HOJA DE METRADOS
ESTRUCTURA, ARQUITECTURA Y EQUIPAMIENTO
CODIGO DESCRIPCION UND N° CÁLCULO METRADO METRADO
VECES L A H PARCIAL TOTAL
RESERVORIO RAP-01, V = 25 M3
1.00 TRABAJOS PRELIMINARES
TRAZO Y REPLANTEO M2 17.26
1.00 4.00 4.00 16.00
1.00 1.05 1.20 1.26
LIMPIEZA DE TERRENO M2 17.26
IDEM TRAZO Y REPLANTEO
2.00 MOVIMIENTO DE TIERRAS
EXCAVACION DE TERRENO M3 22.35
RESERVORIO 1.00 4.00 4.00 0.59 9.40
SOBREEXCAV RESERVORIO LADO Y 1.00 1.00 4.00 0.59 2.35
SOBREEXCAV RESERVORIO LADO Y 1.00 1.00 2.80 0.59 1.65
SOBREEXCAV RESERVORIO LADO X 2.00 6.00 1.00 0.59 7.05
CAJA DE VALVULAS 1.00 1.05 1.20 0.59 0.74
SOBREEXCAVACION CAJA DE VALVULAS 2.00 1.05 0.60 0.59 0.74
1.00 1.20 0.60 0.59 0.42
REFINE Y NIVELACION M2 17.26
1.00 4.00 4.00 16.00
1.00 1.05 1.20 1.26
RELLENO Y NIVELACION M3 8.68
SOBREEXCAV RESERVORIO LADO Y 1.00 1.00 4.00 0.59 2.35
SOBREEXCAV RESERVORIO LADO X 1.00 1.00 2.80 0.59 1.65
SOBREEXCAV RESERVORIO LADO X 1.00 6.00 1.00 0.59 3.53
SOBREEXCAVACION CAJA DE VALVULAS 2.00 1.05 0.60 0.59 0.74
1.00 1.20 0.60 0.59 0.42
ELIMINACION DE DESMONTE M3 17.08
EXCAVACION 22.35
RELLENO 8.68
ELIMINACION 13.67
ELIMINACION 1.25% ESPONJ 17.08
3.00 CONCRETO SIMPLE
CONCRETO FC 100 KG/CM2 PARA SOLADO M3 1.60
1.00 4.00 4.00 0.10 1.60
EMBOQUILLADO DE PIEDRA FC 175 KG/CM2 E= 0.20 M2 1.00 1.00 0.50 0.50 0.50
4.00 CONCRETO ARMADO
CONCRETO PARA LOSA DE FONDO FC 210 KG/CM2 M3 3.32
RESERVORIO 1.00 4.60 4.60 0.15 3.17
CAJA 1.00 0.90 1.50 0.10 0.14
DADO 1.00 0.30 0.20 0.20 0.01
ENCOFRADO PARA LOSA DE FONDO M2 3.29
RESERVORIO X 2.00 4.60 0.15 1.38
RESERVORIO Y 2.00 4.60 0.15 1.38
CAJA X 2.00 0.90 0.10 0.18
CAJA Y 1.00 1.50 0.10 0.15
DADO 1.00 1.00 0.20 0.20
ACERO PARA LOSA DE FONDO KG 3.32 70.00 232.47
CONCRETO PARA MUROS FC 210 KG/CM2 M3 5.25
RESERV EJE X 2.00 4.00 2.10 0.15 2.52
RESERV EJE Y 2.00 3.70 2.10 0.15 2.33
CAMARA MUROS X 2.00 1.20 0.80 0.15 0.29
CAMARA MUROS Y 1.00 0.90 0.80 0.15 0.11
ENCOFRADO PARA MUROS M2 67.32
RESERV INT 2.00 2.10 3.70 15.54
RESERV INT 2.00 2.10 3.70 15.54
RESERV EXT 2.00 2.10 4.00 16.80
RESERV EXT 2.00 2.10 4.00 16.80
CAMARA MUROS 2.00 1.05 0.80 1.68
CAMARA MUROS 1.00 1.20 0.80 0.96
ACERO PARA MUROS KG 5.25 70.00 367.29
CONCRETO FC 210 KG/CM2 PARA LOSA MACIZA M3 1.90
RESERV 1.00 4.20 4.20 0.10 1.76
INGRESO -1.00 0.60 0.60 0.10 -0.04
CAJA 1.00 1.20 1.05 0.10 0.13
INGRESO -1.00 0.60 0.60 0.10 -0.04
BOCA INGRESO RESERVORIO 1.00 2.80 0.15 0.10 0.04
BOCA INGRESO CAJA 1.00 2.80 0.15 0.10 0.04
ENCOFRADO PARA LOSA MACIZA M2 19.75
RESERV 1.00 3.70 3.70 13.69
INGRESO -1.00 0.60 0.60 -0.36
FRISOS TECHO 1.00 16.80 0.10 1.68
VOLADO TECHO 1.00 16.80 0.20 3.36
FRISO INGRESO 1.00 2.40 0.10 0.24
CAMARA 1.00 0.90 0.90 0.81
INGRESO -1.00 0.60 0.60 -0.36
VOLADO TECHO CAMARA 1.00 3.45 0.10 0.35
FRISO TECHO CAMARA 1.00 3.45 0.10 0.35
ACERO PARA LOSA MACIZA KG 70.00 1.90 133.14
5.00 REVOQUES Y ENLUCIDOS
TARRAJEO DE LOSA PISO CON IMPERMEABILIZANTE M2 13.69
1.00 3.70 3.70 13.69
TARRAJEO DE MUROS CON IMPERMEABILIZANTE M2 31.08
2.00 3.70 2.10 15.54
2.00 3.70 2.10 15.54
TARRAJEO INTERIOR DE MUROS M2 3.69
CAMARA PARED 4.00 0.90 0.80 2.88
CAMARA PISO 1.00 0.90 0.90 0.81
TARRAJEO EXTERIOR DE MUROS M2 53.70
RESERVORIO 2.00 4.00 2.10 16.80
2.00 4.00 2.10 16.80
-1.00 1.05 1.20 -1.26
CAMARA 2.00 1.20 0.80 1.92
1.00 1.05 1.20 1.26
TECHO RESERV 1.00 4.20 4.20 17.64
-1.00 0.60 0.60 -0.36
TECHO CASETA 1.00 1.20 1.05 1.26
-1.00 0.60 0.60 -0.36
DERRAMES M2 43.45
FRISOS RESERV 2.00 4.40 8.80
FRISOS RESERV 2.00 4.40 8.80
VOLADO RESERV 2.00 4.40 8.80
VOLADO RESERV 2.00 4.40 8.80
FRISO INGRESO RESERV 4.00 0.60 2.40
FRISO CAMARA 2.00 1.20 2.40
1.00 1.05 1.05
2.00 0.60 1.20
2.00 0.60 1.20
6.00 PINTURA
PINTADO DE MURO EXTERIOR M2 43.30
2.00 4.00 2.10 16.80
2.00 4.00 2.10 16.80
2.00 1.20 0.80 1.92
1.00 1.05 1.20 1.26
2.00 4.40 0.15 1.32
2.00 4.40 0.15 1.32
2.00 4.40 0.15 1.32
2.00 4.40 0.15 1.32
4.00 0.60 0.15 0.36
2.00 1.20 0.15 0.36
1.00 1.05 0.15 0.16
2.00 0.60 0.15 0.18
2.00 0.60 0.15 0.18
7.00 CERCO PERIMÉTRICO
CERCO DE ALAMBRE DE PUAS M 4.00 8.00 32.00
PRUEBAS Y LIMPIEZA
PRUEBA HIDRAULICA M3 1.00 25.00 25.00
LIMPIEZA Y DESINFECCIÓN M2 2.00 3.70 2.10 15.54 60.31
2.00 3.70 4.20 31.08
1.00 3.70 3.70 13.69
EVACUACION DE AGUA M3 1.00 25.00 25.00
PRUEBA DE CALIDAD DE CONCRETO UND 9.00
LOSA 3.00 3.00
MURO 3.00 3.00
TECHO 3.00 3.00
PRUEBA DE COMPACTACION UND 1.00 1.00 1.00
6.00 EQUIPAMIENTO
TAPA METALICA SANITARIA 60 X 60 e = 1/8" UND 2.00 2.00
ESCALINES DE FOGO 1" UND 2.10 3.33 7.00
TUBO DE VENTILACION 2" UND 2.00 2.00
LINEA DE INGRESO
TEE FOGO D1 UND 1.00 1.00
CODO FOGO 90º D1 UND 3.00 3.00
VALVULA COMPUERTA DE BRONCE ROSCADO D1 UND 2.00 2.00
UNION UNIVERSAL DE FOGO D1 UND 4.00 4.00
NIPLE DE ROSCA D1 UND 7.00 7.00
TUBO DE FOGO ROSCADO D1 M 5.00 5.00
LINEA DE SALIDA
CANASTILLA D2 UND 1.00 1.00
TEE FOGO D2 X D1 UND 1.00 1.00
VALVULA COMPUERTA DE BRONCE ROSCADO D2 UND 1.00 1.00
UNION UNIVERSAL DE FOGO D2 UND 2.00 2.00
NIPLE DE ROSCA D2 UND 3.00 3.00
TUBO DE FOGO ROSCADO D2 M 2.50 2.50
LINEA DE REBOSE
NIPLE DE FOGO 3" X 0.15 M UND 1.00 1.00
REDUCCION 3" X 2" UND 1.00 1.00
CODO FOGO 90º 2" UND 4.00 4.00
TEE FOGO 2" X 2" UND 3.00 3.00
VALVULA COMPUERTA DE BRONCE ROSCADO 2" UND 1.00 1.00
UNION UNIVERSAL FOGO 2" UND 2.00 2.00
NIPLE DE GOFO 2" UND 3.00 3.00
TAPON DE FOGO 2" UND 2.00 2.00
TUBERIA DE PVC 2" M 13.00 13.00
MONTAJE DE INSTALACIONES HIDRAULICAS UND 1.00 1.00