{(5)/(6)-1}

VALOR AJUSTE POR OTROS

(7)=(2)*(3)*{(8)/(9)-1}

AJUSTE TOTAL 10 =(4)+(7)

Riego de liga con emulsión asfáltica tipo CRR-1 o CRR-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-3

VALOR A AJUSTAR SIN ASFALTOS (11)

ICCP ENERO/10/ ICCP NOVIEMBRE/2008

Page 13: Anexo Acta de Ajustes

ANEXO AL ACTA No.0034 DE AJUSTE DE PRECIOS AL CONTRATO 199 DE 2008

CORRESPONDIENTE AL ACTA DE RECIBO PARCIAL DE OBRA No. 13 DEL MES DE MARZO AÑO 2010

DATOS BASICOS:

MES DE INICIO NOVIEMBRE DE 2008

VALOR TONELADA DE ASFALTO 80/100 INICIAL (6) $ 1,150,405.00

ICCP INICIAL (9) 124.05

ICCP ENERO DE 2010 121.58

MES DE AJUSTE MARZO DE 2010

VALOR TONELADA DE ASFALTO 80/100 MES DE AJUSTE (5) 814,000.00

ICCP MES DE AJUSTE (8) 123.14

AJUSTES POR ASFALTO

ITEM DESCRIPCIÓN UND. CANTIDAD A AJUSTAR (3)

3,2,7 M2 2,121.00 924.60 1,196.40 - - - -

3,2,11 M3 455,112.00 154,154.00 300,958.00 - - - -

3,2,13 M3 463,168.00 162,207.00 300,961.00 - - - -

AJUSTE TOTAL POR ASFALTO -

AJUSTES OTROS ITEMS

TOTAL AJUSTE (13)=(11)*{(12)-1}

$ 62,239,086 0.980088673921806 -1,239,263.00

AJUSTE TOTAL POR OTROS ITEMS -1,239,263.00

TOTAL AJUSTE -1,239,263.00

SON: MENOS UN MILLÓN DOSCIENTOS TREINTA Y NUEVE MIL DOSCIENTOS SESENTA Y TRES PESOS M/CTE.

Se firma la presente en Bogotá, D.C. a los Diecisiete (16) días del mes de Abril de 2010

LUIS FERNANDO ATUESTA MALDONADO GUILLERMO EDUARDO ÁVILA ÁLVAREZDOBLE A INGENIERIA S.A. UNIVERSIDAD NACIONAL DE COLOMBIACONTRATISTA INTERVENTOR

PRECIO UNIT

COSTO DIRECTO

VALOR DEL ASFALTO DEL

ITEM (1)

VALOR DE OTROS DEL

ITEM (2)

VALOR AJUSTE POR ASFALTO (4) = (1)*(3)*{(5)/(6)-1}

VALOR AJUSTE POR OTROS

(7)=(2)*(3)*{(8)/(9)-1}

AJUSTE TOTAL 10 =(4)+(7)

Riego de liga con emulsión asfáltica tipo CRR-1 o CRR-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-2

Suministro, colocación y compactación de mezcla asfáltica 80-100 MDC-3

VALOR A AJUSTAR SIN ASFALTOS (11)

ICCP ENERO/10/ ICCP NOVIEMBRE/2008