11 Cronograma de Avance de Obra Valorizado

2
CRONOGRAMA DE AVANCE DE OBRA VALORIZADO Presupuesto : Fecha de reporte : 10/30/2014 Fecha base : OCTUBRE 2014 Constructora : Item Descripción CANT. QUINCENA 01 QUINCENA 02 QUINCENA 03 TOTAL 01 ESTRUCTURAS 43,942.44 01.01 OBRAS PROVISIONALES 6,498.86 01.01.01 CARTEL DE OBRA 3.60X7.20 1,557.61 1,557.61 0.00 0.00 1,557.61 01.01.02 ALMACEN Y OFICINA PROVISIONAL 1,254.40 418.09 413.95 422.36 1,254.40 01.01.03 DEPOSITO PARA ALMACENAR AGUA 250.00 82.50 82.50 85.00 250.00 01.01.04 FLETE TERRESTRE 3,436.85 2,405.80 0.00 1,031.06 3,436.85 01.02 TRABAJOS PRELIMINARES 2,607.05 01.02.01 DESMONTAJE DE ESTRUCTURAS METALICAS EXISTENTES 2,371.25 2,371.25 0.00 0.00 2,371.25 01.02.02 DESMONTAJE DE COBERTURA EXISTENTE 131.36 131.36 0.00 0.00 131.36 01.02.03 DEMOLICION DE MURO EXISTENTE 104.44 104.44 0.00 0.00 104.44 01.03 MOVIMIENTO DE TIERRAS 16,808.48 01.03.01 NIVELACION Y RELLENO COMPACTADO CON TERRENO NATURAL 3,273.24 3,273.24 0.00 0.00 3,273.24 01.03.02 EXCAVACION PARA CIMIENTOS HASTA 1.00 mTERRENO NORMAL 2,568.75 2,568.75 0.00 0.00 2,568.75 01.03.03 RELLENO COMPACTADO CON MATERIAL PROPIO 1,572.57 1,258.06 314.51 0.00 1,572.57 01.03.04 RELLENO COMPACTADO CON MATERIAL GRANULAR (AGREGADO FILTRANTE) 6,005.27 2,402.11 1,201.05 2,402.11 6,005.27 01.03.05 RELLENO CON PIEDRA GRADUADA DE 4" 1,377.93 275.59 0.00 1,102.34 1,377.93 01.03.06 RELLENO CON ARENA GRUESA PARA CONFINAMIENTO DE BIODIGESTOR 289.93 57.99 0.00 231.94 289.93 01.03.07 ELIMINACION CON TRANSPORTE (CARGUIO A MANO) R=25 m3/día 1,720.79 0.00 1,376.63 344.16 1,720.79 01.04 CONCRETO SIMPLE 10,122.64 01.04.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% PIEDRA 620.13 620.13 0.00 0.00 620.13 01.04.02 SOLADO e=4" 40.72 40.72 0.00 0.00 40.72 01.04.03 FALSO PISO e=4" DE CONCRETO 1:10 9,461.79 9,461.79 0.00 0.00 9,461.79 01.05 CONCRETO ARMADO 7,905.41 01.05.01 ZAPATAS 395.34 01.05.01.0CONCRETO EN ZAPATAS f'c=210 kg/cm2 331.71 331.71 0.00 0.00 331.71 01.05.01.0ACERO fy=4200 kg/cm2 GRADO 60 en ZAPATAS 63.63 63.63 0.00 0.00 63.63 01.05.02 SOBRECIMIENTO 1,537.54 01.05.02.0CONCRETO EN SOBRECIMIENTOS f'c=175 kg/cm2 827.31 827.31 0.00 0.00 827.31 01.05.02.0ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTOS 521.35 521.35 0.00 0.00 521.35 01.05.02.0ACERO fy=4200 kg/cm2 GRADO 60 en SOBRECIMEINTO 188.88 188.88 0.00 0.00 188.88 01.05.03 COLUMNAS 1,985.84 01.05.03.0CONCRETO EN COLUMNAS f'c=210 kg/cm2 735.90 735.90 0.00 0.00 735.90 01.05.03.0ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS 734.99 734.99 0.00 0.00 734.99 01.05.03.0ACERO fy=4200 kg/cm2 GRADO 60 en COLUMNAS 514.95 514.95 0.00 0.00 514.95 01.05.04 MESADAS Y PLACAS LIVIANAS 3,986.69 01.05.04.0CONCRETO ELEMENTOS MENORES f'c=175 kg/cm2 1,398.20 0.00 1,118.56 279.64 1,398.20 01.05.04.0ENCOFRADO Y DESENCOFRADO NORMAL EN PLACAS LIVIANAS 1,474.18 0.00 1,179.34 294.84 1,474.18 01.05.04.0ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 1,114.31 0.00 891.45 222.86 1,114.31 02 ARQUITECTURA 152,608.36 02.01 ALBAÑILERIA 4,594.43 02.01.01 4,594.43 918.89 3,675.54 0.00 4,594.43 02.02 REVOQUES ENLUCIDOS Y MOLDURAS 8,590.10 02.02.01 TARRAJEO PRIMARIO RAYADO C/MEZCLA 1:5 870.17 0.00 783.15 87.02 870.17 02.02.02 TARRAJEO DE MUROS INTERIORES 1,017.79 0.00 916.01 101.78 1,017.79 02.02.03 TARRAJEO DE COLUMNAS 5,890.64 0.00 5,301.58 589.06 5,890.64 02.02.04 TARRAJEO DE VIGAS 408.26 0.00 367.43 40.83 408.26 02.02.05 TARRAJEO DE POSA DE LODOS 403.24 0.00 362.92 40.32 403.24 02.03 PISOS Y PAVIMENTOS 35,729.59 02.03.01 CONTRAPISO DE 2" 10,349.53 0.00 10,349.53 0.00 10,349.53 02.03.02 PISO DE CERAMICO DE 30 X 30 cm 21,711.10 0.00 6,513.33 15,197.77 21,711.10 02.03.03 VEREDAS 3,668.96 02.03.03.0CONCRETO f'c=175 kg/cm2 EN VEREDAS 3,146.33 0.00 3,146.33 0.00 3,146.33 02.03.03.0ENCOFRADO Y DESENCOFRADO DE VEREDAS 243.73 0.00 243.73 0.00 243.73 02.03.03.0JUNTAS ASFALTICAS 117.31 0.00 117.31 0.00 117.31 02.03.03.0CURADO CON ADITIVO QUIMICO EN CONCRETO 161.59 0.00 161.59 0.00 161.59 02.04 ZOCALOS Y CONTRAZOCALOS 987.33 02.04.01 ZOCALO DE CERAMICA 20 X 20 EN BAÑO O SIMILAR 616.10 0.00 616.10 0.00 616.10 02.04.02 CONTRAZOCALO DE CEMENTO PULIDO 371.23 0.00 371.23 0.00 371.23 02.05 CARPINTERIA DE MADERA 1,038.42 0.00 02.05.01 PUERTA DE MADERA CONTRAPLACADA 1,038.42 0.00 0.00 1,038.42 1,038.42 02.06 CARPINTERIA METALICA 45,448.98 0.00 02.06.01 PUERTA METALICA P-01(INGRESO PRINCIPAL) 440.68 0.00 0.00 440.68 440.68 02.06.02 TIJERAL METÁLICO S/DISEÑO 19,236.30 11,541.78 5,770.89 1,923.63 19,236.30 02.06.03 VIGUETA METÁLICA S/DISEÑO 25,772.00 15,463.20 7,731.60 2,577.20 25,772.00 02.07 COBERTURAS 39,282.28 0.00 02.07.01 COBERTURA DE PLANCHA METÁLICA ALUZIN 39,282.28 7,856.46 0.00 31,425.82 39,282.28 02.08 PINTURA 16,937.23 0.00 02.08.01 PINTURA BASE EN MUROS INTERIORES Y EXTERIORES 7,529.30 1,505.86 0.00 6,023.44 7,529.30 02.08.02 PINTURA LATEX EN MUROS INTERIORES 8,557.06 1,711.41 0.00 6,845.65 8,557.06 02.08.03 PINTURA ESMALTE EN CARPINTERIA METÁLICA Y CONTRAZOCALO 850.87 170.17 0.00 680.70 850.87 03 INSTALACIONES ELECTRICAS 5,392.39 0.00 03.02 CABLE THW CABLEADO DE 4 mm2 294.00 58.80 0.00 235.20 294.00 03.03 CABLE THW CABLEADO DE 2.5 mm2 134.00 26.80 0.00 107.20 134.00 03.04 TABLEROS DISTRIBUCION CAJA METALICA CON 12 POLOS 247.80 49.56 0.00 198.24 247.80 03.05 CONEXION DE TABLERO NUEVO A TABLERO EXISTENTE 350.00 70.00 0.00 280.00 350.00 03.06 SALIDA PARA CENTRO DE LUZ 1,197.95 239.59 0.00 958.36 1,197.95 03.07 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE + L.T. A PRUEBA DE AGUA 1,299.27 259.85 0.00 1,039.42 1,299.27 03.08 TUBERIA PVC-SAP ELECTRICA DE 20 mm 158.40 31.68 0.00 126.72 158.40 03.09 ARTEFACTO FLUORESCENTE RAS-E CON EQUIPO Y LAMPARA DE 3x40 W 1,385.02 277.00 0.00 1,108.02 1,385.02 03.01 ARTEFACTO FLUORESCENTE PARA ADOSAR CIRCULAR 325.95 65.19 0.00 260.76 325.95 04 INSTALACIONES SANITARIAS 15,055.38 04.01 SISTEMA DE DESAGUE INTERIOR 2,030.37 "MEJORAMIENTO DEL LOCAL COMUNAL DE USOS MÚLTIPLES EN LA LOCALIDAD DE PICHONES ALTO - DISTRITO DE LAS LOMAS - PROVINCIA DE PIURA - PIURA" MURO LADRILLO K.K.DE ARCILLA 18 H ( 0.09x0.13x0.24) AMARRE DE SOGA JUNTA 1.5 cm. MORTERO 1:1:5

description

EXCEL PARA CRONOGRAMA DE OBRA

Transcript of 11 Cronograma de Avance de Obra Valorizado

Page 1: 11 Cronograma de Avance de Obra Valorizado

CRONOGRAMA DE AVANCE DE OBRA VALORIZADO

Presupuesto :

Fecha de reporte : 10/30/2014

Fecha base : OCTUBRE 2014

Constructora :

Item Descripción CANT. QUINCENA 01 QUINCENA 02 QUINCENA 03 TOTAL01 ESTRUCTURAS 43,942.44

01.01 OBRAS PROVISIONALES 6,498.86

01.01.01 CARTEL DE OBRA 3.60X7.20 1,557.61 1,557.61 0.00 0.00 1,557.6101.01.02 ALMACEN Y OFICINA PROVISIONAL 1,254.40 418.09 413.95 422.36 1,254.4001.01.03 DEPOSITO PARA ALMACENAR AGUA 250.00 82.50 82.50 85.00 250.0001.01.04 FLETE TERRESTRE 3,436.85 2,405.79 0.00 1,031.06 3,436.8501.02 TRABAJOS PRELIMINARES 2,607.05

01.02.01 DESMONTAJE DE ESTRUCTURAS METALICAS EXISTENTES 2,371.25 2,371.25 0.00 0.00 2,371.2501.02.02 DESMONTAJE DE COBERTURA EXISTENTE 131.36 131.36 0.00 0.00 131.3601.02.03 DEMOLICION DE MURO EXISTENTE 104.44 104.44 0.00 0.00 104.4401.03 MOVIMIENTO DE TIERRAS 16,808.48

01.03.01 NIVELACION Y RELLENO COMPACTADO CON TERRENO NATURAL 3,273.24 3,273.24 0.00 0.00 3,273.2401.03.02 EXCAVACION PARA CIMIENTOS HASTA 1.00 mTERRENO NORMAL 2,568.75 2,568.75 0.00 0.00 2,568.7501.03.03 RELLENO COMPACTADO CON MATERIAL PROPIO 1,572.57 1,258.06 314.51 0.00 1,572.5701.03.04 RELLENO COMPACTADO CON MATERIAL GRANULAR (AGREGADO FILTRANTE) 6,005.27 2,402.11 1,201.05 2,402.11 6,005.2701.03.05 RELLENO CON PIEDRA GRADUADA DE 4" 1,377.93 275.59 0.00 1,102.34 1,377.9301.03.06 RELLENO CON ARENA GRUESA PARA CONFINAMIENTO DE BIODIGESTOR 289.93 57.99 0.00 231.94 289.9301.03.07 ELIMINACION CON TRANSPORTE (CARGUIO A MANO) R=25 m3/día 1,720.79 0.00 1,376.63 344.16 1,720.7901.04 CONCRETO SIMPLE 10,122.64

01.04.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% PIEDRA 620.13 620.13 0.00 0.00 620.1301.04.02 SOLADO e=4" 40.72 40.72 0.00 0.00 40.7201.04.03

FALSO PISO e=4" DE CONCRETO 1:10 9,461.799,461.79

0.00 0.00 9,461.7901.05 CONCRETO ARMADO 7,905.41

01.05.01 ZAPATAS 395.34

01.05.01.01 CONCRETO EN ZAPATAS f'c=210 kg/cm2 331.71 331.71 0.00 0.00 331.7101.05.01.02 ACERO fy=4200 kg/cm2 GRADO 60 en ZAPATAS 63.63 63.63 0.00 0.00 63.6301.05.02 SOBRECIMIENTO 1,537.54

01.05.02.01 CONCRETO EN SOBRECIMIENTOS f'c=175 kg/cm2 827.31 827.31 0.00 0.00 827.3101.05.02.02 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTOS 521.35 521.35 0.00 0.00 521.3501.05.02.03 ACERO fy=4200 kg/cm2 GRADO 60 en SOBRECIMEINTO 188.88 188.88 0.00 0.00 188.8801.05.03 COLUMNAS 1,985.84

01.05.03.01 CONCRETO EN COLUMNAS f'c=210 kg/cm2 735.90 735.90 0.00 0.00 735.9001.05.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS 734.99 734.99 0.00 0.00 734.9901.05.03.03 ACERO fy=4200 kg/cm2 GRADO 60 en COLUMNAS 514.95 514.95 0.00 0.00 514.9501.05.04 MESADAS Y PLACAS LIVIANAS 3,986.69

01.05.04.01 CONCRETO ELEMENTOS MENORES f'c=175 kg/cm2 1,398.20 0.00 1,118.56 279.64 1,398.2001.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL EN PLACAS LIVIANAS 1,474.18 0.00 1,179.34 294.84 1,474.1801.05.04.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 1,114.31 0.00 891.45 222.86 1,114.3102 ARQUITECTURA 152,608.36

02.01 ALBAÑILERIA 4,594.43

02.01.01MURO LADRILLO K.K.DE ARCILLA 18 H ( 0.09x0.13x0.24) AMARRE DE SOGA JUNTA 1.5 cm. MORTERO 1:1:5 4,594.43

918.89

3,675.54 0.00 4,594.4302.02 REVOQUES ENLUCIDOS Y MOLDURAS 8,590.10

02.02.01 TARRAJEO PRIMARIO RAYADO C/MEZCLA 1:5 870.17 0.00 783.15 87.02 870.1702.02.02 TARRAJEO DE MUROS INTERIORES 1,017.79 0.00 916.01 101.78 1,017.7902.02.03 TARRAJEO DE COLUMNAS 5,890.64 0.00 5,301.58 589.06 5,890.6402.02.04 TARRAJEO DE VIGAS 408.26 0.00 367.43 40.83 408.2602.02.05 TARRAJEO DE POSA DE LODOS 403.24 0.00 362.92 40.32 403.2402.03 PISOS Y PAVIMENTOS 35,729.59

02.03.01 CONTRAPISO DE 2" 10,349.53 0.00 10,349.53 0.00 10,349.5302.03.02 PISO DE CERAMICO DE 30 X 30 cm 21,711.10 0.00 6,513.33 15,197.77 21,711.1002.03.03 VEREDAS 3,668.96

02.03.03.01 CONCRETO f'c=175 kg/cm2 EN VEREDAS 3,146.33 0.00 3,146.33 0.00 3,146.3302.03.03.02 ENCOFRADO Y DESENCOFRADO DE VEREDAS 243.73 0.00 243.73 0.00 243.7302.03.03.03 JUNTAS ASFALTICAS 117.31 0.00 117.31 0.00 117.3102.03.03.04 CURADO CON ADITIVO QUIMICO EN CONCRETO 161.59 0.00 161.59 0.00 161.5902.04 ZOCALOS Y CONTRAZOCALOS 987.33

02.04.01 ZOCALO DE CERAMICA 20 X 20 EN BAÑO O SIMILAR 616.10 0.00 616.10 0.00 616.1002.04.02 CONTRAZOCALO DE CEMENTO PULIDO 371.23 0.00 371.23 0.00 371.2302.05 CARPINTERIA DE MADERA 1,038.42 0.0002.05.01 PUERTA DE MADERA CONTRAPLACADA 1,038.42 0.00 0.00 1,038.42 1,038.4202.06 CARPINTERIA METALICA 45,448.98 0.0002.06.01 PUERTA METALICA P-01(INGRESO PRINCIPAL) 440.68 0.00 0.00 440.68 440.6802.06.02 TIJERAL METÁLICO S/DISEÑO 19,236.30 11,541.78 5,770.89 1,923.63 19,236.3002.06.03 VIGUETA METÁLICA S/DISEÑO 25,772.00 15,463.20 7,731.60 2,577.20 25,772.0002.07 COBERTURAS 39,282.28 0.0002.07.01 COBERTURA DE PLANCHA METÁLICA ALUZIN 39,282.28 7,856.46 0.00 31,425.82 39,282.2802.08 PINTURA 16,937.23 0.0002.08.01 PINTURA BASE EN MUROS INTERIORES Y EXTERIORES 7,529.30 1,505.86 0.00 6,023.44 7,529.3002.08.02 PINTURA LATEX EN MUROS INTERIORES 8,557.06 1,711.41 0.00 6,845.65 8,557.0602.08.03 PINTURA ESMALTE EN CARPINTERIA METÁLICA Y CONTRAZOCALO 850.87 170.17 0.00 680.70 850.8703 INSTALACIONES ELECTRICAS 5,392.39 0.0003.02 CABLE THW CABLEADO DE 4 mm2 294.00 58.80 0.00 235.20 294.0003.03 CABLE THW CABLEADO DE 2.5 mm2 134.00 26.80 0.00 107.20 134.0003.04 TABLEROS DISTRIBUCION CAJA METALICA CON 12 POLOS 247.80 49.56 0.00 198.24 247.8003.05 CONEXION DE TABLERO NUEVO A TABLERO EXISTENTE 350.00 70.00 0.00 280.00 350.0003.06 SALIDA PARA CENTRO DE LUZ 1,197.95 239.59 0.00 958.36 1,197.9503.07 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE + L.T. A PRUEBA DE AGUA 1,299.27 259.85 0.00 1,039.42 1,299.2703.08 TUBERIA PVC-SAP ELECTRICA DE 20 mm 158.40 31.68 0.00 126.72 158.4003.09 ARTEFACTO FLUORESCENTE RAS-E CON EQUIPO Y LAMPARA DE 3x40 W 1,385.02 277.00 0.00 1,108.02 1,385.0203.01 ARTEFACTO FLUORESCENTE PARA ADOSAR CIRCULAR 325.95 65.19 0.00 260.76 325.9504 INSTALACIONES SANITARIAS 15,055.38

04.01 SISTEMA DE DESAGUE INTERIOR 2,030.37

"MEJORAMIENTO DEL LOCAL COMUNAL DE USOS MÚLTIPLES EN LA LOCALIDAD DE PICHONES ALTO - DISTRITO DE LAS LOMAS - PROVINCIA DE PIURA - PIURA"

Page 2: 11 Cronograma de Avance de Obra Valorizado

Item Descripción CANT. QUINCENA 01 QUINCENA 02 QUINCENA 03 TOTAL04.01.01 SALIDA DESAGUE DE PVC SAL 2" 501.96 100.39 401.57 0.00 501.9604.01.02 SALIDA DESAGUE DE PVC-SAL 4" 720.84 144.17 576.67 0.00 720.8404.01.03 SALIDA VENTILACION DE PVC-SAL 2" 177.08 35.42 141.66 0.00 177.0804.01.04 REGISTRO DE BRONCE 2" 43.15 8.63 34.52 0.00 43.1504.01.05 REGISTRO DE BRONCE 4" 86.30 17.26 69.04 0.00 86.3004.01.06 RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC SAL DE 4" 293.40 58.68 234.72 0.00 293.4004.01.07 RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC SAL DE 2" 207.64 41.53 166.11 0.00 207.6404.02 REDES COLECTORAS 3,345.58 0.0004.02.01 EXCAVACION MANUAL DE ZANJAS PARA TUB. PVC DN 4". 46.56 46.56 0.00 0.00 46.5604.02.02 TUBERIA DE PVC SAL DE 4" 227.44 45.49 181.95 0.00 227.4404.02.03 CAJAS DE REGISTRO DE DESAGUE 10" x 20" 802.62 160.52 642.10 0.00 802.6204.02.04 RELLENO COMPACTADO DE ZANJA CON MATERIAL PROPIO 158.48 31.70 126.78 0.00 158.4804.02.05 SUMINISTRO Y COLOCACION DE BIODIGESTOR 2,110.48 422.10 844.19 844.19 2,110.4804.03 SISTEMA DE AGUA FRIA 1,781.91 0.0004.03.01 EXCAVACION MANUAL DE ZANJAS PARA TUB. 46.56 46.56 0.00 0.00 46.5604.03.02 VALVULA COMPUERTA DE 1" 152.42 0.00 0.00 152.42 152.4204.03.03 RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC C-10 DE 3/4" 103.46 0.00 82.77 20.69 103.4604.03.04 SALIDA DE AGUA FRIA TUBERIA PVC C-10 O 1/2" 898.04 0.00 718.43 179.61 898.0404.03.05 VALVULA COMPUERTA DE 3/4" 288.68 0.00 230.94 57.74 288.6804.03.06 RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC C-10 DE 1/2" 165.62 0.00 132.50 33.12 165.6204.03.07 RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC C-10 O 1" 127.13 0.00 101.70 25.43 127.1304.04 CISTERNA Y TANQUE DE AGUA 7,897.52 0.0004.04.01 SUMINSTRO E INSTALACION DE CISTERNA DE 5000 LTS. 5,434.68 1,086.94 1,086.94 3,260.81 5,434.6804.04.02 SUMINSTRO E INSTALACION DE TANQUE DE 2,500 LTS. 2,462.84 492.57 492.57 1,477.70 2,462.8405 OTROS 2,871.86 0.0005.01 LIMPIEZA FINAL DE OBRA 348.77 0.00 0.00 348.77 348.7705.02 SUMINSTRO E INSTALACION DE ELECTROBOMBA DE 0.5 HP 327.11 65.42 0.00 261.69 327.1105.03 VIDRIO SEMIDOBLE INCOLORO CRUDO 924.80 184.96 0.00 739.84 924.8005.04 POZO A TIERRA 1,271.18 0.00 0.00 1,271.18 1,271.1806 MOBILIARIO 2,160.96 0.0006.01 SILLAS DE PLASTICO REFORZADAS 1,779.60 355.92 0.00 1,423.68 1,779.6006.02 ESCRITORIO CON ESTANTE 381.36 76.27 0.00 305.09 381.36

74,615.45 59,271.45 88,144.49

COSTO DIRECTO 222,031.39

GASTOS GENERALES 22,203.14

UTILIDAD (10%) 22,203.14

SUBTOTAL 266,437.67

IGV (18%) 47,958.78

TOTAL PRESUPUESTO 314,396.45 33.60% 26.70% 39.70%