CLAVE CONCEPTO
EJE TRAMO
LOSA DE CIMENTACION
CIMENTACION
ZAPATAS (CIMENTACION)
EXCAVACION B, C 1-2 Y 3 1.50 1.50 1.50 6 20.25 M3 ZAPATAS
PLANTILLA DE F'C=100 KG/CM2 DE 6CM DE ESP. B, C 1-2 Y 3 1.50 1.50 6 13.50 M2 ZAPATAS
CIMBRADO Y DESCIMBRADO 1.30 0.15 24 4.68 M2 CIMENTACION ZAPATA
CIMBRADO Y DESCIMBRADO 0.40 1.29 12 6.19 M2 DADO
0.40 1.29 12 6.19 M2 DADO
17.06 M2
ACERO DEL # 4 @ 15 CM. AMBOS LADOS 1.42 0.993 120 169.21 KG PARRILLAS
ACERO DEL # 4 @ ( VERTICALES ) 2.00 0.993 48 95.33 KG DADOS
264.54 KG
ACERO DEL # 2 @ 15 CM. ESTRIBOS. 1.72 0.248 66 28.15 KG ESTRIBOS DEL DADO
CONCRETO DE F'C= 200 KG/CM2 1.30 1.30 0.15 6 1.52 M3 CIMENTACION ZAPATA
0.40 0.40 1.29 6 0.96 M3 DADO
2.48 M3
VOL. EXC. - VOL. CONCR.
RELLENO 20.25 - 2.48 17.77 M3 ZAPATA DADO
MURETE DE ENRACE ( CIMENTACION )EXCAVACION A 1 - 3 18.00 0.70 1.00 1 12.60 M3
3 A - C 11.00 0.70 1.00 1 7.70 M3
MAS CASTILLOS DE 15 X 15 CMS 0.20 0.20 0.30 9 0.11 M3
20.41 M3 EXCAVACION
PLANTILLA DE F'C=100 KG/CM2 DE 6CM DE ESP. A 18.00 0.70 1 12.60 M2
3 11.00 0.70 1 7.70 M2
20.30 M2
MURETE DE ENRACE CON BLOCK ( CIMENTACION ) A 1 - 3 18.00 1.00 1 18.00 M2
3 A - C 11.00 1.00 1 11.00 M2CASTILLOS 0.15 1.00 -9 -1.35 M2 ( - )
OBSERVACIONESLOCALIZACION
NUMEROS GENERADORES
OBRA:
MUNICIPIO:
LOCALIDAD:
FECHA:
RESULTADOLARGO
( m )
ESPESOR
( m )UNIDADPZAS
ANCHO
( m )
ALTO
( m )
ACERO
( KG/ML )
7/27/2019 Generador Nave Industrial
2/4
27.65 M2 MURETE
VOL. EXC. - VOL. MURO
RELLENO EN ZANJAS DE MURETE 20.41 - 4.35 16.06 M3 MURETE DE ENRACE (CIM.)
CASTILLOS 15X15 CMS.
CIMBRAS EN CASTILLOS A 1 - 3 0.15 1.00 12 1.80 M23 A - C 0.15 1.00 6 0.90 M2
2.70 M2
ACERO No. 2 ESTRIBOS @ 15 CMS. 0.72 0.248 72 12.86 KG
12.86 KG
ACERO No. 3 VERTICALES 1.30 0.559 36 26.16 KG
26.16 KG
CONCRETO DE F'C= 200 KG/CM2 0.15 0.15 1.00 9 0.20 M3 CASTILLOS EN MURETE0.20 M3
CADENA DE DESPLANTE O CONTRATRABESCADENA DE DESPLANTE O CONTRATRABES
CIMBRADO Y DESCIMBRADO A 1 - 3 18.00 0.20 1 3.60 M2
3 A - C 11.00 0.20 1 2.20 M2
5.80 M2
LONG. DESARR.
ACERO DEL # 2 ( ALAMBRON ) ANILLETAS A 1 - 3 18.00 0.74 0.248 121 22.21 KG CADENA DE DESPLANTE
ACERO DEL # 2 ( ALAMBRON ) ANILLETAS 3 A - C 11.00 0.74 0.248 74 13.64 KG CADENA DE DESPLANTE
35.85 KG
ACERO DEL # 3 (VARILLA RECTA) A 1 - 3 18.15 0.559 4 40.58 KG CADENA DE DESPLANTE
ACERO DEL # 3 (VARILLA RECTA) 3 A - C 11.15 0.559 4 24.93 KG CADENA DE DESPLANTE
65.51 KG
CONCRETO DE F'C= 200 KG/CM2 A 1 - 3 18.00 0.15 0.20 1 0.54 M3 CADENA DE DESPLANTE
3 A - C 11.00 0.15 0.20 1 0.33 M3 CADENA DE DESPLANTE
0.87 M3
PISO FIRME DE CONCRETO DE F'C=250 KG/CM2PISO FIRME DE CONCRETO DE F'C=250 KG/CM2LIMPIA TRAZO Y NIVELACION A - C 1 - 3 18.00 11.00 1 198.00 M3
198.00 M3
DESPALME DE ESTRUCTURA A - C 1 - 3 18.00 8.00 0.40 1 57.60 M3
57.60 M3
RELLENO EN PLATAFORMA DE CIMENTACION A - C 1 - 3 18.00 8.00 0.38 1 54.72 M3
54.72 M3
7/27/2019 Generador Nave Industrial
3/4
CIMBRA FRONTALES A 1 - 3 18.00 0.15 1 2.70 M2
3 A - C 11.00 0.15 1 1.65 M2
4.35 M2
PISO FIRME DE 15 CM DE ESPESOR. PULIDO FINO A - C 1 - 3 18.00 11.00 0.15 1 29.70 M329.70 M3
MALLA LAC 6 - 6/4 - 4 A - C 1 - 3 18.00 11.00 1 198.00 M2
6.45 M2 TRASLAPES
204.45 M2
7/27/2019 Generador Nave Industrial
4/4
CLAVE CONCEPTO
EJE TRAMOPZAS RESULTADO UNIDAD OBSERVACIONES
NUMEROS GENERADORES
OBRA:
MUNICIPIO:
LOCALIDAD:
FECHA:
LOCALIZACION LARGO( m )
ANCHO
( m )
ALTO
( m )
ESPESOR
( m )
ACERO
( KG/ML )